Citation : 2009 Latest Caselaw 58 Bom
Judgement Date : 9 December, 2009
1
IN THE HIGH COURT OF JUDICATURE OF BOMBAY
BENCH AT AURANGABAD
WRIT PETITION NO.7080 OF 2009
Narshima Constructions Pvt. Ltd.
Through its Managing Director,
Mr.Mohan Kashinathrao Kale,
Age:47 Yrs., occu. Contractorship
r/o Dhanshree, Dhanora Road,
Beed, Dist. Beed (M.S.) - PETITIONER
VERSUS
1)
The State of Maharashtra
Through Secretary
Public Works Department,
Mantralaya, Mumbai-32.
2) The Chief Engineer,
Public Works Region,
Bandhkam Bhavan, Adalat Rd.,
Aurangabad.
3) The Superintending Engineer,
Special Project Circle,
Bandhkam Bhavan, Aurangabad.
4) The Executive Engineer,
Special Project Division No.1,
Nagar Road, Beed, Dist.Beed.
5) Government of India,
Through Secretary,
Ministry of Surface, Transport
Department of Road Transport &
Highway, New Delhi. - RESPONDENTS
*****
Mr.VJ Dixit, Sr. Counsel holding for
Mr.J.N.Singh, Advocate for Petitioner;
Mr.RP Phatke AGP for Respondent Nos. 1 to 4;
::: Downloaded on - 09/06/2013 15:23:44 :::
2
Mr.Alok Sharma, Assistant Solicitor General for
Union of India for Respondent No.5.
-----
CORAM : NARESH H. PATIL &
K.U.CHANDIWAL, JJ.
DATE : 9th December, 2009.
ORAL JUDGMENT (PER: NARESH H.PATIL, J.)
1) Rule. Rule made returnable forthwith. By consent of parties heard finally.
2) The petitioner, a private limited company under the India Companies Act, 1956, participated in the tender process, pursuant to
the Tender Notice/National Competitive Bid dated
26.8.2008 for carrying out the work for widening two-lanes Kalyan-Nanded-Nirmal Road NH-222 KM 376/00 to 395/00 (hereinafter to be referred to
as the work under the tender). The estimated cost put under the tender is Rs.9,39,87,460/-. The petitioner submitted his tender bid with the
concerned authorities.
3) The petitioner mainly raises its challenge on the ground that (i) carrying out the work under the tender by joint venture is prohibited by the respondents as per clause 4.4.
Part-I of National Competitive Bidding (for
short,NCB); (ii) Sub- Clause (A)(b) of clause 4.5 of the NCB as regards satisfactory completion
of earlier work to the extent of 90% of the contract value was unreasonable; and (iii) The respondents authorities claimed certain
amenities for the Department under the caption `Errata'. We may here itself find it convenient to quote Clauses 4.4; 4.5 (A)(b) and relevant
clauses shown under the caption "Errata", set
out in the National Competitive Bidding, which read as under :
"4.4. Bids from Joint Ventures are not acceptable; or Bids from
prequalified firms or prequalified joint ventures only will be
acceptable.
4.5(A) To qualify for award of the contract, each bidder in its name should have in the last five years as referred to in Appendix.
(a).................................
(b) Satisfactorily completed(not less than 90% of contract value), as a prime contractor (or as a nominated subcontractor, where the
subcontract involved execution of
all main items of work described in the bid document, provided further
that all other qualification criteria are satisfied) at least one similar work of value not less than
amount indicated in Appendix (usually not less than 50% of estimated value of contract).
Errata Name of Work - Widening to two lane
KM 315/00 to 321/00 & km 332/00 to 336/600 Kalyan-Nagar-Pathardi- Padalsingi-Gadhi-Majalgaon-Parbhnai-
Nanded-Nirmal Road NH-222 in the State of Maharashtra.
Cost put to Tender :- Rs.
9,39,87,460/-
The following amendments are made in Tender Booklet as per below :-
(I) In VOLUME-II (original and copy) TECHNICAL SPECIFICATIONS Page No.40
Clause :- Amenities to department.
Inspection vehicles for
Engineer.
The entire Para is deleted and
instead, following shall be read: Special Conditions :-
1) The successful contractor shall
provide one brand new vehicle to department for inspection purpose of
TATA Sumo Victa Model CX seven seater without any extra cost to Government. The vehicle shall remain
in the custody of the department and shall be the sole property of the Government. The contractor shall
provide the above described vehicle
duly insured and getting RTO passed at his own expenses in the name of
the Executive Engineer, Special Project Division No.1, Beed. The contractor shall provide above
vehicle within one month from the date of issue of work order, failing
which an amount of 5.50 lakhs (Rupees five lakhs and fifty
thousand) will be recovered from the first R.A. Bill of this work.
2) In addition to this the successful contractor shall provide
following amenities without any extra cost to Government.
i) 4 nos. of 2.00 Ton carrier split air conditioners model -2 T ESR ELLA
ii) 1. No.of Richo AFICIO MP 2000 Le
Xerox Machine.
iii) 1 No. of Fax machine, Model Panasonic 981.
iv) 15 Nos. of Neelkamal Chairs. V) 2 Nos. of Printer, model-Canon 2900 Laserjet.
vi) 2 Nos. of Luminous Make Inverters Model-800 VA with 2 years warranty with 1 No. Exide make SF
brand Fall tubular Battery model 150
Ah with 3 years warranty and installation thereof."
4) The learned Senior Counsel Shri Dixit submitted that Joint ventures are accepted
formula in the matters of carrying out huge work under contract and the concept of joint-ventures
is not alien to bidding in tender. According to the learned Counsel,the petitioner would be
ousted and deprived owing to arbitrary and unreasonable conditions mentioned in the Clauses 4.4. and 4.5.(A)(b), for which, reliance was placed by the learned Counsel on the reported
Judgment of the Apex Court in the matter of New Horizons Limited and Anr. Vs. Union of India - (1995) 1 SCC 478.
5) As regards clause 4.4.(A)(b) of the NCB, it was submitted that in the matters of identical
nature, the respondents authorities have reduced
the value of the work completed by the bidder. But, in the present case, the Respondent No.2 -
Chief Engineer erred in exercising his discretion by fixing 90% of the value of the contract work for deciding the eligibility of the petitioner.
The Counsel further submitted that the amenities demanded by the Department from the bidders/tenderers are arbitrary and unreasonable
and in identical situation of a tender of like
nature, the Chief Engineer had waived the condition as regards providing the amenities and
had even reduced the value of the contract work. Certain documents were placed on record by the petitioner to substantiate their contention that
the Chief Engineer has wrongly exercised his powers in rejecting the representation made by
the petitioner for making corrections/amendments/alterations in the
conditions of the tender document.
6) The Respondent nos. 2 to 4 have filed their affidavit in reply through Mr. Hemant
Sampatrao Pagare, Superintending Engineer, Special Project Circle, Aurangabad. The deponent states that the Ministry of Surface Transport, Department of Road Transport & Highways, Government of India, is a necessary party to the proceedings of this writ petition. On the issue
raised by the petitioner in respect of value of
the work, it was contended by the deponent that clauses 4.4. and 4.5(A)(b), Part-I, are the
conditions stipulated in the Standard Bidding Document (SBD) and those conditions are commonly applied throughout the area of operation wherever
the work of this nature is undertaken by the Ministry/Department. The deponent further submitted that in the present case the estimated
costs of the work is Rs.939.87 lakhs and,
therefore, the value of the similar work was fixed at Rs. 846.00 lkahs, i.e. at 90% of the
estimated costs which is well above the limit of 50% and it is in tune with the conditions stipulated in the SBD.
7) As regards the issue of joint-ventures,
it is submitted that clause 4.4 of the SBD provides that Bids from joint ventures for the
projects above Rs.100.00 corers are acceptable. Therefore, the present project/work being less than Rs.100 crores, joint venture bidding is declined.
8) As regards the various amenities to be provided to the Department by the bidder, it is contended that these clauses are general in nature and routinely followed as they are essential for effective supervision of the work
in question to be carried out by the bidder.
9) The learned Counsel for the respondents
placed reliance on reported judgment of this Court in the matter of Bhaskar Industries Ltd. Vs. Maharashtra State Electricity Distribution
Company Ltd. reported in 2007-EQ(BOM)-0-1230. The learned Counsel Shri Sharma submitted that the powers of judicial review by this Court, in
exercise of extra ordinary writ jurisdiction, are
limited. It was submitted that the State can have its own terms of invitation of tender and it
is not open for the judicial scrutiny. According to the learned Counsel, the Courts would not interfere with the terms of the tender notice
unless it is shown to be either arbitrary or discriminatory or actuated by malice.
10) We have considered the submissions
advanced by the learned Counsel for the parties and perused the documents placed before us and the Judgments cited by the parties. As regards the challenge made by the petitioner in respect
of joint venture, we find satisfactory explanation given by the respondents. These clauses of tender are part of Standard Bidding Document (SBD) issued by the Government of India, Ministry of Surface Transport, Department of Road Transport & Highway. As regards the issue
relating to value of the work, the Chief Engineer
had already considered the representation of the petitioner and had reduced the value of the work
done earlier by the petitioner from Rs. 939.87 lakhs to Rs. 846.00 lakhs, which is above 50% as provided in clause 4.5 (A)(b) in Part-I of the
tender document.
11) The issue regarding scope of judicial
review in the matters of contract, tender and
commercial nature are well-settled, for which we may refer to the observations made by the Apex
Court in para 10 of the Judgment in the matter of Global Enery Ltd. Vs. Adani Exports Ltd. reported in 2005-EQ(SC)-0-450, which read as under :
"10. The principle is,
therefore, well settled that the terms of the invitation to tender
are not open to judicial scrutiny and the courts cannot whittle down the terms of the tender as they are in the realm of contract unless they
are wholly arbitrary discriminatory or actuated by malice. This being the position of law, settled by a catena of decisions of this court, it is rather surprising that the learned Single Judge passed an
interim direction on the very first
day of admission hearing of the writ petition and allowed the appellants
to deposit the earnest money by furnishing a bank guarantee or a bankers' cheque till three days
after the actual date of opening of the tender the order of the learned Single Judge being wholly illegal,
was, therefore, rightly set aside by
the Division Bench."
12) However, we are not convinced with the submissions advanced by the learned Counsel Shri Sharma on the issue of amenities to be provided
by the bidder to the Department and which are shown under the caption `Errata' referred herein
above. On instructions of the Officer, present in the Court, learned Counsel Shri Sharma
submitted that for effective supervision over the work in question, a vehicle is necessary for the offices concerned. At the most, the vehicle taken from the bidder would be returned back to
the successful bidder after completion of the work. We find that the special condition, mentioned in the tender booklet, in respect of binding the successful bidder to provide one new brand vehicle to the department for inspection purpose, would be unreasonable and
unconscionable. We also find that the condition
of providing the items, mentioned in clause no.2 of the Special Conditions, by the successful
bidder, is also unreasonable. We do not find any justifiable reason as to why the Central Governmental authorities are not equipped with
the infrastructural items for effective supervision over the work of such a huge magnitude. We are not convinced with the
submissions advanced by the learned Counsel for
the respondents on this aspect of the matter. We are convinced that these conditions are arbitrary
in nature. We are, therefore, inclined to quash and set aside the Special Conditions referred to above under the caption "Errata".
13) The learned Senior Counsel during the
course of hearing has produced a copy of the document, based on which, it was submitted that
the condition of joint venture was waived by the authorities. To this, learned Counsel Shri Sharma submitted that in that case, the tender costs was below Rs. 5 crores. We are convinced with the
submissions advanced on that count by learned Counsel Shri Sharma.
14) In view of the discussions made herein above, the petition is required to be allowed partly. The petition is accordingly allowed
partly. The petitioner fails in raising challenge
to the clauses 4.4 and 4.5(A)(b) of the tender document in respect of joint venture and value of
the work. As regards the special conditions under the caption "Errata", mentioned above, the petition is allowed to that extent. We set
aside the aforesaid special conditions.
15) Rule made partly absolute in the
aforesaid terms. Interim relief stands vacated.
sd/- sd/-
(K.U.CHANDIWAL) (NARESH H. PATIL)
JUDGE JUDGE
bdv/wp7080.09
Authentic copy
(BD VADNERE,PS)
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!