Citation : 2024 Latest Caselaw 4429 AP
Judgement Date : 18 June, 2024
APHC010224302009
IN THE HIGH COURT OF ANDHRA
PRADESH
[3365]
AT AMARAVATI
(Special Original Jurisdiction)
TUESDAY ,THE EIGHTEENTH DAY OF JUNE
TWO THOUSAND AND TWENTY FOUR
PRESENT
THE HONOURABLE JUSTICE DR V R K KRUPA SAGAR
FIRST APPEAL NO: 210/2009
Between:
Sri S.mojaruddin @ S.mansoor ...APPELLANT
AND
Syndicate Bank Mani Branch and Others ...RESPONDENT(S)
Counsel for the Appellant:
1. C PRAKASH REDDY
Counsel for the Respondent(S):
1. M V RAMANA
The Court made the following:
2
Dr. VRKS, J
A.S.No.210 of 2009
THE HON'BLE JUSTICE Dr. V.R.K.KRUPA SAGAR
APPEAL SUIT No.210 of 2009
JUDGMENT:
1. Plaintiff lost his money claim before the trial court and therefore preferred this appeal under section 96 CPC impugning the judgement dated 06.01.2009 of learned Additional Senior Civil Judge, Kurnool who dismissed his suit in O.S.No.288 of 2006. Respondents herein are the defendants in the suit.
2. Syndicate Bank intended to open SSI branch of the bank. Sri S.Mojaruddin alias S.Mansoor/ appellant owns plot nos. 1 and 2 situated in Survey Number 454/1, 453 of Kallur Village within Municipal Corporation of Kurnool which is described in the plaint schedule. It is undisputed that plaintiff expressed his readiness to construct a building in his plaint schedule open site and the bank agreed to take it on lease. Accordingly, Sri S.Mojaruddin/ plaintiff/ appellant commenced certain works in his plaint schedule vacant site and thereafter the works were stopped allegedly at the behest of the officers of the responding bank. It is in the context of these facts the controversy erupted between the parties
3. In the plaint filled by this appellant he refers to two letters addressed by the defendants (Ex.A1 dated 24.03.2005 and Ex.A2 dated 26.04.2005). It is pleaded that since by these letters he was
Dr. VRKS, J
requested by the defendant bank to commence the construction of the building, he started construction work in the month of May, 2005. He continued the work till the end of October, 2005. Thereafter, the defendants called upon him to express their inability to open their branch in the building that was proposed to be constructed by the plaintiff on the plaint schedule site. Till the end of May, 2006, the defendants did not ask him to resume the work. It is further pleaded that between May, 2005 and October, 2005 plaintiff consulted an architect, got the soil excavated by digging it up to the depth of six feet. He dug a bore well and installed an electric submersible motor in the plaint schedule site. He stocked materials like sand, cement, iron and stone for the purpose of construction of the building. He gave details of the expenditure incurred by him.
4. It is specifically pleaded at paragraph No.4 of the plaint that the plaintiff had to incur these expenditures by doing the works as directed by the defendants through their plans and revised plans which were to be approved by the Municipal Corporation, Kurnool. Plaintiff had paid fees to get the approval of the plans and did the further work. As the defendants committed breach of contract it caused loss to the plaintiff in many ways which include altering the nature of the property by digging the pits and by expending money to carry on the construction and disruption of the work caused damage to the reputation of the plaintiff. It is in those circumstances, he claimed Rs.1,93,106/- towards the cost
Dr. VRKS, J
of construction, purchase of materials, payments made towards the fees for approval of the plans. He claimed Rs.85,750/- towards the estimated cost for filling up of the excavated pits so as to restore its earlier shape. He claimed Rs.3,00,000/- towards damages for loss of reputation because of breach of contract. Accordingly, he sued the defendants for Rs.5,78,856/- with 18% future interest over the said amount and for costs and such other reliefs.
5. 1st defendant filed its written statement and 2nd dependent filed a memo adopting the same. After making specific denials of assertions made in the plaint, it is pleaded by defendants that the plaintiff had suppressed certain material facts. It is stated that it was in response to the tenders floated by it, plaintiff had approached it and it accepted the bids and accordingly agreed for the building to be constructed by the plaintiff. It is specifically pleaded that plaintiff executed requisite documents wherein he agreed to confirm the offer of the defendants to construct the building at the earliest by strictly adhering to the terms and conditions imposed by the bank and that the construction should be in terms of the specifications and norms of the Reserve Bank of India with a provision for strong room. Defendants handed over specific drawings and plans to the plaintiff and the plaintiff assured them that he would embark upon the construction only after obtaining due approval from the competent authority, namely, Municipal Corporation. It is pleaded that the construction
Dr. VRKS, J
shall be only with the prior approval of the Municipal Corporation and the construction should be in accordance with the guidelines prescribed by the Reserve Bank of India and any irregular or unathorised or illegal construction would cause threat of demolition at any time at the hands of the Municipal Corporation and any such eventuality would cause irreparable loss to the functioning and reputation of the defendant Bank. It is specifically pleaded in the written statement that even the plans submitted by plaintiff to Municipal Corporation never confirmed to the required and stipulated plans sought by defendants and the plaintiff failed to carry necessary amendment to the plans despite persistent request by the defendants. That the defendants were in a hurry to open their SSI branch but the plaintiff was recalcitrant and was not getting necessary approvals from the Municipal Corporation within the required time. The plaint averred expenditure and the damages are denied as incorrect and false. If the plaintiff had incurred any expenditure without fulfilling the statutory obligations, it would be at his risk only and he could not blame the defendant Bank. The technical bid signed by the plaintiff endorse the same stand point. Plaintiff committed default with the full knowledge of the facts and consequences and he is not entitled for any part of the suit claim. He is not entitled to claim damages for breach of contract and cannot mix it up with his claim for compensation for loss of alleged reputation. The valuation and the court fee paid is incorrect. They sought dismissal of the suit.
Dr. VRKS, J
6. Based on the rival pleadings, the learned trial court settled the following issues for trial: -
1. Whether the plaintiff is entitled for suit amount of Rs.5,78,856/- from defendants 1 and 2?
2. Whether the plaintiff is entitled for interest as claimed?
3. To what relief?
In proof of the respective contentions, plaintiff testified as PW.1 and got examined PW.2 and 3 and got marked Exs.A1 to A17. A branch manager of Syndicate Bank, Kurnool testified as DW.1 and Exs.B1 to B2 were marked.
7. The learned trial court considered the evidence adduced on both sides and considered the arguments advanced on both sides and held that plaint contained false averments when it stated that the defendant bank approached him. In fact, the defendant bank floated tenders and plaintiff approached them and tendered his bids which were accepted by the bank. It observed that though the plaintiff was alleging that he had submitted for sanction of building plans by the municipal corporation, he did not file copies of those plans and did not file any written approvals from the Municipal Corporation permitting him to proceed with the construction. Though he examined PW.2/ the engineer, who also said that there were completed drawings
Dr. VRKS, J
of building, they were never filed in the court. It recorded that from the evidence it could not see anything to say that plaintiff had applied for approval of the plans to the municipality. That, the plaintiff seems to have started the construction without obtaining necessary permission from the Municipal Corporation. It recorded a finding that it is for that reason, the bank insisted not to go further with the construction and asked him to stop the work. It observed that there was breach of contract and that breach was committed by the plaintiff and not by the defendant Bank. It found from the pleadings and evidence on both sides that the plaintiff had sold out the plaint schedule property and PW.3 purchased the same under registered sale deed dated 27.09.2006 and thereafter he also sold out the property to others. After assessment of the evidence, it is stated that excavation and other works that were carried out on the plaint schedule site by the plaintiff did not result in any damage to the plaint schedule site and the plaintiff did not suffer any loss and he had sold out his property without suffering any loss. With reference to the expenditure stated to have been incurred by the plaintiff, after furnishing reasons, it recorded that the evidence adduced was not satisfactory. The damage claimed is incorrect. Thus, it held that plaintiff failed to prove loss and the damages sustained by him. Accordingly, it dismissed the suit. Aggrieved by it, plaintiff preferred this appeal. In the memorandum of grounds of appeal, it is urged that: -
Dr. VRKS, J
• The impugned judgement failed to weigh the evidence appropriately and failed to appreciate proper probabilities in accordance with the law.
• It committed grave errors in dismissing the suit.
• The impugned judgement of the trial court clearly shows discussion of unnecessary aspects by the trial court and clearly missing out in addressing actual dispute between the parties.
• It failed to consider Exs.A1 to A17 appropriately.
• That the evidence on record indicates that the bank officer visited the work site and observed that the appellant/ plaintiff had carried out certain works for digging the pits.
• For digging pits, approved municipal plan was not required. The pits were dug, submersible water motor was installed for the purpose of carrying out the works of the construction of the building and all that works did not require any approved municipal plans but the trial court negatived the claim of the petitioner on the erroneous assumption of want of approved municipal plans.
Dr. VRKS, J
• Under Ex.A7 and A8, plaintiff had paid fees to the municipality for obtaining sanctioned plans and the trial court failed to consider them.
• That the trail court while appreciating the evidence of PW.2 wrongly stated that his evidence did not support the case of the plaintiff while it supported the case of defendants.
• Trial court ought to have accepted the evidence of PW.1 and 2 and the various bills and receipts filed by appellant/ plaintiff and should have awarded the money claimed in the plaint but it erroneously dismissed the suit.
• That the trial court invented new facts which were not part of the pleadings and it referred to certain documents which were never filed by the parties before the court.
For all these reasons, it is seeks to upset the impugned judgement
8. Sri C.Prakash Reddy, the learned counsel for appellant submits that the appellant/ plaintiff applied for sanctioned plans. In terms of section 437 of the Hyderabad Municipal Corporation Act, 1955 if the sanction was not accorded within 30 days and if the plans were not returned, it can be deemed that the sanction was granted and in such an event the appellant was fully within his competence to proceed further with the construction of the
Dr. VRKS, J
proposed building. Learned counsel for appellant cited for this contention, the law laid down by this Court in BOC India Limited V. Municipal Corporation of Hyderabad1.
9. Respondent-Bank made appearance through its learned counsel. Despite several chances, no arguments were advanced for respondents.
The points that fall for consideration: -
1. Whether there was breach of contract between the parties and if so, who was at fault?
2. Whether the appellant/ plaintiff, through evidence disclosed the loss sustained by him and whether the respondents are liable to pay the suit claimed amounts?
3. Whether the impugned judgement of the trial court is erroneous on facts or law?
POINT Nos.1, 2 and 3: -
10. Plaintiff claims to own the plaint schedule property. Ex.A11 is certified copy of registered sale deed dated 04.09.2000. Ex.A16 is the certified copy of registered sale deed dated
Manu/AP/0782/1996/1996(1) ALT 185
Dr. VRKS, J
17.08.1998. It is under these two documents, he acquired ownership over the plaint schedule property. On this aspect defendants have not raised any contest.
11. In the plaint, it is stated that the defendant Bank intended to establish SSI branch and was looking forward for a premises and the written statement of the defendant also admits of the same.
12. Between the plaintiff and the defendant there were negotiations and the essence of it was that the plaintiff would construct a building in his own plaint schedule property and the defendant agreed to take it on lease. In proof of it t, there is Ex.B1 filed by the defendant. Under this document, plaintiff laid his financial bid in the format provided by the bank whereunder rate per square feet on the carpet area was fixed at Rs.10/-. The other terms of the lease are also available there. There is also Ex.B2 whereunder a technical bid was filed by the plaintiff with the defendant. This refers to the details and the quality of the premises that was to be offered by the plaintiff to the defendant. Both these documents contain the signatures of plaintiff. During cross-examination, plaintiff as PW.1 verified them and admitted that they bear his signatures. Then there is Ex.A1. This is a letter dated 24.03.2005 addressed by the defendant bank to the plaintiff/ appellant. Subject matter of the letter is about construction of new premises for SSI branch at Kallur. It reads that the bank is pleased to consider the bid laid by the plaintiff for construction of new premises and for leasing out the same to the
Dr. VRKS, J
bank for housing its SSI branch. It then refers to the terms and conditions. It specified that this lease period would be for a period of 10 years from the date of taking over possession. It further mentions that Rs.7/- per square feet per month for first 5 years would be the rent. For the next 5 years, it would be enhanced by 20%. It mentioned that the owner of the premises had to execute construction agreement and for that purpose a copy was also enclosed. Be it noted, the copy of the format is not annexed to this document. In paragraph No.6 at page 3 of the written statement of the defendant it is averred "the plaintiff executed the requisite documents to confirm the offer of the defendants to construct the building.....". This was spoken to by DW.1 also. Thus, in accordance with what is mentioned in Ex.A1 letter of the bank the needed construction agreement was entered into between the parties. It is a matter of importance to note that neither party filed the said construction agreement before the trial court or here. Be that as it may. Ex.A1 further refers that the lease deed would be executed and registered at the time Bank takes over the possession. It also states that the premises and strong room shall be constructed as per Bank specifications and as per the approved plan of the municipality. Then it is mentioned that furnishing works at new premises is to be taken up early so that minimum time is spent to occupy the premises after taking possession. This Ex.A1 makes clear that between the parties the necessary details stood settled and the contract stood executed.
Dr. VRKS, J
13. A month thereafter, defendant Bank issued Ex.A2 letter dated 26.04.2005 to the plaintiff. Under this letter the bank mentioned that they enclosed the drawings and layout plan and specifications for the proposed SSI branch and advised the plaintiff to start the construction of the building at the earliest complying to the specifications and the plan layout enclosed therewith. Though, it is mentioned in Ex.A2 that it is annexed to Ex.A2, they are not exhibited as they are not annexed to Ex.A2. Be it noted that neither party produced copies of those drawings and layout plan and the specifications. Be that as it may. This letter in Ex.A2 gives clear instruction to the plaintiff to start the construction. It goes without saying that the construction should be in accordance with the needs of the bank which include that the proposed construction should be completed in accordance with the specifications and drawings given by the defendant.
14. Having received Ex.A2 letter dated 26.04.2005, it is averred in the plaint and PW.1 deposed that he commenced his work of construction from May, 2005. That he embarked upon this project is a fact that is seen through the evidence of PW.1. Further, there is evidence of a civil engineer who testified as PW.2 and he said that plaintiff approached him telling him that he agreed to construct a building enabling the defendant Bank to establish its branch thereon and requisitioned his services. PW.2 said that in accordance with the request made by the plaintiff, he started looking after the construction works which commenced from May,
Dr. VRKS, J
2005. Both witnesses/ PW.1 and 2 said that the plaint schedule site consists of black soil and had to be dug up and accordingly they dug it up to a depth of 6 feet. They further deposed that as the water is required for the purpose of construction, they dug a borewell and installed an electric submersible motor. They also said that the required sand, cement, iron and stones were procured and stocked at the site. They further said that the excavation work was done till October, 2005. Ex.A3 is a cash bill dated 08.10.2005 issued by authorized dealer for Texmo industries indicating that plaintiff purchased submersible motor worth Rs.12,026/-. Ex.A4 is a cash bill dated 08.10.2005 issued by Sree Vasavi Agencies showing purchase of pipes and certain items by the plaintiff worth Rs.45,100/-. There is Ex.A5 dated 16.08.2005 issued by V.J. Associates, Architects, Interior Designers and Engineers. It is a cash bill given for excavation work done in the plaint schedule property and it listed out seven works carried by it and put together their worth is Rs.1,57,180/-. It stated that the said money was received by them from the plaintiff. All this evidence go to show that certain works on the plaint schedule property were done by the plaintiff in pursuance of Ex.A2 request of the defendant to commence the construction of the building.
15. Plaintiff as PW.1 said that the officers of the defendant had even inspected the site and noticed the progress of the work. It further said that all of a sudden in October, 2005, the defendant
Dr. VRKS, J
called upon the plaintiff and told him that they could not open their branch in the proposed building. Therefore, he stopped further work. Thus, after October, 2005, he did not carry out further work. According to plaintiff, he had to stop the work because of defendant who said that it would not open its branch in the said building. It is here the controversy has erupted. In paragraph No.7 at page 4 of its written statement defendant denied these allegations. In the preceding and subsequent paragraphs defendant pleaded that the plaintiff failed to obtain approved municipal plans and the defendant was not prepared to occupy a building that do not conform to the standards prescribed by the RBI and that do not conform to approved building plan. Thus, by inference, it admits that in October, 2005, plaintiff stopped his work and he had to stop his work because an objection was raised by the defendant that he was trying to construct a building without approved municipal plans and without adhering to the specifications prescribed by the defendant Bank. DW.1/ the branch manager of the bank testified on behalf of defendant Bank. He said that he was not a witness to any of the facts and he was giving his evidence based on the record. In his cross- examination, he said that he never visited the plaint schedule site and never verified what was the work carried out there. He also said that he had no personal knowledge of the terms and conditions between the parties about construction of this building. He further said that he never verified Ex.A series bills and challans exhibited by the plaintiff in his evidence. He admitted the
Dr. VRKS, J
truthfulness and correctness of Ex.A1 and A2 letters addressed by the bank to the plaintiff. He further said that except Ex.B1 and B2, he had no other record to say anything in support of the contentions raised by the defendant. He further said that he does not know the date on which bank gave instructions to the plaintiff and asked him not to proceed with further construction. The sworn evidence of PW.1 and 2 that they did certain works on the plaint schedule site and the plaintiff incurred certain expenditure remained undisputed through the evidence of DW.1 as he did not know anything about it and he did not verify on ground whether there was any work done or not and he did not even verify the evidence presented in the court through bills etc., so as to say whether they were genuine or not. In that view, the plaintiff through evidence demonstrated his case as true making it clear that the plaintiff incurred expenditure that was referred in the plaint.
16. The fact that the work was done for some time and was stopped thereafter is a proved and established fact. Plaintiff commenced his work only after he received Ex.A1 and A2. Thus, on written instructions he commenced his work. Defendant alleges certain violations on part of the plaintiff. Therefore, it had to inform him to conform to the standard or to dissolve the contract entered into between the parties. Section 66 of Indian Contract Act, 1872, states that revocation or recession of a contract has to be communicated to the opposite party in the
Dr. VRKS, J
same manner as the law demands for communication of proposals. When the defendant, in writing, instructed the plaintiff to commence the work, it is expected to do the same by a written communication when it wanted the plaintiff not to go further with the work. From the pleadings and evidence on both sides, it is crystal clear that the defendant Bank never issued any letter to the plaintiff explaining its stand with a request to the plaintiff not to go further with the construction in the plaint schedule site. Defendant did not produce the contract between the parties so as to enable the court to know the method of communication of any such revocation and therefore the revocation has to be in the same manner as the proposal and acceptance took place. In the case at hand, proposal and acceptance occurred in the form of letters and law expects similar form of communication through letters asking to stop the work. It is in this context, one had to necessarily agree to what the plaintiff had stated that orally defendant requested to stop the work and he accordingly stopped the work. Thus, the stoppage of work was at the instance of defendant.
17. According to defendants, plaintiff failed to obtain approved building plan and the defendant Bank would not occupy a building that does not conform the needs specified by them and approved municipal building plan. Then the question comes up, whether the plaintiff had applied for approved building plans or not. Ex.A7 dated 16.08.2005 and Ex.A8 dated 06.01.2006 are the challans
Dr. VRKS, J
under which requisite fees was paid by the appellant to the Municipal authorities. PW.1 stated that time was consumed by the defendant in furnishing plans and thereafter canceling them and giving him revised plans. He said that he submitted necessary fees to the Municipality and applied for sanction. It has to be recorded that by the time the suit was initiated until the conclusion of the trial nothing was brought on record as to what had happened to the plans submitted by the plaintiff to the Municipality. In the written statement, there is a specific assertion on part of the defendant that its technical officers visited the site and found that the construction was not in accordance with the sanctioned plans. It states that obtaining sanctioned plans is a pre-requisite for commencement of the work. But none of the technical officer who allegedly visited the site testified before this court. DW.1 who deposed at the trial did not even visit the site. How did anyone say that only by looking at a pit that was dug it could be said that it is not in accordance with the required building plan. The contention of the defendant is that the work should not be commenced without an approved building plan. Having taken such a contention, it is for the bank to demonstrate the same through the contractual terms entered into between it and the plaintiff. It failed to do it. That omission to produce the contractual terms shall lead to an adverse inference to the effect that to commence the excavation of the site and installing a borewell there was no condition precedent for obtaining approved building plan. Therefore, the entire defence raised by the
Dr. VRKS, J
defendant Bank has no strength to stand on a fact. Therefore, the contentions of defendants have to be rejected. The activities carried on by the plaintiff are merely digging the soil and installing a bore well. In essence, the activities so rendered are not forbidden by law. He did all that only acting upon the promise of the bank that it would occupy the building that was to be constructed by the plaintiff. Further, by a written letter or notice, defendant never notified the plaintiff to stop the work despite its pleaded case that its technical officer visited the premises. It indulged in a communication only after it received Ex.A12 notice dated 03.06.2006 from the plaintiff. It gave Ex.A13 reply notice dated 02.07.2006. It does not behove well with the bank.
18. From the record, one would notice a contention on part of the bank that the appellant/ plaintiff failed to carryout the promised work within time. It shall be noticed the pleadings and evidence on both sides are totally silent about any agreed timelines for completion of the work. The written contract between parties was not made part of the evidence by either side so as to notice whether it stipulated any time frame. In such circumstances, it has to be necessarily recorded as provided in Section 46 of the Indian Contract Act, 1872 that the engagement must be performed within a reasonable time. One who contends has to prove. Defendant bank contended violation of timelines. Therefore, it was its obligation to prove it. It failed in proving that. It also failed in showing that the necessary work was not
Dr. VRKS, J
commenced by plaintiff within reasonable time. It further failed to show that the work that was done by the appellant/ plaintiff was done beyond reasonable period. Therefore, the impugned judgment of the trial court in finding fault with the plaintiff in complying the timelines is erroneous.
19. The discussion made above make it very clear that it is at the behest of the defendant Bank the plaintiff commenced to construct a building and accordingly he dug up the land and installed a borewell and stocked some material for progressing with the construction and thereafter the defendant stopped him from proceeding further and that was done without any proved or acceptable reason. Since the work was done by the plaintiff, as requested under the contract and since there is breach of contract and since this breach occurred because of the defendant the plaintiff laid his claim for the damages and compensation. Between the contracting parties, the contract work had to be stopped only because of the defendant and since the dependent failed to demonstrate the lawfulness of such stopping on its part, the other party to the contractor/ plaintiff/ appellant is entitled to compensation for the loss it sustained. That is the law as one could see from section 73 of the Indian Contract Act, 1872.
20. From the evidence, one would see, the appellant spent Rs.1,93,106/- towards the works that were done. That claim is proved through the evidence of PW.1 and 2 and Exs.A3, A4 and A5. PW.1 and 2 deposed that since the work was stopped there
Dr. VRKS, J
was no further purpose to construct a building to be utilised by the bank and therefore the pit has to be refilled. It is in this regard, there is evidence of PW.3 and also Ex.A6 dated 16.08.2005 to the affect that for filling up the excavated trench it would cost about Rs.85,750/-. Plaintiff also produced Ex.A17/ stamped receipts showing that he had to expend Rs.1,00,000/- for closing the pit. In the plaint, he claimed Rs.85,750/- for this purpose. Therefore, put together, towards actual expenditure incurred, appellant is entitled to recover Rs.2,78,856/- (1,93,106/- +85,750/). Be it noted that the plaintiff did what all he could do to mitigate the loss consequent on the breach. He said that the sand, cement, iron that he stocked up for this work were expended by him for some other works. Therefore, one shall not say that plaintiff is avarice.
21. Appellant also seeks Rs.3,00,000/- as compensation for loss of reputation. Be it noted that plaintiff has not laid a claim for compensation for breach of contract on the ground he suffered loss in his earnings because of breach committed by defendant. He only claims damages for loss of reputation as he had to stop the construction of the building for the bank. It has to be said that a builder's reputation would be affected adversely if building is not constructed is hardly a reason in the facts and circumstances of this case. He is a contractor by profession and does real-estate business. As per his own statements given in the court as PW.1, the property did not suffer any further loss is clear from the fact
Dr. VRKS, J
that he had sold it to PW.3 without any loss and PW.3 further sold it to others. It is not the case of the plaintiff that there was any deterioration in the value of the property because of the work he carried out on it. Section 73 of the Indian Contract Act provides that in estimating loss or damage arising from a breach of contract the means which existed of remedying the inconvenience caused by the non-performance of the contract must be taken into account. It further states that compensation is not to be given for any remote and indirect loss or damage sustained by reason of the breach. Tested by those principles, the loss of reputation and damages claimed has to be held as remote and indirect loss. Therefore, appellant is not entitled for such unsubstantiated and unsustainable part of the claim.
22. The view taken by the trail court is erroneous on the facts established before it. It is a civil case and the disputed facts are to be proved or disproved through evidence. Preponderance of probabilities is based on evidence. Despite the fact that the defendant did not produce any worthwhile evidence demolishing the facts demonstrated by the plaintiff through his evidence, the trial court refused to grant even those expenses actually incurred. Its conclusions are against the facts and the contentions available on record. The reason that impelled the trial court to disallow the suit claim was hinged on absence of municipal plans. Be it noted that the evidence produced and the challans filed in the form of Exs.A7 and A8 do indicate plaintiff applying for approved plans.
Dr. VRKS, J
Municipality could either approve them or disapprove them. There is nothing on record showing that it disapproved them. There is also nothing on record that it approved them. If neither of them happened one would go by what the law says. In the ruling that is referred earlier, it was laid down that after lapse of 30 days, it is deemed that plans were approved. Nothing contrary is shown either to the trial court or to this court in that regard. Moreover, defendant failed to demonstrate at the trial that by looking at a trench or a pit in a site, it is able to say that the proposed construction is not in accordance with the standard specified by it to the plaintiff. Therefore, there was no material before the trial court to hold that the works that were done by the plaintiff were against contractual terms or against the submitted plans. It is seen that the contention of the defendant that obtaining approved municipal plans is a pre-requisite even to dig up the site and install a bore well is not proved. In such circumstances, there was no justification for the trial court in not granting that expenditure to the plaintiff. This Court cannot sustain the impugned judgment to the extent of its failure to grant the actual expenditure incurred. Trial court is right in not granting damages for loss of reputation as it failed to approach the dispute in proper perspective.
23. In summation, it has to be said that there was a breach of contract and that the breach was on part of defendant/respondent and the appellant/ plaintiff is entitled to a part of the suit claim only. Accordingly, all these points are answered.
Dr. VRKS, J
24. In the result, this appeal is allowed. Consequently, judgment dated 06.01.2009 of learned Additional Senior Civil Judge, Kurnool in O.S.No.288 of 2006 is set aside. The claim of the appellant/ plaintiff in O.S.No.288 of 2006 is allowed in part. The plaintiff/ appellant is entitled for Rs.2,78,856/- with 12% interest per annum over the said sum from the date of suit till the date of this judgment and thereafter at 6% interest per annum till realization. Appellant is entitled to proportionate costs all throughout.
As a sequel, miscellaneous applications pending, if any,
shall stand closed.
_____________________________ Dr. V.R.K.KRUPA SAGAR, J Date: 18.06.2024 Dvs
Dr. VRKS, J
THE HON'BLE JUSTICE Dr. V.R.K.KRUPA SAGAR
Date: 18.06.2024
Dvs
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!