Citation : 2024 Latest Caselaw 1217 AP
Judgement Date : 14 February, 2024
1
NJS, J
WP_1300_2024
IN THE HIGH COURT OF ANDHRA PRADESH::AMARAVATI
THE HON'BLE SRI JUSTICE NINALA JAYASURYA
WRIT PETITION No.1300 of 2024
Between:-
Braithwaite and Co. Ltd., M/s Cognition
Projects Pvt. Ltd., Consortium, 5 Hide
Road, Kolkata-700043 Rep. by its
Authorized Person Mr Sundara Nanda
Barman S/o Ashutosh Barman, Aged
about 43 years R/o D.No.220/1. Raipur
Road. Regent Estate. Kolkata. West
Bengal.
.... Petitioner
And
Union of India, Rep. by its Chairman and
CEO, Railway Board, Room No.256A, Rail
Bhavan, Raisina Road, New Delhi, India
and others
.... Respondents
Counsel for the Petitioner : Mr.C.V.Mohan Reddy, Senior
Counsel, assisted by
Mr.C.Prakash Reddy.
Counsel for the Respondents: Mr.B. Narasimha Sharma,
Additional Solicitor General,
assisted by Mr. Jupudi V.K.
Yagna Dutt.
ORDER:
This Writ Petition is filed, inter alia, to declare the order
of the 4th respondent - Chief Project Manager, East Coast
Railways, Waltair, in terminating the contract of "Major Up-
gradation of Visakhapatnam Railway Station of East Coast
NJS, J WP_1300_2024
Railway on Engineering, Procurement and Construction (EPC)
mode as arbitrary, illegal, without power or authority and
suffers from total non-application of mind and in violation of
Article 19 (1) (g) of the Constitution of India and to
consequently set aside the same.
BRIEF FACTS:
2) The relevant facts, as per the affidavit filed in support of
the Writ Petition, are, in brief, set out as under:
3) The 2nd respondent-The Rail Land Development Authority
issued a Request For Proposal (RFP) vide RFP Notice dated
14.06.2022, inviting proposals through e-tendering on single
stage two cover bidding system from interested eligible bidders
as per the conditions of bid documents for "Major UP-Gradation
of Visakhapatnam Railway Station of East Coast Railway on
Engineering, Procurement and Construction (EPC) Mode". M/s.
Braithwaite & Co. Ltd., (A Government of India Undertaking),
whose administrative control was taken over by the Ministry of
Railways from Ministry of Heavy Industries on 06.08.2010 and
M/s. Cognition Projects Pvt. Ltd., formed a consortium called
M/s. Braithwaite & Co. Ltd., and M/s. Cognition Projects Pvt.
Ltd., (Consortium) - M/s Braithwaite & Co. Ltd., as the lead
NJS, J WP_1300_2024
member of the said consortium, participated in the tender
process and emerged as selected bidder. Accordingly, a Letter
of Acceptance (LoA) was issued on 14.09.2022 specifying that
the period of the construction is 36 months from the
Appointed Date. The petitioner in terms of the LoA furnished
Performance Security of Rs.11,66,73,024/- on 07.10.2022 and
thereafter the 2nd respondent, on behalf of Her Majesty, the
President of India, entered into EPC Agreement
No.RLDA/2022/CA-04 with the petitioner Consortium on
15.11.2022.
4) The Agreement value is Rs.388,91,00,790/-. As per the
Agreement, the contract work has to be completed in
accordance with the specifications and drawings and
conditions of the Contract on or before 29.11.2025 and the
works shall be maintained for a period of 18 months from the
date of issue of completion certificate. After issuance of Letter
of Acceptance, joint site inspections were conducted on
19.09.2022, 16.10.2022 and 18.10.2022 and during the said
visits, Railway Officials instructed some major modifications in
the already approved Master Plan and the petitioner addressed
a letter dated 28.10.2022 for confirmation of the modifications.
NJS, J WP_1300_2024
On 03.11.2022 the respondents addressed a communication,
inter alia, stating that the Master Plan prepared also contain
provision for Additional two (02) railway tracks and one (1)
platform.
5) In view of the same, the scope of the work is revised
significantly as the area of the Air Concourse to be built as well
as the length of the Foot Over Bridge (FOB) is increased to a
considerable magnitude, resulting in enhancement in the cost
of construction. It also resulted in preparation of Master Plan
afresh and the Revised Master Plan was approved by the
respondents on 20.04.2023.
6) In the meanwhile, the respondents issued 15 days Notice
on 24.03.2023 for termination of contract alleging failure on
the part of the petitioner in achieving the project milestones.
The petitioner consortium submitted its reply on 05.04.2023
and the respondents did not take any further action.
Subsequently, the 4th respondent issued a Notice dated
06.11.2023 to which the petitioner submitted reply dated
16.11.2023. Thereafter, through the impugned proceedings
dated 26.12.2023, 4th respondent terminated the Contract /
NJS, J WP_1300_2024
Agreement. Challenging the same, the present Writ Petition is
filed.
PETITIONER'S SUBMISSIONS:
7) Mr. C.V.Mohan Reddy, learned Senior Counsel, made
elaborate submissions with reference to various Articles /
Terms of the Agreement.
8) Learned Senior Counsel submits that to the initial
showcause notice dated 24.03.2023, the petitioner submitted
detailed replies and satisfying with the explanation no further
action was taken by the respondents and the petitioner was
merely asked to expedite the works. He submits that though
in terms of the Agreement, the respondent authority shall
provide 'Right of Way' (RoW) to the contractor / petitioner and
provide free access for the execution of the works, the same
was not complied with. On the other hand, stating that there
are defaults on the part of the petitioner, another Notice dated
06.11.2023 was issued and a detailed reply, setting out all the
relevant aspects, was submitted on 16.11.2023. Learned
Senior Counsel submits that the 4th respondent without
appreciating the reply/explanation submitted by the petitioner
terminated the contract in an arbitrary manner. In elaboration
NJS, J WP_1300_2024
and with reference to the obligations of the Authority as
provided under Article 4 of the Agreement, he submits that in
terms of Clause 4.1.3, the Authority shall provide the
petitioner the 'RoW' in accordance with Clause 8.2 and all
forest clearances as required under Clause 4.3. He submits
that in terms of Clause 4.3, the petitioner prepared the
Environment Management Plan (EMP) and submitted for
approval of the Authority on 20.02.2023 and as seen from the
material filed along with Memo dated 10.02.2024 the same
was approved by the authority on 13.11.2023. He submits
that in the absence of approval of EMP, the petitioner cannot
proceed with the work and, therefore, there was no occasion to
the petitioner to proceed with the works.
9) Quoting Article 9 of the Agreement and Clause 9.4, which
deals with 'Felling of trees', he further contends that it is the
obligation of the Authority to remove the trees, which causes
obstruction to the project works and as seen from the material
on record there are more than 100 trees causing obstruction to
the works and only in April, 2023 steps were taken for removal
of the trees. Learned Senior Counsel further submits that in
the process of approving General Arrangement Drawing (GAD)
NJS, J WP_1300_2024
/ Master Plan so many changes were suggested by the
respondents and thereby the scope of work changed. Referring
to Article 13, more particularly Clause 13.2, which deals with
the Procedure for Change of Scope, learned Senior Counsel
submits that no Notice was issued as contemplated under
Clause 13.2.1, but the Contractor was directed to comply with
Clause 13.2.2. While contending that the authorities want to
put the blame on the petitioner without complying with the
Agreement conditions, he submits that detailed GAD / Master
Plans were submitted on 09.12.2022, but the same were
approved on 20.04.2023 as is evident from Ex.P.8. He submits
that all these aspects coupled with the material on record
would clearly establish that there are no defaults on the part of
the petitioner and the authorities to cover up their lapses had
issued notices as if the petitioner is at fault in proceeding with
the works.
10) Referring to Appointed Date as provided in Article 1, he
contends that the Appointed Date shall be taken as the date
on which the authority has provided the Right of Way (RoW)
and forest clearances of the site for the project inconformity
with the Clauses 4.3 and 8.2, that the respondent's
NJS, J WP_1300_2024
assumption that the appointed date means 15 th day of the
Date of Agreement i.e., 30.11.2022 is incorrect. He submits
that in the light of the undisputed material on record, which
goes to show that the revised Master Plan (GAD) was approved
on 20.04.2023, felling of trees was completed on 20.05.2023,
and the Environment Master Plan was approved on
13.11.2023, the Appointed Date shall be reckoned from
anyone of the said dates and if the same is taken into
consideration, there is no breach of milestones by the
petitioner.
11) Referring to Clause 10.4 of Article 10, which deals with
Extension of time for completion, learned counsel further
contends that the delay in providing the Right of Way,
Environmental / forest clearance, approval of GAD (Master
Plan) and change of scope of work are attributable to the
respondents and the petitioner is therefore entitled for
extension of time. He submits that the 4th respondent without
even applying his mind to the relevant clauses of the
Agreement had terminated the contract and the action under
challenge smacks of arbitrariness. While pointing out that even
as per the respondents' counter there is no change in the
NJS, J WP_1300_2024
scope of work, that there are no disputed questions of facts
and stating that the arguments at present are confined to the
extent of non-compliance of the Agreement conditions by the
respondents, learned Senior Counsel submits that the action
of the 4th respondent in treating the appointed date as
30.11.2022 is incorrect and this Court in exercise of
jurisdiction under Article 226 of the Constitution of India can
interfere in the matter.
12) Quoting Article 21 of the Agreement, which provides for
termination of contract, the learned Senior Counsel submits
that in the notice issued to the petitioner there is no mention
as to whether there was any breach of milestones / milestones
not achieved and further that no Notice under Clause 21.1.1(c)
granting 45 days time for achieving the project milestones was
issued. He submits that the action of the 4th respondent is,
therefore capricious, illegal and amounts to violation of
principles of natural justice. Learned Senior Counsel referring
to Memo dated 07.02.2024 further submits that in view of the
suggestions made by the respondents to the Master Plan after
a lapse of long time, the Authority Engineer (S.M. Private Ltd.,)
submitted the plans for approval of the 4th respondent on
NJS, J WP_1300_2024
11.10.2023 and the approval has not been received so far. He
submits that despite the lapses on the part of the respondents,
the petitioner was proceeding with the work. However, in
violation of Agreement conditions, without application of mind,
the Agreement in question was terminated. He submits that
the action of the 4th respondent amounts to disproportionate
punishment and even on that ground the interference of this
Court in exercise of powers under Article 226 of the
Constitution of India is called for.
13) Learned Senior Counsel in support of his contentions
placed reliance on the following judgments:
i) Sahara India (Firm) Lucknow v Commissioner of Income Tax, Central - 1 and Another1;
ii) Kisan Sahkari Chini Mills Ltd. v. Vardan Linkers 2;
iii) M.P. Power Management Co. Ltd. v. Sky Power Southeast Solar India (P) Ltd.,3
iv) State of U.P. v. Sudhir Kumar Singh4
14) Learned Senior Counsel submits that had the
respondents granted extension of time in terms of the
Agreement conditions, the petitioner would have proceeded
(2008) 14 SCC 151
(2008) 12 SCC 500
(2023) 2 SCC 703
(2021) 19 SCC 706 = 2020 SCC OnLine 847
NJS, J WP_1300_2024
with the works. However, the respondent authority invited for
fresh tenders in respect of the works in question at escalated
estimated cost of Rs.433,56,19,990/-, which results in burden
on the exchequer. Making the said submissions, the learned
Senior Counsel seeks the reliefs by setting aside the
proceedings under challenge.
RESPONDENTS' CONTENTIONS:
15) Refuting the said contentions, Mr. B. Narasimha Sarma,
learned Additional Solicitor General of India argued the matter
at length. Drawing attention of this Court to Ex.P1 i.e., the
impugned Proceedings dated 26.12.2023 and the references
therein, he submits that before resorting to action of the
termination notices with regard to the poor progress of the
work by the petitioner were issued, joint meetings were held
with regard to progress of works and ultimately a final
showcause notice was issued on 06.11.2023 mentioning as
many as 43 defaults / lapses on the part of the petitioner. He
submits that after considering reply / explanation of the
petitioner, the impugned termination proceedings have been
issued, meeting all the points in reply by the petitioner. He
submits that the EPC is a self contained code, the terms and
NJS, J WP_1300_2024
conditions agreed therein are binding on both sides and the
action of the 4th respondent in issuing termination proceedings
is in accordance with the contractual terms.
16) Referring to Article 24 which provides for Dispute
Resolution and clauses contained therein, he submits that as
per Clause 24.1.1 all disputes and differences of any kind
whatsoever arising out of or in connection with the contract,
whether during the progress of the work or after its completion
and whether before or after the determination of the contract,
shall be referred by the Contractor / petitioner to the Authority
for conciliation of disputes at the first stage and in the event,
the same are not settled through conciliation, the same can be
referred to Dispute Adjudication Board (DAB) under Clause
24.2, which is the second stage. While referring to Clause
24.2.14, which contemplates that the parties shall not
approach any Court of Law for settlement of such disputes or
differences, unless an attempt has first been made by the
parties to settle such disputes or differences through DAB, he
further submits that a third level mechanism is provided for
settlement of disputes or differences by 'Standing Arbitral
Tribunal' under Clause 24.3. He also reference to Clause
NJS, J WP_1300_2024
24.3.18, which provides that in case of any dispute or
differences, resulting in Court cases between Contractor &
Authority, the jurisdiction shall be of Courts at Delhi only. Be
that as it may. He submits that the termination of the
Agreement is in terms of Clause 21.1 and that the same is
legal and valid. He contends that the jurisdiction of the Writ
Court under Article 226 of the Constitution of India can be
invoked only in those circumstances, where there is violation
of principles of natural justice, the authority acts without
jurisdiction / incompetent authority or the statutory
provisions are violated. He submits that the case on hand
would not fall in any one of the exceptions and all the disputes
can be examined / raised before the Dispute Redressal
Mechanism. He also submits that there is no whisper in the
affidavit as to why the alternative remedy is not effective.
While contending that the matter involves examination of
disputed questions of facts, based on the terms of the
Agreement / contract, he submits that the petitioner cannot be
permitted to seek relief in a proceeding under Article 226 of the
Constitution of India for enforcement of its contractual rights
or adjudication of disputed facts.
NJS, J WP_1300_2024
17) While contending that the Appointed Date would be
30.11.2022 i.e., fifteen days from the date of Agreement dated
15.11.2022, the learned counsel submits that pursuant to
LOA, Right of Way was given to the petitioner on 19.09.2022
and again on 07.12.2022 in terms of Clause 8.2.1, that as per
Clause 4.3 an obligation is cast on the petitioner to prepare the
Environment Management Plan (EMP) and forest clearance is
not required as mentioned in Annexure-IV Schedule - A of the
Agreement (Page No.447) and the same cannot be a reason to
postpone the Appointed Date. Referring to the Termination
Proceedings, he submits that the petitioner has not achieved
various project milestones which have an adverse effect on the
execution of works, the learned counsel seeks to justify the
said proceedings that the same are in conformity with the
terms and conditions of the Agreement. He submits that the
Appointed Date as mentioned in the Show Cause Notice is in
tune with the Agreement conditions, that EPC is a special
contract involving technical matters and in terms of Clause
3.1.1, the total obligation is on the petitioner / contractor to
perform all the works in respect of the Project in question. He
submits that as the petitioner had committed defaults, two
NJS, J WP_1300_2024
Notices were issued pointing out the same and after adverting
to each and every submission of the petitioner in the reply to
the Show Cause Notice, the 4th respondent issued the
Termination Proceedings by recording findings. He contends
that the scope of Judicial Review under Article 226 of the
Constitution of India is limited to the extent of examination of
decision making process only and the Court would not sit over
the decision of the decision making Authority. While stating
that the time is essence, convenience of public is of the utmost
consideration and the impugned termination of the
proceedings after due opportunity to the petitioner were
passed twelve months after entering into the Agreement, he
submits that the decision making process in the present case
is in compliance with the principles of natural justice, fair play
and repeated opportunities to the petitioner, pointing out the
lapses shows that there is no arbitrariness as alleged by the
petitioner. He further submits that it is also not a case of
malafides and in such circumstances, it is not a fit case to
exercise the jurisdiction of this Court under Article 226 of the
Constitution of India.
NJS, J WP_1300_2024
18) Referring to the contentions with regard to the Appointed
Date, approval of environmental plans, felling of tress and
approval of GAD / Master plan, he submits that each and
every default / lapse was elaborately considered by the 4th
respondent and detailed reasoning / finding was recorded in
the impugned proceedings. He submits that the decision of
termination is not arbitrary or irrational, but supported by
ample material in conformity in terms of the Agreement and
there is no perversity. He submits that the project is of great
importance, all the works are time bound and most of the
preliminary works are not even started by the date of the Show
Cause Notice, which was issued, eleven months after entering
into the Agreement. He submits that by the date of issuance of
Show Cause Notice, the petitioner has executed only 1.1% of
the works as against the target of 33%. He submits that
number of communications were addressed to the petitioner
and as there is a failure on the part of the petitioner, the
Agreement has been terminated. He submits that it is an
administrative decision in terms of the Agreement conditions
well supported by reasons and warrants no interference by this
Court.
NJS, J WP_1300_2024
19) Adverting to the contention with regard to change of
scope of work, the learned Senior Counsel referring to a
Communication dated 03.11.2022(Ex.R4) submits that the
Master plan prepared also contains provision for additional
two tracks and End platform. While stating that as
communicated to the petitioner vide Letter dated
15.11.2022(Ex.R5) that detailed procedure for execution of
works not covered under the scope of EPC will be dealt with in
terms of Article 13, he submits that the petitioner was not
showing progress even at the elementary stage of works and
repeated notices were issued with regard to poor progress of
works, as is evident from the impugned proceedings. He
submits that there is no dispute that the jurisdiction of the
Court under Article 226 of the Constitution of India is not
totally barred and can be exercised when action is challenged
on the grounds of malafides, arbitrariness, irrationality,
favouritism or perversity, but interpretation of the clauses in
the Agreement cannot be undertaken. He contends that the
Appointed Date cannot be substituted under judicial review.
20) The learned Additional Solicitor General of India while
stating that there is no dispute with regard to the propositions
NJS, J WP_1300_2024
laid down in the decisions relied on by the learned Senior
Counsel for the petitioner, submits that the said decisions are
distinguishable on facts and in the present case principles of
natural justice are complied with by issuing Show Cause
Notices and the action of the 4th respondent is in exercise of
powers in terms of the Agreement, not arbitrary or capricious
as contended on behalf of the petitioner. He submits that the
escalation in the Project Cost is because of levy of 18% GST as
against 12% GST when the Agreement in question was entered
into and also in view of the variance of costs. Making the said
submissions, the learned counsel submits that there are no
merits in the case warranting interference by this Court under
Article 226 of the Constitution of India.
21) Mr.C.V.Mohan Reddy, learned Senior Counsel made
submissions, in reply, reiterating the earlier contentions.
22) This Court has considered the submissions made and
perused the material on record.
23) At the outset, it may be pertinent to state that as the
disputes in relation to the Project in question which is of great
public importance are between the petitioner consortium,
which is led by M/s.Braithwaite & Company Limited, a
NJS, J WP_1300_2024
Government of India undertaking and the East Coast Railways,
on the other hand, this Court initially expressed a view that
the same can be resolved by the parties by mutual
discussions. As seen from the Minutes of the Meeting dated
05.02.2024 which are placed for perusal of this Court by the
learned Additional Solicitor General of India, it is discernable
that the petitioner as well as the respondents are attributing
lapses / delays / defaults against each other, which indicates
that there are no chances of amicable settlement. Be that as it
may.
24) The learned Senior Counsel for the petitioner, inter alia,
contended that the impugned Termination Proceedings are
violative of principles of natural justice, suffers from non-
application of mind and smacks of arbitrariness. That if the
Appointed Dates are reckoned from any of the three dates i.e.,
20.04.2023 or 30.05.2023 or 13.11.2023, there is no breach of
milestones. There are no disputed questions of facts involved
and writ petition can be entertained.
25) On the other hand, the learned Additional Solicitor
General of India had pointed out that notices were issued to
the petitioner from time to time with regard to poor progress of
NJS, J WP_1300_2024
work, two Show Cause Notices were issued setting out the
deficiencies / defaults in execution of the works and thereafter
a detailed order is passed by dealing with all the points in
reply to the notices, that in such circumstances, there is no
violation of principles of natural justice, the Writ Court cannot
sit in appeal over the decision of the decision making authority
/ 4th respondent, Agreement provides for conciliation and
arbitration, matter involves examination of disputed questions
of facts, that the Appointed Date cannot be substituted.
26) On an appreciation of the matter and perusal of the
material, it is discernible that before passing the Termination
Proceedings impugned in the present Writ Petition, opportunity
was afforded to the petitioner and therefore, it is not a case
where the proceedings under challenge are without any notice.
As is evident from the references in the impugned proceedings
and which is not contradicted, notices on different dates were
issued to the petitioner regarding poor progress of work. Thus,
there is compliance with principles of natural justice.
27) Whether poor progress of work is a consequence of not
giving RoW as per the Agreement conditions or due to delay in
seeking or granting approval of plans, whether the petitioner /
NJS, J WP_1300_2024
contractor could as well proceeded with the preliminary works
etc., without approvals, are all matters which involve a deep
probe.
28) That delays are attributable to the Authority and though
the Agreement provides for extension of time, without
application of mind to the Agreement conditions the impugned
proceedings are issued are matters that require examination of
Agreement conditions with reference to factual aspects which
cannot be undertaken by this Court in a proceeding under
Article 226 of the Constitution of India.
29) Though elaborate contentions were raised with reference
to reckoning of Appointed Date either from the approval of
environment plan or felling of tress or the approval of GAD
plans i.e., dated 20.04.2023, 30.05.20223 and 13.11.2023
respectively, in the light of the rival contentions about non-
adherence to the obligations by the respective parties, this
Court is of the opinion that these matters cannot be gone into
as the same fall in the realm of disputes between the parties. It
is also not a case of malafides nor was there any challenge that
the proceedings of the 4th respondent are without jurisdiction.
Suffice to state that by virtue of novation of the Agreement vide
NJS, J WP_1300_2024
Ex.P.37, respondent No.4 has power to terminate the
Agreement. As to whether termination proceedings are justified
or not, involves examination of factual aspects / disputed
questions of fact, which cannot be undertaken in the present
proceedings under Article 226 of the Constitution of India. It
is not in dispute that the Agreement provides for dispute
redressal mechanism at different levels and arbitration in
terms of the Arbitration and Conciliation Act.
30) In State of U.P. & Others v. Bridge & Roof Company
(India) Ltd.5, the Hon'ble Supreme Court was dealing with a
judgment of a Division Bench of the Allahabad High Court,
wherein the dispute relates to certain payments in respect of a
works contract, which the respondent-Company claims are
due to it, whereas the appellant contends that it is entitled to
retain it. The Hon'ble Supreme Court while opining that the
contract between the parties therein is the contract in the
realm of private law, not a statutory contract and it is governed
by the provisions of the Contract Act or, may be, also by
certain provisions of the Sale of Goods Act, inter alia , held that
"any dispute relating to interpretation of the terms and
(1996) 6 SCC 22
NJS, J WP_1300_2024
conditions of such a contract cannot be agitated, and could
not have been agitated, in a writ petition, that it is a matter
either for arbitration as provided by the contract or for the civil
court or as the case may be." The Hon'ble Supreme Court at
Para No.21 further held as follows:
"21.There is yet another substantial reason for not entertaining the writ petition. The contract in question contains a clause providing inter alia for settlement of disputes by reference to arbitration (clause 67 of the contract). The arbitrators can decide both questions of fact as well as questions of law. When the contract itself provides for a mode of settlement of disputes arising from the contract, there is no reason why the parties should not follow and adopt that remedy and invoke the extraordinary jurisdiction of the High Court under Article 226. The existence of an effective alternative remedy - in this case, provided in the contract itself - is a good ground for the court to decline to exercise its extraordinary jurisdiction under Article 226. The said article was not meant to supplant the existing remedies at law but only to supplement them in certain well-recognized situations. As pointed out above, the prayer for issuance of a writ of mandamus was wholly misconceived in this case since the respondent was not seeking to enforce any statutory right of theirs nor was it seeking to enforce any statutory obligation cast upon the appellants. Indeed, the very resort to Article 226 - whether for issuance of mandamus or any other writ, order or direction - was misconceived for the reasons mentioned supra."
NJS, J WP_1300_2024
31) Looking to the facts of the present case and the stand
taken by the petitioner that the delay is occurred at the
instance of the respondents, which is contradicted in the
counter-affidavit by attributing defaults on the part of the
petitioner, this Court is of the view that whether the delays are
due to lapses on the part of the respondents and the
termination is not lawful are matters for adjudication by the
Arbitral Tribunal. In the event, it is found that the delays are
attributable to the respondents, the petitioner can as well be
compensated suitably.
32) Further, the decision of the 4th respondent was rendered
after examination of the explanation with reference to the
several alleged defaults. This Court has no expertise to
examine the same nor expected to do so. As contended by the
learned Additional Solicitor General of India, this Court is
concerned with the decision making process and would not sit
as an Appellate Authority. In view of the Arbitration Clause, it
is not desirable to record any finding or conclusion with regard
to the contention that the impugned Termination Proceedings
smacks of arbitrariness, vitiated by non-application of mind or
violative of terms of the Agreement conditions.
NJS, J WP_1300_2024
33) The Hon'ble Supreme Court in Kerala State Electricity
Board & Another v. Kurien E.Kalathil & Others 6 was dealing
with an Appeal against the orders of the High Court and with
regard to contention about the maintainability of the writ
petition opined that "interpretation and implementation of a
Clause in a Contract cannot be the subject matter of a writ
petition and that "if a term of contract is violated, ordinarily
the remedy is not the writ petition under Article 226 of the
Constitution of India. That is a matter for adjudication by a
Civil Court or in arbitration if provided for in the contract."
The Hon'ble Supreme Court, however, in the facts of the said
case while holding that alternative remedy is no longer
efficacious due to lapse of time, modified the order of the High
Court by reducing the interest.
34) There can be no second opinion that violation of
principles of natural justice or public law element would justify
the exercise of powers under Article 226 of the Constitution of
India. It all depends upon the facts of each case as to whether
having regard to the scope of dispute to be resolved, the Court
will still entertain the petition.
(2000) 6 SCC 293
NJS, J WP_1300_2024
35) In M.P.Power Management Company Limited v. Sky
Power Southeast Solar India Private Limited7, on which
reliance was placed by the learned Senior Counsel for the
petitioner, the Hon'ble Supreme Court was dealing with the
decision of High Court, wherein the writ petition challenging
the order of termination of power projects agreement was
allowed. The Hon'ble Supreme Court while elaborately dealing
with the scope of judicial review of State action in a matter
arising from non-statutory contract in the attending facts and
circumstances of the said case, was not inclined to interfere
with the decision of the High Court. The Hon'ble Supreme
Court while recording its conclusions at Para No.82.1 that the
writ jurisdiction is a public law remedy and a matter which lies
entirely within a realm of affairs of public body, may not lend
itself for being dealt with under the writ jurisdiction of the
Court, at Para No.82.3 held that "the mere fact that relief is
sought under a contract which is not statutory, will not entitle
the respondent State in a case by itself to ward off scrutiny of
its action or inaction under the contract, if the complaining
party is able to establish that the action / inaction is, per se,
(2023) 2 SCC 703
NJS, J WP_1300_2024
arbitrary." At Para No.82.7, the Hon'ble Supreme Court opined
as follows:
"82.7. The existence of an alternate remedy, is undoubtedly, a matter to be borne in mind in declining relief in a writ petition in a contractual matter. Again, the question as to whether the writ petitioner must be told off the gates, would depend upon the nature of the claim and relief sought by the petitioner, the questions, which would have to be decided, and, most importantly, whether there are disputed questions of fact, resolution of which is necessary, as an indispensible prelude to the grant of the relief sought. Undoubtedly, while there is no prohibition, in the writ court even deciding disputed questions of fact, particularly when the dispute surrounds demystifying of documents only, the Court may relegate the party to the remedy by way of a civil suit."
36) The Hon'ble Supreme Court at Para No.82.10 while
opining that "the reach of Article 14 enables a writ court to
deal with arbitrary State action even after a contract is entered
into by the State and wide variety of circumstances can
generate causes of action for invoking Article 14 and the
Court's approach in dealing with the same, would be guided
by, undoubtedly, the overwhelming need to obviate arbitrary
State action, in cases where the writ remedy provides an
effective and fair means of preventing miscarriage of justice
NJS, J WP_1300_2024
arising from palpably unreasonable action by the State", at
Para No.82.11, inter alia , opined as follows:
"82.11............Ordinarily, the cases of termination of contract by the State, acting within its contractual domain, may not lend itself for appropriate redress by the writ court. This is, undoubtedly, so if the Court is duty- bound to arrive at findings, which involve untying knots, which are presented by disputed questions of facts. Undoubtedly, in view of ABL(ABL International Ltd., v. Export Credit Guarantee Corpn.of India Ltd., (2004) 3 SCC
553), if resolving the dispute, in a case of repudiation of a contract, involves only appreciating the true scope of documentary material in the light of pleadings, the Court may still grant relief to an applicant. We must enter a caveat. The Courts are today reeling under the weight of a docket explosion, which is truly alarming. If a case involves a large body of documents and the Court is called upon to enter upon findings of facts and involves merely the construction of the document, it may not be an unsound discretion to relegate the party to the alternate remedy. This is not to deprive the Court of its constitutional power as laid down in ABL. It all depends upon the facts of each case as to whether, having regard to the scope of the dispute to be resolved, whether the Court will still entertain the petition."
37) In view of the self imposed restraints and as the
matter involves examination of disputed questions of facts,
in the considered opinion of this Court, the exercise of
jurisdiction under Article 226 of the Constitution of India,
NJS, J WP_1300_2024
more particularly in view of the availability of arbitration
Clause in the Agreement, is not warranted.
38) M/s.N.G.Projects Limited v. M/s.Vinod Kumar
Jain8 is a case where the Hon'ble Supreme Court was
dealing with an appeal filed against the decision of a
Division Bench of High Court of Jharkhand at Ranchi,
whereby the Order of the learned Single Judge allowing the
Writ Petition was confirmed. The issue relates to awarding
of tender in respect of the works for reconstruction of
Nagaruntari - Dhurki - Ambakhoriya Road. Referring to a
catena of cases relating to Award of tenders and the scope
of interference by the Court, the Hon'ble Supreme Court
while opining that the Writ Court should refrain itself from
imposing its decision over the decision of the employer as to
whether or not to accept the bid of a tenderer, inter alia ,
held that "Courts should be even more reluctant in
interfering with contracts involving technical issues as
there is a requirement of the necessary expertise to
adjudicate upon such issues. The approach of the Court
should be not to find fault with magnifying glass in its
2022 LiveLaw(SC) 302
NJS, J WP_1300_2024
hands, rather the Court should examine as to whether the
decision-making process is after complying with the
procedure contemplated by the tender conditions. If the
Court finds that there is total arbitrariness or that the
tender has been granted in a malafide manner, still the
Court should refrain from interfering in the grant of tender
but instead relegate the parties to seek damages for the
wrongful exclusion rather than to injunct the execution of
the contract."
39) Though the said judgment of the Hon'ble Supreme
Court was rendered against the background of granting of
tenders, this Court is of the opinion that the expressions of
the Hon'ble Supreme Court referring to the various earlier
precedents are guiding factors where the issues involve
interpretation of terms and conditions of the Agreement
entered into between the parties.
40) For the aforegoing reasons and the conclusions
arrived at, the matter involves disputed questions of fact
and interpretation of terms and conditions of the
Agreement. Therefore, this Court is not inclined to exercise
powers under Article 226 of the Constitution of India.
NJS, J WP_1300_2024
41) The writ petition, is, however disposed of, leaving it
open to the petitioner to avail the remedy of arbitration in
terms of the Agreement and raise all contentions, in the
event of which, the same shall be dealt with uninfluenced
by the observations, if any made by this Court. There shall
be no order as to costs.
As a sequel, pending miscellaneous petitions, if any, shall stand closed.
_______________________ NINALA JAYASURYA, J.
Date: 14.02.2024.
Ssv/BLV
NJS, J WP_1300_2024
IN THE HIGH COURT OF ANDHRA PRADESH::AMARAVATI
THE HON'BLE SRI JUSTICE NINALA JAYASURYA
Date:14.02.2024.
Ssv/BLV
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!