           HIGH COURT OF ANDHRA PRADESH :: AT AMARAVATI

      MAIN CASE No.M.A.C.M.A.No.48 of 2019

                            PROCEEDING SHEET

Sl.   DATE                            ORDER                              OFFICE
No.                                                                       NOTE
09) 09.05.2023 BSS, J

                 I.A.No.1 of 2019 in Cross-objections No.19 of
                         2019 in MACMA No.48 of 2019
                     I have heard both sides.      For the reasons
               stated in the affidavit of the petitioner, the delay
               in representing the Cross-objections is condoned.

                                                             ______
                                                               BSS,J
                 I.A.No.2 of 2019 in Cross-objections No.19 of
                         2019 in MACMA No.48 of 2019
                     I have heard learned counsel for the
               petitioner/R3-insurance    company     as    well    as
               learned counsel for the respondents / claimants /

appellants. This petition is filed by the petitioner - insurance company to condone the delay of 89 days in filing the cross-objections in MACMA No.48 of 2019, which was filed by the claimants seeking enhancement of compensation. Now, the contention of the petitioner-insurance company is that they filed cross-objections questioning the quantum of compensation and other grounds which they raised in the cross-objections have to be Contd....

Contn....

considered by the Court. The reason for delay in filing cross-objections is that they received grounds of appeal on 27.02.2019 about filing of MACMA and thereafter they secured required documents and then filed cross-objections, due to administrative constraints, delay occurred.

After considering the contention of learned counsel for the petitioner - insurance company, the delay in filing cross-objections is condoned on condition that the petitioner-insurance company shall deposit a sum of Rs.50,000/-(Rupees fifty thousand only) towards part of compensation amount before the Tribunal within 30 days from today, otherwise, the petition shall stand dismissed without reference to the Court.

______ BSS,J M.A.C.M.A.No.48 of 2019

I have heard learned counsel for the appellant Mr.B.V.Krishna Reddy, as well as learned counsel for R3 - Insurance company Mr.V.Veerabhadrachary.

List the case on 15.06.2023 under the caption of 'judgment'.

______ BSS,J Rns

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter