ORDER:

The petitioner had been awarded the contracts for

taking up "Neeru-Chettu" Programme for Renovation and

Restoration of Bund from KM.5.380 to 5.430 and KM 3.620

to 3.670 of Kandaleru Reservoir in Rapur Mandal, SPSR

Nellore District, vide Agreement No.2EE/2017-18 dated

24.12.2018 supplement No.4EE/2018-19 and Agreement

No.3EE/2017-18 dated 18.07.2017 Supplement

No.3EE/2017-18 dated 15.12.2018. After execution of the

said works, final bills for Rs.7,48,205/- and Rs.4,97,818/-

had been prepared and submitted to the concerned for

payment. As the payment of the said amounts has not been

made by the respondents, the petitioner had approached this

Court, by way of this writ petition.

2. It is the contention of the petitioner that even

though the respondents admitted that the petitioner is

entitled for payment of the aforesaid sums of money, no

payment is being made. The petitioner contends that such

non-payment of money is clearly arbitrary and high-handed

requiring the interference of this Court.

3. This Court, in various orders, including the

judgment of a learned Single Judge of this Court dated

05.10.2021 in W.P.No.10038 of 2021 and batch had taken

the view that such non-payment of dues is arbitrary and that

such dues need to be cleared by the respondents at the

earliest.

4. The learned Government Pleader submits that the

respondent authorities are verifying the claims of the

petitioner and would be in a position to make payment only

after such verification is completed.

5. In view of the aforesaid directions of this Court in

various cases and after hearing the submissions of the

learned counsel for the petitioner, learned Government

Pleader for Irrigation, this writ petition is disposed of with a

direction to the respondents to complete the verification

process within a period of three weeks from the date of

receipt of a copy of this order and thereafter to pay the

amounts due to the petitioner depending upon the outcome

of the verification, within a period of six weeks. It is clarified

that in the event of the verification process not being

completed within the aforesaid period of three weeks, the

respondents shall pay the amounts due to the petitioner,

without insisting upon any further time for verification. It

would also be open to the petitioner to agitate his/her/their

claim for interest, if any payable by the respondents, in an

appropriate forum. There shall be no order as to costs.

As a sequel, pending miscellaneous petitions, if any,

shall stand closed.

____________________________ R. RAGHUNANDAN RAO, J

25.01.2023 RKS

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter