Citation : 2022 Latest Caselaw 9174 AP
Judgement Date : 29 November, 2022
HON'BL SRI JUSTICE U. DURGA PRASAD RAO
AND
HON'BLE SRI JUSTICE T.RAJASEKHAR RAO
C.M.A. No.317 of 2005
JUDGMENT: (Per Hon'ble Sri Justice U. Durga Prasad Rao)
The challenge in this appeal is to the order dated 31.03.2004
in O.P.No.646/1998 passed by the learned Principal District Judge,
Visakhapatnam confirming the award dated 30.01.1998 passed by
the sole arbitrator.
2. The respondent herein is the claimant and the appellant
herein is the respondent before the sole arbitrator. For convenience
sake, they are referred in this appeal as they are arrayed in the
award proceedings.
3. The matrix of the case is briefly thus:
(a) The respondent entrusted construction of UCO Bank
building at Visakhapatnam Steel Plant Township to the claimant,
who is a Contractor. The building was stipulated to be constructed
between September 1991 and February 1993. The claimant
completed the construction in the first week of February 1993 vide
exhibits C16 and C.19 certificates issued by the Bank in this
regard. The value of the work was Rs.19,94,000/- and contractor
was paid Rs.17,71,293.83 ps leaving a balance of Rs.2,22,706.17
ps as mentioned in Ex.C.19. As per agreement, the maintenance
period of the building was for one year i.e., from 08.02.1993 to
08.02.1994.
(b) While so, on 31.03.1994, the respondent Bank instructed
the claimant to execute certain works and they were executed by
him as per the proceedings under Ex.C.21. As those works were
entrusted to him after expiry of the period of maintenance, he
claimed for payment of the extra works. However, the bank
repudiated his claim on the ground that it issued Completion
certificates under Exhibits P15, P16 & P19 and thereafter
contractor cannot make any claim. In view of the said dispute, the
matter was referred to the sole arbitrator Sri J.Rajulu Reddy, Chief
Engineer, Railways (Retd.) and Panel Member of the Indian
Council of Arbitration, Visakhapatnam. Before Arbitrator, the
claimant made 13 claims in his claim statement and interest
separately. Claim No.11 contains sub-heads (a) to (k). The
respondent Bank also made counterclaim of Rs.1,34,133/- towards
liquidated damages, Rs.70,900/- towards cost of rectification of
leakages and Rs.7,500/- towards cost of rectification and repairs of
balance works. It also claimed interest. After hearing both parties,
the arbitrator settled the claims of the claimant as follows:
Claim Particulars of the Amount Amount
No. claim claimed awarded /
(in Rs.) rejected
(in Rs.)
1 Dismantling of garbage 450.00 Rejected
bin
2 Cutting & removing of 12400.00 7400.00
62 Palmariah trees
3&4 Uprooting the Plants 3000.00 Rejected
and clearing the site 1200.00
5 Earthwork excavation 7011.60 7011.60
beyond 2 mts. depth
6 Well portion works 1,19,459.15 66,849.60
viz., removal of soil (Restricted to
slurry and treatment of 66,849.60)
sand filling
7 Claim for water tank 12012.00 Rejected
repair
8 Fabrication of UCO 10000.00 10000.00
Bank logos, windows
etc.
9 PVC pipes to drain out 1000.00 Rejected
water
10 Enamel paints for two 10000.00 5000.00
coats for doors and
windows
11 Final bills : (a) 6648.00
(a) to (k) (b) 5840.27
(c) 6515.43
(d) 17500.00 7500.00
(e) Rejected
(f) 5000.00
(g) 2400.00
(h) 3600.00
(i) 600.00
(j) 325.00
(k) Fixing of MC 20000.00
boards
12 EMD 16500.00 16500.00
13 Security Deposit 120000.00 113099.00
Interest @ 18% per annum is awarded in respect of above amounts
(c) So far as the counterclaim of Rs.1,34,133/- towards
liquidated damages is concerned, the arbitrator observed that as per
Exhibits C15, C16 & C19 the contract work was completed by
08.02.1993 and the subsequent correspondence after the expiry of
the maintenance period of one year i.e., 08.02.1994 amounts to
redoing of the works as per the letter of the respondent dated
31.03.1994 which naturally constitute extra work. The claim for
liquidated damages does not stand the test of any extension of the
period of the original contract and there was no correspondence
from the respondent pointing out any extension of the contract
period inviting penal action in terms of the contract at that time.
(d) He further observed that after completion of the work by
08.02.1993, one full monsoon period passed off without any
complaint during the year 1993 and there was no documentary
evidence that the roof slab of the bank building was leaking. It was
only in March 1994, the respondent brought to the notice of the
claimant about the leakage i.e., more than a year after certificate of
completion. Learned arbitrator further observed that on inspection
of the bank building by him, he noticed that there was no indication
of any structural distress of the slabs etc. and in his opinion,
fundamentally no water proof weathering course with the specified
slopes of the roof drainage was provided as per engineering
standards and the leakage must have been taken place due to acute
stagnation of rain water over the roof slab during heavy monsoon
and the rain water downfall pipes provided to drain away the rain
water from the roof slab were found to be grossly inadequate and
were not provided as per basic technical requirements as is seen
from the drawings of the bank building produced before him and as
such the leakage of the roof slab could be attributed to lack of
provision of specified weathering course as per the standards with
requisite slops. Hence, the counterclaim of the respondents
towards leakage of Rs.70,900/- was rejected. Similarly, the cost of
rectification of defects to a tune of Rs.7,500/- is concerned, learned
Arbitrator observed that the said claim does not stand the test as
those works were to be taken up after the completion of the
maintenance period of one year. Thus, in essence, the arbitrator
rejected the counterclaim entirely.
(e) Aggrieved, the respondent filed O.P.No.646/1998 in the
Court of the learned Principal District Judge, Visakhaptnam under
Section 34 of the Arbitration & Conciliation Act, 1996. After
hearing both parties, learned Judge while approving the award in
toto, dismissed the O.P. with costs.
Hence, the CMA.
4. Heard learned counsel for the appellant Sri E.Sambasiva
Pratap and Sri M.Bala Naga Srinivas, counsel representing M/s.
Bharadwaj Associates for the respondent.
5. Learned counsel for the appellant during his arguments fairly
submitted that his main plank of argument is on two aspects i.e.,
firstly with regard to the claim No.6 and secondly with regard to
the award of interest at 18%. In expatiation, learned counsel
argued that claim No.6 relates to removal of the soil slurry from the
well existing in the site and the claimant made a claim of
Rs.1,19,459.15 ps and to establish his claim, the claimant filed
certain documents on the last date of hearing without giving prior
notice to the respondent and therefore, the respondent had no
occasion to give effective reply in respect of the said claim and
documents. However, without rejecting the documents the
arbitrator has accepted them and allowed the claim on the strength
of those documents. Therefore, the said claim and award are unjust
and illegal. Nextly, he argued that the arbitrator awarded high rate
of interest of 18% p.a. without any reason. In the normal course,
the rate of interest would not exceed 8%. In this regard, he placed
reliance on Oriental Structural Engineers Private Limited v.
State of Kerala1. He would submit that the learned District Judge
has not appreciated the contention of the respondent in right
perspective in this regard.
6. Per contra, learned counsel for the respondent while
supporting the award and the order in O.P., argued that both the
(2021) 6 SCC 150
orders were based on sound reasoning and require no revisit. He
thus prayed to dismiss the appeal.
7. The point for consideration is whether there are merits in the
CMA to allow?
8. Point: We gave our anxious consideration to respective
arguments. Claim No.6 relates to the execution of the work of
removal of soil slurry from the well existing in the construction site
at a depth of 6 meters. The claim was made for Rs.1,19,459.15 ps.
However, after deducting the amounts received from the
respondent, the claimant restricted his claim to Rs.66,849.60 ps.
Regarding this claim, the arbitrator noted that as per the
instructions of the respondent, the claimant undertook the removal
of soil slurry from the well at a depth of 6 meters by making the
treatment with sand filling etc. The arbitrator observed that the
execution of the said work involved several difficult works such as
lifting of slurry, bailing of water by deploying 5 H.P. motor and
filling the same with sand as per the specifications and the details
of the work executed was given in Ex.C11 dated 28.11.1991. The
arbitrator further observed that the claimant gave notice to the
respondent under Order XII Rule 8 CPC for furnishing certain
documents with respect to the said work. The claimant filed
certain documents on the last date of hearing which were not given
any exhibit marks. However, he (arbitrator) referred them in his
proceedings. The arbitrator further observed that the respondent in
his affidavit admitted about the existence of the well and filling up
of the same as an additional item of work and made payments to
the tune of Rs.29,303.61 ps. However, the claimant admitted that
he received Rs.41,800/- and also Rs.10,810.95 ps and thus
restricted his claim to Rs.66,849.60 ps. The arbitrator observed
that the respondent has not denied or rejected the claim of the
claimant by sending any reply to Ex.C11. The arbitrator has finally
stated that after going through the documents and hearing the
arguments of both sides and also considering the practical
engineering problems in executing the work relating to the well as
per the specifications to ensure the stability to the main structure,
he was allowing the claim for balance amount of Rs.66,849.60 ps.
(a) In the above context, learned Principal District Judge,
rejecting the contention of the respondent that the arbitrator
without any basis approved the claim and he unjustly accepted the
documents filed on the last day of hearing, observed that the
arbitrator has not completely relied upon the documents by
ignoring the arguments as well as the case of the bank and passed
the award. On the other hand, after considering the practical
engineering problems in executing the work relating to the well as
per specifications to ensure stability of the main structure, awarded
the amount. Learned Principal District Judge further observed that
the arbitrator has taken into consideration the affidavit submitted
by the bank also. Learned Principal District Judge concluded that
the finding of the arbitrator was sound and do not require any
interference. We have meticulously scrutinized the findings of the
arbitrator and observations of the learned Principal District Judge
in respect of claim No.6. We unhesitatingly say, we agree with
their findings. True that certain documents were filed by the
claimant on the final hearing date. However, the approval of the
claim No.6 by the arbitrator was not on the sole basis of those
documents but on considering the practical engineering problems
involved in bailing out the slush and slurry from the well and
filling up of the same with sand to ensure the stability of main
structure. Hence, we find no merit in the contention of the
appellant in this regard.
(b) Then, interest is concerned, the claimant claimed interest
@ 24% p.a. on the ground that the respondent bank had charged
him the same rate of interest on the overdraft cash credit account of
the claimant. The respondent did not deny but stated that the
interest rates would fluctuate from time to time as per the RBI
guidelines. Though the claimant issued notice to the respondent
bank to produce the records of RBI guidelines pertaining to the
interest rates charged by the banks from time to time during the
relevant period, however, the respondent did not produce those
circulars. Taking these aspects into consideration, the arbitrator
awarded 18% interest.
(c) It is a case where the arbitrator awarded interest on
delayed payment. Since the respondent which is a banking
institution was charging interest on the overdraft facilities of the
account of the claimant, it is needless to emphasize, he too
deserves interest on the delayed payments. The rate is concerned,
in similar circumstances, in Oriental Structural Engineers
Private Limited case (1 supra) the Apex Court awarded simple
interest @ 8% p.a. on the sum left unpaid considering the same as
just and equitable. In that view, we hold that in the instant case
also, the claimant deserves simple interest at 8% p.a. instead of
18% p.a. as awarded by the arbitrator.
9. In the result, while upholding the award passed by the
Arbitrator and confirmed by the learned Principal District Judge,
Visakhapatnam, we, however, modify the rate of interest to 8% p.a.
simple on the claims approved by the arbitrator. The C.M.A. is
disposed of accordingly. No costs in the C.M.A.
_________________________ U.DURGA PRASAD RAO, J
______________________ T.RAJASEKHAR RAO, J 29.11.2022 mva
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!