Citation : 2022 Latest Caselaw 9648 AP
Judgement Date : 15 December, 2022
THE HON'BLE SRI JUSTICE R.RAGHUNANDAN RAO
ARBITRATION APPLICATION No.58 of 2015
ORDER:
The case of the applicant is as follows:
2. The applicant had entered into an agreement with the
respondent for executing certain Civil, Structural and Plumbing
works in the establishment of the respondent at Kurnool by way of
an agreement, which is contained in the work order awarded by the
respondent dated 22.09.2010.
3. The applicant states that it took up the work and
executed the work. However, payments due to the applicant were not
made. The applicant was due for Rs.19,55,580/- towards the unpaid
dues and a sum of Rs.7,22,541/- towards non returning of retention
money to the applicant. In all, the applicant claims Rs.26,78,127/-
being the amounts due on account of non settlement of these
amounts. The applicant further contends that material of the
applicant, lying at the works place, was used by the respondent
company without reimbursing the applicant. The applicant claims
that a sum of Rs.78,28,600/- has to be paid to the applicant on this
account. The applicant also contends that the respondent would be
liable to pay a sum of Rs.31,13,344/- as the amount of the rents
liable to be paid by the respondent for using the material in the
construction. In all, the applicant claims an amount of
Rs.1,28,97,530/- as being due to the applicant.
4. The applicant raised the issue of payment of these dues
in its legal notice dated 24.04.2014 sent to the respondent. The said
notice also stated that if the amounts are not settled within 15 days
and the applicant is not allowed to retrieve its material, the matter
should be referred to an Arbitrator consented by both parties. As the
respondent neither paid the said amounts nor referred the matter for
arbitration, the present application has been filed under Section 11
of the Arbitration Conciliation Act, 1996 for appointment of an
arbitrator.
5. The respondent has filed a counter affidavit stating that a
work order was placed on the applicant on 17.09.2010 for
construction of Multi Storied Industrial Calcium Hypo Chlorite
Building. According to the said work order, work was to be
commenced on 22.09.2010 and completed by 22.07.2011. The said
work was not executed completely and the applicant started making
unsustainable claims to avoid liquidated damages. The respondent
denied any liability to pay any amount of money to the applicant. The
respondent also contended that the claim for the alleged use of
material of the applicant and the rent claimed on the said use of the
material would be outside the purview of the work order dated
17.09.2010 and as such, the applicant cannot seek reference of the
said claims to arbitration.
6. The respondent has taken the stand that it is the
applicant who was due to the respondent and the applicant had in
fact requested the respondent to waive the said debit balance. The
respondent has disputed the maintainability of the present
application on the ground that the legal notice dated 24.04.2014 is
barred by limitation as the schedule date of completion was
22.07.2011. The respondent also contends that there was final
accord and satisfaction in view of the letters of the applicant dated
14.03.2014 and the subsequent E-mails dated 12.06.2014 and
17.06.2014.
7. The respondent contends that the letter dated
14.03.2014, given by the Managing Director of applicant requests the
respondent to remove the debit balance and to allow the applicant to
take back the material at the site and that this would be the final
settlement arrived between the parties. The E-mails exchanged
between the applicant and the respondent between 12.04.2014 and
26.004.2014 shows that the respondent treated the letter dated
14.03.2014 as full and final settlement of all dues and claims
between the parties. However, the E-mail of 26.04.2014 shows that
the applicant had disputed this view of the respondent apart from
disputing the fact stated by the respondent in the E-mails sent by
the respondent to the applicant.
8. Sri N.Pramod learned counsel appearing for the applicant
would submit that the claims made by the applicant have been
denied by the respondent and as such, disputes have arisen between
the parties. He relies upon special condition clauses 42 and 43 to
contend that all disputes between the parties would have to be
resolved by way of arbitration if resolution, by mutual consultation,
does not happen.
9. Sri S.S.Bhatt learned counsel appearing for the
respondent reiterates the objections raised in the counter affidavit,
about the maintainability of the application itself.
10. The question of whether any amounts are due from the
respondent to the applicant and whether any amounts are due from
the applicant to the respondent are matters of dispute which would
have to be resolved, as per the terms of the work order, which
provides for reference to Arbitration. The respondent has raised
objections as to whether such reference is permissible.
11. The first objection of the respondent is that the claim is
barred by limitation. The execution of the contract was to be
completed by 22.07.2011. The applicant had issued a legal notice
dated 24.04.2014 setting out its claims and asking for reference to
arbitration. This letter is within three years from the schedule date of
completion. Section 21 of the Arbitration Act stipulates that issuance
of a notice requesting arbitration would be treated as the date on
which the arbitral proceedings have commenced. It is not clear as to
which period of limitation is to be applied and how the claim and
request for Arbitration is barred. In any event, without taking a final
view on this aspect, the fact remains that the question of limitation is
a mixed question of law and fact and the same can be referred to the
arbitral Tribunal for a decision.
12. The second objection raised by the respondent is that
there is a final settlement in relation to the work order and
consequently the present application is not maintainable. The
learned counsel for the applicant relies upon the following decisions
to support his contention.
1) M/s. P.K Ramaiah and Company vs Chairman & Managing
Director, national Thermal Power Corporation.1
2) Union of India and Others vs. Master Construction Company2
1994 Supp (3) SCC 126
3) Sri Matha Manikeshwari Enterprises vs. General Manager,
South Central Railway, Secunderabad and Others3
4) Indian Oil Corporation Limited vs. NCC limited4
5) Secunderabad Cantonment Board vs Ramachandraiah and
Sons5.
13. In all these Judgments, the Court had taken the view
that, where there is full accord and satisfaction of the claims, further
arbitral proceeding including applications for appointment of an
Arbitral Tribunal would not be maintainable. However, the question
that would still remain before this Court is whether there was such
final settlement of dues between the parties.
14. The case of the respondent is that the letter dated
14.03.2014 given by the Managing Director of the applicant amounts
to a final settlement. The applicant disputes this contention.
15. The E mail communications between the applicant and
the respondent between 12.06.2014 and 17.06.2014 reveals that the
letter of 14.03.2014 is treated, by the respondent, as an offer of full
and final settlement. However, the applicant states in his E-mail
dated 26.06.2014 that there was no final settlement. The Applicant
(2011) 12 SCC 349
2015 (1) ALD 431
2022 SCC online SC 896
(2021) 5 SCC 705
also contends that, even otherwise, nothing has been shown to
demonstrate that the respondent, in pursuance of the alleged final
offer of the applicant, had taken the necessary steps to return all the
material of the Applicant. This has itself become a disputed question
of fact which would have to be looked into by the arbitrator.
16. The Respondent also contends that the claim of
compensation for alleged consumption of the material of the
Applicant and the rents claimed on that account fall outside the
purview of the contract and the arbitration clause in clauses 42 and
43 of the special conditions set out in the work order. The said
clauses read as follows:
17. In these circumstances, this is a fit case for the dispute
to be referred to Arbitration.
18. Accordingly, this Arbitration Application is allowed and
Justice Smt. Kongara Vijaya Lakshmi, Former Judge of the High
Court of Andhra Pradesh, Plot No.9/B, Road No.7, Filmnagar,
Jubilee Hills, besides Filmnagar Cultural Center, Hyderabad is
appointed as the Arbitrator to decide the claims made by the
applicant in the legal notice dated 24.04.2014. The learned
Arbitrator shall fix her fees in accordance with the 4th schedule to the
Arbitration and Conciliation Act, 1996. The arbitration shall proceed
in accordance with clauses 42 and 43 of the work order dated
17.09.2010. There shall be no order as to costs.
Miscellaneous petitions, pending if any, shall stand closed.
___________________________________ JUSTICE R.RAGHUNANDAN RAO Date :15.12.2022 RJS
THE HON'BLE SRI JUSTICE R.RAGHUNANDAN RAO
ARBITRATION APPLICATION No.58 of 2015
Date : 15.12.2022
RJS
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!