Citation : 2021 Latest Caselaw 3780 AP
Judgement Date : 27 September, 2021
MVR,J
I.C.O.M.A.O.A.No.10 of 2021
1
HON'BLE SRI JUSTICE M. VENKATA RAMANA
I.C.O.M.A.O.A.No.10 of 2021
ORDER:
This petition is filed under Section 9 of Arbitration and
Conciliation Act, 1996 for grant of an ad-interim order directing the
respondent to deliver the cargo mentioned in the petition schedule to
it on receipt of pro-rata price as agreed under the contract
No.SGTL/026/2021-BN dated 24.03.2021, which was scheduled to
reach Visakhapatnam port on 08.09.2021.
2. The case of the petitioner is as under:
The petitioner is a proprietary concern engaged in the business
of cashew and other allied products. It sought by means of an order,
supply of 550 MT of raw cashew inshell originating from an African
country called 'Benin' and the respondent agreed to supply the same.
Accordingly, a contract was entered into on 24.03.2021 in between
them, undertaking to supply raw cashew inshell for a price, at 1126
US dollars per unit, for a total value of 6,19,300 US dollars.
According to the petitioner, the delivery of this commodity was to
commence and complete in April 2021 with a grace period of ten
days. For this purpose, the petitioner claimed that it paid 92,895/-
US dollars towards 15% of the advance and that the respondent
committed breach in supplying the commodity as agreed upon. On
account of this breach, the petitioner claimed that various obligations
it had entered into with the third parties for supply of cashew nuts
were affected. In the process, it claimed that it suffered in its profits
at 375 US dollars for metric tone and that there was also possibility of
making more profit. The petitioner claimed that the cargo in this MVR,J I.C.O.M.A.O.A.No.10 of 2021
respect was reaching Visakhapatnam on board vessel MAERSK
RUBICON in containers bearing No's: MRKU7845410 and MRKU7882265.
It further claimed that respondent had sent a packing schedule in the
name of the petitioner for this cargo on 23.7.2021 by WhatsApp and
therefore, it is entitled for delivery of this cargo the moment it
reached the port of destination.
3. Stating that there is need for arbitration in the matter under
GAFTA (The grain and Feed Trade Association) Rules, which it is
intending to invoke for the loss and damages suffered by it on
account of conduct of the respondent, the petitioner requested to
grant an interim order as prayed in this petition.
4. At the stage of admission, this matter is heard as to
maintainability as well as necessity of passing an order as prayed.
5. By the date of presentation of this petition, as per the
averments therein, the ship containing the cargo in question was yet
to reach the destination, viz. Visakhapatnam. A copy of the bill
reflecting the sales contract dated 24.03.2021 is filed along with this
petition. The destination port stated therein is Tuticorin, India. The
entire claim of the petitioner is based on this sales contract and
supplies to receive by April, 2021. The arbitration sought to be
invoked is on account of loss and damages suffered in receiving
deliveries as per its contract within due time. It is further based on
making an advance at 15% of total value of the contract as well as the
cargo to be supplied to the petitioner.
MVR,J I.C.O.M.A.O.A.No.10 of 2021
6. The nature of interim relief sought in this petition now requires
consideration. It is for the purpose of delivering the cargo on receipt
of pro-rata price, as per the sale contract, once it reached
Visakhapatnam Port. The relief so sought is in the nature of
a continuous direction, making the respondent to deliver the goods
upon receiving the price to the extent of goods delivered.
7. Learned counsel for the petitioner in the course of hearing
relied on NATIONAL ALUMINIUM CO.LTD. v. GERALD METALS SA1. It
was in turn preferred against the judgment of Division Bench of this
Court at Hyderabad between the same parties reported in 2004(3)
ALT 749. A careful reading of this judgment of Hon'ble Supreme
Court makes out that it was decided on the grounds of equity and
balance of convenience only, since their Lordships felt that it was
unnecessary to go into the questions of fact and law. Added to it,
this ruling relating to an international arbitration is prior to
amendment of Arbitration and Conciliation Act in the year 2015.
8. Therefore, the above ruling cannot be applicable for the
purposes as the petitioner required this Court to consider.
9. The very nature of the relief as an interim measure sought by
the petitioner is not amenable to grant. The parties to the contract
shall follow the terms of contract in respect of delivery of the goods.
In case of any loss or damage suffered as alleged, the remedy for
them is elsewhere. It cannot be in the nature of requiring the
respondent to continue to deliver the goods, basing on a proposed
claim for damages to make good the loss, by the petitioner against it.
(2004)9 SCC 307 MVR,J I.C.O.M.A.O.A.No.10 of 2021
Section 9 of Arbitration and Conciliation Act cannot be invoked in this
manner and for such purpose. This petition as such is not
maintainable.
10. Therefore, finding no justification to entertain this application,
the same has to be rejected and accordingly, this petition is
dismissed at admission stage.
___________________ M. VENKATA RAMANA, J Dt: 27.09.2021 Rns MVR,J I.C.O.M.A.O.A.No.10 of 2021
HON'BLE SRI JUSTICE M. VENKATA RAMANA
I.C.O.M.A.O.A.No.10 of 2021
Date:27.09.2021
Rns
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!