Citation : 2021 Latest Caselaw 3751 AP
Judgement Date : 24 September, 2021
IN THE HIGH COURT OF ANDHRA PRADESH: AMARAVATI
HON'BLE Mr. JUSTICE ARUP KUMAR GOSWAMI, CHIEF JUSTICE
ARBITRATION APPLICATION No.165 of 2014
(Through Video-Conferencing)
V.B. Cold Storage Private Limited, rep. By Director
Badam Krishna Murthy, S/o. Late Pentayya, aged
48 years, Rajulathallavalasa village, Bhimili (M),
Visakhapatnam District, Andhra Pradesh ... Applicant
Versus
Bajaj Allianz General Insurance Company Limited, rep.
by its Manager, 3rd floor, P.G. Plaza, V.I.P. Road,
Visakhapatnam (A.P.) ... Respondent
Counsel for the applicant : Mr. S.V.S.S. Siva Ram
Counsel for the respondent : Mr. P. Rajasekhar
Date of hearing : 16.07.2021
Date of judgment : 24.09.2021
JUDGMENT
This application is filed under Section 11(4) and (6) of the
Arbitration and Conciliation Act, 1996 (for short, "the Act of 1996") for
appointment of an arbitrator.
2. The applicant is in the business of running a cold-storage for
perishable consumables belonging to farmers/vendors. It had taken a
Standard Fire & Special Perils Policy from the respondent-company for the
year 2010-11. For the year 2011-12, the applicant had taken two
Standard Fire & Special Perils Policies bearing Nos.OG-12-1819-4005-
00000009 for Rs.2,00,00,000/- (Rupees Two Crores) and OG-12-1819-
4005-00000010 for Rs.3,00,00,000/- (Rupees Three Crores) from the 2 HCJ A.A.No.165 of 2014
respondent-company on 28.05.2011. It was regularly paying the premium
and submitting monthly stock declaration statements.
3. On 21.12.2011, a major fire accident had taken place in the
cold-storage unit due to short circuit resulting in the entire premises of the
cold-storage unit being gutted. All the commodities stored in the cold
storage also went up in flames. On that day itself, the applicant informed
the respondent about the incident. Discussions had ensued in between
the representatives of the applicant and the respondent with regard to
calculation of the claim and the applicant was informed that the
calculation of loss would be on the basis of average of everyday stock
values of each month, which was not acceptable to the applicant as the
applicant has been submitting declaration statements basing on the
quantum of stock stored on the last date of each month.
4. It is pleaded that the applicant had suffered losses to the tune of
Rs.1,51,34,922/-. On 07.03,2012, the applicant addressed a letter to the
surveyors of the respondent, amongst others, requesting to complete the
survey report at the earliest and also requesting to recommend to the
respondent to release an interim amount of Rs.60,00,000/- to disburse the
same to some farmers who were under great financial loss.
5. A letter dated 05.05.2012 was issued by the applicant to the
respondent to pay the claim amount of Rs.1,51,34,922/- and another
letter dated 25.05.2012 was issued requesting to finalize the report on the
basis of the declaration submitted by the applicant. A letter dated
23.07.2012 was issued by the respondent that the stock declaration
statements submitted by the applicant did not conform to the procedure
laid down in the fire declaration policy and requested the applicant to 3 HCJ A.A.No.165 of 2014
submit fresh declarations on either the average of the values at risk on
each day of the month or the highest value at risk during the month,
much to the consternation of the applicant, as the respondent had never
made a whisper that the stock declaration statements submitted by the
applicant were not conforming to the fire declaration policy for the
previous three years.
6. Subsequently, on 08.08.2012, the respondent sent a letter to the
applicant enclosing a copy of the surveyor's letter along with the mode of
assessment and requesting the applicant to give its consent to enable the
respondent to process the claim. It is the pleaded case of the applicant
that because of the turn of events, he was in a very depressed state of
mind and as vendors/farmers were constantly pressing the applicant to
settle the claims and had threatened the applicant with dire consequences
if the claims were not settled, the applicant had no option but to accept
the survey report, which settled the claim of the applicant for
Rs.62,88,241/-. Accordingly, he was compelled to sign the Indemnity
Bond, which was a pre-requisite condition for release of the aforesaid
amount. On 12.12.2012, the applicant addressed a letter to the
respondent informing that he was compelled to accept the insurance claim
under duress and that the applicant would treat the issue of settlement as
a dispute and that the applicant would initiate arbitration proceedings as
per clause 10 of the General Conditions of the Commercial Package Policy
and the said letter was received by the respondent on 17.12.2012. On a
request being made, one Sri Vijairagavan agreed to be an arbitrator and
he entered on arbitration proceedings on 06.04.2013 and communicated
the same to the applicant and the respondent. The arbitrator issued
proceedings dated 18.04.2013 and requested the respondent to appoint 4 HCJ A.A.No.165 of 2014
an arbitrator within the time schedule prescribed in the policies to enable
both the arbitrators to appoint a third arbitrator forming a tribunal and
proceed for resolution of the dispute. The respondent, however, did not
appoint a second arbitrator and such fact was also communicated by the
arbitrator to the applicant. Since the respondent had not taken any
action, recourse is taken by the applicant seeking appointment of an
arbitrator on behalf of the respondent.
7. A counter-affidavit was filed by the respondent. While admitting
that the entire premises of the cold-storage unit was gutted along with all
the commodities stored in the cold-storage unit belonging to various
farmers/vendors, it is stated that the applicant having received an amount
of Rs.62,88,241/- as full and final settlement of his claim by voluntarily
executing Indemnity Bond, Discharge Bond and also consent letter
without raising any protest and demur, cannot seek appointment of an
arbitrator. It is stated that the declaration submitted by the applicant was
not in conformity with the procedure prescribed in the policy and the
I.R.D.A. surveyors assessed the loss by two methods - by one method,
assessment was quantified at Rs.63,00,216/- and by the other method, at
Rs.48,44,496/- and the applicant had accepted the second method of
assessment. The plea set up by the applicant that the claim was accepted
under duress was denied and it is pleaded that the execution of Indemnity
Bond, Discharge Bond and consent letter were voluntarily accepted by the
applicant and, therefore, the arbitration application is liable to be
dismissed as there was no existing dispute.
8. A reply-affidavit was filed by the applicant reiterating the plea of
execution of documents under duress. It is stated that within a week
from the receipt of an amount of Rs.62,88,241/-, the applicant addressed 5 HCJ A.A.No.165 of 2014
a letter to the respondent requesting it to pay the balance claimed
amount and, therefore, the present application for appointment of an
arbitrator is maintainable.
9. Mr. S.V.S.S. Siva Ram, learned counsel for the applicant, submits
that acceptance of the amount under duress to tide over difficulties faced,
cannot stand in the way of appointment of an arbitrator on the
respondent's side, as the respondent had not paid the balance amount of
Rs.93,50,466/-. He placed reliance on a three-Judge Bench judgment of
the Hon'ble Supreme Court in Mayavati Trading Private Limited v.
Pradyuat Deb Burman, reported in (2019) 8 SCC 714, a judgment of
the Hon'ble Supreme Court in Oriental Insurance Co. Ltd. V. Dicitex
Furnishing Ltd., reported in (2020) 2 SCC 464 and a judgment dated
13.02.2019 rendered by a learned single Judge of the High Court for the
State of Telangana in M/s. Sitaram Spinners Pvt. Ltd., Hyderabad v.
New India Assurance Co. Ltd., Secunderabad (Arbitration
Application No.22 of 2017), wherein the learned single Judge had
observed that in view of Section 11(6-A) of the Act of 1996, the High
Court while considering the application under Section 11(5) & (6) of the
Act of 1996 shall confine itself to examination of the existence of an
arbitration agreement and no more.
10. Abiding by the stand taken in the counter-affidavit,
Mr. P. Rajasekhar, learned counsel for the respondent, submits that the
Indemnity Bond, Discharge Bond and consent letter were voluntarily
executed by the applicant and after four months of such execution, a false
plea is raised that such execution of documents was made under duress
and in compelling circumstances. It is contended that as the applicant
had acknowledged the amount of Rs.62,88,241/- as full and final 6 HCJ A.A.No.165 of 2014
settlement of all the claims of the applicant, there is no dispute regarding
any claim remaining outstanding and, therefore, the application is
mis-conceived.
11. I have considered the submission of the learned counsel for the
parties and have perused the materials on record.
12. At the outset, it will be relevant to take note of Clause 10 relating
to dispute resolution as engrafted in the Commercial Package Policy.
Clause 10 reads as under:
"10. Dispute Resolution
a) If any dispute or difference shall arise as to the quantum
to be paid under this Policy (liability being otherwise
admitted), such difference shall independently of all other
question be referred to the decision of a sole arbitrator to
be appointed in writing by the parties to or if they cannot
agree upon a single arbitrator within 30 days of any party
invoking arbitration, the same shall be referred to a panel
of three arbitrators, comprising of two arbitrators one to
be appointed by each of the parties to the
dispute/difference and the third arbitrator to be appointed
by such two arbitrators and arbitration shall be conducted
under and in accordance with the provisions of the
Arbitration and Conciliation Act, 1996. The law of the
arbitration will be Indian law, and the seat of arbitration
and venue for all hearings shall be within India.
b) It is clearly agreed and understood that no difference or
dispute shall be referable to arbitration as herein before 7 HCJ A.A.No.165 of 2014
provided if the Company has disputed or not accepted
liability under or in respect of this Policy.
c) It is hereby expressly stipulated and declared that it shall
be a condition precedent to any right of action or suit
upon this Policy that the award by such
arbitrator/arbitrators of the amount of the loss or damage
shall be first obtained.
d) It is also hereby further expressly agreed and declared
that if the Company shall disclaim liability to the insured
for any claim hereunder and such claim shall not, within
12 calendar months from the date of such disclaimer
having been made the subject matter of a suit in a court
of law, then the claim shall for all purposes be deemed to
have been abandoned and shall not thereafter be
recoverable hereunder.
e) In the event that these arbitration provisions shall be held
to be invalid then all such disputes or differences shall be
referred to the exclusive jurisdiction of the Indian Courts."
13. It is to be noted that the respondent has not denied that the
Commercial Package Policy is not applicable in between the parties and
that there is no agreement for resolving the disputes through arbitration.
Thus, the existence of an arbitration clause in the contract of insurance is
not in dispute. The question that arises for consideration is whether the
discharge of liability in the present case upon acceptance of the
compensation amount by signing the Indemnity Bond, Discharge Bond
and consent letter was voluntary or under coercion or undue influence 8 HCJ A.A.No.165 of 2014
and whether the applicant is justified in invoking Section 11(6) of the Act
of 1996.
14. In United India Insurance Company Limited v. Antique Art
Exports Private Limited, reported in (2019) 5 SCC 362, the Hon'ble
Supreme Court, while noting that execution of full and final settlement,
receipt or a discharge voucher in itself cannot be a bar to arbitration, had
relied on para 44 of the judgment in National Insurance Company
Limited v. Boghara Polyfab (P) Ltd., reported in (2009) 1 SCC 267.
In Boghara Polyfab (P) Ltd. (supra), at para 44, it was observed as
follows:
"44. None of the three cases relied on by the appellant lay
down a proposition that mere execution of a full and final
settlement receipt or a discharge voucher is a bar to
arbitration, even when the validity thereof is challenged
by the claimant on the ground of fraud, coercion or
undue influence. Nor do they lay down a proposition that
even if the discharge of contract is not genuine or legal,
the claims cannot be referred to arbitration. In all the
three cases, the Court examined the facts and satisfied
itself that there was accord and satisfaction or complete
discharge of the contract and that there was no evidence
to support the allegation of coercion/undue influence."
15. It was held that a mere plea of fraud, coercion or undue influence
in itself is not enough and the party who alleged the same is under an
obligation to prima facie establish the same by placing satisfactory 9 HCJ A.A.No.165 of 2014
material on record before the Chief Justice or his Designate to exercise
power under Section 11(6) of the Act of 1996.
16. In para 20 of the Antique Art Exports Private Limited (supra),
it was held as follows:
"20. The submission of the learned counsel for the
respondent that after insertion of sub-section (6-A) to
Section 11 of the Amendment Act, 2015 the jurisdiction
of this Court is denuded and the limited mandate of the
Court is to examine the factum of existence of an
arbitration and relied on the judgment in Duro Felguera,
SA v. Gangavaram Port Ltd. [Duro Felguera,
SA v. Gangavaram Port Ltd., (2017) 9 SCC 729 : (2017) 4
SCC (Civ) 764] The exposition in this decision is a general
observation about the effect of the amended provisions
which came to be examined under reference to six
arbitrable agreements (five agreements for works and
one corporate guarantee) and each agreement contains a
provision for arbitration and there was serious dispute
between the parties in reference to constitution of
Arbitral Tribunal whether there has to be Arbitral Tribunal
pertaining to each agreement. In the facts and
circumstances, this Court took note of sub-section
(6-A) introduced by the Amendment Act, 2015 to Section
11 of the Act and in that context observed that the
preliminary disputes are to be examined by the arbitrator
and are not for the Court to be examined within the
limited scope available for appointment of arbitrator 10 HCJ A.A.No.165 of 2014
under Section 11(6) of the Act. Suffice it to say that
appointment of an arbitrator is a judicial power and is not
a mere administrative function leaving some degree of
judicial intervention; when it comes to the question to
examine the existence of a prima facie arbitration
agreement, it is always necessary to ensure that the
dispute resolution process does not become unnecessarily
protracted.
17. In the factual matrix of the case as presented in Antique Art
Exports Private Limited (supra), the Hon'ble Supreme Court observed
that prima facie no dispute subsisted after the discharge voucher being
signed by the respondent without any demur or protest and claim being
finally settled with accord and satisfaction and after 11 weeks of the
settlement of claim a letter was sent on 27-7-2016 for the first time
raising a voice in the form of protest that the discharge voucher was
signed under undue influence and coercion with no supportive prima facie
evidence being placed on record. Accordingly, in absence thereof, it was
held that it must follow that the claim had been settled with accord and
satisfaction leaving no arbitral dispute subsisting under the agreement to
be referred to the arbitrator for adjudication.
18. Section 11 (6-A) of the Act of 1996 was inserted by Act 3 of 2016
with effect from 23.10.2015. Section 11 (6-A) reads as follows:
"11. (6-A) The Supreme Court or, as the case may be, the
High Court, while considering any application under sub-
section (4) or sub-section (5) or sub-section (6), shall,
notwithstanding any judgment, decree or order of any 11 HCJ A.A.No.165 of 2014
court, confine to the examination of the existence of an
arbitration agreement."
19. Section 11(6-A) was omitted by Act 33 of 2019. However, Section
3 of the Amendment Act of 2019 insofar as it pertains to this omission has
not yet been brought into force.
20. In Duro Felguera, SA v. Gangavaram Port Ltd., reported in
(2017) 9 SCC 729, at para 48, the Hon'ble Supreme Court had observed
that the intention of the legislature is crystal clear that the court should
and need only look into one aspect, which is the existence of an
arbitration agreement. What are the factors for deciding as to whether
there is an arbitration agreement is the next question. The resolution to
that is simple, in that it needs to be seen if the agreement contains a
clause which provides for arbitration pertaining to the disputes which
have arisen between the parties to the agreement. At para 59, it was
observed that scope of the power under Section 11(6) of the Act of 1996
was considered in the decisions in SBP & Co. v. Patel Engg. Ltd.,
reported in (2005) 8 SCC 618 and Boghara Polyfab (P) Ltd. (supra)
and the said position continued till the amendment was brought about in
the year 2015. It was emphasized that after the amendment, all that the
courts need to see is whether an arbitration agreement exists - nothing
more nothing less. It was further observed that the legislative policy and
purpose is essentially to minimise the Court's intervention at the stage of
appointing the arbitrator and this intention as incorporated in Section
11(6-A) ought to be respected.
21. In Mayavati Trading Private Limited (supra), it was observed
that prior to insertion of Section 11 (6-A), the Hon'ble Supreme Court in 12 HCJ A.A.No.165 of 2014
several judgments, beginning with SBP & Co. (supra) has held that at
the stage of a Section 11(6) application being filed, the court need not
merely confine itself to the examination of the existence of an arbitration
agreement but could also go into certain preliminary questions such as
stale claims, accord and satisfaction having been reached, etc.
22. Following Duro Felguera (supra), the Hon'ble Supreme Court in
Mayavati Trading Private Limited (supra) observed that the law prior
to the 2015 Amendment that has been laid down by the court which
would have included going into whether accord and satisfaction has taken
place, has now been legislatively overruled. It was held that Section
11(6-A) is confined to the examination of the existence of an agreement
and is to be understood in the narrow sense as has been laid down in the
judgment in Duro Felguera (supra) and taking that view, the judgment
in Antique Art Exports Private Limited (supra) was overruled as
having not laid down the correct law.
23. In Oriental Insurance Company and another v. Dicitex
Furnishing Limited, reported in (2020) 4 SCC 621, the decision of the
Bombay High Court appointing an arbitrator was challenged on the
ground that Dicitex having accepted the proffered amounts and having
withdrawn the reservation and protest, it could not have argued that it
was subjected to coercion or that the appellant forced it to sign the final
discharge voucher. The Bombay High Court had, prima facie, observed
that it would be appropriate that the issue raised by the Oriental
Insurance Company that Dicitex had signed such discharge voucher
unconditionally and the issue raised by Dicitex that the same was under
duress and coercion is conclusively decided by the Arbitral Tribunal and if
necessary, by leading oral evidence.
13 HCJ
A.A.No.165 of 2014
24. On consideration of the materials on record, the Hon'ble Supreme
Court dismissed the appeal. It was also observed at para 26 as follows:
"26. An overall reading of Dicitex's application [under
Section 11(6)] clearly shows that its grievance with
respect to the involuntary nature of the discharge
voucher was articulated. It cannot be disputed that
several letters -- spanning over two years--stating that it
was facing financial crisis on account of the delay in
settling the claim, were addressed to the appellant. This
Court is conscious of the fact that an application under
Section 11(6) is in the form of a pleading which merely
seeks an order of the court, for appointment of an
arbitrator. It cannot be conclusive of the pleas or
contentions that the claimant or the party concerned can
take in the arbitral proceedings. At this stage, therefore,
the court which is required to ensure that an arbitrable
dispute exists, has to be prima facie convinced about the
genuineness or credibility of the plea of coercion; it
cannot be too particular about the nature of the plea,
which necessarily has to be made and established in the
substantive (read : arbitration) proceeding. If the court
were to take a contrary approach and minutely examine
the plea and judge its credibility or reasonableness, there
would be a danger of its denying a forum to the applicant
altogether, because rejection of the application would
render the finding (about the finality of the discharge and
its effect as satisfaction) final, thus, precluding the 14 HCJ A.A.No.165 of 2014
applicant of its right event to approach a civil court.
There are decisions of this Court (Associated
Construction v. Pawanhans Helicopters Ltd. [Associated
Construction v. Pawanhans Helicopters Ltd., (2008) 16
SCC 128] and Boghara Polyfab [National Insurance Co.
Ltd. v. Boghara Polyfab (P) Ltd., (2009) 1 SCC 267 :
(2009) 1 SCC (Civ) 117] which upheld the concept of
economic duress. Having regard to the facts and
circumstances, this Court is of the opinion that the
reasoning in the impugned judgment [Dicitex Furnishing
Ltd. v. Oriental Insurance Co. Ltd., 2015 SCC OnLine Bom
5055] cannot be faulted.
25. In Dicitex Furnishing Limited (supra), the Hon'ble Supreme
Court had not considered Section 11(6-A) of the Act of 1996. The
decision rendered by the three-Judge Bench in Mayavati Trading
Private Limited (supra) was also not brought to the notice and it was
on the basis of consideration of the materials on record, the Hon'ble
Supreme Court had accepted that Dicitex was facing financial distress and
economic distress and in view of its various urgent business liabilities, it
apparently signed the said discharge voucher reluctantly and that the
Oriental Insurance Company had refused to accept such discharge
voucher signed by Dicitex with letter of protest.
26. In view of the decision rendered in Mayavati Trading Private
Limited (supra), wherein a three-Judge Bench of the Hon'ble Supreme
Court had observed that as Section 11(6-A) is confined to the examination
of the existence of an arbitration agreement and is to be understood in a
narrow sense and as the law which enabled the court to examine as to 15 HCJ A.A.No.165 of 2014
whether accord and satisfaction had taken place has been legislatively
overruled, it will not be necessary for this Court to go into the aforesaid
question as to whether the applicant had voluntarily executed Indemnity
Bond, Discharge Bond and also consent letter or whether the applicant
had signed such indemnity bond, discharge bond and also consent letter
unconditionally and the same is left open to be decided by the Arbitral
Tribunal.
27. In Vidya Drolia and others v. Durga Trading Corporation,
reported in (2019) 20 SCC 406, a reference was made to a Bench of
three Judges vide order dated 28.02.2019 as it doubted the legal ratio
expressed in Himangni Enterprises v. Kamaljeet Singh Ahluwalia,
reported in (2017) 10 SCC 706 that landlord-tenant disputes governed
by the provisions of the Transfer of Property Act, 1882 are not arbitrable
as this would be contrary to public policy. The reference was answered in
Vidya Drolia and others v. Durga Trading Corporation, reported in
(2021) 2 SCC 1, which, hereinafter shall be referred to as Vidya Drolia
2 (supra) whenever necessary. The Hon'ble Supreme Court observed that
the issues required to be answered relate to two distinct but
interconnected matters, viz:
"2.1. (i) Meaning of non-arbitrability and when the
subject-matter of the dispute is not capable of being
resolved through arbitration.
2.2. (ii) The conundrum -- "who decides" -- whether the
court at the reference stage or the Arbitral Tribunal in
the arbitration proceedings would decide the question of
non-arbitrability.
16 HCJ
A.A.No.165 of 2014
2.3. The second aspect also relates to the scope and
ambit of jurisdiction of the court at the referral stage
when an objection of non-arbitrability is raised to an
application under Section 8 or 11 of the Arbitration and
Conciliation Act, 1996 (for short "the Arbitration Act")."
28. In Vidya Drolia 2 (supra), the Hon'ble Supreme Court
propounded a four-fold test for determining when the subject matter of
the dispute in an arbitrable agreement is not arbitrable. It was also
observed that the aforesaid principles ought to be applied with care and
caution. While overruling the ratio laid down in Himangni Enterprises
(supra), it was held that landlord-tenant disputes are arbitrable as the
Transfer of Property Act does not forbid or foreclose arbitration. It was,
however, held that landlord-tenant disputes covered and governed by
rent control legislation would not be arbitrable when specific court or
forum has been given exclusive jurisdiction to apply and decide special
rights and obligations. Such rights and obligations can only be adjudicated
and enforced by the specified court/forum, and not through arbitration.
The Hon'ble Supreme Court at para 86 held that the legal position as to
who decides the question of non-arbitrability under the Act of 1996 can
be divided into four phases, which reads as follows:
"86. The legal position as to who decides the question of
non-arbitrability under the Arbitration Act can be divided
into four phases. The first phase was from the
enforcement of the Arbitration Act till the decision of the
Constitution Bench of seven Judges in Patel Engg.
Ltd. [SBP & Co. v. Patel Engg. Ltd., (2005) 8 SCC 618] on
26-10-2005. For nearly ten years, the ratio expressed 17 HCJ A.A.No.165 of 2014
in Konkan Railway Corpn. Ltd. v. Mehul Construction
Co. [Konkan Railway Corpn. Ltd. v. Mehul Construction
Co., (2000) 7 SCC 201] , affirmed by the Constitution
Bench of five Judges in Konkan Railway Corpn.
Ltd. v. Rani Construction (P) Ltd. [Konkan Railway Corpn.
Ltd. v. Rani Construction (P) Ltd., (2002) 2 SCC 388] ,
had prevailed. The second phase commenced with the
decision in Patel Engg. Ltd. [SBP & Co. v. Patel Engg.
Ltd., (2005) 8 SCC 618] till the legislative amendments,
which were made to substantially reduce court
interference and overrule the legal effect of Patel Engg.
Ltd. [SBP & Co. v. Patel Engg. Ltd., (2005) 8 SCC 618]
vide Act 3 of 2016 with retrospective effect from 23-10-
2015. The third phase commenced with effect from 23-
10-2015 and continued till the enactment of Act 33 of
2019 with effect from 9-8-2019, from where commenced
the fourth phase, with a clear intent to promote
institutionalised arbitration rather than ad hoc arbitration.
The amendments introduced by Act 33 of 2019 have been
partially implemented and enforced."
29. Reference was made to the two-Judge Bench decision in Boghara
Polyfab (P) Ltd. (supra) wherein the Hon'ble Supreme Court had
identified and segregated the issues that arise for consideration in an
application under Section 11 the Act of 1996 into three categories and had
reproduced para 22 in that context. It will be appropriate to take note of
para 22.1 of Boghara Polyfab (P) Ltd. (supra), which is as under:
18 HCJ
A.A.No.165 of 2014
"22.1. The issues (first category) which the Chief
Justice/his designate will have to decide are:
(a) Whether the party making the application has
approached the appropriate High Court.
(b) Whether there is an arbitration agreement and
whether the party who has applied under Section 11 of
the Act, is a party to such an agreement."
30. The Hon'ble Supreme Court in Vidya Drolia 2 (supra), in the
Indian context, adopted three categories as identified in Boghara
Polyfab (P) Ltd. (supra). It was observed as follows:
"138 ...
The first category of issues, namely, whether the party
has approached the appropriate High Court, whether
there is an arbitration agreement and whether the party
who has applied for reference is party to such agreement
would be subject to more thorough examination in
comparison to the second and third categories/issues
which are presumptively, save in exceptional cases, for
the arbitrator to decide. In the first category, we would
add and include the question or issue relating to whether
the cause of action relates to action in personam or rem;
whether the subject-matter of the dispute affects third-
party rights, have erga omnes effect, requires centralised
adjudication; whether the subject-matter relates to
inalienable sovereign and public interest functions of the
State; and whether the subject-matter of dispute is 19 HCJ A.A.No.165 of 2014
expressly or by necessary implication non-arbitrable as
per mandatory statute(s). Such questions arise rarely
and, when they arise, are on most occasions questions of
law. On the other hand, issues relating to contract
formation, existence, validity and non-arbitrability would
be connected and intertwined with the issues underlying
the merits of the respective disputes/claims. They would
be factual and disputed and for the Arbitral Tribunal to
decide."
31. While dealing with the omission of sub-section (6-A) by Act 33 of
2019, it was observed that the same was with a specific object and
purpose and is relatable to substitution of sub-sections (12), (13) and (14)
of Section 11 of the Act of 1996 by Act 33 of 2019.
32. In the light of the above background, it was observed that it would
be wrong to accept that post omission of sub-section (6-A) of Section 11,
the ratio in SBP & Co. (supra) would become applicable.
33. Proceeding to examine the question as to whether the word
"existence" in Section 11 refers to contract formation (whether there is an
arbitration agreement) and excludes the question of enforcement
(validity) and therefore the latter falls outside the jurisdiction of the court
at the referral stage, it was held that existence of an arbitration
agreement pre-supposes a valid agreement. It was held that a
reasonable and just interpretation of "existence" requires understanding
the context, the purpose and the relevant legal norms applicable for a
binding and enforceable arbitration agreement. An agreement evidenced
in writing has no meaning unless the parties can be compelled to adhere 20 HCJ A.A.No.165 of 2014
and abide by the terms. A void and unenforceable understanding is no
agreement to do anything. In that context, it was held that existence of
an arbitration agreement means an arbitration agreement that meets and
satisfies the statutory requirements of both the Arbitration Act and the
Contract Act and when it is enforceable in law. At paragraphs, 139, 140 &
141, it was observed as follows:
"139. We would not like to be too prescriptive, albeit
observe that the court may for legitimate reasons, to
prevent wastage of public and private resources, can
exercise judicial discretion to conduct an intense yet
summary prima facie review while remaining conscious
that it is to assist the arbitration procedure and not usurp
jurisdiction of the Arbitral Tribunal. Undertaking a detailed
full review or a long-drawn review at the referral stage
would obstruct and cause delay undermining the integrity
and efficacy of arbitration as a dispute resolution
mechanism. Conversely, if the court becomes too
reluctant to intervene, it may undermine effectiveness of
both the arbitration and the court. There are certain cases
where the prima facie examination may require a deeper
consideration. The court's challenge is to find the right
amount of and the context when it would examine the
prima facie case or exercise restraint. The legal order
needs a right balance between avoiding arbitration
obstructing tactics at referral stage and protecting parties
from being forced to arbitrate when the matter is clearly
non-arbitrable."
21 HCJ
A.A.No.165 of 2014
140. Accordingly, when it appears that prima facie review
would be inconclusive, or on consideration inadequate as
it requires detailed examination, the matter should be left
for final determination by the Arbitral Tribunal selected by
the parties by consent. The underlying rationale being not
to delay or defer and to discourage parties from using
referral proceeding as a ruse to delay and obstruct. In
such cases a full review by the courts at this stage would
encroach on the jurisdiction of the Arbitral Tribunal and
violate the legislative scheme allocating jurisdiction
between the courts and the Arbitral Tribunal.
Centralisation of litigation with the Arbitral Tribunal as the
primary and first adjudicator is beneficent as it helps in
quicker and efficient resolution of disputes."
141. The court would exercise discretion and refer the
disputes to arbitration when it is satisfied that the contest
requires the Arbitral Tribunal should first decide the
disputes and rule on non-arbitrability. Similarly, discretion
should be exercised when the party opposing arbitration
is adopting delaying tactics and impairing the referral
proceedings. Appropriate in this regard, are observations
of the Supreme Court of Canada in Dell Computer
Corpn. v. Union des Consommateurs & Olivier
Dumoulin [Dell Computer Corpn. v. Union des
Consommateurs & Olivier Dumoulin, 2007 SCC OnLine
Can SC 34 : (2007) 2 SCR 801 : 2007 SCC 34] , which
read: (SCC OnLine Can SC paras 85-86) 22 HCJ A.A.No.165 of 2014
"85. If the challenge requires the production and review
of factual evidence, the court should normally refer the
case to arbitration, as arbitrators have, for this purpose,
the same resources and expertise as courts. Where
questions of mixed law and fact are concerned, the court
hearing the referral application must refer the case to
arbitration unless the questions of fact require only
superficial consideration of the documentary evidence in
the record.
86. Before departing from the general rule of referral, the
court must be satisfied that the challenge to the
arbitrator's jurisdiction is not a delaying tactic and that it
will not unduly impair the conduct of the arbitration
proceeding. This means that even when considering one
of the exceptions, the court might decide that to allow the
arbitrator to rule first on his or her competence would be
best for the arbitration process."
34. It was further held that the court at the referral stage would apply
the prima facie test with regard to the expression "existence of an
arbitration agreement" in Section 11 of the Arbitration Act, which includes
aspect of validity of an arbitration agreement on the basis of principles set
out in the judgment. In cases of debatable and disputable facts, and good
reasonable arguable case, etc., the court would force the parties to abide
by the arbitration agreement as the Arbitral Tribunal has primary
jurisdiction and authority to decide the disputes including the question of
jurisdiction and non-arbitrability.
23 HCJ
A.A.No.165 of 2014
35. The Hon'ble Supreme Court held that limitation law being
procedural and normally disputes being factual, it would be for the
arbitrator to decide guided by the facts found and the law applicable. The
court at the referral stage can interfere only when it is manifest that the
claims are ex-facie time-barred and dead or there is no subsisting dispute.
All other cases should be referred to the Arbitral Tribunal for decision on
merits. It was also held that similar would be the position in case of
disputed "no-claim certificate" or defence on the plea of novation and
"accord and satisfaction"
36. At para 154, discussion under the heading "Who Decides
Arbitrability", is crystallized as follows:
"154. Discussion under the heading "Who Decides
Arbitrability?" can be crystallised as under:
154.1. Ratio of the decision in Patel Engg. Ltd. [SBP &
Co. v. Patel Engg. Ltd., (2005) 8 SCC 618] on the scope of
judicial review by the court while deciding an application
under Sections 8 or 11 of the Arbitration Act, post the
amendments by Act 3 of 2016 (with retrospective effect
from 23-10-2015) and even post the amendments vide Act
33 of 2019 (with effect from 9-8-2019), is no longer
applicable.
154.2. Scope of judicial review and jurisdiction of the court
under Sections 8 and 11 of the Arbitration Act is identical
but extremely limited and restricted.
24 HCJ
A.A.No.165 of 2014
154.3. The general rule and principle, in view of the
legislative mandate clear from Act 3 of 2016 and Act 33 of
2019, and the principle of severability and competence-
competence, is that the Arbitral Tribunal is the preferred
first authority to determine and decide all questions of
non-arbitrability. The court has been conferred power of
"second look" on aspects of non-arbitrability post the
award in terms of sub-clauses (i), (ii) or (iv) of Section
34(2)(a) or sub-clause (i) of Section 34(2)(b) of the
Arbitration Act.
154.4. Rarely as a demurrer the court may interfere at
Section 8 or 11 stage when it is manifestly and ex facie
certain that the arbitration agreement is non-existent,
invalid or the disputes are non-arbitrable, though the
nature and facet of non-arbitrability would, to some extent,
determine the level and nature of judicial scrutiny. The
restricted and limited review is to check and protect parties
from being forced to arbitrate when the matter is
demonstrably "non-arbitrable" and to cut off the
deadwood. The court by default would refer the matter
when contentions relating to non-arbitrability are plainly
arguable; when consideration in summary proceedings
would be insufficient and inconclusive; when facts are
contested; when the party opposing arbitration adopts
delaying tactics or impairs conduct of arbitration
proceedings. This is not the stage for the court to enter
into a mini trial or elaborate review so as to usurp the 25 HCJ A.A.No.165 of 2014
jurisdiction of the Arbitral Tribunal but to affirm and uphold
integrity and efficacy of arbitration as an alternative
dispute resolution mechanism."
37. In view of the discussions above, notwithstanding that the
petitioner had executed Indemnity Bond, Discharge Bond and consent
letter, as the petitioner had raised various pleas with regard to such
execution, the dispute between the parties is required to be referred to an
arbitrator, as there is a valid arbitration agreement.
38. Resultantly, the Arbitration Application is allowed. Dr. Justice
B. Siva Sankara Rao is appointed as arbitrator to adjudicate the disputes
between the parties. No costs. Pending miscellaneous applications, if any,
shall stand closed.
39. The fee of the arbitrator as well as the other terms and conditions
shall be settled by the parties in consultation with the arbitrator so
appointed. Registry will send a copy of this order to Dr. Justice B. Siva
Sankara Rao in his proper address.
Sd/-
ARUP KUMAR GOSWAMI, CJ
MRR
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!