Citation : 2021 Latest Caselaw 4127 AP
Judgement Date : 21 October, 2021
THE HON'BLE SRI JUSTICE A.V.SESHA SAI
WRIT PETITION No.10421 OF 2021
ORDER:
This Writ Petition, filed under Article 226 of the
Constitution of India, calls in question the order passed by
the Superintending Engineer, Operation Circle, APCPDCL,
Ongole, respondent No.3 herein, vide Letter bearing
LR.No.SE.O.OGL.TECH.E.DOC.E.No. 261047/2021 dated
12.05.2021, terminating L.S.Agreement No.105/2020-21
dated 18.09.2020.
2. According to the petitioner, it is a Proprietory
concern and the deponent of the writ affidavit, who is the
Proprietor of the petitioner-Proprietory concern, has been
eking out his livelihood by executing electrical work
contracts. The Andhra Pradesh Electrical Licencing Board,
Government of Andhra Pradesh, issued electrical contract
licence Grade-A in favour of the petitioner and the same is
being renewed from time to time, enabling the petitioner to
undertake operation and maintenance works at 33/11 K.V.
Sub-Stations. In response to a tender floated by respondent
No.2 for carrying out Manning of Sub-Stations, Operation
and Maintenance including Watch and Ward at 33/11 K.V.
Sub-Stations, the petitioner herein participated in the said
process of tenders and emerged as successful bidder for the
Sub-Stations at Adusumilli, Karamchedu, Swarna,
Edupulapadu, Motupalli, Vallapalli, Uppumaguluru,
Vemavaram, Komminenivari-palem, Velamvaripalem. The
Superintending Engineer, respondent No.3 herein, executed
L.S.Agreement on 18.09.2020, covering all the above said
Sub-Stations in favour of the petitioner herein for
undertaking the works for a period of two years, commencing
from 01.09.2020 to 31.08.2022. According to the petitioner,
he appointed the Shift Operators/Watchmen and intimated
the same to respondent Nos.3 to 5 to take necessary steps for
verification of certificates by duly fixing the dates. The
Executive Engineer, Chirala, respondent No.4 herein issued a
notice dated 07.12.2020, asking the petitioner to produce the
following:
(1) Validity of Original Grade-A Electrical Contract Licence cum original permit books.
(2) Supervisor in person along with Original permit certificate and Book.
(3) Wireman in person along with Original permit certificate.
(4) Equipment along with test certificate.
3. It is pleaded by the petitioner herein in the
affidavit filed in support of the Writ Petition that by way of a
reply dated 24.12.2020 (acknowledged by the office of
respondent No.4 on 28.10.2020), he produced the entire
information sought.
4. The Executive Engineer, Addanki, respondent
No.5 herein issued a notice dated 07.12.2020, asking the
same information as sought by respondent No.4 in the above
mentioned notice dated 07.12.2020 and according to the
petitioner, vide reply dated 16.12.2020, he produced the
entire information sought and the office of respondent No.5
also acknowledged the same on the even date.
5. Subsequently, vide letter dated 05.02.2021,
respondent No.3/Superintending Engineer instructed the
petitioner to attend his office on or before 11.02.2021 with
relevant documents, pertaining to Wireman permit No.0-
304244 along with the persons during office working hours of
any working day between 10.30 a.m. and 5.00 p.m. and also
directed the petitioner to produce the following
documents/information:
1. Original Appointment Letters issued to Supervisor & Wiremen.
2. Attendance Register of Supervisor and Wiremen.
3. Salary particulars paid to supervisor and Wiremen including E.P.F., E.S.I./Insurance Register numbers.
4. List of contract works done by the agency along with Purchase Orders/Work Orders details.
5. Performance Certificate issued by the department.
6. Ownership/Rental receipts paid by the agency for the address location specified.
6. In reply to the same, according to the petitioner,
he submitted explanation dated 11.02.2021, enclosing the
following:
1) Valid A grade licence original.
2) Supervisor and wireman competency certificates original.
3) Super permit book upto 33KV original book.
4) Wire man permit book copies.
5) Superviser in person.
6) Wireman in person - two persons.
7) Insulation megger 2.5KV, 0.5000 M ohm.
8) Insulation megger 1000 volts, 0-500 M ohm.
9) Insulation megger 500 volts, 0-100 m ohm.
10) Earth megger 0-10 M ohm, 0-1000 M ohm.
11) Tong Tester voltage 0-750 volts Amps 0-1000 amps Resistance 0-20 K ohm
12) 7 to 11, Equipment test certificates enclosed.
13) Attendance Register of Supervisor and Wireman's.
14) Salary particulars paid to supervisor and wireman's including E.P.F., ESI/Insurance Register Numbers.
15) List of contract works done by the agency along with purchase orders/work order details.
16) Ownership/Rental receipts paid by the agency for the address location specified.
7. Vide letter bearing No.LR.No.SE.O.OGL.TECH.F.
DOC.E.No.257476/2021 dated 03.04.2021, the
Superintending Engineer, respondent No.3 herein, issued a
final notice, pointing out the following alleged lapses on the
part of the petitioner herein:
1. The Particulars of E.P.F., ESI in respect of 2 Nos working wire men namely R.Bala Krishna and K.Sambasiva Rao for the period 01.09.2020 (i.e., date of Agreement) to 31.12.2020 are not submitted.
2. The particulars of Salary payment made through Bank along with proof of Bank Account details in respect of 2 Nos working wire men namely R. Bala Krishna and K.Sambasiva Rao for the period 01.09.2020 (i.e., date of Agreement) to 31.01.2021 are not submitted.
3. As per the Attendance Register 2 Nos working wiremen were not engaged full time for the said work as given below.
8. In response to the above letter, the petitioner herein
submitted a reply dated 07.04.2021 and eventually, the
Superintending Engineer-respondent No.3 herein, vide letter
dated 12.05.2021, terminated the L.S.Agreement dated
18.09.2020. This Writ Petition filed under Article 226 of the
Constitution of India assails the validity and legal sustainability
of the said order of termination.
9. The respondents herein have filed counter affidavit
and a reply is also filed by the writ petitioner.
10. Heard Sri V.Venugopal Rao, learned counsel for the
petitioner and Sri Y.Nagireddy, learned Standing Counsel for the
respondent-Corporation, apart from perusing the material
available on record.
11. Contentions/submissions of Sri V.Venugopal Rao,
learned counsel for the petitioner:
(1) The order impugned in the present Writ Petition is
highly illegal, arbitrary, unreasonable, malafide, discriminatory
and violative of Articles 14 and 19(1)(g) of the Constitution of
India.
(2) The grounds assigned by the respondent-authorities for
terminating the L.S.Agreement are neither sustainable nor
tenable in the eye of law.
(3) The reason assigned in the impugned order that there
was no valid Grade-A Electrical Contractor's Licence as on date
of tender is contrary to the orders dated 30.03.2021 and the
respondent ought to have seen that the deemed suspension was
on account of Covid-19 pandamic and the licence stood extended
with retrospective effect.
(4) The competent authority to issue A-Grade Licence is the
A.P.Electrical Licencing Board, which granted licence renewal
upto14.07.2021 and the Board issued the licence on production
of one Supervisor permit and 2 Wiremen permit and the Board
alone is competent to verify and take action and respondents, if
have any doubt as regards the licence and requirements
contained therein cannot initiate action on their own, but can
report the same to the Board for necessary action, if any.
(5) The respondents herein have absolutely no jurisdiction
to ask information about EPF/ESI, Salary payment and other
particulars as regards the salary payments and the attendance
registers.
12. Contentions/submissions of Sri Y.Nagireddy, learned
Standing Counsel for the respondents:
(1) The present Writ Petition filed under Article 226 of the
Constitution of India is not maintainable as the issue raised in
the Writ Petition pertains to contract.
(2) The contention that the respondents have no
jurisdiction to verify EPF and ESI payments is not tenable in
view of Clauses 6(iii) and 7(ii) & (vi) of the L.S.Agreement.
(3) The contention as regards the alleged harassment and
discrimination is neither true nor has any basis and the
petitioner herein has utterly failed to prove the same by
adducing evidence.
(4) At the time of entering into contract, the petitioner
herein had no valid A-Grade contract licence in his favour and
no intimation was furnished to the respondents about the letter
of the Chief Electrical Inspector dated 30.03.2021.
(5) Clause 36 of the L.S.Agreement mandates filing of
returns before the EPF authorities.
(6) As per Clause 33(T) of the L.S.Agreement, all disputes
arising out of the contract are to be decided in the Courts
situated in the geographical limits of the respective Operation
Circles, as such, the petitioner herein has to file a Civil Suit
before the jurisdictional Civil Court for reddressal of grievances,
if any.
13. In the above background, now the issue which this
Court is called upon to answer in the present Writ Petition is
"Whether the petitioner is entitled for any relief from this Court
under Article 226 of the Constitution of India, having regard to
the facts and circumstances of the case?
14. It is very much manifest from a reading of the
impugned order that on four grounds, the Superintending
Engineer-respondent No.3 herein terminated the L.S.Agreement.
They are:
(1) As per the report received from CEIG (Chief Electrical
Inspector to Government), the "Grade A" Electrical Contractors
Licence issued in favour of the petitioner was deemed to be
under suspension and the petitioner submitted an invalid Grade-
"A" Electrical Licence at the time of submission of the tenders
and the petitioner violated the terms and conditions of the tender
specifications.
(2) Particulars of E.S.I., E.P.F., in respect of 2 Nos. working
Wiremen, namely, R.Balakrishna and K.Sambasiva Rao for the
period 01.09.2020 i.e., the date of agreement, till 31.12.2020
were not submitted.
(3) Particulars of Salary Payment made through Bank along
with proof of Bank account details in respect of 2 Nos. working
Wiremen, namely, R.Balakrishna and K.Sambasiva Rao for the
period from 01.09.2020 i.e., the date of agreement till
31.01.2021 were not submitted.
(4) As per the attendance register 2 Nos. working Wiremen
were not engaged full time for the work as given below:
No. of days engaged Sl.No. Month R.Balakrishna K.Sambasiva Rao
15. In order to consider and adjudicate the validity and
the sustainability of the above said grounds assigned in the
impugned order for terminating the L.S.Agreement, it would be
apposite and appropriate to refer to the notices issued by
respondent No.3 prior to issuing the impugned order and the
explanations offered by the petitioner in response to the same. It
is very much evident from a reading of the letter bearing
No.LR.NO.SE.O.OGL.TECH.F.DOC.E.No.749499/2021 dated
05.02.2021 of the Superintending Engineer-respondent No.3
that respondent No.3 in the said letter indicated only about the
letters of respondent Nos.4 and 5 dated 01.02.2021 and
02.02.2021, wherein respondent Nos.4 and 5 alleged to have
stated that 1 No. Wireman permit No.0-304244 pertaining to 'A'
Grade licence was not produced and respondent No.3 in the said
letter dated 05.02.2021 also instructed the petitioner to produce
as many as 6 documents, namely:
1. Original Appointment Letters issued to Supervisor & Wiremen.
2. Attendance Register of Supervisor and Wiremen.
3. Salary particulars paid to supervisor and Wiremen including E.P.F., E.S.I./Insurance Register numbers.
4. List of contract works done by the agency along with Purchase Orders/Work Orders details.
5. Performance Certificate issued by the department.
6. Ownership/Rental receipts paid by the agency for the address location specified.
16. In response to the said letter dated 05.02.2021,
the petitioner herein submitted a reply dated 11.02.2021,
enclosing as many as 16 documents as mentioned in the
preceding paragraph. Thereafter, vide letter dated
03.04.2021, the Superintending Engineer-respondent No.3
herein issued another notice and the petitioner submitted a
reply dated 07.04.2021 and both the replies dated
11.02.2021 and 07.04.2021 were duly acknowledged by the
office of respondent No.3 and the respondents have not
denied the submission of the said explanations and the
documents enclosed. A perusal of the said
explanations/replies dated 11.02.2021 and 07.04.2021
reveal, in clear and unequivocal terms, that the petitioner
herein enclosed all the relevant documents as regards the
alleged lapses indicated in the show cause notices dated
05.02.2021 and 03.04.2021.
17. With regard to Grade-A Contractor's Licence, both
the petitioner as well as the respondents herein seek to place
reliance on the letter bearing No.Lr.No.EI/Gnl/APELB/D.No.
209 dated 30.03.2021.
18. The specific contention advanced on behalf of the
respondents herein is that at the time of tender process
including L.S.Agreement, the Grade-A Contractor's Licence of
the petitioner was under deemed suspension, as such, the
very tender submitted by the petitioner herein was invalid
and liable for rejection.
19. In order to resolve the issue as regards Grade-A
Contractor's Licence, it may be highly essential to verify the
letter dated 30.03.2021 of the Electrical Inspector. According
to the said letter dated 30.03.2021, there is absolutely no
controversy as regards the permit of one Wireman, namely,
K.Sambasiva Rao and the controversy is only with regard to
the Wireman permit of one Sri R.Balakrishna. According to
the said letter dated 30.03.2021, permit of R.Balakrishna, a
Wireman, bearing No.0-302766 was valid during the period
from 22.06..2015 to 21.06.2020 and subsequently, the
permit holder did not approach the office of the Electrical
Inspector for renewal of his permit within the time, but
subsequently, the said permit came to be revalidated from
14.12.2020 to 13.12.2025. The Electrical Inspector also
opined that in view of the same, the Contractor's Licence was
deemed to be under suspension from 21.03.2020 as the said
Wireman permit holder did not renew his permit within one
month from the date of expiry of his permit. According to the
respondents' version, since the subject tender process took
place during the above said interregnum period and as the
licence of the petitioner herein was under deemed
suspension, the very participation of the petitioner in the
said tenders was impermissible. A significant aspect which
this Court cannot lose sight of is that during the above said
interregnum period, the entire world was under a
tremendous agony due to Covid-19 pandemic and obviously,
due to the said ground reality, the Electrical Inspector
ordered revalidation of the permit of Sri R.Balakrishna. It is
also significant to note in this context that Electrical
Inspector, Guntur Division, Guntur, who is the authority
competent to issue Grade-A Contractor's Licence, also
informed the Superintending Engineer, Operation Circle,
Ongole, in the letter bearing No.Lr.No.EI/Gnl/APELB/D.No.
209 dated 30.03.2021 that the office of the Chief Inspector
would not give any suspension order for the Contractor's
Licence and the same was deemed to be suspended during
that period and would be revoked after the permit holder
renewed the permit. In the said letter, the Electrical
Inspector also made it very much clear that such relaxation
had been given in view of the Covid-19 pandemic situation
and as there was no transportation during the period from
March, 2020 to December, 2020. In view of the above
reasons, the contention contra advanced by the respondents
herein that the petitioner herein participated in the tender
process without valid Grade-A Contractor's Licence cannot
stand for judicial scrutiny. Therefore, the ground assigned in
the impugned order to the said effect is neither sustainable
nor tenable in the eye of law.
20. As regards the other grounds, namely, non-
submission of ESI, EPF pertaining to 2 Nos. Wireman, Salary
Payment and Attendance Register, it is required to be noted
that in response to the notices dated 05.02.2021 and
03.04.2021, the petitioner herein submitted elaborate
replies/explanations dated 11.02.2021 and 07.04.2021 duly
enclosing various documents including the documents
sought by the petitioner herein, but the Superintending
Engineer-respondent No.3 herein in the impugned order
conveniently mentioned that only certain details were
furnished by the petitioner, but did not mention the details of
the said information. Having called for the information, vide
notices dated 05.02.2021 and 03.04.2021 and having
acknowledged the replies/explanations dated 11.02.2021
and 07.04.2021, this Court does not find any valid reason/
justification on the part of respondent No.3-Superintending
Engineer in not referring to and not considering the contents
of the said explanations and the documents enclosed
therewith. This exercise undertaken by respondent No.3, in
the considered opinion of this Court, is patently arbitrary and
infringes the fundamental right guaranteed to the citizens
under Article 14 of the Constitution of India and this Court
does not find any justification on the part of respondent No.3
in undertaking the process of termination of the
L.S.Agreement in such an arbitrary manner. It is a settled
and well-established principle of law that when the impugned
action is patently arbitrary and illegal, the Writ Petition is
maintainable even in contractual matters in view of the law
laid down by the Hon'ble Supreme Court in Tata Cellular Vs.
Union of India1. In the case on hand, this Court finds such a
contingency, as such, the contention contra advanced by the
learned counsel for the respondents as regards the
maintainability of the Writ Petition is not sustainable. In the
considered opinion of this Court, the judgment of the Hon'ble
Supreme Court dated 21.11.2001 passed in Appeal (Civil)
No.7932 of 2001 in the case of State of Bihar and others Vs.
Jain Plastics and Chemicals Limited, on which reliance is
placed by the learned counsel for the petitioner, would not
render any assistance to the petitioner, having regard to the
facts and circumstances of the present Writ Petition.
21. For the aforesaid reasons, the Writ Petition is
allowed, setting aside the impugned order passed by the
Superintending Engineer-respondent No.3 herein, vide Letter
bearing LR.No.SE.O.OGL.TECH.E.DOC.E.No.261047/2021
dated 12.05.2021 and the matter is remanded to respondent
No.3 for fresh consideration of the issues and for passing
appropriate orders/taking appropriate action strictly in
accordance with law after giving opportunity of hearing to the
petitioner herein and taking into account the contents of the
1996 AIR 11 = 1994 SCC (6) 651
explanations/replies submitted by the petitioner dated
11.02.2021 and 07.04.2021 and in the light of the
observations made supra. There shall be no order as to costs
of the Writ Petition.
Interlocutory applications pending, if any in the Writ
Petition, shall stand closed.
__________________ A.V.SESHA SAI, J
21.10.2021 siva
THE HON'BLE SRI JUSTICE A.V.SESHA SAI
WRIT PETITION No.10421 OF 2021
21.10.2021 siva
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!