Citation : 2021 Latest Caselaw 1787 AP
Judgement Date : 31 March, 2021
HON'BLE SRI JUSTICE D.V.S.S.SOMAYAJULU
W.P.No.5309 of 2021
ORDER:
This writ petition is filed for the following relief:
"To issue an appropriate writ or order or direction more particularly one in the nature of Writ of Mandamus declaring the proceedings in Roc.No.555/2015G4 dated 24.02.2021 issued by the 2nd Respondent canceling the Work Order dated 25.08.2020 is highly illegal, arbitrary and violative of principles of natural justice and accordingly set aside the same with a consequential directions to the Respondents to permit the Petitioner to execute the works as per Work Order dated 25 08 2020...."
This Court has heard Sri Dheera Kanishk, learned
counsel for the petitioner and Sri Manohar Reddy learned
counsel appearing for respondent Nos.2 to 4. For the 1st
respondent, Government Pleader for Municipal
Administration appears.
Counsel for the petitioner points out that the
petitioner's work was terminated by proceedings dated
24.02.2021. He raises two essential contentions (a) that the
termination was not because of any failure in the contract
and (b) that the petitioner was not given a copy of the
complaint submitted by a third party on the basis of which he
was removed.
Learned counsel submits that the petitioner was issued
a work for supplying vehicle/tipper to the town planning
section of the respondent for a period of eight months along
with a driver and five workers. However, he points out that
the petitioner's services were terminated on the basis of a
complaint given by one Sri Ismail Thahir. He admits that
even though the enquiry has taken place, it is not related to
his failure to perform the contract and therefore, he argues
that the termination is bad. It is also submitted that the copy
of the complaint alleged to have been received is not given to
him. Therefore, there is a failure of the rules of natural
justice.
Sri Manohar Reddy, learned standing counsel for the
respondent relies upon the impugned order and points out
that the due process of law was followed. He points out that
the statement of the petitioner is also recorded by the
Commissioner before the impugned order was passed. It is
also clarified that the petitioner participated in the enquiry
and after considering the statements recorded, evidence
gathered etc., the impugned order was passed. He took the
Court through the order dated 24.02.2021 which is impugned
in this writ petition to argue that it is a perfectly reasoned
order passed after considering the facts and the evidence.
Learned counsel for the petitioner also relied upon the
case law, which is filed by him along with a memo vide USR
No.18785 of 2021. The first grievance of the petitioner is
that since the complaint given by the said Sri Ismail Thahir is
not supplied, the petitioner was handicapped in preparing a
reply. It is also argued that rules of natural justice were
totally flouted. On this ground itself, the learned counsel
submitted that the enquiry should be set aside.
However, this Court notices that a show cause notice
was issued on 29.12.2020 to which a reply was issued by the
petitioner on 27.02.2021. Only on 08.01.2021 he gave a
letter requesting for a copy of the complaint. This letter
dated 08.01.2021 appears to have been delivered to the
respondent on 08.02.2021. It is also clear that the
petitioner's statement was recorded on 08.02.2021 in the
Commissioners' chamber. Therefore, this Court holds that
the petitioner participated in the enquiry without any
reservation. The date of service of the letter is also not clear,
whether it is 08.01.2021 or 08.02.2021. This Court,
therefore, holds that it cannot be presumed that there is a
failure of the rules of natural justice. Prejudice also does not
appear to have been caused since the petitioner knew facts
that are alleged against him and also participated in the
enquiry.
However, the second issue alleged by the petitioner is
more important in the opinion of this Court. In the grounds
that are urged, it is very clearly stated that the contract work
has been satisfactorily executed and more than 50% was
completed. In said para (d) of the grounds, it is also urged
that there is no complaint about the execution of the work.
In the course of hearing, learned counsel relied upon a
case law and a case reported in M/s. Pancham Singh v. The
State of Bihar1. In that case, the Full Bench of the Patna
High Court commented upon the cancellation of a contract,
dehorns the terms of the contract. Relying upon
Radhakrishna Agarwal v. State of Bihar2, the Full Bench
held that a contract cannot be cancelled, dehors any of its
terms and that such an action is per se violative of Article 14
of the Constitution of India.
The contract agreement between the parties is also filed.
It is for supply of a tipper with five workers and one driver.
Therefore, the essence of the contract is the supply of vehicle
with workers thereon. However, the ground on which the
action was taken against the petitioner is that on 23.12.2020,
a board of a business venture called Moghal Biryani Palace, is
removed without prior intimation. Later, when the owner
came and met the petitioner, he was abused. This is the gist
1991 SCC Online Part 31
AIR 1977 SC 1496
of the complaint against the petitioner. A show cause notice
was issued; an enquiry was conducted and ultimately, his
contract was terminated. A reading of the clauses of the
contract does not show that the respondents have reserved a
right to cancel the contract in the event of the personal
behavior of the tender/contractor being improper. The order
impugned does not refer to any of the terms and conditions of
the contract which could be relied upon for terminating the
contract. The conduct of the petitioner in removing a board
and not taking care of it is not an issue that is covered by the
terms and conditions of the contract. Even though the
petitioner participated in the said enquiry, it cannot be said
that the respondents have a right to cancel the contract
agreement. The actions of a State or State Authorities should
be informed by a reason and based upon law and the terms of
the contract.
During the course of hearing, no provision of law was
brought to the notice of this Court which would justify the
termination of the order. Similarly, no term of the contract
which would justify the termination in case of such alleged
misconduct/misbehavior is brought to the notice of the
Court.
The mere fact that the petitioner participated in this
interview cannot be held against him. In the opinion of this
Court, the action taken by the respondent is per se illegal and
incorrect. The judgment of the Hon'ble Supreme Court which
is referred to in the Full Bench judgment of the Patna High
Court is in the opinion of this Court is applicable to the facts
of the case. Cancellation of the contract was not for the
breach of any of the terms of the contract. The cancellation is
dehors the terms of the contract and hence, it is held to be
per se illegal. The proceedings dated 24.02.2021 are set
aside.
The counsel for the petitioner argued that the works
were to be completed in March, 2021. In the opinion of this
Court, restoration of the contract and ordering status quo
ante is not really called for. The black mark on the record of
the petitioner in the form of termination of the contract is set
aside without ordering restoration. It is however, left open to
the petitioner to proceed against the respondent-Municipality,
if he so desires for recovery of monetary
compensation/damages etc.
With these observations, the writ petition is allowed. No
order as to costs.
As a sequel, the miscellaneous petitions if any shall
stand dismissed.
________________________ D.V.S.S.SOMAYAJULU,J
Date : 31.03.2021 KLP
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!