Citation : 2021 Latest Caselaw 1431 AP
Judgement Date : 8 March, 2021
HON'BLE SMT JUSTICE KONGARA VIJAYA LAKSHMI
Writ Petition No.5094 of 2021
ORDER:
This Writ Petition is filed to declare the action of the
respondents in conducting the tender process with respect to tender
notification dated 21.01.2021 and rejecting the petitioner's technical
bid as arbitrary and illegal.
2. Case of the petitioner is that, the second respondent issued
e-procurement tender notification on 21.01.2021 for supply of shoes
and socks and as per the tender notification, last date for uploading of
corrigendum is 03.02.2021, bid closing date is 06.02.2021, technical
evaluation is on 08.02.2021, opening of financial bid is on 09.02.2021
and reverse auction is on 09.02.2021. As per corrigendum-3, last date
for uploading of corrigendum is 08.02.2021, bid closing date is
10.02.2021, technical evaluation is on 11.02.2021 and 13.02.2021,
opening of financial bids is on 16.02.2021 and reverse auction is on
16.02.2021. Section II of the tender document deals with instructions to
the bidders and as per Clause 1.1 (h) of Section II, the firm should
furnish solvency certificate; the second respondent issued corrigendum-
I on 08.02.2021 amending clause (h) of Clause 1.1 as "the firm should
furnish latest solvency certificate for minimum value of 50% of ECV"; as
per the said amended clause, petitioner uploaded the solvency
certificate dated 11.02.2021 issued by the Chartered Accountant; it is
not mentioned either in the original bid document or in the
corrigendums that the solvency certificate should be issued by the
Bank; along with the petitioner Four other bidders participated in the
tender and among them only Bata India Limited and the Fourth
KVL, J WP No.5094 of 2021
respondent submitted solvency certificates furnished by the Bank and
one Manjeet Plastic Industries initially submitted solvency certificate
issued by the chartered accountant, but later, after the bid closing
date, they furnished solvency certificate issued by the Bank; the
officers of the respondents informed the said Manjeet Plastic Industries
about the requirement of submission of solvency certificate issued by
the Bank in advance and hence they furnished the same and got
themselves qualified in technical evaluation and participated in the
reverse auction; on 23.02.2021 petitioner received a phone call from
one Bharat Kumar, Joint Director, asking him to submit solvency
certificate issued by the Bank and on 24.02.2021 the authorized
signatory of the petitioner addressed a mail to the second respondent
stating that as per the tender document petitioner has already
submitted all the documents and if the petitioner has to submit any
other document a request was made to send a mail, however no reply
was received to the said mail and that on 25.02.2021 petitioner
submitted solvency certificate issued by the bank through mail and
informed the same to the second respondent i.e., Mr. Vijay Kumar and
on 26.02.2021 morning petitioner tried to contact the second
respondent, but there was no response; it was also informed to the
Project Director through Whatsapp that the petitioner sent solvency
certificate issued by the Bank through mail which was acknowledged by
the said Vijay Kumar and in the noon the Project Director informed the
petitioner that the time has lapsed for submission of solvency
certificate; had the petitioner been informed about the requirement of
furnishing of the solvency certificate issued by the Bank, the petitioner
would have furnished the same at the earliest; the respondents
informed about the requirement of furnishing of solvency certificate by
KVL, J WP No.5094 of 2021
the bank to some other bidders in advance with an intention to
eliminate the petitioner and the Third respondent disqualified the
petitioner in the technical evaluation and the reverse tendering was
conducted on 26.02.2021 and the Fourth respondent was declared as
L1; the procedure adopted is mala fide and to favour someone.
3. Counter affidavit is filed by the second respondent stating,
inter alia, that as per Clause 6(b) of Section I of the tender document
the bidder has to keep track of any changes by viewing addendum/
corrigendum on time to time basis in the e-procurement platform and
in response to the notification, seven bidders participated and out of
seven bidders only two firms i.e., Bata India Limited and the Fourth
respondent herein have submitted all the required documents and the
petitioner and another firm by name Manjeet Plastic Industries were
asked on 17.02.2021 over phone to submit solvency certificates issued
by the Bank by 24.02.2021 and subsequently the said Manjeet Plastic
Industries submitted the solvency certificate dated 16.02.2021, issued
by the Bank on 24.02.2021 and when the matter was placed before the
procurement committee on 24.02.2021 and the committee took a
decision to disqualify those firms who have not furnished the required
documents as on 24.02.2021 and decided to qualify Manjeet Plastic
Industries and disqualified the petitioner herein; Mr. Bharat Kumar,
Joint Director, called the petitioner only to remind about the solvency
certificate; three firms i.e., Bata, Lehar-4th respondent herein and
Manjeet Plastic Industries have become technically qualified and
hence, their financial bids were opened and reverse tendering was
done.
KVL, J WP No.5094 of 2021
4. Reply-affidavit is filed by the petitioner stating inter-alia
that, other two firms also submitted solvency certificate issued by the
Chartered Accountant and not bank, which shows that there is
ambiguity in the said condition; even in the corrigendum-I issued on
08.02.2021, it is not stated that the solvency certificate has to be
issued by the bank and no time limit is prescribed for submission of the
solvency certificate; as per clause 3.2 of Section II the tender
document any such addenda/corrigenda shall be posted on the e-
procurement website only and no other communication shall be made
to any firm in this regard; petitioner was not informed on 17.02.2021
and that it was informed only on 23.02.2021 through telephone call
with regard to furnishing of solvency certificate issued by the bank,
without prescribing any time limit for submission of the same;
petitioner submitted solvency certificate issued by the bank on
25.02.2021 and that the respondents did not dispute the submission of
the solvency certificate issued by the bank on 25.02.2021 in the
counter-affidavit.
5. Additional counter-affidavit is filed by the 2nd respondent
after reply affidavit has been filed, stating inter-alia that the tender
evaluation committee has decided in its meeting held on 16.02.2021 to
extend the time limit by one week to submit the solvency certificate
issued by the bank and informed all four bidders on the very same day
i.e., 16.2.2021, which was confirmed by the petitioner at page 66 of
the writ affidavit (whatsapp message) and that the petitioner despite
receiving the information did not submit the said document by cut-off
date i.e., 23.02.2021.
KVL, J WP No.5094 of 2021
6. In the light of the above pleadings, whether tender process
adopted by the respondents 1 to 3 is fair and transparent or not has to
be analyzed.
7. Heard Sri C.Subodh, learned counsel for the petitioner,
learned Advocate General, appearing on behalf of respondents 1 to 3
and Sri Ch. Dhanamjaya, learned counsel appearing for the 4th
respondent.
8. Section II of the tender document deals with instructions to
bidders. Clause 1 deals with minimum eligibility criteria for
participating in the bid and as per clause 1.1(h), the firm should furnish
solvency certificate. Corrigendum was issued on 08.02.2021 and clause
1.1(h) was amended as 'the firm should furnish latest solvency
certificate for a minimum value of 50% of the ECV'. Complying with the
said condition in corrigendum, petitioner submitted solvency
certificate, issued by the Chartered Accountant, as the original bid
document and the Corrigendum-I does not say that the solvency
certificate should be issued by the bank. As seen from the counter-
affidavit, in addition to the petitioner, two other firms also submitted
solvency certificates issued by the Chartered Accountant which shows
that the tender document is vague. According to the petitioner, he
received a phone call on 23.02.2021 from one Bharath Kumar, Joint
Director, asking him to submit solvency certificate issued by the bank
and he submitted the same on 25.02.2021 and informed the same
through e-mail and also informed to one Mr. Vijay Kumar on 26.02.2021
and also informed the Project Director through whatsapp message that
the petitioner sent solvency certificate through email. In the counter-
affidavit, which was filed on 01.03.2021, the 2nd respondent did not
KVL, J WP No.5094 of 2021
deny making of a phone call to the petitioner on 23.02.2021, but
according to him, it was only a reminder call and that the petitioner
was asked to submit solvency certificate issued by the bank on
17.02.2021 itself. In the additional counter-affidavit, at paragraph 7 of
the affidavit, it is stated that all the four bidders were informed to
submit solvency certificate issued by the bank on 16.02.2021. In the
additional counter-affidavit, at paragraph 8, it is also stated that the
same was confirmed by the petitioner at page 66 of the writ petition.
Page 66 of the writ papers show a whatsapp message sent by the
petitioner's employee by name Kavitha. It shows that the said
employee sent the said message informing that one day before they
have submitted solvency certificate and the same was confirmed by Mr.
Vijay Kumar and they also pasted the copy of the solvency certificate in
the said whatsapp message. It also shows that a reply has been sent by
the 2nd respondent stating that the time has lapsed for submission of
the solvency certificate. But no date is visible in the said whatsapp
message. There is no confirmation by the petitioner in the said
whatsapp message about the receipt of information with regard to
submission of solvency certificate on 16.02.2021 as is stated in the
additional counter-affidavit, in the whatsapp message.
9. Though Sri Ch. Dhanamjaya, learned counsel appearing for the
4th respondent submits that the petitioner was informed about the
solvency certificate by the bank much prior to 23.02.2021 and that a
reminder phone call was made on 23.02.2021, there is no proof
produced to that effect by the respondents.
10. As seen from the pleadings, admittedly, petitioner submitted
solvency certificate issued by the bank on 25.02.2021 and the financial
KVL, J WP No.5094 of 2021
bid was opened on 26.02.2021 and the reverse tender was also
conducted on the same day. Assuming for a moment that the petitioner
was only reminded on 23.02.2021 to give solvency certificate issued by
the bank and that he was originally informed on 17.02.2021 according
to the first counter-affidavit and according to the additional counter-
affidavit on 16.02.2021, petitioner has in fact submitted the same on
25.02.2021 that is one day before the financial bids were opened, but
the same was not taken into consideration.
11. In the counter-affidavit, it is stated that petitioner and
Manjeet Plastic Industries were informed through phone on 17.02.2021
about furnishing of the solvency certificate issued by the bank. It is also
admitted by the 2nd respondent that the said Manjeet Plastic Industries
has submitted the solvency certificate of the bank which is dated
16.02.2021 on 23.02.2021. The allegation of the petitioner is that as
the said Manjeet Plastic Industries was informed in advance with regard
to submission of the solvency certificate issued by the bank and hence
the said Manjeet Plastic Industries could obtain the same on
16.02.2021. As the said Manjeet Plastic Industries is not a party to the
present writ petition, this court is not going into further details of the
said aspect.
12. According to the first counter-affidavit filed by the 2nd
respondent, the e-procurement committee has decided in its meeting
held on 24.02.2021 to disqualify the firms who have not submitted the
said certificates, even though admittedly petitioner was asked to
furnish the same on 23.02.2021. A reasonable time of two days is also
not given to the petitioner herein. Admittedly he submitted the said
certificate before opening of financial bid. It is also relevant to note
KVL, J WP No.5094 of 2021
that according to the corrigendum-3, financial bids have to be opened
on 16.02.2021, but in fact, they were opened on 26.02.2021.
13. The discrepancies in the two counter-affidavits filed by the
respondents are, (a) in the first counter-affidavit, it is stated that in
the Procurement Committee meeting it was decided to disqualify those
firms who have not furnished the required documents as on 24.02.2021.
In the additional counter-affidavit, it is stated that the petitioner did
not submit the certificate by the cut-off date i.e., 23.02.2021. Both the
counter-affidavits gave different cut-off dates. (b) In the first counter-
affidavit, it is stated that the petitioner was informed about the
solvency certificate issued by the Bank on 17.02.2021 and according to
the additional counter-affidavit, petitioner was informed on
16.02.2021.
14. Clause 3 of Section II deals with amendment of bid
document. Clause 3 of Section II reads as follows:
"3.1 At any time prior to the deadline for submission of bids, the tender calling authority may, for any reasons, whether at its own initiative or in response to a clarification requested by a prospective bidder, modify the bidding documents by amendment.
3.2 Any such addenda/corrigenda shall be posted on the e-procurement website only and no other communication shall be made to any firm in this regard.
3.3 In order to allow prospective bidders reasonable time in which to take the amendment into account in preparing their bids, the purchaser, at its discretion, may extend the deadline for the submission of bids."
15. As seen from the said clause, any addenda/corrigenda shall
be posted on the e-procurement website only and no other
communication shall be made to any firm in this regard. But
admittedly, in this case, communication was made through phone calls
to produce the solvency certificate issued by the bank.
KVL, J WP No.5094 of 2021
16. Learned Advocate General relies upon the Clause 5.1 (o.p.q)
of Section-II of the tender document, which reads as under:
"5.1 (o) Balance sheet, P&L account for the financial years 2017-18, 2018-19 & 2019-20 duly certified by the CA shall be uploaded.
(p) CA certified audit reports for last 3 years shall be uploaded and
(q) Positive net worth certified by CA for the last 2 years shall be uploaded."
and submits that the petitioner ought to have submitted solvency
certificate of the bank as per the above clauses.
17. Clause 5.1 'o' and 'p' did not deal with the solvency
certificate at all. As seen from 5.1 (q), it only says that positive net
worth certified by the Chartered Accountant for the last 2 years has to
be uploaded. Even the said clauses deal with the Chartered Accountant
certificates and not the Bank certificates. The said certificate is
different from what is sought now according to the corrigendum.
Admittedly, petitioner has submitted the solvency certificate issued by
the Chartered Accountant for Rs.44.00 crores vide letter dated
11.02.2021.
18. Learned Advocate General also relied upon G.O.Ms.No.94
Irrigation and CAD (PW-COD) Department dated 01.07.2003, which is
issued by the Irrigation and CAD Department with regard to tender
procedures and registration of contractors. Annexure-II of the said G.O.
deals with the rules for registration of contractors. Relying upon the
said Annexure-II learned Advocate General submits that the solvency
certificate has to be produced only from the scheduled bank.
19. Clause (1)(f) of Annexure-II reads as follows:
KVL, J WP No.5094 of 2021
"(f) The following documents shall be submitted along with the application seeking registration as a contractor in a particular class or category.
(i) Application form (in the proforma prescribed in the Annexure-VI with Rs.2/- court fee stamp, affixed thereon.
(ii) Proof of payment of registration fees;
(iii) Solvency certificate:
(a) The solvency certificate for the amounts shown under item (iv) of the Annexure-III shall be obtained from the officer of the Revenue Department of the rank not below the Tahsildar in the proforma in Annexure (V)(a);
(b) The certificates may also be obtained from a scheduled bank in the proforma given in the Annexure (V)(b)."
20. As seen from clause 1(f), the said documents are required for
seeking registration of contractor and not for submission of the bid in a
tender document. Secondly, Clause 1(f)(iii)(b) says that the solvency
certificate may also be obtained from the scheduled bank. Burt it does
not say that compulsorily it has to be obtained from the bank. The
word 'may' is mentioned therein and hence, the above G.O. does not
come to the aid of the respondents.
21. Learned Advocate General also relies upon the copy of the
solvency certificate issued by the bank in favour of the petitioner on
03.04.2020 for submission along with a bid and states that the
petitioner is aware of the said condition even in 2020. But the tender
document for which such a solvency certificate is submitted by the
petitioner is not available on record and hence, it is not known as to
what was the tender condition at that particular period of time, which
mandated the petitioner to produce such a certificate.
KVL, J WP No.5094 of 2021
22. Learned Advocate General submits that it is not the case of
the petitioner that tender conditions are tailor made, or to qualify
some one or disqualify some one, or they are impossible of
performance and that the condition with regard to solvency certificate
is also not challenged. The challenge of the petitioner is not with
regard to tender condition and that it is impossible of performance but
his contention is that proper procedure is not followed before finalizing
the tender and that the tender is vague.
23. The judgment of the Division Bench of this Court relied upon
by the learned Advocate General in 'Universal Cables Ltd. vs. State of
Andhra Pradesh1' will not come to the aid of the respondents.
24. As seen from the facts of the present case, there is violation
of doctrine of a level playing field. The Division Bench of this Court in
the above mentioned judgment at paras 15 and 16 held as follows:
"Although a citizen has a fundamental right, under Article 19(1)(g), to carry on a trade or business, he does not have the fundamental right to insist that the Government, or any other individual, should carry on business with him. The Government, or the individual concerned, has the right to enter into a contract with a particular person or to determine person or persons with whom he or it will deal. Krishnan Kakkanth v. Government of Kerala, (1997) 9 SCC 495). If the State, or its instrumentalities, act reasonably, fairly and in public interest, interference by Courts is restricted, since no person can claim a fundamental right to carry on business with the Government. (Michigan Rubber (India) Ltd.'s case (supra)). All that such a person can claim is that, in competing for the contract, he should not be unfairly treated and discriminated to the detriment of public interest. (Association of Registration Plate's case (supra); Erusian Equipment & Chemicals Ltd. v. State of W.B.,: (1975) 1 SCC 70). In determining the infringement of the right, guaranteed under Article 19(1) of the
2018(5) ALD 130
KVL, J WP No.5094 of 2021
Constitution of India, the nature of the right alleged to have been infringed, the underlying purpose of the restriction imposed, the extent and urgency of the evil sought to be remedied thereby, the disproportion of the imposition, the prevailing conditions at the time, enter into the judicial verdict. (Laxmi Khandsari v. State of U.P.,: AIR 1981 SC 873; Treveli v. State of Gujarat, AIR 1968 SC 1323; Herekchand Ratanchand Banthia v. Union of India, : AIR 1970 SC 1453; Krishnan Kakkanth's case (supra)).
A "level playing field" is a situation in which everyone has a fair and equal chance of succeeding. This, in commercial parlance, is a concept of fairness and requires all eligible players to be permitted to play by the same set of rules. A playing field is at a level if no external interference affects the ability of players to compete fairly. In the matter of awarding Government contracts, the doctrine of 'level playing field' plays an important role. (Shree Ostwal Builders v. State of Maharashtra, : 2008 (4) Mh. LJ 404). This doctrine, embodied in Article 19(1)(g) of the Constitution, provides space within which equally-placed competitors are allowed to bid so as to subserve larger public interest. The terms and conditions, of the invitation to tender, must indicate, with legal certainty, norms and benchmarks. If there is vagueness or subjectivity in the said norms it may result in unequal and discriminatory treatment, and may violate the doctrine of "level playing field". (Reliance Energy Ltd. v. Maharashtra State Road Development Corporation Ltd., (2007) 8 SCC 1). In the matter of inviting tenders, and in awarding Government contracts, public interest is the paramount consideration. (Shree Ostwal Builder's case (supra))."
25. In the said case, the Division bench of this Court held that
although a citizen has no fundamental right to contract, in competing
for the contract, he should not be unfairly treated and discriminated to
the detriment of public interest. All the participating bidders are
entitled to a fair and equal treatment. It was also held that the High
Court should, normally, exercise judicial restraint unless illegality or
arbitrariness, on the part of the employer, is apparent on the face of
KVL, J WP No.5094 of 2021
the record and that the courts can examine the decision making process
and interfere if it is found vitiated by unreasonableness and
arbitrariness. The court does not sit as a court of appeal, but merely
reviews the manner in which the decision is made.
26. But as seen from the facts of this case, this is not a simple
procedural violation, but because of the procedure adopted, prejudice
is caused to the petitioner herein. When the petitioner has admittedly
submitted the solvency certificate on 25.02.2021 itself, the
respondents ought to have considered the case of the petitioner also
instead of disqualifying him on 26.02.2021 as there is vagueness in the
conditions of tender which resulted in unequal and discriminatory
treatment and violated the doctrine of 'level playing field'.
Admittedly, the tender notification does not say that the solvency
certificate has to be produced from the Bank. No proof is produced by
the respondents to show that the petitioner was in fact informed on
17.02.2021 about the submission of solvency certificate issued by the
Bank. But it is admitted by the respondents that a phone call was made
asking or reminding about the solvency certificate on 23.02.2021 and
the same was produced on 25.02.2021. In these circumstances, it
cannot be presumed that the petitioner was informed about the
submission of solvency certificate on 17th or 16th February, 2021 and in
spite of the same, he could not produce the same till 25.02.2021.
27. In the facts and circumstances stated above, the writ
petition is allowed setting aside the impugned tender notification dated
21.01.2021 and the respondents are directed to issue fresh tender
notification without any vagueness, as expeditiously as possible, as the
issue pertains to supply of shoes and socks to the students studying in
KVL, J WP No.5094 of 2021
various schools. No order as to costs. Miscellaneous petitions, if any, in
this writ petition, shall stand closed.
_________________________ KONGARA VIJAYA LAKSHMI, J
Date: 08.03.2021 Note: Furnish CC forthwith.
(BO) NSR/BSS
KVL, J WP No.5094 of 2021
HON'BLE SMT. JUSTICE KONGARA VIJAYA LAKSHMI
Writ Petition No.5094 of 2021 URGENT
Date: 08.03.2021 NSR/BSSs
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!