Citation : 2021 Latest Caselaw 1359 AP
Judgement Date : 4 March, 2021
THE HON'BLE SRI JUSTICE K. SURESH REDDY
CIVIL REVISION PETITION No.87 of 2021
ORDER :
This Civil Revision Petition is filed by the petitioner against
the Judgment and decree, dated 3.12.2020 passed in C.M.A.No.79
of 2019 on the file of the Court of XII Additional District Judge,
Visakhapatnam, confirming the order and decree dated 15.10.2019
in I.A.No.497 of 2019 in O.S.No.1105 of 2019 on the file of the
Court of Rent Controller -cum-IV Additional Junior Civil Judge,
Visakhapatnam.
2. The petitioner before this Court is the defendant in the above
suit and the respondent is the plaintiff. They have been referred as
the same parties in the suit.
3. Brief facts of the case are that the plaintiff is a Firm, which
was registered under the name and style of M/s. Sri Venkateswara
Constructions and it is involved in construction activities. The
defendant is the absolute owner of the plaint schedule property in
an extent of 366.72 square yards in plot No.18 of FCI Layout vide
TP.No.10/7 covered by Survey No.104/1, part of Marripalem
Village within the limits of Greater Visakhapatnam Municipal
Corporation (for short 'GVMC'). Being owner of the said property,
the defendant has taken mortgage loan of Rs.1,90,00,000/-from
the Visakhapatnam Co-operative Bank Limited, Main Branch, Old
Katta Road, Visakhapatnam. Due to his financial crisis, the
defendant requested managing partner of the plaintiff firm by
name Garapati Venkateswara Rao - to pay the said outstanding
amount to the said bank, for which, he assured him that he will
give the said plaint schedule property for construction of
residential complex with his own funds and after obtaining
approval from the GVMC authority. It is also agreed that both of
them share the built up area @ 50% each. Accepting the same, the
plaintiff and the defendant have entered into a memorandum of
understanding on 8.1.2019. As per the said memorandum, the
plaintiff has paid an amount of Rs.1,40,00,000/- to the defendant.
In view of the above payment, the defendant has cleared his
outstanding amount to the said Visakhapatnam Co-operative
Bank. Thereafter, the defendant delivered vacant possession of the
plaint schedule property coupled with irrevocable General Power of
Attorney, dated 31.01.2019. Thereafter, as per Memorandum of
Understanding ( for short 'MOU'), the plaintiff has invested an
amount of Rs.20,00,000/- for the purpose of purchasing T.D.R and
also an amount of Rs.27,00,000/- by way of account payee cheque
to the defendant, which was acknowledged by him for total amount
of Rs.47,00,000/-. In total, the plaintiff has paid an amount of
Rs.1,87,00,000/- to the defendant. For which, the defendant has
executed a Registered Simple Mortgage Deed vide Doc.1013/2019,
dated 7.3.2019 in favour of the plaintiff, acknowledging the
payment of Rs.1,40,00,000/.
4. As per MOU, the plaintiff has to complete the construction
within a period of 18 months with a grace period of 6 months from
the date of obtaining sanctioned plan from the GVMC. They have
entered into registered development agreement coupled with GPA,
dated 31.1.2019 along with registered simple mortgage deed, dated
7.3.2019. As per MOU, the defendant has not handed over the
original sale deed and other link documents to him. Subsequently,
as the defendant is making unlawful demands and has been
obstructing the construction and also trying to dispossess him
from the plaint schedule property, he filed the suit in O.S.No.1105
of 2019 seeking permanent injunction. Along with the suit, he also
filed I.A.No.497 of 2019 under Order XXXIX Rules 1 & 2 Code of
Civil Procedure, 1908 for grant of ad-interim injunction restraining
the defendant from interfering with the peaceful possession and
enjoyment of the plaint schedule property, till the disposal of the
suit.
5. On the other hand, the defendant contended that he has not
delivered vacant possession of the property to the plaintiff and as
such, question of granting interim injunction does not arise. He
also contended that the plaintiff has not placed any document to
show that he paid a sum of Rs.20,00,000/- for purchasing TDR
and also payment of Rs.27,00,000/- and also denied total payment
of Rs.47,00,000/-. But the defendant admitted in his counter that
the terms and conditions enumerated in the development
agreement coupled with GPA are not in dispute. He also pleaded
that as per the terms of development agreement, in para-8, there is
a clause for arbitration "in case of any disputes". As such, he
pleaded that the present suit is not maintainable as there is a
clause of arbitration in the development agreement and sought for
dismissal.
6. The learned trial Judge after going through the entire
material on record and after considering all the aspects, allowed
I.A.No.497 of 2019 in O.S.No.1105 of 2019 on 15.10.2019 and
granted temporary injunction restraining the defendant and his
men from ever interfering with the peaceful possession and
enjoyment of petition schedule property, till the disposal of main
suit. Aggrieved by the said order, the defendant filed C.M.A.79 of
2019 on the file of XII Additional District Judge, Visakhapatnam.
After elaborate discussion, the learned Appellate Judge dismissed
the above said appeal on 3.12.2020 by confirming the order and
decree passed in I.A.No.497 of 2019 in O.S.No.1105 of 2019.
Aggrieved by the same, the petitioner herein filed the present civil
revision petition.
7. Heard learned counsel for the petitioner and learned counsel
for the respondent.
8. Learned counsel for the petitioner submits that as there is a
clause for arbitration as per development agreement, invocation of
jurisdiction of the Civil Court is barred. As such, orders passed by
the trial Judge in I.A.No.497 of 2019 in O.S.No.1105 of 2019
cannot be sustained. He also submitted that as the possession of
plaint schedule property was not delivered to the respondent /
plaintiff, question of granting ad-interim injunction does not arise.
He also urged that the respondent herein obtained permission to
construct apartment, but it does not mean that he has been in
possession and enjoyment of the property. He also stated that the
respondent approached the Court with unclean hands and balance
of convenience is also not there and sought to set aside the order
passed in I.A.No.497 of 2019 in O.S.No.1105 of 2019, dated
15.10.2019, which was confirmed in C.M.A.No.79 of 2019 on the
file of the Court of XII Additional District Judge, Visakhapatnam.
9. On the other hand, learned counsel for the respondent
submits that though the development agreement prescribed a
clause for arbitration, subsequently, the petitioner/defendant
executed a registered Simple Mortgage Deed, dated 7.3.2019 under
Ex.P5, wherein, he has acknowledged payment of Rs.1,40,00,000/-
by the respondent/plaintiff. The relevant portion in Ex.P5 is
extracted herein for kind perusal.
"Later, the mortgager entered into a Development Agreement coupled with irrevocable General Power of Attorney with M/s. Sri Venkateswara constructions, represented by its Managing Partner Sri Garapati Venkateswara Rao, on dated 31.1.2019 bearing Document No.344 of 2019 of Book -1 registered in the Office of the Sub-Registrar, Dwarakanagar, Visakhapatnam District, and delivered the vacant possession of the schedule property to M/s. Venkatewara Constructions. The developer has commenced construction of residential flats thereon with its own funds with plan approved by the Greater Visakhapatnam Municipal Corporation under the name and style of "Subha Santhi Residency" consisting of stilt for parking + ground floor + 4 upper floors and the construction work is under progress."
As such, by virtue of Ex.P5, the earlier Development Agreement
supersedes and the suit filed by the respondent / plaintiff is
maintainable. He further contended that there are no reasonable
and valid grounds to entertain the said petition and the same is
devoid of merit and sought for dismissal.
10. On perusal of the entire material on record, it shows that the
petitioner has been in peaceful possession and enjoyment of the
plaint schedule property and construction is also going as per the
Development Agreement coupled with Irrevocable General Power of
Attorney, dated 31.01.2019, which is not disputed by the petitioner
herein. Further, it is also important to note that the respondent /
plaintiff obtained necessary sanctions from the concerned for
construction of residential apartment and it would be possible only
in the event of delivery of possession of the suit schedule property
by the petitioner in favour of the respondent. Moreover, the
petitioner has executed a registered Simple Mortgage Deed in
favour of the respondent under Ex.P5, where he acknowledged
payment of Rs.1,40,00,000/- and the same was not disputed by
the petitioner. This would clearly indicate that delivery of
possession of the suit schedule property was made by the
petitioner in favour of the respondent under Ex.P5 to start
construction work. Therefore, the contention of petitioner with
regard to non-delivery of possession to the respondent has no legs
to stand and it can be brushed aside.
11. Another important aspect to be noted that the respondent
has placed abundant material on record to show that he has
parted with crores of rupees for development of the suit schedule
property for construction of building and if the temporary
injunction was not granted, it is inevitable to hold that the
respondent would sustain irreparable loss and injury. For that
reason only, the learned IV Additional Junior Civil Judge,
Visakhapatnam allowed the said I.A.No.497 of 2019 and granted
interim injunction as balance of convenience is also in favour of
the respondent and the same was confirmed by the learned XII
Additional District Judge, Visakhapatnam, in C.M.A.No.79 of 2019.
12. Considering all these aspects and for the reasons mentioned
above, it is pertinent to mention that the findings passed by both
the Courts are justifiable and reasonable and this Court has no
hesitation to come to a conclusion that there are no valid grounds
warranting interference of this Court with the orders passed by the
Courts below.
13. In that view of the matter, the Civil Revision Petition is
dismissed as devoid of any merit and the Judgment and decree,
dated 3.12.2020 passed in C.M.A.No.79 of 2019 on the file of the
Court of XII Additional District Judge, Visakhapatnam, is hereby
confirmed. There is no order as to costs.
As a sequel, Miscellaneous Petitions pending, if any, shall
stand closed.
_______________________ K. SURESH REDDY, J 4th March,2021.
RPD.
HON'BLE SRI JUSTICE K. SURESH REDDY
CIVIL REVISION PETITION No.87 of 2021
Dated : 04.03.2021
RPD.
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!