Citation : 2021 Latest Caselaw 885 AP
Judgement Date : 17 February, 2021
IN THE HIGH COURT OF ANDHRA PRADESH : AMARAVATI
HON'BLE MR. JUSTICE ARUP KUMAR GOSWAMI, CHIEF JUSTICE
&
HON'BLE MR. JUSTICE C. PRAVEEN KUMAR
WRIT APPEAL No.65 of 2021
(Taken up through video conferencing)
Container Corporation of India,
CONCOR Bhavan, C-3, Mathura road,
New Delhi -110076 and another.
.. Appellants.
Versus
Devi Engineering & Construction Private Limited,
A company incorporated under the provisions of
the Companies Act, 1956, having its registered office
at Plot No.20, Flat G1, JVY Grand Ground Floor,
Narasanna Nagar, Suryarao Peta, Kakinada-534004
and another.
..Respondents.
Counsel for the Appellants : Mr. J. Prabhakar
Counsel for respondent No.1 : Mr. Naumene Suraparaj Karlapalem
ORAL JUDGMENT
Dt: 17.02.2021
per Arup Kumar Goswami, CJ
Heard Mr. J. Prabhakar, learned Counsel for the appellants. Also
heard Mr. Naumene Suraparaj Karlapalem, leaned Counsel for
respondent/writ petitioner.
2. This writ appeal is directed against the order dated 03.02.2021
passed by learned single Judge in W.P.No.23282 of 2020.
HCJ & CPK, J W.A.No.65 of 2021
3. The operative portion of the aforesaid order reads as follows:
"In these circumstances, the present writ petition is
dismissed, leaving it open to the petitioner to avail of such
remedies, as are available to the petitioner. As far as bank
guarantee dated 01.06.2018 drawn on the 3rd respondent is
concerned, there shall be an injunction restraining the
respondent Nos.1 and 2 from invoking the said bank
guarantee for a period of three (3) weeks. There shall be no
order as to costs."
4. At the outset, it will be relevant to take note of the essential facts for
the purpose of disposal of this writ appeal. Appellant No.1 had invited
tenders for construction of Ware House, retaining Wall cum Compound
Wall, CC Pavement, RCC Kerb Wall, Chain Link Fencing, Approach Road and
Bridge, Electrical Sub-Station and Admin Building in connection with
development of MMLP at Kakinada, vide notification dated 27.02.2018. It is
to be noted that initial estimate of the contract was Rs.32,67,22,247.97. As
the writ petitioner had emerged as the lowest bidder, a Letter of
Acceptance (LOA) was issued to the writ petitioner. As per the terms of the
contract, the contract was to commence on 15.05.2018 and was to be
completed in 18 months, and thus, the scheduled date of the completion of
the original contract was 14.11.2019. As per Clause 16.4 of the General
Conditions of the Contract (GCC), the writ petitioner had submitted a
Performance Bank Guarantee for an amount of Rs.1,63,36,113/-. As the
execution of the contract was not completed within the stipulated date,
extensions were granted from time to time and thereafter, a notice of
termination dated 20.11.2020 was issued requiring the writ petitioner to
HCJ & CPK, J W.A.No.65 of 2021
complete the execution of contract within seven days from the date of the
notice, failing which, it was indicated that the contract would be terminated.
Thereafter, another termination notice, dated 04.12.2020, was issued
directing the writ petitioner to complete the balance works within 48 hours,
failing which, it was indicated that the contract shall be rescinded, Security
Deposit shall be forfeited and the Performance Bank Guarantee shall be
encashed. Being aggrieved, the writ petitioner approached this court by
filing the writ petition.
5. By an order dated 07.12.2020, the learned single Judge restrained
respondents No.1 and 2 (appellants herein) from invoking the bank
guarantee dated 01.06.2018. The said interim order was extended from
time to time.
6. Mr. J. Prabhakar, learned Counsel for the appellants, has assailed the
order of the learned single Judge only on one count, which is to the effect
that once the writ petition was dismissed as not maintainable, the order of
injunction granted by the learned single Judge restraining the appellants
from invoking the bank guarantee for a period of three weeks, could not
have been passed. In support of his submission, the learned Counsel for
the appellants relies on a decision of the Constitution Bench of the Hon'ble
Supreme Court in the case of The State of Orissa v. Madan Gopal
Rungta, reported in AIR 1952 SC 12 and in the case of Bharat Coking
Coal Limited v. Indian Newspaper Society and others, reported in
(2011) 14 SCC 140.
7. Mr. Naumene Suraparaj Karlapalem, learned Counsel for
respondent/writ petitioner, on the other hand, submits that the writ petition
HCJ & CPK, J W.A.No.65 of 2021
was not dismissed as being not maintainable, but by the order impugned,
the writ petitioner was relegated to alternative remedy, and therefore, no
objections can be taken to the injunction order passed by the learned single
Judge. In support of his submission, he places reliance on the judgment of
the Hon'ble Supreme Court in the case of Indus Mobile Distribution
Private Limited v. Datawind Innovations Private Limited and
others, reported in (2017) 7 SCC 678 with particular reference to
paragraph No.20.
8. We have considered the submissions of the learned Counsel for the
parties and perused the material available on record.
9. Perusal of the order of the learned single Judge goes to show that
the appellants herein raised preliminary objections as to the maintainability
of the writ petition. No categorical finding, however, was given with regard
to the question of maintainability raised by the appellants. It was noted in
the order under appeal that there are questions of fact into which, the writ
Court cannot go into, in as much as such issues require a proper hearing
and that apart, it would be necessary to adduce evidence to that effect. It
was also observed that there is an adequate remedy to the writ petitioner
by way of Clause 17-B of the GCC, which provides for reference of all
disputes to arbitration.
10. Learned Counsel for the parties, however, submit that Clause 17-B
was wrongly quoted and it ought to have been Clause 63 and 64 of the
GCC.
HCJ & CPK, J W.A.No.65 of 2021
11. In the case of Indus Mobile Distribution Private Limited v.
Datawind Innovations Private Limited (supra), the Delhi High Court
issued notice on the interim application under Section 9 of the Arbitration
and Conciliation Act, 1996, and restrained the appellant before the Hon'ble
Supreme Court from transferring, alienating or creating any third party
interests in respect of the subject property. The Delhi High Court also
confirmed the order of injunction. It was opined by the Delhi High Court
that only the Courts of Delhi, Chennai and Amritsar would have jurisdiction
to entertain the dispute. The Hon'ble Supreme Court, taking note of the
fact that the juridical seat of arbitration is at Mumbai, held that the Mumbai
Courts alone have jurisdiction to the exclusion of all other Courts in the
country, and in that circumstance, while setting aside the impugned
judgment of the Delhi High Court, had directed that the injunction
confirmed by the impugned judgment will continue for a period of four
weeks from the date of pronouncement of the judgment, so that the
respondents may take necessary steps under Section 9 of the Arbitration
and Conciliation Act, 1996 in a Mumbai Court.
12. In the case of Bharat Coking Coal Limited (supra), the Hon'ble
Supreme Court observed as follows:
"We are of the view that since the writ petition itself
was not maintainable, no interim order for deposit or
payments, etc. could have been made and while dismissing
the writ petition as not maintainable, the High Court ought to
have restored the parties to their original position."
HCJ & CPK, J W.A.No.65 of 2021
13. In the case of The State of Orissa v. Madan Gopal Rungta
(supra), the Hon'ble Supreme Court at paragraph No.6 observed as follows:
"On behalf of the appellant, it was urged that the Court
had no jurisdiction to pass such orders under Article 226,
under the circumstances of the case. This is not a case where
the Court before finally disposing of a petition under Article
226 gave directions in the nature of interim relief for the
purpose of maintaining the status quo. The question which we
have to determine is whether directions in the nature of
interim relief only could be granted under Article 226, when
the Court expressly stated that it refrained from determining
the rights of the parties on which a writ of mandamus or
directions of a like nature could be issued. In our opinion,
Article 226 cannot be used for the purpose of giving interim
relief as the only and final relief on the application as the High
Court has purported to do. The directions have been given
here only to circumvent the provisions of Section 80 of the
Civil Procedure Code, and in our opinion that is not within the
scope of Article 226. An interim relief can be granted only in
aid of and as ancillary to the main relief which may be
available to the party on final determination of his rights in a
suit or proceeding. If the Court was of opinion that there was
no other convenient or adequate remedy open to the
petitioners, it might have proceeded to investigate the case on
its merits and come to a decision as to whether the petitioners
succeeded in establishing that there was an infringement of
HCJ & CPK, J W.A.No.65 of 2021
any of their legal rights which entitled them to a writ of
mandamus or any other directions of a like nature; and
pending such determination it might have made a suitable
interim order for maintaining the status quo ante. But when
the Court declined to decide on the rights of the parties and
expressly held that they should be investigated more properly
in a civil suit, it could not, for the purpose of facilitating the
institution such suit, issue directions in the nature of
temporary injunctions, under Article 226 of the Constitution.
In our opinion, the language of Article 226 does not permit
such an action. On that short ground, that judgment of the
Orissa High Court under appeal cannot be upheld."
14. Perusal of the above mentioned paragraph No.6 of the judgment of
the Hon'ble Supreme Court would go to show that when the Court declined
to decide on the rights of the parties and expressly held that they should be
investigated more properly in a civil suit, it could not, for the purpose of
facilitating the institution of such suit, issue directions in the nature of
temporary injunctions, under Article 226 of the Constitution. In other
words, the Hon'ble Supreme Court had decided that when the Court
expressly stated that it refrained from determining the rights of the parties
on which a writ of mandamus or directions of a like nature could be issued,
in the exercise of powers under Article 226 of the Constitution, no interim
relief would have been granted.
15. At paragraph No.9 in the order under appeal, the learned single
Judge observed as follows:
HCJ & CPK, J W.A.No.65 of 2021
"However, since the petitioner is being relegated to an
alternative remedy, it would only be appropriate to grant an
opportunity to the petitioner to raise such issues, as may be
permissible, to protect the interest of the petitioner relating to
the invocation of the bank guarantee."
Having observed so, the learned single Judge passed the order as extracted
in paragraph No.3 of this judgment.
16. We are of the considered opinion that that the judgment in the case
of The State of Orissa v. Madan Gopal Rungta (supra) is squarely
applicable to the present case. The learned single Judge had not gone into
the adjudication of the lis between the parties and had relegated the writ
petitioner to avail alternative remedy. In that view of the matter, while
dismissing the writ petition, no injunction could have been issued
restraining the appellants from invoking the bank guarantee for a period of
three weeks.
17. In view of the above discussion, we set aside the order of the
learned single Judge to the extent of issuance of injunction restraining the
appellants herein from invoking the bank guarantee.
18. Accordingly, the Writ Appeal is allowed to the extent indicated
above. No costs. Pending miscellaneous applications, if any, shall stand
closed.
ARUP KUMAR GOSWAMI, CJ C. PRAVEEN KUMAR, J
Nn
HCJ & CPK, J
W.A.No.65 of 2021
HON'BLE MR. JUSTICE ARUP KUMAR GOSWAMI, CHIEF JUSTICE & HON'BLE MR. JUSTICE C. PRAVEEN KUMAR
WRIT APPEAL No.65 of 2021
(per Arup Kumar Goswami, CJ)
Dt: 17.02.2021
Nn
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!