Citation : 2021 Latest Caselaw 866 AP
Judgement Date : 16 February, 2021
1
HON'BLE SRI JUSTICE D.V.S.S.SOMAYAJULU
WRIT PETITION No.7426 of 2020
ORDER:
This Writ Petition has been filed by a company, which is
involved in the setting up of cell towers / equipment in order
to provide mobile signal coverage to the public through the
various cell site operators. The petitioner identified the land
in Sy.No.126/1 of Dandamudi Rammohan Rao Street,
Satyanarayanapuram, Vijayawada, for setting up of
Telecommunication Infrastructure Tower. After entering into
the lease deed with the landlord it made an application to the
2nd respondent for grant of permission. The permission was
not granted within the time and relying on a deeming clause
the petitioner started the construction work of a
tower. However, on 03.02.2020 the impugned order was
passed directing the petitioner to stop the construction of the
work. This is on the ground that the neighbours have
seriously complained about the erection of the tower. This
order is now challenged.
This Court has heard Sri T.D.Phani Kumar for the
petitioner and the learned Government Pleader for Municipal
Administration for the 1 respondent and Sri Naresh Kumar st
representing Sri M. Manohar Reddy, learned standing counsel
for the 2 and 3 respondents.
nd rd
Learned counsel for the petitioner argued that as per the
guideline-D of G.O.Ms.No.146, dated 19.06.2015, the
permission is deemed to have been approved / accorded if
permission or refusal is not communicated within 30
days. Learned counsel for the petitioner points out that it is
an admitted fact that the petitioner submitted an application
on 14.09.2019 for construction of a tower. Permission was
not expressly granted nor it was specifically
refused. Therefore, learned counsel submits that as per
guideline-D deemed approval would come into force. He
points out that even if an appeal is filed against the rejection
it should be disposed off within 30 days. He also submits
that this special rule of approving the plan within 30 days has
been incorporated in the GOs., because of the need
recognized by the governments for setting up of
telecommunication towers. These towers relay the signals for
the cell phone users. According to the learned counsel for the
petitioner, recognizing this importance the Government had
introduced this deeming provision and the 30 day limit. He
submits that apart from this the impugned order refers to
alleged complaints given by the third parties /
neighbours. Learned counsel argues that securing the
consent of the neighbours is no longer necessary and that
similar arguments were considered and negatived in
W.P.No.5677 of 2020, wherein the learned single Judge saw
the rules that existed in 2012 and the subsequent
amendment thereto. He points out and rightly shows that the
applicant is only needed to furnish an NOC from the building
owner or the land owner. This submission was accepted by
the learned single Judge. To the same effect, is another order
passed by the learned single Judge in W.P.No.8418 of 2019,
which is appended as a material papers. As far as revision is
concerned, learned counsel submits that if there is radiation
the complaints will have to approach the statutory body called
TERM with regard to radiation. He submits that there is no
radiation effect at all. Therefore, learned counsel argues that
this is a fit case in which order prayed for should be granted.
In reply to this learned standing counsel Sri Manohar
Reddy argues that the petitioner started construction without
securing the approval as required under law. In addition, he
also submits that the neighbours very strongly objected
against the proposed erection of the tower and therefore the
respondents had to step in and stop the construction. It is
his contention that as the approval is not granted the
petitioner cannot continue the construction. Apart from that
he submits that after public had raised serious objections the
respondents had to keep the interest of the public in mind
and reject the application vide endorsement dated
03.02.2020. Therefore, he submits that since the permission
was expressly rejected the petitioner cannot, therefore, insist
that he should be granted a Mandamus and should continue
the construction.
This Court after hearing both the learned counsel
notices that the rule as it stands viz., Guideline D(i) of
G.O.Ms.No.146 clearly states that if permission is not
accorded nor is a refusal is communicated within 30 days
there shall be a deemed approval. This provision has been
specifically introduced in this G.O. Similar 30 day period is
there for disposal of an appeal also. The amendment in the
rules has also been considered by a learned single Judge in
the Judgment passed in W.P.No.5677 of 2000. The change
that is now introduced now merely states that the applicant
should furnish an NOC from the building owner
concerned. In the case on hand there is no dispute that the
building owner has consented. The earlier requirement of
securing NOC from the neighbour owners has been deleted in
the G.O. The consent of the neighbours is no longer
necessary. Similarly, as far as the radiation is concerned, the
complainants have been given an option of approaching the
TERM. This issue was also considered in the judgments
relied upon by the learned counsel for the petitioner viz.,
W.P.No.5677 and 8418 of 2019. There is no scientific or
other evidence produced to show that this particular tower
emits any radiation.
In the opinion of this Court, in the absence of any
tangible material, respondents could not have cancelled the
permission that is deemed to have been granted. The rules
are clear and they provide 30 day period for the accord of
sanction. If sanction is not accorded within this period the
petitioner can rely upon the deeming clause and proceed with
the construction. No other fact has been brought to the
notice of this Court with regard to the construction of the
tower or that it does not meet any other statutory
guidelines. In that view of the matter, this Court is of the
opinion that the petitioner is entitled to an order as prayed
for.
Accordingly, the Writ Petition is allowed. There shall
be no order as to costs.
Consequently, the Miscellaneous Applications pending,
if any, in these Writ Petitions shall also stand allowed.
__________________________ D.V.S.S.SOMAYAJULU, J Date:16.02.2021.
Ssv
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!