Citation : 2021 Latest Caselaw 3246 AP
Judgement Date : 27 August, 2021
IN THE HIGH COURT OF ANDHRA PRADESH : AMARAVATI
HON'BLE MR. JUSTICE ARUP KUMAR GOSWAMI, CHIEF JUSTICE
ARBITRATION APPLICATION No.138 of 2017
(Taken up through video conferencing)
Chinnari Suryanarayana S/o. Satyanarayana,
Aged 53 years, Occu: Business,
R/o.12-31(1)-1A, Official colony,
Srikakulam Town and District and others. .. Applicants
Versus
Nagireddy Srinivasa Rao, S/o. Prabhakara Rao,
Occu: Business, Proprietor A Square Builders
& Developers, R/o. MIG-1, Plot No.54,
Sector-III, M.V.P. Colony,
Visakhapatnam-530 017. .. Respondent
Counsel for the applicants : Mr. Tarlada Rajasekhar Rao
Counsel for respondent : Mr. A.K.Kishore Reddy
Date of hearing : 24.07.2021
Date of order : 27.08.2021
ORDER
Heard Mr. Tarlada Rajasekhar Rao, learned counsel for the
applicants. Also heard Mr. A.K.Kishore Reddy, learned counsel for the
respondent.
2. This is an application filed by the applicants under Section 11(5)
& (6) of the Arbitration and Conciliation Act, 1996 read with the Scheme
for appointment of Arbitrator, 1996 (for short "the Act, 1996"), for
appointment of an Arbitrator.
3. The case of the applicants is that the 2nd applicant is the wife of
the 1st applicant and 3rd and 4th applicants are the children of the 1st and
2nd applicants. They are the owners of land admeasuring 226.2 sq. yards
(222.56 sq. mts.,) in old Sy.No.57/1 part, new survey no.23/2 and land
admeasuring 513.99 sq. yards (429.74 sq. mts.) in old survey No.57/1
part, New survey No.23/2, Patha Srikakulam Rural, Killipalem Panchayat,
Patha Srikakulam village, Srikakulam Mandal, totalling 780.19 sq. yards
(652.316 sq. mts.). The lands are contiguous and they purchased the
same vide Document No.6711/2011 from one Sabbella Adinarayana
Reddy and since the date of purchase, they are in possession.
4. A Development Agreement dated 14.12.2011 was entered into
with the respondent, who is a Developer, for construction of residential
units. It is not necessary to dilate on various terms and conditions of
the Development Agreement for the purpose of this case. Suffice it is to
say that the Development Agreement visualizes that the Developer will
construct 15 dwelling units with a total super built-up area of 16200
sq.ft in each dwelling unit. After completion of 15 units, 6 units were to
be for the applicants and balance 9 units would fall in the share of the
Developer. The development work relating to the share of the owners
was to be completed within one year three months from the date of the
Development Agreement with a grace period of six months, failing which
the applicants are entitled to prevailing local rent for each flat till
handing over of the respective flats by the respondent. The
Development Agreement also recites that the Developer shall not assign
its right of development to any other person, though a sub-contractor
could be appointed by the Developer for specific works on his own
responsibility.
5. The respondent, it is alleged, by violating the terms of the
Development Agreement, entered into an agreement with one
Gurugubelli Raju, who issued a notice dated 08.06.2016 to the
applicants, demanding a certain amount. Stating that the Developer had
completed construction of 9 flats falling into his share, however, with
deviation from the agreed specifications, and made the same ready for
sale, the flats which are allocated to the applicants were left unfinished
by not laying down flooring, electrical lines, plumbing and wood work
etc., a legal notice dated 23.08.2016 was issued by the applicants,
calling upon him to complete the construction of 6 flats according to the
agreed specifications, to restore common electrical connection and
plumbing work as per agreed specifications and to deliver the same to
them after releasing the same from the mortgage which was
fraudulently created by the respondent and to pay rent in terms of the
Development Agreement.
6. The aforesaid notice was refused to be received by the
respondent and as disputes and differences had arisen, a legal notice
dated 06.09.2016 was issued by the applicants nominating one Thota
Bhaskara Rao, District Judge (Retired), as the sole arbitrator and
requesting to intimate as to whether the respondent had any objections
for the above nomination within a period of five days. In the same
notice, it is stated that the first applicant personally and through elders
had approached the respondent as the respondent had not performed in
terms of Development Agreement before the period of one year nine
months expired and also thereafter, but the respondent did not accede
to the demands and had not allowed further negotiations.
7. A reply notice dated 17.09.2016 was issued by the respondents
expressing surprise with the allegations made and contending that there
were no disputes in between them as the applicants had not approached
and also stating that there was an understanding that the 6 flats falling
on the applicants would be delivered after the applicants pay him
towards the expenses incurred by him towards panchayat approval, land
conversion fee, gravel filling etc. It is also stated therein that it is
desirable that they talk to each other and only after talks failed, he
would intimate his choice of the arbitrator.
8. Subsequently, two legal notices dated 08.10.2016 and 15.11.2016
were issued by the respondent demanding Rs.23,50,000/- stating that
he had incurred the amount towards additional expenditure and
amenities, such as, transformer charges, bulk water charges, generator
charges, etc. A notice was issued to the respondent denying the
contents of the notices dated 08.10.2016 and 15.11.2016 stating
categorically that negotiations were held personally and through elders,
but the respondent has not performed his part of contract in terms of
Clause 26 of the Development Agreement dated 14.12.2011.
9. In the aforesaid circumstances, the present application came to
be filed for appointment of arbitrator.
10. The respondent had filed counter-affidavit.
11. At this juncture, it would be appropriate to take note of Clause 26
of the Development Agreement dated 14.12.2011, which reads as
under:
"Any dispute and or differences whatsoever arising under
or in connection with this agreement which could not be
settled by the parties through negotiations shall be settled
by arbitration in accordance with the provisions of the
Indian Arbitration and Conciliation Act by a sole arbitrator
nominated by the parties by mutual consent."
12. In the counter-affidavit filed by the respondent, it is stated that
after starting the development activity, it was noticed that the subject
land was filled with debris and adjacent to the land there is a drainage
canal of about 20 feet width and the drainage system of Srikakulam
town is connected to this canal and the applicants had promised to
share the expenditure to be incurred for removal of the debris and
based on that he started to do the construction work. It is also stated
that only for removal of debris almost one year had elapsed. He had
requested the applicants to come forward for cancellation of the
Development Agreement dated 14.12.2011. At that point of time, the
applicants had assured that the stipulation of time for construction of
units of owners will not be pressed into service. As he had incurred an
expenditure of Rs.1,50,00,000/-, he had proceeded with the
construction work even after time had elapsed as per the Development
Agreement dated 14.12.2011. The work was completed in the month of
December, 2016 and the purchasers occupied 9 flats falling in his share
in the month of December, 2016. When the applicants requested to
handover 6 flats which fell in their share, the respondent demanded the
applicants to pay him back the expenditure which he had incurred and
also requested them to choose persons of their choice to have
negotiations, but the applicants were not interested to negotiate with
the respondent. It is stated that as no negotiations were initiated by the
applicants to settle the dispute, this application is not maintainable.
13. Learned counsel for the applicants submits that many attempts
for negotiations had taken place and the applicants have tried to settle
the dispute by way of negotiations through the intervention of the
elders, but when the respondent had failed to come up with any
response, there is no alternative to the applicants but to approach this
Court by way of filing petition under Arbitration and Conciliation Act read
with Scheme for appointment of Arbitrator.
14. Learned counsel for the respondents has reiterated the stand
taken in the counter-affidavit regarding non-maintainability of the
petition because no negotiations were held earlier. A plea is sought to
be raised that the claim is barred by limitation.
15. In reply, the learned counsel for the applicants submits that no
plea of limitation was taken in the counter-affidavit. He also seeks to
rely upon the judgments in Visa International Limited v.
Continental Resources (USA) Limited, reported in (2009) 2 SCC
55, Indian Oil Corporation Limited v. SPS Engineering Limited,
reported in (2011) 3 SCC 507, and judgment dated 27.11.2019 in
Special Leave Petition (C) No.11476 of 2018 between M/s.
Uttarakhand Purv Sainik Kalyan Nigam Limited v. Northern Coal
Field Limited.
16. I have considered the submissions of the learned counsel for the
parties and have perused the materials on record.
17. In Visa International Limited (supra), on the basis of
exchange of letters between the parties, the Hon'ble Supreme Court
held that the same undoubtedly discloses that attempts were made for
an amicable settlement but without any result leaving no option but to
invoke the arbitration clause.
18. In Indian Oil Corporation Limited (supra), the Hon'ble
Supreme Court had observed that in an application under Section 11 of
the Act, 1996, the Chief Justice or his designate is not expected to go
into the merits of the claim or examine the tenability of the claim. The
Chief Justice or his designate may however choose to decide whether
the claim is a dead claim or whether the parties have, by recording
satisfaction, exhausted all rights, obligations and remedies under the
contract, so that neither the contract nor the arbitration agreement
survived. It was explained that he will do so only when the claim is
evidently and patently a long time-barred claim and there is no need for
any detailed consideration of evidence.
19. In M/s. Uttarakhand Purv Sainik Kalyan Nigam Limited
(supra), the Hon'ble Supreme Court observed that the question of
limitation involves a question of jurisdiction, which is to be determined
having regard to the facts and the law.
20. In the instant case, no plea is taken in the counter-affidavit that
the dispute raised by the applicants is a stale claim and barred by
limitation and, therefore, it is not necessary for this Court to dilate on
the aforesaid issue.
21. Materials on record indicate that flats falling in the share of the
respondent, numbering 9, have been completed by the respondent as a
Developer, and the 6 flats falling in the share of the applicants have
remained incomplete. In all the legal notices issued by the applicants, it
is the categorical stand taken that repeated demands were made by the
applicant No.1 himself and through elders but the request for
performing his part of the contract had fallen on deaf ears.
22. On the other hand, the respondent had also raised various
demands including payment of a sum of Rs.23,50,000/-. That there are
disputes between the parties is evident from the notices exchanged
between them and the pleadings before the Court. From the
correspondence exchanged, it is clear that there is no scope of amicable
settlement. Though the respondent had also raised a demand by way of
raising a dispute from his side, he has not volunteered to come forward
for negotiation by intimating any suitable date for such meeting.
Materials on record persuades me to take a view that the applicants had
made attempts for negotiation and having failed in their attempts to
have an amicable settlement, had no option but to invoke the arbitration
clause.
23. Accordingly, this application is allowed and Mr. T.Venugopal Rao,
District Judge (Retired), D.No.54-14/2-3B, Plot No.52, R.No.1-A,
Srinivasa Nagar, Bank Colony, Vijayawada-520 008 is appointed as
arbitrator to adjudicate the disputes between the parties.
24. The fee of the arbitrator as well as the other terms and conditions
shall be settled by the parties in consultation with the arbitrator so
appointed.
25. Registry will send a copy of this order to Mr. T.Venugopal Rao,
District Judge (Retired), in his proper address.
26. No costs. Pending miscellaneous applications, if any, shall stand
closed.
ARUP KUMAR GOSWAMI, CJ
GM
HON'BLE MR. JUSTICE ARUP KUMAR GOSWAMI, CHIEF JUSTICE
ARBITRATION APPLICATION No.138 of 2017 (Taken up through video conferencing)
Dt: 27.08.2021
GM
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!