Citation : 2017 Latest Caselaw 7239 ALL
Judgement Date : 24 November, 2017
HIGH COURT OF JUDICATURE AT ALLAHABAD AFR Reserved Court No. - 9 Case :- CIVIL REVISION No. - 38 of 2012 Revisionist :- Union Of India Thru' G.M., N.E. Railway And Another Opposite Party :- M/S Variety Industrial Works (P) Ltd. Counsel for Revisionist :- Anil Kumar,Govind Saran Counsel for Opposite Party :- Rahul Sahai Hon'ble Anjani Kumar Mishra,J.
Heard learned counsel for the parties.
This revision has been filed by the General Manager, North
Eastern Railway, Gorakhpur representing the Union of India
against the order dated 24.01.2011 passed in Execution Case
No.7 of 2001, M/s Variety Industrial Works (P) Ltd. Vs. Union
of India, whereby an application dated 04.07.2001 (Application
10-C) for quashing the execution proceedings, has been
rejected.
The facts of the case are that an execution application, 4-C, for
execution of an Arbitration award was filed.
An objection was filed by the revisionist that since the
arbitration proceedings had commenced in the year 1981, the
execution application under the provisions of the new Act was
not maintainable and was liable to be rejected.
It was pleaded that Case No.231 of 1981 was filed in the Court
of Civil Judge (Senior Division), Gorakhpur for appointment of
Arbitrator. Relying upon the judgment in the Apex Court, it has
been submitted that the arbitral proceedings are deemed to
commence when an application for referring the dispute to the
Arbitrator is made. This happened in 1981. The Arbitration
proceedings, were therefore, under the old Act. The award of
the Arbitrator, under the old Act ( Arbitration Act, 1940) is
required to be made Rule of the Court before it becames
executable.
Counsel for the revisionist has placed reliance upon the
decision in U.P. State Sugar Corporation Ltd. Vs. Jain
Construction Co. and another, 2004, 7SCC 332 and Milkfood
Ltd. Vs. GMC Ice Cream (P) Ltd. 2004, 7SCC 288 which holds
that unless otherwise agreed, arbitral proceedings commence on
the date a request is made that the dispute be referred for
Arbitration. Therefore, in view of Section 21 of the Act, the
arbitral proceedings commenced in year 1981, when the
proceedings for appointment of the Arbitrator were initiated by
the opposite party.
Rebuttal 14-C, was filed by the opposite party stating that the
General Manager N.E., Railways, was appointed sole
Arbitrator on 15.11.1999, after the enforcement of the new Act.
The Arbitrator also proceeded in accordance with Arbitration
and Conciliation Act, 1996 and therefore, there is no
requirement of the award being made Rule of the Court. The
execution application had therefore been filed as per Section 36
of the Act, 1996.
It was also pleaded that Case No.231 of 1981 was with regard
to appointment of Arbitrator, under section 20 of the old Act of
1940. The Arbitrator, appointed on 15.11.1999, has passed the
award on 23.01.2001.
It has also been submitted by the opposite party that the
Arbitrator wrote two letters dated 11.08.2000 and 11.9.2000 to
the revisionist, clearly stating his intention to proceed in
accordance with Act 1996 calling upon the revisionist to furnish
their documents and comments, failing which, action would be
taken in accordance with the provisions of Arbitration and
Conciliation Act, 1996.
It is, therefore, contended that the arbitrator proceeded under
the new Act and the revisionists, having participated in these
proceedings, without raising any objection, are precluded from
claiming to the contrary.
Reference has also been made to the Arbitration agreement
between the parties, which provides that the contract would be
governed by the law of India, for the time being in force. On the
date the Arbitrator commenced proceedings, the Arbitration Act
of 1940 stood repealed and therefore, the proceedings were
necessarily, under the Act of 1996.
Reference has also been made by both the Counsel to Section
85 (2-A) and Section 21 of the Arbitration and Conciliation Act
1996.
From the facts noticed above, it is clear that the only point
requiring consideration is whether the award which has been
put to execution in the execution case, would be deemed to be
one under the old Act or it is under the new Act, in which case,
the award would be executable without any requirement of its
being made Rule of the Court as was required under the Act of
1940.
It has been laid down by the Supreme Court that Arbitration
proceedings are deemed to have commenced on the date, a
party applies for referring a dispute to the Arbitrator. In the
case, at hand the proceedings for appointment of Arbitrator
were commenced in the year 1981 long before the Arbitration
and Conciliation Act, 1996 came to be enforced and therefore,
the Arbitration proceedings will be governed by the old Act of
1940.
Having said so, this Court finds that a difficulty arises on
account of Sections 21 and 85 of the Arbitration and
Conciliation Act 1996.
The words "unless, otherwise agreed by the parties" occurring
in Section 21 of the Arbitration and Conciliation Act, 1996 are
significant.
Reference is also required to Section 85 of the Arbitration and
Conciliation Act, 1940, which is quoted below -
" 85. Repeal and savings.
1. The Arbitration (Protocol and Convention) Act, 1937 (6 of 1937), the
Arbitration Act, 1940 (10 of 1940). and the Foreign Awards (Recognition
and Enforcement) Act, 1961 (30 45 of 1961). are hereby repealed.
2. Notwithstanding such repeal,-
a. the provisions of the said enactments shall apply in relation to arbitral
proceedings which commenced before this Act came into force unless
otherwise agreed by the parties but this Act shall apply in relation to
arbitral proceedings which commenced on or after this Act comes into
force;
b. all rules made and notifications published, under the said enactments
shall, to the extent to which they are not repugnant to this Act, be deemed
respectively to have been made or issued under this Act."
The afore-noted provision contain the same words; "unless
otherwise agreed by the parties" which as noticed above, occur
also in Section 21 of the Arbitration and Conciliation Act, 1996.
Upon a conjoint reading of the aforesaid two provisions, it
necessarily follows that although arbitral proceedings are
deemed to commence on the date, a request is made for
referring the dispute for Arbitration and the proceedings would
be governed by the Arbitration Act 1940, but, in case, the
parties agree, the proceedings, despite the above legal position,
may be governed by the Act of 1996.
The controversy in the instant case, therefore, has to be resolved
upon a consideration whether the parties agreed to the
arbitration being conducted in accordance with the Arbitration
& Conciliation Act, 1996.
In this regard, the two letters issued by the sole Arbitrator to the
revisionist, referred to by counsel for the opposite party and
which are available on record in the judgement of this Court
passed in Civil Revision No.595 of 2001 on 25.05.2009, are
crucial.
It emerges that in both these letters, the sole Arbitrator has
clearly stated that action would be taken in accordance with the
provisions of the Arbitration and Conciliation Act 1996.
It is also not disputed that this observation was not objected to
by the revisionist. It is, therefore clear that the Arbitrator
proceeded under the Act of 1996 and the opposite party, has
also proceed to file the execution case relying upon the
provisions of the Act of 1996.
In my considered opinion, once the Arbitrator categorically
stated his intention to proceed under the Act of 1996 and no
objection thereto was raised by the revisionist, it must be
assumed that the revisionist agreed to the application of the
Arbitration and Conciliation Act 1996 in the Arbitration case.
Therefore, the plea, being raised by means of this revision, is hit
by the term," unless otherwise agreed by the parties" occurring
in Sections 21 and 85(2) a of Act, 1996.
Even if not, express, there was a tacit agreement that the arbitral
proceedings before the sole Arbitrator proceed in accordance
with the Arbitration and Conciliation Act 1996.
Therefore, the Court below has rightly held that the award of
the Arbitrator is not required to be made Rule of the court and
the application for quashing the execution case under Section
36, has been rightly rejected. For the same reason, this revision
is without merit.
The revision is accordingly, dismissed.
Order Date :- 24.11.2017
RKM
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!