Monday, 13, Apr, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

25 February vs State Of Uttarakhand And Others
2026 Latest Caselaw 1470 UK

Citation : 2026 Latest Caselaw 1470 UK
Judgement Date : 25 February, 2026

[Cites 1, Cited by 0]

Uttarakhand High Court

25 February vs State Of Uttarakhand And Others on 25 February, 2026

                                                        2026:UHC:1302-DB
 IN THE HIGH COURT OF UTTARAKHAND AT NAINITAL
THE HON'BLE CHIEF JUSTICE MR. MANOJ KUMAR GUPTA
                                 AND
   THE HON'BLE JUSTICE MR. SUBHASH UPADHYAY
               Writ Petition (M/B) No.119 of 2026
                           25 February, 2026

  M/s Sarthi Construction and Infra Private Limited and
  Another
                                          -----Petitioners

                                  Versus

  State of Uttarakhand and Others                    ----Respondents
  ----------------------------------------------------------------------
  Presence:-
  Mr. D.S. Patni, learned Senior Counsel assisted by Mr. Dharmendra
  Barthwal, learned counsel for the petitioners.
  Mr. Yogesh Chandra Tiwari, learned Standing Counsel for the State
  of Uttarakhand/ respondent no.1.
  Mr. Aditya Pratap Singh, learned counsel for Uttarakhand Pollution
  Control Board/ respondent no.2.
  Mr. Manoj Kumar, learned Standing Counsel for the Union of India/
  respondent no.3.
  ----------------------------------------------------------------------
  JUDGMENT :

(per Mr. Manoj Kumar Gupta C. J.)

1. Petitioner no.1 is a private limited company

and petitioner no.2 is Director of the petitioner company.

The petitioner company along with another company M/s

VRS Infra Pvt. Ltd. has formed a joint venture in the

name and style of 'M/s Sarthi Construction and Infra

Private Limited - M/s VRS Infra Pvt. Ltd. (JV)'. The said

JV has been granted an important strategic work -

'Improvement /Construction of 2-Lane with hard shoulder

of Askote-Lipulekh Road From Tawaghat Village to Budhi

Village (Design Km.56.935 to Km.95.748) and from End

of tunnel Portal to Kalimandir (Design Km. 113.828 to

2026:UHC:1302-DB Km.133.078)(Total Design Length = 58.063 Km.) of (NH-

09) under Project Hirak of BRO in the State of

Uttarakhand on EPC Mode, (Tender ID:-

2023_MoRTH_740109_2)' by the Boarder Road

Organization(BRO), Headquarter, Chief Engineer, Project

Hiark vide letter of acceptance dated 07.09.2024.

2. The case of the petitioners is that the JV in

view of it have been granted the aforesaid work sought

permission for installation of a temporary mobile crushing

plant. The road which is to be constructed under the

project is a boarder road and, therefore, the project is of

strategic importance.

3. The application of the petitioners has not been

entertained in view of head office letter dated

27.05.2025 which directs that no application for setting

up of any new stone crushing unit shall be entertained.

The said order was issued by the head office in order to

ensure compliance of an order dated 22.05.2025 passed

in WPMB No.281 of 2025, 'Mahendra Singh & Another Vs.

Union of India & Others'. The operative part of the order

passed in WPMB No.281 of 2025 is extracted below for

ready-reference:

"13. We, therefore, call upon the Secretary, Mining, Government of Uttarakhand and Uttarakhand Pollution Control Board to identify areas in every district, which can be earmarked as dedicated zones for crushing and

2026:UHC:1302-DB dumping of stones/RBM, within six weeks from today. We hope and expect that till the exercise of identification of such area is complete, permission for setting up new stone crushing units may be kept on hold"

4. The specific case of the petitioners is that the

mobile crushing unit which it proposes to set up is of a

temporary nature for captive use during the construction

of the road and after completion of the project the unit

would be dismantled.

5. The further case of the petitioners is that if the

petitioners are not granted permission to set up the

mobile crushing unit it would not be able to meet its

commitments under the contract and it would also be

detrimental to the national interest.

6. Learned Senior Counsel for the petitioners has

referred to an order dated 30.12.2025 passed in the

same PIL (WPMB No.281/2025) whereby the intervention

application filed by the State seeking permission to set

up a temporary mobile crushing plant for Jamrani Dam

Multipurpose Project was allowed considering the fact

that the permission sought was for a temporary mobile

crushing project for captive use only.

7. We find force in the submission of learned

Senior Counsel for the petitioners. Having regard to the

strategic importance of the project and the fact that the

2026:UHC:1302-DB mobile crushing unit sought to be set up is meant for

captive use only and not as a permanent unit, we are of

the opinion that the application of the petitioners should

be considered by respondent no.2 without treating the

order dated 22.05.2025 as any impediment.

8. Learned counsel appearing on behalf of the

Uttarakhand Pollution Control Board also very fairly

states that the application submitted by the petitioners

would be considered on its own merit.

9. Accordingly, we dispose of the writ petition

directing respondent no.2 to pass appropriate order on

the application of the petitioners for setting up of captive

mobile crushing plant at Khata No.50, Survey No.2302,

Village Gunji, Tehsil Dharchula, District Pithoragarh within

a period of four weeks from today.

10. Learned counsel for respondent no.2 shall

communicate the instant order to respondent no.2 for

due compliance.

11. Pending application, if any, also stands

disposed of.

(MANOJ KUMAR GUPTA, C. J.)

(SUBHASH UPADHYAY, J.) Dated: 25.02.2026 SS

SUKHBANT

DN: c=IN, o=HIGH COURT OF UTTARAKHAND, ou=HIGH

2.5.4.20=71978f9c61bfde0ba69967c787b1764ea7bc7dd 4 129a8a6380d49b1885e628615, postalCode=263001,

SINGH st=UTTARAKHAND, serialNumber=2D8B71B8D8E345F6B7F95B1DD4FB4BEB D2B7D72C42261361AED33172F152148D, cn=SUKHBANT SINGH Date: 2026.02.26 14:18:11 +05'30'

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Media

 
 
Latestlaws Newsletter