Tuesday, 12, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

RERA APPEAL/1/2023
2023 Latest Caselaw 620 UK

Citation : 2023 Latest Caselaw 620 UK
Judgement Date : 14 March, 2023

Uttarakhand High Court
RERA APPEAL/1/2023 on 14 March, 2023
                      Office Notes,
                   reports, orders or
SL.                 proceedings or
         Date                                      COURT'S OR JUDGES'S ORDERS
No                   directions and
                   Registrar's order
                    with Signatures
      14.03.2023                        RERA APPEAL No.1 of 2023
                                        Hon'ble Alok Kumar Verma, J.

Present RERA APPEAL has been filed under Section 58 of the Real Estate (Regulation & Development) Act, 2016 against the judgment dated 22.12.2022, passed by the Uttarakhand Real Estate Appellate Tribunal, Dehradun in Appeal No.27 of 2019 to the extent of awarding delayed interest and issue of compensation for not providing modular kitchen, wardrobe and wooden floor to the respondents-complainants.

Heard Mr. Suresh Chandra Sharma, learned counsel with Mr. Mukesh Singh Rawat, learned counsel for the appellant.

Mr. Suresh Chandra Sharma, learned counsel for the appellants, submitted that appellant no.1 alongwith appellant no.2 had purchased the land of 58 bigha from the land owners and after obtaining requisite approvals from Mussoorie Dehradun Development Authority developed the project named "GTM Forest & Hills" in the first phase. The first phase of the project consists of twenty towers having total 256 flats. Respondents/complainants jointly booked a three bed room flat vide Agreement dated 26.11.2006. After completion of construction, the accounts between the respondents/complainants and the appellant no.1 stood settled on 31.03.2013. After execution of sale deed of the flat in favour of the respondents and after issuance of the possession letter, respondent no.1 had sent a legal notice dated 05.02.2014 disputing that the flat was incomplete on the date of execution of the sale deed and as such there was delay of 68 months. The said legal notice was denied by the appellant no.1 stating that the payment against the final demand notice dated 30.06.2012 was settled on 31.03.2013. The possession letter was also sent on 06.11.2013 but, the respondents took possession on 10.01.2014 only.

Mr. Suresh Chandra Sharma, Advocate, contended that the Regulatory Authority cannot reopen the contract concluded prior to coming into force of the said Act 2016; the Regulatory Authority cannot hear the complaint against delayed handing over of possession, where possession was handed over much prior to coming into force the said Act 2016. He further submitted that full and final settlement arrived between the parties cannot be given the different meaning against its very intent and purpose, and, the said Act 2016 is not applicable where the parties have settled their disputes and possession has been handed over and sale deed has been executed.

The present RERA APPEAL is admitted on the following substantial questions of law:-

(1) Whether the Regulatory Authority can reopen the contract concluded prior to coming into force of the Real Estate (Regulation & Development) Act, 2016 where under the rights have already been vested in the respective parties?

(2) Whether the Regulatory Authority can hear the complaint against delayed handing over of possession where possession was handed over much prior to coming into force the Real Estate (Regulation & Development) Act, 2016?

(3) Whether the full and final settlement arrived between the parties can be given the different meaning against its very intent and purpose?

(4) Whether the Real Estate (Regulation and Development) Act, 2016 is applicable where the parties have settled their disputes and possession has been handed over and sale deed has been executed?

Issue notice to the respondents. Steps to be taken within a week. List on 25.04.2023.

In the facts and circumstances of the case, the effect and operation of the order dated 29.07.2019, passed by the Uttarakhand Real Estate Regulatory Authority and the impugned judgment dated 22.12.2022 passed by the Uttarakhand Real Estate Appellate Tribunal, Dehradun are stayed till the next date of listing.

(Alok Kumar Verma, J.) 14.03.2023 Arti

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter