Tuesday, 12, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Khushal Singh Adhikari vs State Of Uttarakhand & Others
2022 Latest Caselaw 895 UK

Citation : 2022 Latest Caselaw 895 UK
Judgement Date : 24 March, 2022

Uttarakhand High Court
Khushal Singh Adhikari vs State Of Uttarakhand & Others on 24 March, 2022
           IN THE HIGH COURT OF UTTARAKHAND
                       AT NAINITAL
                    Writ Petition (M/S) No.1847 of 2021

Khushal Singh Adhikari                                             ...Petitioner
                                            Vs.

State of Uttarakhand & others                                   .....Respondents

With Writ Petition (M/S) No.1848 of 2021

Khushal Singh Adhikari ...Petitioner Vs.

State of Uttarakhand & others                                   .....Respondents

                                          With
                    Writ Petition (M/S) No.1849 of 2021

Khushal Singh Adhikari                                             ...Petitioner
                                            Vs.

State of Uttarakhand & others                                   .....Respondents

                                          With
                    Writ Petition (M/S) No.1850 of 2021

Khushal Singh Adhikari                                             ...Petitioner
                                            Vs.

State of Uttarakhand & others                                   .....Respondents
                                          With
                    Writ Petition (M/S) No.2041 of 2021

Khushal Singh Adhikari                                             ...Petitioner
                                            Vs.

State of Uttarakhand & others                                   .....Respondents


Mr. Shobhit Saharia, Advocate, for the petitioner. Mr. S.S. Chauhan, Advocate, for the respondent/2 to 5. Mr. M.S. Bisht, Brief Holder, for the State of Uttarakhand/1.

Hon'ble Sharad Kumar Sharma, J (Oral)

The petitioner, which is a proprietorship firm, and a registered "A" class contractor with the Public Works Department, has agitated his grievances, as against the impugned order dated 23rd August 2021, which has been passed by respondent no.4, which was

uploaded online by Respondent No.4 on 23rd August 2021. As a consequence of which, the petitioner contends, that he would be deprived of submitting his tenders to participate in the bidding process, which has been resorted to or would be resorted to in future by the respondents. Owing to the attraction of the implications, as it has been referred to in the impugned communication, debarring the petitioner's entitlement to participate due to the set of allegations mentioned in second column of Clause 6.8, which is extracted hereunder:-

"6.8 The Procurement Evaluation Committee checked the experience and qualifications of the responsive bidders as per details provided in Attachment 6-B. The following bidders were found not to be technically qualified.

S.N.                Name of Bidder            Brief         reasons      for
                                              rejection

1.       M/s Panch Ghati construction         1.Slow        progress      in
                                              ongoing work. As per
                                              CE                      Letter
                                              no.1004/URRDA/2021,
                                              21.07.2021

2.       M/s Khushal Singh Adhikari           1.Not maintaining road
                                              during DLP as per SBD
                                              as      per     CE      Letter
                                              no.1004/URRDA/2021,
                                              27.07.2021

3.       M/s GDS Infrastructure               1.Slow        progress      in
                                              ongoing work. As per
                                              CE                       letter
                                              no.1004/URRDA/2021,
                                              21.07.2021



2. There are two fold arguments, which would be primarily required to be considered, at this stage, in order to summarize the controversy without barging into the merits of the matter, the

petitioner contends that the very foundation of the passing of the impugned order happens to be the letter of the Chief Engineer No.1004/URRDA/2021, Dated 27th July 2021, which was already earlier the subject matter of consideration in the writ petition, which was decided by this Court, vide its judgment dated 13.08.2021, rendered by this Court in a Writ Petition being WPMS No.1600 of 2021, "M/s Doon Associates, Suraj Kund Bageshwar, District Bageshwar Vs. State of Uttarakhand & others", wherein, this Court while harmoniously construing the effect of the correspondence of the Chief Engineer dated 27th July 2021, along with the implications of Clause 47(ii) as observed and considered in paragraph Nos.5 and 6, of the said judgment, the Writ Petition, which was preferred by the M/s Doon Associates, Suraj Kund, District Bageshwar was dismissed. The relevant paragraph Nos.5 and 6, of the said judgment, is extracted hereunder:-

"5. In fact, the intention which has been expressed therein are that on an establishment of a fact, as directed by the order dated 27.07.2021, if it stands established after undergoing the process of scrutinization of records as contemplated under Clause 4.7 (II) infact it is an act, which is yet to be resorted to by the respondents and no positive or adverse direction is contained, as such to disqualify the petitioner from participating in his future contracts. In fact, if the said observation made in the list too is taken into consideration, the action of disqualifying the petitioner, would only be based upon the proceedings, which were contemplated to be held in pursuance to the operative portion of the office memorandum dated 27.07.2021, which has been extracted above.

6. I am of the view that if both the documents are read harmoniously infact, there is no positive order which has been passed, as such by the respondents till now, whereby the petitioner has been held to be rejected or disqualify to participate in the future tendering process, there cannot be a writ petition under a premonition, that an action may or is likely to be taken, which can give a cause of action to the petitioner, to file a writ. Filing of a writ petition and that too by invoking an extra ordinary jurisdiction of the Court under Article 226 of the Constitution of India, would

only accrue to the petitioner when there is an actual action taken, against the petitioner and not under an anticipated action."

3. It has been argued by the learned counsel for the petitioner that once the High Court has already ventured into a judicial scrutiny of the order dated 27th July 2021, and its correlated implications to Clause 4.7(ii). In that eventuality, without putting a challenge to the judgment dated 13th August 2021, before any superior forum, the implications of the order dated 27th July 2021, could not have been borrowed by the respondents, for the purposes of holding the petitioner to be incapable to participate in the bidding process, due to the alleged, allegations of non completion of the work, as it has been mentioned in the second column, as extracted above, against petitioners name.

4. It is an admitted position, which is not being disputed by any of the Counsel for the parties, that the judgment rendered by this Court earlier on 13.08.2021 in Writ Petition No.1600 of 2021, had attained its finality, and is still intact nor has been set aside or quashed, by any competent court, and once the said order of 27.07.2021, itself has been construed by the Court by its judicial dictum, it could not have been extracted to create any impediment against the petitioner, in participating in the tendering process by attracting the implications of Clause 4.7(ii), because drawing an inference from a letter when it has been considered by the Court i.e. the letter of 27th July 2021, it would amount to as if the decision which has been taken by the respondent No.4, later on herein, on 23rd August 2021, would amount to be sitting over the judgment rendered by the High Court. Hence, on this prima facie view the decision of the Chief Engineer dated 23rd August 2021, is faulted of.

5. By way of retaliation of the arguments, the learned counsel for the respondent had submitted and has opposed the motion of the petitioner on two grounds (1) That due to inaction on the part of the petitioner to complete the projects already assigned to him under the terms of the contract, he had been issued with the notices,

cautioning him to complete the work projects assigned to him under the contract, and hence the learned counsel for the respondent submits that since the notices for the completion of work, to the assigned projects, were already issued to the petitioner, it would be deemed that the petitioner was noticed by the respondents for an action which were contemplated under Clause 4.7(ii).

6. This contention of the respondents counsel, is not acceptable by this Court, for the reason being that a notice, which was issued to the petitioner for the purposes of completion of the work for which the, concluded contract was already subsisting in favour of the petitioner, cannot be extracted to be read, as if to be a notice for the purposes of passing of the impugned order of withholding the petitioner's right to participate in the tendering process by way of the implications of Clause 4.7(ii) and that too particularly in the light of the order dated 27th July 2021. Hence, this argument is not accepted, that the notices issued for completion of the work assigned to the petitioner is to be treated as to be a notices for the purposes of the impugned action of debarment of the petitioner in the tendering process.

7. Learned counsel for the respondent has submitted, that the action, which has been taken by the Chief Engineer by passing the impugned order is not alien to the terms of the Standard Bidding Document because the employee had reserved its rights to disqualify the bidder from participating in the tendering process by attracting the implications of Clause 4.7(ii). The relevant clause 4.7(ii), is extracted hereunder:-

"4.7 Even though the bidders meet the above qualifying criteria, they are subject to be disqualified if they have:

(i) made misleading or false representations in the forms, statements, affidavits and attachments submitted in proof of the qualification requirements; and/or

(ii) record of poor performance such as abandoning the works, not properly completing the contract,

inordinate delays in completion, litigation history, or financial failures etc; and/or

(iii) participated in the previous bidding for the same work and had quoted unreasonably high or low bid prices and could not furnish rational justification for it to the Employer."

8. In fact this Court is of the view that Clause 4.7(ii), where it confers a right to the employer, to debar a prospective bidder, to participate in the future or present tendering process, due to his previous poor performance or due to the abandoning of the work, and various other parameters, which has been given, therein. In case, if it is isolatedly and unilaterally attracted by the employer, this Court is of the view that it would be obviously having a direct nexus of an infringement of a legal right envisaged with the contractor, as protected under Article 19 (g) of the Constitution of India, to be read with Article 14, of the Constitution of India, because the consequential action taken under Clause 4.7( ii), would obviously be an act of infringement of civil right, and which as per opinion of this Court, it could have been resorted by the respondents only after hearing the bidder; in order to enable him to justify as to whether any of the covenants of Clause 4.7( ii), would at all be attracted to be applied in the set of circumstances, herein, for the passing of the impugned order.

9. Since having apparently not resorted to the said process, of providing an opportunity of hearing I am of the view that attraction of Clause 4.7(ii), by a unilateral decision taken by the Executive Engineer, would be contrary to the common constitutional mandate, that is a deprivation of a civil right, which could only be resorted to after giving an opportunity of hearing.

10. Exclusively for the aforesaid two reasons, this Court is inclined to allow the writ petition, set aside the impugned orders, but obviously, it would be without prejudice to the rights of the respondents, that if at all they intend to attract Clause 4.7(ii), they

would take a decision only after providing an opportunity of hearing to the petitioner, and particularly also after considering the impact of the earlier judgment rendered by this Court qua the order of the Chief Engineer dated 27th July 2021, for the purposes of taking the impugned action, if it is at all required.

11. The learned Counsel for the respondent had referred to the judgment rendered by the Hon'ble Apex Court in Civil Appeal No.1846 of 2022, "M/s N.G. Projects Limited Vs. M/s Vinod Kumar Jain & others", which was emanating from a Division Bench judgment of Jharkhand High Court, in relation to a contracting issue between the two rival parties, and the scope of judicial interference by writ courts under Article 226 of the Constitution of India.

12. The wider principles, which has been sought to be advocated by the learned Counsel for the respondent is that the writ courts under Article 226 of the Constitution of India, should be slow in venturing into the vitalities of the contractual matters, because it is always the work exigencies, which plays a pre-dominant role, which is to be ensured to be completed within the specified time in the wider public interest. There cannot be any iota of doubt to the said principles, but this Court is of the view that the wider phenomena which has been considered by the Hon'ble Apex Court in the said matter, is slightly distinguishable, in order to be made applicable in the circumstances of the present case, where a clever device has been crafted by the respondents to overcome the affect of the judgment, particularly when, which has taken away the foundation of the impugned order by comparatively scrutinizing of the affect of Clause 4.7(ii), as well as the order dated 27th July 2021, which has been referred to in the impugned order of 23rd August 2021.

13. Hence, for the reasons aforesaid, the writ petitions are allowed subject to the liberty already reserved above for the respondents. However, this order would not create any impediment for the respondents to proceed with the opening of the technical bids,

as per the terms of the standard bidding documents, as applicable in the present controversy.

(Sharad Kumar Sharma, J.) 24.03.2022 NR/

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter