Thursday, 14, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

WPMS/103/2019
2021 Latest Caselaw 4748 UK

Citation : 2021 Latest Caselaw 4748 UK
Judgement Date : 25 November, 2021

Uttarakhand High Court
WPMS/103/2019 on 25 November, 2021
IN THE HIGH COURT OF UTTARAKHAND
                     AT NAINITAL
     ON THE 25TH DAY OF NOVEMBER, 2021
                            BEFORE:
     HON'BLE SHRI JUSTICE MANOJ KUMAR TIWARI


      WRIT PETITION (M/S) No. 103 of 2019

BETWEEN:

Roop Singh Kathayat.                         ..........Petitioner
      (By Mr. Shobhit Saharia, Advocate)

AND:
State of Uttarakhand & others.               ....Respondents
      (By Mr. T.S. Phartiyal, Addl. C.S.C. with Mr. M.S. Bisht,
      Brief Holder for the State of Uttarakhand and Mr. S.S.
      Chauhan, Advocate for respondent nos. 2 to 6)


                        JUDGMENT

Respondent no. 2 had issued a notice inviting e-tender for six different works for relaying/construction of roads under Pradhan Mantri Gram Sadak Yojana (PMGSY). Total 6 tenders were received in respect of package No. UT 04-16, i.e., relaying of road between Narsingh Danda to Bhagina Bhandari, including that of the petitioner. However, bid submitted by petitioner for aforesaid work has been rejected.

2. Petitioner is aggrieved by rejection of his bid. The Bid Evaluation Report is on record as Annexure No.3 to the writ petition. Perusal of the same reveals that a Procurement Evaluation Committee headed by Chief Engineer, PMGSY, was

constituted, which examined bids to determine their responsiveness. The said Committee found the bid submitted by petitioner as non-responsive, on the ground that demand draft of bid security was not submitted in original. The recommendation made by Procurement Evaluation Committee was accepted by Bid Accepting Authority. The decision of Procurement Evaluation Committee was uploaded on website, against which petitioner filed a complaint. Petitioner's complaint was rejected by Tender Technical Committee on 22.12.2018. Thus, feeling aggrieved, petitioner has approached this Court.

3. Learned counsel for petitioner contends that petitioner had submitted Demand Draft amounting to ` 8,25,000/- in original, towards bid security, therefore, rejection of his bid on the ground that demand draft was not submitted in original is illegal. He further contends that respondent no.5 was serving as Superintending Engineer, PMGSY, Srinagar, therefore, he could not have signed bid evaluation report dated 13.12.2018 as Superintending Engineer, PMGSY, Pithoragarh and Chief Engineer, PMGSY, Kumaon.

4. Learned counsel appearing for respondent nos. 2, 3 and 4 however contended that petitioner had not submitted the original demand draft as bid security as per condition of tender document but he had submitted scanned copy of demand draft, with his technical bid, therefore, his bid was not confirming to the

conditions, therefore, it was rightly rejected. He further pointed out that respondent no.5 is posted as Superintending Engineer, PMGSY, Pithoragarh, and he was holding additional charge of Chief Engineer, PMGSY, Kumaon region, therefore, he signed the Technical Evaluation Report dated 13.12.2018 in dual capacity. The charge certificate dated 03.12.2018, which shows that respondent no.5 assumed additional charge as Chief Engineer, PMGSY, Kumaon region is on record as Annexure No.1 to the counter affidavit. He further submitted that technical bid of three bidders, namely, M/s Barai Construction, M/s Panchghati Construction and petitioner were rejected on this ground that Bank Draft of bid security was not submitted in original.

5. Ground of rejection of petitioner's bid is referable to a condition in Instruction to bidders. Clause 16.3 of Instruction to Bidders provides that a bid not accompanied by acceptable bid security, shall be rejected as non-responsive.

6. Petitioner has contended that he had submitted bid security through bank draft in original, in the Office of Superintending Engineer at Pithoragarh, on 05.12.2018. However, this statement is refuted by learned counsel for respondent nos. 2, 3 and 4. There is no material on record to corroborate the stand now taken before this Court. Whether petitioner had submitted Bank Draft with his bid or not, is a question of fact. Since respondents have refuted

the submission made on behalf of petitioner that he had submitted original copy of Bank Draft, therefore, there is a dispute whether Bank Draft was submitted in original by petitioner or not. Such disputed question of fact cannot be decided by this Court while exercising power of judicial review under Article 226 of the Constitution of India.

7. Learned counsel for the petitioner then submitted that respondent no.5 was purposely brought to Pithoragarh in order to extend undue favours to rival bidders. He further submitted that petitioner was wrongly eliminated from zone of consideration with a view to facilitate award of Contract to other bidders, who had formed a cartel.

8. Learned counsel appearing for respondent nos. 2, 3 and 4 however disputes this allegation made against respondent no.5. He submits that respondent no.5 was already posted as Superintending Engineer at Pithoragarh and as Chief Engineer, PMGSY, Kumaon had proceeded on leave, therefore, respondent no.5 was given additional charge as Chief Engineer, in terms of order dated 22.11.2018 passed by Competent Authority in Uttarakhand Rural Roads Development Agency.

9. Learned counsel for the respondents further pointed out that petitioner's bid alone was not rejected for not submitting demand-draft in

original, but technical bid of two other bidders was rejected, on the same ground.

10. It is not uncommon in Government Departments that whenever a temporary vacancy is occurred on an administrative position, a subordinate officer is asked to perform the duties of such administrative position in addition to his own duties. From the evidence brought on record, it is revealed that respondent no. 5 was posted as Superintending Engineer at Pithoragarh and, due to temporary vacancy caused on the post of Chief Engineer, he was given additional charge as Chief Engineer. Therefore, the allegation of foul play against respondent no. 5, is without any substance.

11. Having regard to the facts and circumstances of the case, rejection of bid of the petitioner cannot be said to be arbitrary or illegal. Even otherwise also, this Court does not find any substance in the allegation of wrong doing, by respondent no.5.

12. For the aforesaid reasons, this Court does not find any reason to interfere in the matter.

13. Accordingly, the writ petition fails and is hereby dismissed. No order as to costs.

(MANOJ KUMAR TIWARI, J.) Navin

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter