Tuesday, 12, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Riot Narayan Ghosh vs The State Of Tripura
2025 Latest Caselaw 701 Tri

Citation : 2025 Latest Caselaw 701 Tri
Judgement Date : 28 March, 2025

Tripura High Court

Riot Narayan Ghosh vs The State Of Tripura on 28 March, 2025

                                 Page 1 of 14




                       HIGH COURT OF TRIPURA
                             AGARTALA
                             Arb.P. No.05/2024
Riot Narayan Ghosh, Contractor, son of Late Basanta Kr. Ghosh, resident of
village of Matri Bhaban, Subhash Palli, P.O. & P.S.-Ambassa, District-Dhalai
Tripura, Pin-799289.
                                                         ......... Petitioner(s).
                                 VERSUS
1. The State of Tripura, represented by the Secretary & Commissioner, Public
Works Department, Government of Tripura, having his office at Secretariat
Building, P.O.-Kunjaban, P.S.-New Capital Complex, District-West Tripura,
PIN-799006.
2. The Chief Engineer, Public Works Department (R&B), Government of
Tripura, having his office at Pandit Nehru Complex, P.O.-Kunjaban, P.S.-New
Capital Complex, District-West Tripura, PIN-799006.
3. The Superintending Engineer, 5th Circle, Public Works Department (R&B),
Government of Tripura, having his office at Ambassa, District-Dhalai Tripura.
4. The Executive Engineer, Ambassa Division, Public Works Department
(R&B), Government of Tripura, having his office at Jawharnagar, District-
Dhalai Tripura.
                                                    .........Respondent(s).
For Petitioner(s)              : Mr. Koomar Chakraborty, Advocate.
For Respondent(s)              : Mr. Kohinoor Narayan Bhattacharyya, G.A.

     HON'BLE THE CHIEF JUSTICE MR. APARESH KUMAR SINGH

               Date of hearing and judgment: 28th March, 2025.

                       Whether fit for reporting : YES.

                     JUDGMENT & ORDER(ORAL)


Heard Mr. Koomar Chakraborty, learned counsel appearing for the

petitioner and Mr. Kohinoor Narayan Bhattacharyya, learned Government

Advocate appearing for the respondents-State.

2. Under Agreement No. T/ 09/ CE/ PWD (R&B)/ SE (Project)/ EE/

PWD (R&B)/AMB/2013-14 (Annexure-1) and work order dated 20.11.2013

relating to "Construction of RCC bridge over Gandacherra on the road from

Gandacherra to Raishyabari at Ch. 1.00 km under Ambassa Division, Dhalai

Tripura", petitioner claims to have executed the work in all respects by

31.12.2021 and raised his tentative claim before the Executive

Engineer/respondent No.4 on 21.05.2024. However, his claim was declined by

letter dated 31.05.2024. Thereafter, he approached the Superintending

Engineer/respondent No.3 on 11.06.2024 for release of his outstanding dues.

But such claims were also rejected on 05.07.2024. Thereafter, petitioner

submitted an application before the Chief Engineer/respondent No.2 for

reference of the claims/disputes for adjudication under Clause 22 of the

Agreement by nomination of an arbitrator. On 02.09.2024 the Chief

Engineer/respondent No.2 appointed one Sri P.K. Datta, TJS Grade-I (retired)

as the sole arbitrator to adjudicate the disputes between the parties. Thereafter,

again on 06.09.2024 another arbitrator namely Sri Subash Sikdar, TJS Grade-I

(retired) officer was appointed as the sole arbitrator. Petitioner, on his part, also

submitted that a request had been made for appointment of Sri A.K. Nath,

retired District Judge, TJS Grade-I as an arbitrator vide letter dated 08.08.2024.

However, learned counsel for the petitioner submits that since the Chief

Engineer/respondent No.2 is disqualified to appoint an arbitrator in view of the

2015 amendment to the Arbitration and Conciliation Act, 1996, petitioner has

approached this Court under Section 11(6) of the Arbitration & Conciliation

Act, 1996 (as amended) read with Section 12 thereof, for appointment of a sole

arbitrator.

3. A counter affidavit has been filed by the respondents pursuant to

the order dated 26.09.2024. The counter affidavit avers in reply to paragraph-

2.4 of the petition on the merits of the dispute urged by the petitioner, inter

alia, asserting as under:

That, there were 28 days inevitable delay in handing over the site

for which the contractor was not eligible for any compensation under clause

39.3.5 of the agreement.

As regards statements made in paragraph-2.5 of the Arbitration

Petition, it is stated that various correspondences were made with the petitioner

in this respect. The work was completed on 31.12.2021 as per office record but

beyond the stipulated period of completion of work by 6 years 6 months

approximately.

4. It is further stated that provisional time extensions were given

from time to time to keep the agreement alive till completion of the work. As

against the claim of certain amount of bills as unpaid, it is stated at paragraph-8

that out of Rs.2,53,30,433/-, Rs.2,50,29,251/- was paid to the agency and

balance amount of Rs.3,01,182/- remained unpaid which shall be paid after

approval of the time extension with necessary deduction of levy if imposed by

the competent authority. The respondents state that petitioner raised certain

disputes and vide letter dated 08.08.2024 addressed to the Chief Engineer,

PWD (R&B) prayed for appointment of an independent and impartial arbitrator

to adjudicate the dispute arising between the parties for the aforesaid work.

It is further stated that in exercise of the power conferred under

Clause 22 of the agreement, the Chief Engineer, PWD (R&B), Tripura

appointed Shri Subhas Sikdar, Grade-I Officer of TJS (Retired) to act as a sole

arbitrator to adjudicate the dispute between the parties from the panel formed

by the High Court of Tripura vide notification dated 03.04.2023 (Annexure-

R/3).

It is further submitted that petitioner vide letter dated 21.05.2024

had raised Tentative Claims under Clause 22.1 of the agreement for

compensation amounting to Rs.1,40,27,314/- which is not tenable as per the

terms and conditions of the contract. Petitioner was also communicated by

letter dated 31.05.2024 that such claims are not acceptable by the department

(Annexure-R/5). Petitioner had submitted letter dated 11.06.2024 to the

Superintending Engineer, PWD(R&B), 5th Circle raising Tentative Claims

under Clause 22.2 of the agreement (Annexure-R/6). The Superintending

Engineer, PWD(R&B), 5th Circle vide letter dated 05.07.2024 rejected his

claim (Annexure-R/7). Then petitioner submitted a letter to the same

Superintending Engineer on 15.07.2024 seeking arbitration in respect of his

claim of Rs.1,40,27,314/- which according to the respondents is unjustified

(Annexure-R/8). In this sequence of dates vide application dated 08.08.2024

(Annexure-7) addressed to the Chief Engineer, PWD(R&B), Agartala,

petitioner sought reference of the dispute for adjudication by an arbitrator

(Annexure-R/9).

5. It is further stated that the Chief Engineer, PWD(R&B), Agartala

vide memorandum dated 29.08.2024 appointed Sri S. Dasgupta, TJS, Grade-I

(Retired) as sole arbitrator (Annexure-R/10). However, the said appointment

made vide aforesaid memorandum was cancelled due to administrative reasons

by the Chief Engineer vide letter dated 31.08.2024 (Annexure-R/11). Then the

respondent-Chief Engineer, PWD(R&B), Agartala vide memorandum dated

02.09.2024 appointed Sri P.K. Datta, TJS Grade-I (Retired) as the sole

arbitrator for adjudication of the dispute raised by the petitioner (Annexure-

R/12). Mr. Datta is also nominated in the panel. His name in the panel is

prepared vide Notification dated 03.04.2023 issued by the High Court. It is

asserted that in place of the said arbitrator, the Chief Engineer, PWD(R&B),

Agartala appointed another arbitrator Sri Subash Sikdar, TJS Grade-I (Retired)

vide memorandum dated 06.09.2024. The Chief Engineer, PWD(R&B) is the

competent authority to issue the order as per the stipulation contained in the

agreement. The Fifth and Seventh Schedule of Arbitration and Conciliation

Act, 1996 do not stand in the way of such appointment (Annexure-R/13).

6. Further averments have been made in relation to the merits of the

dispute. The respondents have vehemently denied that as per the amendment of

the Act of 1996 dated 23.10.2015 and 09.08.2019, the Chief Engineer,

PWD(R&B) is statutorily disqualified to act as an arbitrator and for

appointment of sole arbitrator. Petitioner has raised his claim for payment of

dues after promulgation of the Amendment Act of the Arbitration and

Conciliation Act, 1996 effected on 09.08.2019. Based on these averments, the

respondents have defended their decision to appoint Sri Subash Sikdar, TJS

Grade-I, Retired Officer as a sole arbitrator.

7. Learned Government Advocate Mr. Kohinoor Narayan

Bhattacharyya appearing for the State has in substance submitted that the

majority judgment in the case of Central Organisation for Railway

Electrification vrs. ECI SPIC SMO MCML (JV), A Joint Venture Company

reported in 2024 SCC OnLine SC 3219 does not render the appointment of the

sole arbitrator Sri Subash Sikdar, TJS Grade-I (Retired) as ineligible or that it

suffers from lack of appointment of an independent and impartial arbitrator.

Though the Clause 22 for appointment of an arbitrator can be said to be

unilateral in nature as it confers authority upon the Office of Chief Engineer

but such appointment has not been made from any panel curated by the

department or by the Chief Engineer. The sole arbitrator has been appointed

from a panel constituted by the High Court in exercise of the powers under

Section 11(3-A) of the Arbitration and Conciliation Act, 1996 (as amended).

It is submitted that the named arbitrator does not suffer from any

ineligibility as prescribed under Section 12(1) read with Section 12(5) of the

Amended Act. Moreover, petitioner has not expressed any apprehension as to

the independence and impartiality of the named arbitrator apparently since he is

not one out of any panel curated by the Chief Engineer or any officer of the

department whether sitting or retired.

It is submitted that the whole intent of the Act of 1996 is to see

that the Arbitration Proceedings are undertaken by an independent and

impartial arbitrator. This Court also while exercising the powers under Section

11 is required to ensure that the appointment is of an independent and impartial

arbitrator. The objection raised by the petitioner is just for the sake of

objection. Moreover, the petitioner has also proposed the name of an arbitrator

out of the same panel curated by this Court vide notification dated 03.04.2023.

In such circumstances, this Court on principle may not like to interfere in the

appointment of an arbitrator by the Chief Engineer in terms of Clause 22

invoked by the petitioner himself if the named arbitrator does not suffer from

any ineligibility on account of any of the conditions enumerated under Section

12(1) read with Schedule-V or Schedule-VII of the Act.

8. Learned counsel for the petitioner has also placed reliance upon

the case of Central Organisation for Railway Electrification (supra) to

support his submission. It is submitted that the Apex Court in the said decision

has held that principle of equal treatment of parties applies at all stages of

arbitration proceedings, including the stage of appointment of arbitrators.

However, a clause that allows one party to unilaterally appoint a sole arbitrator

gives rise to justifiable doubts as to the independence and impartiality of the

arbitrator. It hinders equal participation of the other party in the appointment

process of arbitrators. He has referred to paragraph-169 containing the majority

judgment in Central Organisation for Railway Electrification (supra). He

submits that on the principles of Qui facit per alium facit per se if the

arbitration clause provides for appointment of an arbitrator by one of the party,

i.e. the Chief Engineer who is ineligible to act as an arbitrator in view of the

amendment to the Act of 1996 made effective from 15.10.2015, such authority

could also be ineligible to appoint an arbitrator whether an officer of the same

department or from any other panel. He submits that the decision of the Apex

Court in the case of TRF Limited vrs. Energo Engineering Projects Limited

reported in (2017) 8 SCC 377 applies to such a scenario. Such an appointment

is likely to give justifiable doubts as to the independence and impartiality of the

arbitrator since the contractor is restricted from choosing its arbitrator and

moreover, the appointed arbitrator would be presumed to owe allegiance to the

authority who has appointed him. However, learned counsel for the petitioner

does not dispute that no apprehension has been expressed by the petitioner in

clear terms as to lack of independence or impartiality on the part of learned

arbitrator appointed by the respondent-Chief Engineer as required under

Schedule-V or Schedule-VII of the Act of 1996 read with Sections 12(1) and

12(5) thereof. In such circumstances, learned counsel for the petitioner submits

that this Court may instead of permitting the respondents to make such an

appointment, appoint any independent arbitrator as per its discretion which will

be acceptable to the petitioner.

9. I have considered the submissions of learned counsel for the

parties. I have referred to the relevant necessary details, both on merits and the

legal issue raised for consideration before this Court on the question of

appointment of an arbitrator by the respondent authority-Chief Engineer in

terms of Clause-22 of the agreement.

10. The ratio of the majority judgment in Central Organisation for

Railway Electrification (supra) as summarized at paragraph-169 of the

judgment is extracted hereunder:

"169. In view of the above discussion, we conclude that:

a. The principle of equal treatment of parties applies at all stages of arbitration proceedings, including the stage of appointment of arbitrators;

b. The Arbitration Act does not prohibit PSUs from empanelling potential arbitrators. However, an arbitration clause cannot mandate the other party to select its arbitrator from the panel curated by PSUS;

c. A clause that allows one party to unilaterally appoint a sole arbitrator gives rise to justifiable doubts as to the independence and impartiality of the arbitrator. Further, such a unilateral clause is exclusive and hinders equal participation of the other party in the appointment process of arbitrators;

d. In the appointment of a three-member panel, mandating the other party to select its arbitrator from a curated panel of potential arbitrators is against the principle of equal treatment of parties. In this situation, there is no effective counterbalance because parties do not participate equally in the process of appointing arbitrators. The process of appointing arbitrators in CORE (supra) is unequal and prejudiced in favour of the Railways;

e. Unilateral appointment clauses in public-private contracts are violative of Article 14 of the Constitution;

f. The principle of express waiver contained under the proviso to Section 12(5) also applies to situations where the parties seek to waive the allegation of bias against an arbitrator appointed unilaterally by one of the parties. After the disputes have arisen, the parties can determine whether there is a necessity to waive the nemo judex rule; and

g. The law laid down in the present reference will apply prospectively to arbitrator appointments to be made after the date of this judgment. This direction applies to three-member tribunals."

11. The Apex Court in the majority judgment has dealt with the

legislative scheme under Section 11 of the Act which provides that parties are

free to agree on a procedure for appointing the arbitrator or arbitrators. The

procedure for appointment agreed by the parties is subject to the power of the

Supreme Court or the High Court under Section 11(6) to appoint an arbitrator

in cases where the parties do not agree on a procedure or if the parties or the

arbitrator fail to act following the agreed procedure. Section 11(6) allows

judicial involvement as a default mechanism and not as an independent basis

for choosing the arbitrators irrespective of the parties' agreement. Further,

parties can invoke Sections 11(3), 11(4) or 11(5), as the case may be, only

upon the failure of the agreed procedure for appointment of arbitrators.

12. When appointing an arbitrator under Section 11, the appointing

authority has to ensure the appointment of independent and impartial

arbitrators in terms of Section 11(8). At paragraph-37 of the majority judgment,

the Apex Court has referred to Section 11(8) which prescribes that the High

Court shall seek a disclosure in writing from the prospective arbitrator in terms

of sub-section (1) of Section 12 having due regard to (a) any qualifications

required for the arbitrator by the agreement of the parties; and (b) the contents

of the disclosure and other considerations as are likely to secure the

appointment of an independent and impartial arbitrator.

13. Section 11 is based on Article 11 of the Model Law. Before the

2015 amendment, the Apex Court upheld arbitrator appointment clauses which

gave one party "unfettered discretion" to appoint a sole arbitrator. It was also

held that there was no bar under the Arbitration Act for an employee of a

government or Public Sector Undertaking, which is a party to an arbitration

agreement to act as an arbitrator. However, it was observed that there could be

justifiable apprehension about the independence or impartiality of an employee

arbitrator who was the "controlling or dealing authority" regarding the subject

contract or if the arbitrator was a direct subordinate to the officer whose

decision was the subject matter of the dispute.

14. The 2015 amendment mandates arbitrators to make disclosures

before their appointment in terms of the categories specified under the Fifth

Schedule. The Fifth Schedule prescribes thirty-four categories that give rise to

justifiable doubts as to the independence or impartiality of arbitrators. These

categories are classified as follows: (i) the relationship of the arbitrator with the

parties or counsel; (ii) the relationship of the arbitrator to the dispute; (iii) the

arbitrator's direct or indirect interest in the dispute; (iv) previous services

rendered by the arbitrator to one of the parties or other involvement in the case;

(v) relationship between an arbitrator and another arbitrator or counsel; (vi)

relationship between arbitrator and party and others involved in the arbitration,

and (vii) other circumstances.

15. The 2015 amendment has incorporated Section 12(5) to provide

for ineligibility of a person to be appointed as an arbitrator whose relationship

with the parties or counsel or the subject matter of the dispute falls under any

of the categories specified in the Seventh Schedule.

Section 12(5) provides that notwithstanding any prior agreement

to the contrary, any person whose relationship, with the parties or counsel or

the subject matter of the dispute, falls under any of the categories specified in

the Seventh Schedule shall be ineligible to be appointed as an arbitrator.

Provided that parties may, subsequent to disputes having arisen between them,

waive the applicability of this sub-section by an express agreement in writing.

16. The Seventh Schedule to the Arbitration Act divides the specified

categories based on three factors: (i) arbitrator's relationship with the parties or

counsel; (ii) the relationship of the arbitrator to the dispute; and (iii) arbitrator's

direct or indirect interest in the dispute.

17. In the case of Central Organisation for Railway Electrification

(supra), the Apex Court at paragraph-46 of the judgment referred to the

categories that are relevant for the said reference as under:

"1. The arbitrator is an employee, consultant, advisor or has any

other past or present business relationship with a party;

5. The arbitrator is a manager, director or part of the management,

or has a similar controlling influence, in an affiliate of one of the parties if the

affiliate is directly involved in the matters in dispute in the arbitration."

18. Section 12(5) overrides any prior procedure for appointing the

arbitrators agreed upon between the parties under Section 11(2) due to the non

obstante clause. However, the proviso to Section 12(5) allows parties to waive

the applicability of that provision after the dispute has arisen. This proviso

secures "real and genuine party autonomy" by allowing parties to waive the

applicability of Section 12(5).

19. In this background of the observations made by the Apex Court

and in the light of the ratio rendered by the majority judgment in Central

Organisation for Railway Electrification (supra), the question which arises for

consideration is whether appointment of an arbitrator not out of a panel curated

by the Chief Engineer but from a panel curated by the High Court in exercise

of the power under Section 11(3-A) of the Act of 1996 vide notification dated

03.04.2023 would still render the appointment bad in the eye of law on the

grounds of lack of independence or impartiality of the arbitrator or hitting the

principles of party autonomy. In the conclusion drawn by the Apex Court in the

majority judgment at paragraph-169, the Apex Court has on the one hand held

that the principle of equal treatment of parties applies at all stages of arbitration

proceedings including the stage of appointment of arbitrators. At the same

time, it has held at sub-paragraph (b) that the Arbitration Act does not prohibit

PSUs from empanelling potential arbitrators. However, an arbitration clause

cannot mandate the other party to select its arbitrator from the panel curated by

PSUs.

20. The question in the present case is whether if the Arbitration Act

does not prohibit PSUs from empanelling potential arbitrators and the arbitrator

named in the present case is not one who is one from a panel curated by the

PSU or by the Chief Engineer concerned but from a panel constituted by the

High Court comprising of retired Judicial Officers and others, could it be still

said that the other party has been forced to select an arbitrator from the panel

curated by the Chief Engineer. Had that been a case, it could have raised

justifiable doubts as to the independence and impartiality of the arbitrator on

the counts which have been discussed in the Central Organisation for Railway

Electrification judgment (supra) and referred to in the foregoing paragraphs as

well as per the categories enumerated under Fifth Schedule or Seventh

Schedule of the Act of 1996. In fact, the petitioner himself has proposed the

name of an arbitrator out of the same panel constituted by the High Court under

Section 11(3-A) of the Act of 1996 (as amended). The petitioner has not

expressed any apprehension as to the independence or impartiality of the

arbitrator nominated by the respondent-Chief Engineer from the panel

constituted by the High Court under Section 11(3-A) of the Act.

It appears that the contention of the petitioner is more academic

than real being guided by the principle that if the Chief Engineer is himself

ineligible to act as an arbitrator between the parties, he is equally ineligible to

appoint an arbitrator. The petitioner has not been compelled to accept an

arbitrator out of a panel curated by the Chief Engineer. The petitioner had

himself invoked Clause-22 for appointment of an arbitrator. The independence

or impartiality of the nominated arbitrator has not been raised by the petitioner.

In such a situation, when the parties have agreed to a procedure for

appointment of an arbitrator and the choice of arbitrator is not from a panel

curated by one of the parties, the nomination of an arbitrator from a panel

constituted by this Court cannot be said to be improper. Moreover, when the

Chief Engineer has exercised due caution and discretion in not nominating any

officer from the same department whether sitting or retired or a person from a

panel curated by him.

21. Viewed in this perspective, this Court is of the considered view

that appointment of an arbitrator may be from the same panel constituted under

Section 11(3-A) of the Act by the High Court vide notification dated

03.04.2023 by substituting another person as an arbitrator would be an exercise

more of formality rather than of any purpose or substance. The entire object of

the Act is to ensure that arbitration proceedings are held by independent and

impartial arbitrators. On that issue, no apprehension has been raised by the

petitioner. As such, petitioner should not have any grudge if the arbitrator

appointed from the panel curated by this Court under Section 11(3-A) of the

Act vide notification dated 03.04.2023 by the respondent is to adjudicate the

dispute between the parties.

22. Therefore, this Court does not find any reason to interfere in the

matter. The instant petition is dismissed.

Pending application(s), if any, shall also stand disposed of.




                                                         (APARESH KUMAR SINGH), CJ




Pulak



PULAK BANIK     Digitally signed by PULAK BANIK
                Date: 2025.04.07 14:23:35 +05'30'
 

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter