Citation : 2023 Latest Caselaw 706 Tri
Judgement Date : 29 August, 2023
HIGH COURT OF TRIPURA
AGARTALA
IA 03 OF 2023 IN ARB. A 01 OF 2023
1.The State of Tripura, represented by the Secretary Public Works
Department, PN Complex, Gurkhabasti, Agartala, West Tripura.
2.The Executive Engineer, Resource Division, Panchamukh,
A.D. Nagar, Agartala-799003, West Tripura.
....Applicant-Appellants.
Vrs.
Jain Irrigation System Ltd., Contractor, Jain Plastic Park,
PO Box No.72, NH No.6, Bambhori, Jalgaon,
Maharastra, PIN-425001.
....Respondent.
Present:
For the applicant- : Mr. D. Bhattacharya, G.A.
appellants Mr. Karnajit De, Addl. G.A.
For the respondent : Mrs. S. Deb (Gupta), Advocate.
Ms. Rumpa Dey, Advocate.
Date of hearing : 03.08.2023
Date of delivery of : 29.08.2023
judgment & order
Whether fit for reporting : Yes
HON'BLE THE CHIEF JUSTICE MR. APARESH KUMAR SINGH
HON'BLE MR.JUSTICE ARINDAM LODH
JUDGMENT & ORDER
[ Arindam Lodh, J.]
This is an application under Section 5 of the Limitation Act,1996
for condoning the delay of 74 days in preferring the Commercial Appeal under
Section 13(1A) of the Commercial Courts Act,2015 against the judgment
dated 19.11.2022, passed by the learned District Commercial Court, West
Tripura, Tripura in Civil Misc (Arbitration) 08 of 2020.
2. Facts
of the case of the applicant/appellants (here-in-after
referred to as the applicants) in a nutshell, are that the respondent-contractor
had entered into a contract with the Executive Engineer, Resource Division,
Panchamukh, Agartala for the purpose of procurement of UPVC pipes of
different diameter and pressure for PHE and MI Scheme in Tripura during the
year 2002-2003. The respondent being the lowest bidder of the Notice Inviting
Tender dated 17.06.2002, supply orders were issued to execute the said
contract. Accordingly, the respondent in course of execution of the said supply
order had engaged one transport contractor to carry those materials as per
supply order by truck vehicle, but the transporter carried the same by rail from
Jalgaon to Guwahati instead of truck vehicle which caused a delay of two days
and on that ground the applicants herein reduced the agreed rate between 9.82
to 10.5 per cent in all categories and thereby made less payment of Rs.23.01
lakhs. Thereafter, an Arbitrator was appointed to decide the dispute by the
order of this High Court and accordingly, learned Arbitrator has decided the
case with the following terms:
"In the result, it is decided and/or held that the petitioner is entitled to an amount of Rs.13,82,575/- with 9% simple interest thereon with effect from 04.07.2007. The respondent shall pay the amount to the petitioner with interest within 45(forty five) days of the date of award failing which, it shall carry penal interest @ 12% P.A. with quarterly rests, w.e.f. 04.07.2007.
The respondent shall further pay to the petitioner costs of arbitration including that of petitioner‟s part of Arbitrator‟s fees i.e. total Rs.1,46,449/-. That payment also shall be made within 45 days from the date of award failing which, it shall also carry interest @ 12% P.A. with effect from the date of award.
Further, the petitioner since paid the respondent‟s part of Arbitrator‟s fees of Rs.1,21,449/- on 17.03.2020, the respondent shall pay back the amount to the petitioner with 12% interest with quarterly rests w.e.f. 17.03.2020 till the amount is paid. If the respondent fails to make the payment within 30 days from the date of award, the petitioner will be at liberty to realize/recover the amount from the respondent with 18% interest w.e.f. 17.03.2020 in accordance with law. The interest part shall be the personal liability of the concerned Chief Engineer, PWD(WR) and the authority of the respondent shall realize the amount (interest part) from the salary etc. of the concerned Chief Engineer, PWD(WR) in due course."
3. Being aggrieved, the applicants herein, had preferred an appeal
against the said Arbitral award before the learned Commercial Court, West
Tripura, Agartala under Section 34 of the Arbitration and Conciliation Act
whereby, the learned Commercial Court set aside the Arbitral award partly
and upheld the remaining part of the award.
4. Having dissatisfied with the order of learned Commercial Court,
the applicants herein, preferred the instant condonation application with a
prayer for condoning delay of 74 days in preferring the connected appeal.
Section 13(1A) of the Commercial Courts Act, 2015 prescribes a limitation of
60(sixty) days for preferring an appeal from the date of judgment or order. It
also provides that an appeal shall lie from such orders passed by a
Commercial Division or a Commercial Court that are specifically enumerated
under Order XLIII of the Code of Civil Procedure, 1908 (5 of 1908) as
amended by this Act and Section 37 of the Arbitration and Conciliation
Act,1996 (26 of 1996).
5. In the instant application, the applicants have explained the
reasons for causing delay in preferring the connected appeal stating inter alia
that the impugned judgment was passed on 19.11.2022 and after passing of the
said judgment, they applied for certified copy on 23.11.2022, which was
delivered on 30.01.2023. On receipt of the certified copy, learned Addl. Govt.
Pleader on 14.02.2023 had sent the file to the Executive Engineer Resource
Division with opinion to prefer an appeal. Thereafter, the Executive Engineer,
Resource Division sent the file to the office of the Chief Engineer PWD(WR)
on 22.02.2023 for getting opinion of the Law Department. Thereafter,
22.02.2023, the file was sent to the Nodal Officer, Legal Cell for further
course of action. On 24.02.2023, the Nodal Officer again sent the file to the
Chief Engineer, PWD(WR) for sending the file to the Law Department for
getting opinion and accordingly, on 26.02.2023, the Secretary PWD sent the
file to the Law Department. On 03.03.2023, the file was sent to the Secretary
PWD from the Law Department with opinion. Thereafter, on 07.03.2023, the
file was sent to the Nodal Officer for further course of action. The Nodal
Officer on 13.03.2023, sent the file to the learned Government Advocate and
on 17.03.2023 marked the file to Addl. Government Advocate for preferring
appeal. On 20.03.2023, after drafting of the Arbitration Appeal the file was
sent to the Nodal Officer for getting the Arbitration Appeal vetted from the
Law Department and on that day itself, the Nodal Officer sent the file to the
Chief Engineer PWD(WR) for further course of action and accordingly, the
Chief Engineer PWD(WR) sent the file to the Secretary PWD on 20.03.2023
for sending the same to the Law Department. On 24.03.2023 after vetting the
file was sent to the Secretary PWD for further course of action. Thereafter, on
28.03.2023, the Chief Engineer PWD (WR) sent the file to the Addl.
Government Advocate for filing of the appeal which was received by the
office of learned Government Advocate on 29.03.2023.
6. The applicants contended that the connecting appeal ought to
have been filed on or before 18.01.2023, but, due to inter departmental
movement of the file, 74 days delay had been occurred and hence, the
statutory period of filing the appeal was expired. It is further urged that the
said delay was beyond the control and was not intentional.
7. Mr. D. Bhattacharya, learned Government Advocate assisted by
Mr. K. De, learned Addl. G.A. appearing for the applicants at the time of
hearing submitted that there were no deliberate laches on the part of the
applicants in preferring the appeal and the delay of 74 days has been caused
due to the bonafide reasons. Mr. Bhattacharya, learned G.A. further submitted
that unless the delay is condoned, the applicants shall suffer irreparable loss.
So, the delay should be condoned for fair ends of justice.
8. Mrs. S. Deb(Gupta), learned counsel appearing for the
respondent-contractor opposing the submission of learned G.A. contended that
the learned District Commercial Court passed the impugned judgment and
order on 19.11.2022 which was undoubtedly within the full knowledge of the
learned counsel of the applicants. She further submitted that the learned
counsel for the applicants had applied for the certified copy of the impugned
judgment on 23.11.2022 and on 30.01.2023, the certified copy of the
impugned judgment was received by the learned counsel of the applicants.
Mrs. Deb (Gupta), learned counsel again strongly argued that from the note of
the Copying Department, it was revealed that the learned counsel for the
applicants had provided the requisite stamps and folios before the Copying
Department on 08.12.2022 and consequently on 09.12.2022 the certified copy
was ready for delivery. Accordingly, she stressed upon her submission that
there is no explanation from 09.12.2022 to 30.01.2023 i.e. for 51 days delay.
According to learned counsel, the applicants have not acted with due diligence
pursuing the appeal and the application for condonation of delay does not
assign satisfactory explanation to condone such delay and as such, the same
should be dismissed.
9. We have heard learned counsel for the parties and meticulously
gone through reasons assigned in the application for condonation of delay and
the written objection filed the respondent. It is apparent from the contention
raised by the applicants in the application that the impugned judgment and
order was passed on 19.11.2022 and they had applied for obtaining certified
copy of that judgment on 23.11.2022. But, they collected the certified copy of
the impugned judgment on 30.01.2023, though, at the time of argument, Mrs.
Deb (Gupta), learned counsel for the respondent in conformity with the
statement made in the the counter affidavit candidly submitted that from the
note of the Copying Department, it was revealed that on 08.12.2022, learned
counsel for the applicants had provided the requisite stamps and folios before
the Copying Department and on 09.12.2022 the certified copy was ready for
delivery. It is clear that there is no cogent reason as to why they could not
collect the certified copy of the impugned judgment during the period from
09.12.2022 to 30.01.2023 i.e. within 51 days. There is no explanation what
prevented the applicants for not collecting the certified copy within the said 51
days. So, we do not find any justified reasons to allow the petition for
condonation of delay even on merit, since the grounds stated for condonation
of delay can in no way be termed as „sufficient cause‟ and at least such reason
for the delay in pushing the file from one office to other office cannot be
regarded as „sufficient cause‟ to convince the Court for the purpose of
condoning the delay. In that context, the applicants, in our considered opinion,
were grossly negligent for inaction on their part which suffers from lack of
bona fides and the reason for the delay assigned in the application cannot be
said to be a cogent reason or "sufficient reason" in filing the appeal in time.
This can be said in one sense a deliberate negligence on the part of the counsel
or litigant which has taken note of by this court. We may unhesitantly hold
that the applicants had enough lackadaisical attitude to pursue the appeal.
10. A Division Bench of this court comprising both of us has dealt
with and decided similar issue in IA No.02/2022 in Commercial App. No.1 of
2023, titled as Hindustan Steelworks Construction Ltd. Vrs. The State of
Tripura & Ors.
11. Added to it, what have been observed here-in-above, the
objectives of the establishment of Commercial Courts are required to be
fulfilled by the beneficiaries of the Act. The Act is to provide for speedy
disposal of high value commercial disputes involving complex facts and
questions of law. It was aimed at early resolution of commercial disputes
which would definitely create a positive image to the investors across the
world as regards the independent and responsive Indian legal system. In the
Statement of Objects and Reasons of Amendment Act 28 of 2018, it is clearly
stated that the global economic environment has since become increasingly
competitive and to attract business at international level, India needs to further
improve its ranking in the World Bank „Doing Business Report‟ which, inter
alia, considers the dispute resolution environment in the country as one of the
parameters for doing business. It was further observed by the legislature that
the tremendous economic development had ushered in enormous commercial
activities in the country including foreign direct investments, public private
partnership, etc., which had prompted initiating legislative measures for
speedy settlement on commercial disputes, widen the scope of the courts to
deal with commercial disputes and facilitate ease of doing business.
12. To fulfill and achieve the objects, the parties approaching the
Commercial Courts to resolve their disputes arising out of business/trade, etc.,
transactions, must adhere to the procedures laid down as embodied in the Act.
Keeping in view of the objectives of the Commercial Courts Act,
the provision prescribing limitations has marked a distinction to that of the
provisions laid down in the Limitation Act,1963.
13. In view of this, the litigants participating in commercial disputes
under the Commercial Courts Act must be vigilant to the procedures
mentioned in the Act itself. We may recollect that the law of limitation gets its
root in two Latin maxims, one of which is „Vigilantibus et Non- Dormientibus
Jura Subvenieunt‟ which means that the law will assist only those who are
vigilant about their rights and not those who sleep over them. The above
maxims are clearly applicable to consider the prayer for condonation filed by
any of the parties to the disputes under the Commercial Courts Act. So,
according to us, an application for condonation of delay under Section 5 of the
Limitation Act in filing appeals arising out of commercial suits must be
considered in the context of the object of speedy resolution of disputes. In
other words, considering the object, the legislature wanted to achieve, i.e. for
speedy disposal of commercial suits, for appeals filed under Section 37 of the
Arbitration Act that are governed by Articles 116 and 117 of the Limitation
Act or Section 13(1-A) of the Commercial Courts Act, a delay beyond 90
days, 30 days or 60 days respectively, may be condoned by way of exception
and not by way of rule. It is also to be kept in mind that Commercial Courts
Act, 1015 is a special law and the Limitation Act is a general law.
14. In view of the above factual and legal positions, we are of the
opinion that the applicants have failed to explain the sufficient cause for
condonation of delay of 74 (seventy four) days in preferring the appeal after
expiry of statutory period. The period of delay of 74 (seventy four) days in
preferring the appeal is not found to be reasonable and thus, cannot be said to be a
short delay.
15. Accordingly, the instant condonation application (IA
No.03/2023) stands dismissed. Consequently, the Arbitration Appeal 01/2023
shall also stand dismissed. Pending application(s), if any, also stands
dismissed.
(ARINDAM LODH),J (APARESH KUMAR SINGH),CJ
Digitally signed by SANJAY
SANJAY GHOSH GHOSH
Date: 2023.08.31 17:10:16 +05'30'
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!