Citation : 2026 Latest Caselaw 655 Tel
Judgement Date : 13 April, 2026
IN THE HIGH COURT FOR THE STATE OF TELANGANA AT HYDERABAD
THE HONOURABLE SRI JUSTICE N.V. SHRAVAN KUMAR
W.P. No.11220 of 2026
Date: 13.04.2026
Between:
Mohammed Osman
... Petitioner
And
The State of Telangana,
Represented by its Principal Secretary,
Municipal Administration and Urban Development,
Secretariat, Hyderabad and Five others.
... Respondents
ORDER:
Questioning inaction on the part of the respondents No.2 to 4 in
taking action pursuant to the representation of the petitioner dated
17.03.2026 to take action against the illegal construction carried out
by the respondents No.5 and 6 in respect of residential property in
Ward No.8 bearing House No.2-123, admeasuring 667.00 square
yards, situated at Mankhal Revenue village under Thukkuguda
Municipality, Maheshwaram Mandal, Ranga Reddy district, (subject
property) petitioner filed the present writ petition with a consequential
prayer to direct the respondents No.2 to 4 to forthwith to demolish the
illegal and unauthorized construction carried out by the respondents
No.5 and 6.
2. The learned counsel for the petitioner would submit that the
petitioner is the absolute owner and possessor of the subject property
by virtue of registered gift deed bearing Document No.4244/21 dated NVSK,J
13.02.2021 and presently residing at Hyderabad. Taking advantage of
his absence at the subject property and his health conditions,
unofficial respondents No.5 and 6 have illegally trespassed into the
subject property and have been carrying out unauthorized
construction and raising structure thereon without obtaining any
valid permission from the competent authority.
3. In this regard, petitioner made a representation dated
17.03.2026 to the respondent No.3 to take immediate action and to
demolish the illegal structure made on the subject property however,
the official respondents did not take any action thereon. Hence, the
petitioner filed the present writ petition.
4. On the other hand, the learned Standing Counsel
Smt. M.Bhagyasri appearing for the official respondents would submit
that the representation dated 17.03.2026 will be considered, if not
already considered, and appropriate action would be initiated,
in accordance with law, and would submit to pass appropriate orders.
5. Heard the learned counsel for the petitioner and the learned
Standing Counsel appearing for the official respondents and perused
the material made available on the record.
6. The main grievance of the petitioner is that though he brought
to the notice of the official respondents, by way of representation
dated 17.03.2026, about the illegal/unauthorised construction at the
subject property, the official respondents have failed to initiate any NVSK,J
action against the illegal construction made by the unofficial
respondents No.5 and 6.
7. Since this Court, time and again, directed the Municipal
Authorities to initiate action against the illegal constructions by
following due process of law, it is noticed that the authorities are
failing to initiate action against the illegal constructions. However,
in some of the cases, authorities are issuing statutory notices and
thereafter not proceeding further to initiate further course of action
unless writ petitions are filed for not considering complaints/
representations made to civic authorities.
8. It is not out of place to mention Section 7(6) of the Telangana
State Building Permission Approval and Self Certification System
(TS-BPASS) Act, 2020 (for short 'the TS-BPASS Act') which also
encourages citizens to put on notice to the Civic Authorities regarding
unauthorized constructions. Section 7(6) of the TS-BASS Act is
extracted for reference.
"7. Approval of Building Permissions- ....
(6) Citizens shall be encouraged to bring to the notice of Municipality and District Collector cases where unauthorized construction or construction in violation of or in excess of permissions, in the manner prescribed.
The identity of such informers shall be kept confidential. All such cases shall be examined within a week from such information and NVSK,J
appropriate action initiated. The information shall be incentivized in all such cases where the information, furnished by him is found to be correct."
9. For better appreciation, this Court deems it appropriate to refer
some of the relevant Sections of Greater Hyderabad Municipal
Corporation Act, 1955 (hereinafter referred to as 'the GHMC Act').
Section 428 of the GHMC Act, 1955
428. Notice to be given to commissioner of intention to erect a building: (1) Every person who intends to erect a building shall give to the commissioner notice of his said intention in a form, obtained for this purpose under Section 435, specifying the position of the building intended to be erected, the description of building, the purpose for which it is intended, its dimensions and the name of the person whom he intends to employ to supervise its erection.
Section 433 of GHMC Act, 1955
433. Notice to be given to the Commissioner of intention to make additions, etc., :- "Every person who shall intend.
(a) to make any addition to a building; or
(b) to make any alteration or repairs to a building; not being a frame-building, involving the removal or re-erection of any external or party-wall thereof or of any wall which supports the roof thereof, to an extent NVSK,J
exceeding one-half of such wall above the plinth level, such half to be measured in superficial feet; or
(c) to make any alteration or repairs to a frame-building, involving the removal or re-erection of more than one-half of the posts in any such wall thereof as aforesaid or involving the removal or re-erection of any such wall thereof as aforesaid to an extent exceeding one-half of such wall above the plinth level, such half to be measured in superficial feet; or
(d) to make any alteration in a building involving:--
(i) the sub-division of any room in such building so as to convert the same into two or more separate rooms.
(ii) the conversion of any passage or space in such building into a room or rooms; or
(e) to remove or reconstruct any portion of a building abutting on a street which stands within the regular line of such street; shall give to the Commissioner in a form obtained for the purpose under section 435 notice of his intention, specifying the portion of the building in which such work is to be executed, the nature and extent of the intended work, the particular part or parts, if any, of such work which is or are intended to be used for human habitation and the name of the person whom he intends to employ to supervise its execution."
NVSK,J
Section 451 of GHMC Act, 1955
"451. Inspection of buildfings in course of erection, alteration etc.:- The Commissioner may at any time during the erection or re-erection of a building or the execution of any such work as is described in Section 433 make an inspection thereof without giving previous notice of his intention so to do."
Section 452 of GHMC Act, 1955
452. Demolition or alteration of the building work unlawfully commenced, carried on or completed and appeal thereon:- (1) If the Commissioner is satisfied that the construction or re-construction of any building or execution of any work as described in Section 433 is commenced or carried out contrary to the provisions of the Act or building rules or bye-
laws made thereunder, he shall make a provisional order requiring the person who is constructing or re-constructing such building or executing such work or has constructed or re-constructed such building or executed such work to demolish such unauthorized construction or re-construction or work within a period specified to bring such construction or re-construction of the building or work in conformity with the provisions of the Act or building rules or Bye-laws made thereunder and may also direct that until the said order is complied with, the concerned person shall refrain from proceeding with such construction or reconstruction of the building or work.
NVSK,J
Section 456 of GHMC Act, 1955
"Dangerous Structures
Removal of structures, trees etc., which are in ruins or likely to fall:- (1) If it shall at any time appear to the Commissioner that any structure (including under this expression any building, wall, parapet, pavement, floor, steps, railings, door or window frames or shutters or roof, or other structure and anything affixed to or projection from or resting on, any building, wall, parapet or other structure) is in ruinous condition or likely to fall, or is in any way dangerous to any person occupying, resorting to or passing by, such structure or any other structure or place in the neighbourhood thereof, the Commissioner may, by written notice, require the owner or occupier of such structure to do one or more of the following things, namely:--
(i) to pull down,
(ii) to secure,
(iii) to remove, or
(iv) to repair such structure or thing, and to prevent all cause of danger therefrom.
(2) The Commissioner may also, if he thinks fit, require the said owner or occupier by the said notice, either forthwith or before proceedings to pull down, secure, remove or repair the structure or things, to set up a proper and sufficient hoard or fence for the protection of passers-by and other persons, with a convenient platform and hand-rail, if there be room enough for the same the Commissioner shall think the same desirable, to serve as footway for passengers outside of such hoard or fence.
NVSK,J
(3) If it appears to the Commissioner that the danger from a structure which is ruinous or about to fall is imminent, he may, before giving notice as aforesaid or before the period of notice expires, fence off, take down, secure or repair the said structure or take such steps or cause work to be executed as may be required to arrest the danger.
(4) Any expenses incurred by the Commissioner under sub-section (3) shall be paid by the owner or occupier of the structure.
(5) (a) Where the Commissioner is of opinion whether on receipt of an application or otherwise that the only or the most convenient means by which the owner or occupier of structure such as is referred to in sub-section (1) can pull down, secure, remove or repair such structure, is by entering any of the adjoining premises belonging to some other person the Commissioner after giving such person a reasonable opportunity of stating any objection may, if no such objection is raised or if any objection which is raised appears to him invalid or insufficient, by an order in writing, authorise the said owner or occupier to enter such adjoining premises.
(b) Every such order bearing the signature of the Commissioner shall be a sufficient authority to the person in whose favour it is made, or to any agent or person employed by him for this purpose, after giving to the owner of the premises reasonable written notice of his intention so to do, to enter upon the said premises with assistants and workmen, at any time between sunrise and sun set, and to execute the necessary work.
NVSK,J
(c) In executing, any work under this section as little damage as possible shall be done to the adjoining owner's property, and the owner or occupier of premises for the benefit of which the work is done, shall --
(i) cause the work to be executed with the least practicable delay;
(ii) pay compensation to any person who sustains damage by the execution of the said work.
Section 461-A of GHMC Act, 1955
"461-A. Powers to seal unauthorized
construction/development of premises:-
(1) It shall be lawful for the Commissioner, at any time, before or after making an order for the removal or discontinuance of any unauthorized development or construction under section 461, to make an order directing the sealing of such development or property or taking the assistance of police, for the purpose of carrying out the provisions of the Act."
Section 636 of GHMC Act, 1955
"636. Work or thing done without written permission of the Commissioner to be deemed unauthorized:- (1) If any work or thing requiring the written permission of the Commissioner under any provision of this Act, or any rule, regulation or bye-law is done by any person without obtaining such written permission or, if such written permission is subsequently suspended or revoked for any reason by the Commissioner, such work or thing shall be deemed to be unauthorised and subject to any other provision of this Act the NVSK,J
Commissioner may at any time, by written notice, require that the same shall be removed, pulled down or undone as the case may be, by the person so carrying out or doing if the person carrying out such work or doing such thing is not the owner at the time of such notice then the owner at the time of giving such notice shall be liable for carrying out the requisitions of the Commissioner.
(2) If within the period specified in such written notice the requisitions contained therein are not carried out by the person or owner, as the case may be, the Commissioner may remove or alter such work or undo such thing and the expenses thereof shall be paid by such person or owner as the case may be."
10. On perusal of the above provisions, it is clear that the
respondent authorities are vested with statutory powers to inspect any
property and after putting on notice and after giving fair opportunity
of hearing to the concerned parties, may take appropriate action
against the unauthorized constructions on such properties,
in accordance with law.
11. The Hon'ble Supreme Court in Shanti Sports Club and Ors. Vs.
Union of India (UOI) and Ors 1, held that violators of the Town Planning
Scheme cannot be granted any relief. The relevant observations are as
under:
((2009) 15 SCC 705) NVSK,J
"52. Before concluding, we consider it necessary to enter a caveat. In all developed countries, great emphasis has been laid on the planned development of cities and urban areas. The object of planned development has been achieved by rigorous enforcement of master plans prepared after careful study of complex issues, scientific research and rationalisation of laws. The people of those countries have greatly contributed to the concept of planned development of cities by strictly adhering to the planning laws, the master plan etc. They respect the laws enacted by the legislature for regulating planned development of the cities and seldom there is a complaint of violation of master plan etc. in the construction of buildings, residential, institutional or commercial.
In contrast, scenario in the developing countries like ours is substantially different. Though, the competent legislatures have, from time to time, enacted laws for ensuring planned development of the cities and urban areas, enforcement thereof has been extremely poor and the people have violated the master plans, zoning plans and building regulations and bye-laws with impunity. In last four decades, almost all cities, big or small, have seen unplanned growth. In the 21st century, the menace of illegal and unauthorized constructions and encroachments has acquired monstrous proportions and everyone has been paying heavy price for the same. Economically affluent people and those having support of the political and executive apparatus of the State have constructed buildings, commercial complexes, multiplexes, malls etc. in blatant violation of the municipal and town planning laws, master plans, zonal development plans and even the sanctioned building plans. In most of the cases of illegal or unauthorized constructions, the officers of the municipal and other regulatory bodies turn blind NVSK,J
eye either due to the influence of higher functionaries of the State or other extraneous reasons. Those who construct buildings in violation of the relevant statutory provisions, master plan etc. and those who directly or indirectly abet such violations are totally unmindful of the grave consequences of their actions and/or omissions on the present as well as future generations of the country which will be forced to live in unplanned cities and urban areas. The people belonging to this class do not realize that the constructions made in violation of the relevant laws, master plan or zonal development plan or sanctioned building plan or the building is used for a purpose other than the one specified in the relevant statute or the master plan etc., such constructions put unbearable burden on the public facilities/amenities like water, electricity, sewerage etc. apart from creating chaos on the roads. The pollution caused due to traffic congestion affects the health of the road users. The pedestrians and people belonging to weaker sections of the society, who cannot afford the luxury of air- conditioned cars, are the worst victims of pollution. They suffer from skin diseases of different types, asthma, allergies and even more dreaded diseases like cancer. It can only be a matter of imagination how much the government has to spend on the treatment of such persons and also for controlling pollution and adverse impact on the environment due to traffic congestion on the roads and chaotic conditions created due to illegal and unauthorized constructions. This Court has, from time to time, taken cognizance of buildings constructed in violation of municipal and other laws and emphasized that no compromise should be made with the town planning scheme and no relief should be given to the violator of the town planning NVSK,J
scheme etc. on the ground that he has spent substantial amount on construction of the buildings etc. - K. Ramdas Shenoy v. Chief Officers, Town Municipal Council, Udipi 1974 (2) SCC 506, Dr. G.N. Khajuria v. Delhi Development Authority 1995 (5) SCC 762, M.I. Builders Pvt. Ltd. v. Radhey Shyam Sahu 1999 (6) SCC 464, Friends Colony Development Committee v. State of Orissa 2004 (8) SCC 733, M.C. Mehta v. Union of India 2006 (3) SCC 399 and S.N. Chandrasekhar v. State of Karnataka 2006 (3) SCC 208.
53. Unfortunately, despite repeated judgments by the this Court and High Courts, the builders and other affluent people engaged in the construction activities, who have, over the years shown scant respect for regulatory mechanism envisaged in the municipal and other similar laws, as also the master plans, zonal development plans, sanctioned plans etc., have received encouragement and support from the State apparatus. As and when the courts have passed orders or the officers of local and other bodies have taken action for ensuring rigorous compliance of laws relating to planned development of the cities and urban areas and issued directions for demolition of the illegal/unauthorized constructions, those in power have come forward to protect the wrong doers either by issuing administrative orders or enacting laws for regularization of illegal and unauthorized constructions in the name of compassion and hardship. Such actions have done irreparable harm to the concept of planned development of the cities and urban areas. It is high time that the executive and political apparatus of the State take serious view of the menace of illegal and unauthorized constructions and stop their NVSK,J
support to the lobbies of affluent class of builders and others, else even the rural areas of the country will soon witness similar chaotic conditions. " (Emphasis supplied).
22. Further, the Hon'ble Supreme Court in Esha Ekta Apartments Co-operative Housing Society Ltd. and Ors. Vs. Municipal Corporation of Mumbai and Ors (2013) 5 SCC 357, held that Constitutional Courts ought not to exercise their equitable jurisdiction to regularize illegal and unauthorized constructions. The relevant observations are as under:
"45. In view of the above discussion, we hold that the Petitioners in the transferred case have failed to make out a case for directing the Respondents to regularize the construction made in violation of the sanctioned plan. Rather, the ratio of the above- noted judgments and, in particular, Royal Paradise Hotel (P) Ltd. v. State of Haryana and Ors. (supra) is clearly attracted in the present case. We would like to reiterate that no authority administering municipal laws and other similar laws can encourage violation of the sanctioned plan. The Courts are also expected to refrain from exercising equitable jurisdiction for regularization of illegal and unauthorized constructions else it would encourage violators of the planning laws and destroy the very idea and concept of planned development of urban as well as rural areas."
(emphasis supplied)"
12. It is also relevant to refer to the orders passed by the Hon'ble
Supreme Court in Writ Petition (Civil) No.295 of 2022 (2024 INSC
866) (Bulldozer's Case), wherein the Hon'ble Supreme Court gave NVSK,J
certain directions and guidelines to the Government for manner of
proceeding in demolition of the unauthorized construction.
13. Since the provisions of the GHMC Act, 1955 mandates issuance
of notice to the person concerned and the GHMC authorities are
empowered to examine and decide the issue with respect to
unauthorized constructions, by issuing notice to the concerned
parties, the respondent authorities are directed to issue notice to the
concerned parties. As such, in the present case, issuance of notice to
the unofficial respondents No.5 and 6 is dispensed with.
14. Having considered the above facts and circumstance,
recording the submission made by the learned counsel appearing on
either side, without expressing any opinion on the merits of the case
and after considering judicial precedents referred to hereinabove,
this Court deems it appropriate to dispose of the writ petition directing
the respondent authorities to consider the petitioners' representation
dated 17.03.2026 and after giving fair opportunity of hearing to
petitioner and respondents No.5 and 6 after verifying the sanctioned
plan and other relevant documents, shall pass appropriate orders
strictly in accordance with law, as expeditiously as possible,
preferably, within a period of six (06) weeks, from the date of receipt of
a copy of this order and communicate the same to the petitioner.
It is made clear that if the allegations made by the petitioner are found
to be true, the respondent authorities shall take appropriate action
strictly in accordance with law.
NVSK,J
15. It is clarified that in the event of respondents No.5 and 6 are
otherwise aggrieved may avail remedy of filing application for the
modification of this order, in accordance with law.
16. Accordingly, with the above directions, this writ petition is
disposed of. There shall be no order as to costs.
As a sequel, miscellaneous applications, if any pending,
shall stand closed.
________________________________ JUSTICE N.V. SHRAVAN KUMAR Date: 13.04.2026 LSK
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!