Monday, 13, Apr, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

M/S. Klr Industries Ltd vs M/S. Legend Estates Pvt. Limited
2026 Latest Caselaw 241 Tel

Citation : 2026 Latest Caselaw 241 Tel
Judgement Date : 1 April, 2026

[Cites 2, Cited by 0]

Telangana High Court

M/S. Klr Industries Ltd vs M/S. Legend Estates Pvt. Limited on 1 April, 2026

Author: P. Sam Koshy
Bench: P. Sam Koshy
                                Page 1 of 7



       IN THE HIGH COURT FOR THE STATE OF TELANGANA
                       AT HYDERABAD

           THE HONOURABLE SRI JUSTICE P. SAM KOSHY

                Arbitration Application No.13 of 2025

                      Date of order : 01.04.2026

BETWEEN :


M/s.KLR Industries Ltd. and 8 others
                                                            ... Applicants
                                  and
M/s.Legend Estates Pvt. Limited and another
                                                         ... Respondents

ORDER :

The instant Arbitration Application has been filed by the applicants

under Section 11(5) & (6)(6A) of the Arbitration and Conciliation Act,

1996 praying the Court to appoint an arbitrator on behalf of applicants

and respondents to adjudicate the claims and disputes arising under the

Registered Development Agreement-cum-General Power of Attorney, vide

Document No.6414 of 2014, dated 14.11.2014, and to award costs of

application.

2. Heard Mr. M. Sreyas Reddy, learned counsel for the applicants; and

Mrs.Manjari S. Ganu, learned counsel for the respondents.

3. The brief facts leading to filing of instant arbitration application by

the applicants is that applicants herein are absolute owners and

possessors of land admeasuring 3296 Sq.yds. (or) 27 guntas and 29

Sq.yds., purchased by the applicants under various registered sale

deeds. The said land is an extent of Acs.2.11 gts. and 57 Sq.yds.

situated in Survey Nos.126/A & AA, 199/A & AA, 201, 204/AA to 206/A,

AA, E, EE, U, UU, 206/P, 209 and 210, situated at Kokapet Village,

Rajendranagar Mandal, Ranga Reddy District.

4. The respondent No.1, after enquiring with the applicants' title and

possession over the above subject properties, had approached the

applicants with an intention to develop the above subject lands. After

negotiations, the applicants have agreed for the proposal put up by the

respondents, and accordingly a registered Development Agreement-cum-

General Power of Attorney, vide Document No.6414 / 2014, dated

12.12.2014, was entered into between the applicants and respondents

for development of the subject lands. Under the said agreement, the

applicants are entitled for 50% of the villas in the gated community. It

was further agreed by both parties that the respondents shall handover

the villas allotted to applicants within a period of 36 months from the

date of obtaining sanction and permission from the Hyderabad

Metropolitan Development Authority, with a further grace period of 6

moths.

5. Learned counsel for the applicants contended that since the date of

entering into development agreement, the respondents have delayed

execution of the project in constructing villas; the respondents, contrary

to the terms of development agreement, have alienated open plot

Nos.196, 197 part, 202 part and 203 admeasuring 1,506 Sq.yds and 197

part, 198, 201 and 202 part admeasuring 1,506 Sq.yds., under two sale

deeds vide Document No.781 of 2015 and 783 of 2015, dated

11.02.2015; aggrieved, the applicants lodged a police complaint dated

05.01.2020.

6. Learned counsel for the applicants further contended that the

applicants have been following up with respondents for successful

completion of the project; since the respondents have failed in completion

of villas, the applicants decided to accept / receive the construction value

as per the existing market rates from respondents so as to enable the

applicants to complete the construction work on their own; despite best

efforts put in by the applicants in pursuing the respondents to complete

the project within time and to deliver 50% share of villas to the

applicants, the respondents till date have not taken steps to complete the

project as was agreed between the parties under the said Development

Agreement; accordingly, a legal notice was issued to the respondents by

the applicants on 09.09.2024 calling upon the respondents to make

payment towards value of the construction and damages calculated in

favour of applicants along with interest @ 24% per annum within 15

days from the date of receipt of notice as per terms and conditions of the

Development Agreement, dated 14.11.2014; despite receipt of the said

notice by the respondents, the respondents have failed to pay the

amounts, and instead given a reply notice dated 25.10.2024 with all false

and frivolous allegations.

7. Learned counsel for the applicants further submitted that, left with

no other option, the applicants preferred to invoke arbitration clause (20)

of the said development agreement, dated 14.11.2014, wherein it was

agreed by both parties that in case of any dispute arising between the

parties, the matter would be referred to a sole arbitrator; and

accordingly, a legal notice dated 13.11.2024, invoking Clause (20) of the

Development Agreement dated 14.11.2014, was issued to the

respondents calling upon the respondents to give consent for

appointment of an arbitrator between the applicants and respondents for

adjudicating the dispute between them; however, the respondents, after

receipt of the said notice, refused to give reply, which led to filing of the

instant Arbitration Application under Section 11 of the Arbitration and

Conciliation Act, 1996.

8. On 14.02.2025, notice was ordered to the respondents. Thereafter,

learned counsel, appearing on behalf of the respondents, entered

appearance and sought time for filing counter-affidavit in the matter.

9. Counter-affidavit has been filed by respondent No.2, i.e., the

Managing Director of respondent No.1-Company, stating that the

applicants have fraudulently issued a letter dated 24.08.2016 directing

the respondents to stop construction work immediately till disposal of

Civil Suits, viz., O.S.No.1065 of 2007 and O.S.No.1034 of 2015; on

account of stay granted by the Trial Court, the respondents could not

proceed with completion of project; after withdrawal of the above suits by

the applicants, the respondents have resumed construction work and

completed most of the works; the respondents are ready and willing to

complete the construction work, but it is on account of ongoing litigation

and stay orders obtained from the Trial Court by the applicants, the

respondents could not complete the project; and therefore, contended

that the instant arbitration application need not be entertained by the

Court since respondents have agreed to complete construction work.

10. Having heard the contentions put forth on either side and on a

perusal of the record, and also taking into the consideration the facts

and circumstances of the case, given the nature of dispute that had been

raised and canvassed by the applicants and also considering the

arbitration clause (20) contained in the Development Agreement that has

been entered into between applicants and respondents on 14.11.2014

and prima facie proof of service of notice on the respondents also having

been filed by the applicants, this Court is inclined to allow the arbitration

application.

11. Accordingly, this Court appoints Hon'ble Sri Justice Challa

Kodanda Ram, retired Judge, resident of Plot No.68, Road No.71, Phase-

III, Jubilee Hills, Hyderabad - 500 033, Mobile No.83310 10695, as the

sole Arbitrator to resolve the dispute between the parties.

12. Needless to state that both parties are at liberty to raise all claims

and counter claims before the sole arbitrator who in turn shall conduct

the arbitration proceedings in accordance with provisions of the Act.

The venue of arbitration shall be decided mutually by the parties subject

to consultation and agreement of the learned Arbitrator. The fee payable

to the learned Arbitrator shall also be decided mutually by the parties in

consultation and agreement with the learned Arbitrator.

13. Accordingly, the Arbitration Application stands allowed. No costs.

14. As a sequel, miscellaneous petitions, pending if any, shall stand

closed.

___________________ P. SAM KOSHY, J

Date: 01.04.2026 Note:

The Registry is directed to furnish copy of this order to the learned sole arbitrator

B/o.

Ndr

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Media

 
 
Latestlaws Newsletter