Wednesday, 13, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Vijay Kumar Yerram vs The State Of Telangana
2025 Latest Caselaw 5305 Tel

Citation : 2025 Latest Caselaw 5305 Tel
Judgement Date : 4 September, 2025

Telangana High Court

Vijay Kumar Yerram vs The State Of Telangana on 4 September, 2025

Author: Abhinand Kumar Shavili
Bench: Abhinand Kumar Shavili
  THE HON'BLE SRI JUSTICE ABHINAND KUMAR SHAVILI
                         AND
 THE HON'BLE SRI JUSTICE VAKITI RAMAKRISHNA REDDY

                      WRIT APPEAL No.992 OF 2025

JUDGMENT:

(Per Hon'ble Sri Justice Abhinand Kumar Shavili)

This Writ Appeal is filed aggrieved by the order, dated

02.09.2025, passed in I.A.No.2 of 2025 in W.P.No.21699 of 2025 by a

learned Single Judge of this Court, whereby, the interim order, dated

26.08.2025, passed in the said Writ Petition was recalled upon contest.

2. Heard Sri K. Vivek Reddy, learned Senior Counsel representing

Sri K. Pratik Reddy, learned counsel for the appellant,

Sri G. Madhusudhan Reddy, learned Standing Counsel for GHMC,

appearing for respondent Nos.2 to 4 and Sri V. Ravi Kiran Rao,

learned Senior Counsel representing Sri T.S. Anirudh Reddy, learned

counsel for respondent No.6.

3. Learned Senior Counsel appearing for the appellant had

contended that the appellant has 25% share in respondent No.6-

company. Respondent No.6 has started a project for construction of a

multistoried residential building by name and style 'Namitha 360 Life'

in Survey Nos.12(P) and 13(P) situated at Izzathanagar Village, 2 AKS,J & VRKR,J

Serilingampally Mandal, Ranga Reddy District, after obtaining

necessary permission from GHMC on 30.05.2019. Initially,

respondent No.6 has obtained building permission for construction of

multistoried residential building consisting of 2 Cellars + 3 stilts + 25

upper floors. However, within the validity of the permission,

respondent No.6 could not complete the entire project and there were

also certain deviations in the construction. While so, respondent No.6

is making efforts to construct another three extra floors and has

applied for building permission, but the GHMC has declined to grant

revised sanction plan for three additional floors. The GHMC vide

proceedings, dated 03.12.2024, has informed respondent No.6 that

there are 14 shortfalls from the original sanctioned plan and until and

unless respondent No.6 rectifies the shortfalls as pointed out in the

proceedings, dated 03.12.2024, the GHMC will not consider the case of

respondent No.6 for grant of revised sanction plan for construction of

three additional floors.

4. Learned Senior Counsel appearing for the appellant had further

contended that GHMC has once again inspected the subject premises 3 AKS,J & VRKR,J

and issued proceedings, dated 11.05.2025, reiterating its stand

that respondent No.6 must comply with the shortfalls and this time,

the GHMC has pointed out 18 shortfalls. Instead of complying

with/rectifying the said shortfalls, respondent No.6 is proceeding

with construction and if the construction is made contrary to the

sanctioned plan, the appellant would also be put to irreparable loss

and hardship, as admittedly, he is also one of the share-holders in

respondent No.6-company.

5. Learned Senior Counsel appearing for the appellant had further

contended that GHMC has revalidated the permission, which was

earlier granted to respondent No.6, vide proceedings, dated 11.06.2025,

without ensuring whether respondent No.6 has rectified the shortfalls

as pointed out in the proceedings, dated 03.12.2024 and 11.05.2025. In

those set of circumstances, challenging the proceedings, dated

11.06.2025, the appellant has approached this Court by filing the

subject W.P.No.21699 of 2025. Initially, the learned Single Judge vide

interim order, dated 26.08.2025, was pleased to grant interim direction

directing respondent No.6 not to proceed with further construction till 4 AKS,J & VRKR,J

the next date of hearing. Seeking to vacate the said order, dated

26.08.2025, respondent No.6 filed vacate stay application i.e. I.A.No.2

of 2025 and upon contest, the learned Single Judge was pleased to

vacate the interim order, dated 26.08.2025, without appreciating any

of the contentions raised by the appellant.

6. Learned Senior Counsel appearing for the appellant had further

contended that though GHMC has issued proceedings, dated

03.12.2024 and 11.05.2025, directing respondent No.6 to

rectify/comply with the shortfalls which were pointed out in those

proceedings, respondent No.6 without rectifying the shortfalls is

proceeding with construction. Learned Senior Counsel had further

contended that the learned Single Judge could not have permitted

respondent No.6 to go ahead with the construction. If the

construction is contrary to the sanctioned plan, the entire project will

collapse. This issue was clearly dealt with by the Honourable

Supreme Court in Rajendra Kumar Barjatya and another v. U.P.

Avas Evam Vikas Parishad and others1, wherein the Honourable

Supreme Court has categorically held that even if the constructions

Civil Appeal No.14604 of 2024, dated 17.12.2024.

5 AKS,J & VRKR,J

are as old as 24 years and if those constructions are found to be

contrary to the sanctioned plan, the authorities can always take action

against those illegal constructions. In the instant case, respondent

No.6 is proceeding with the construction contrary to the sanctioned

plan. Therefore, the learned Single Judge could not have vacated the

interim order granted in favour of the appellant. Therefore,

appropriate orders be passed in the Writ Appeal by setting aside the

impugned order, dated 02.09.2025, passed in I.A.No.2 of 2025 in

W.P.No.21699 of 2025 and allow the Writ Appeal and further, direct

respondent No.6 not to proceed with the construction, unless and

until respondent No.6 rectifies/complies with the shortfalls as pointed

out by the GHMC vide proceedings, dated 03.12.2024 and 11.05.2025.

7. On the other hand, learned Senior Counsel appearing for

respondent No.6 had contended that if respondent No.6 is prevented

from going ahead with the construction, respondent No.6 would not

be in a position to clear the shortfalls as pointed out by the GHMC

vide proceedings, dated 03.12.2024 and 11.05.2025. Learned Senior

Counsel had further contended that respondent No.6 undertakes that 6 AKS,J & VRKR,J

it would strictly comply with the original sanctioned plan, dated

30.05.2019, and also the proceedings, dated 11.06.2025, revalidating

the permission and only thereafter, it would seek revised building

permission for construction of three additional floors. Learned Senior

Counsel had further contended that let GHMC not issue Occupancy

Right Certificate, if the building is constructed contrary to the

sanctioned plan.

8. Learned Senior Counsel appearing for respondent No.6 had

further contended that respondent No.6 is willing to rectify the

shortfalls, so that GHMC can reconsider the case of respondent No.6

for construction of three additional floors by granting appropriate

permission. Therefore, the learned Single Judge was justified in

vacating the interim order and permitting respondent No.6 to go

ahead with the construction. Therefore, there are no merits in the

Writ Appeal and the same is liable to be dismissed.

9. Learned Senior Counsel appearing for respondent No.6 had

further contended that the appellant has filed civil case against

respondent No.6 and there is litigation going on between the 7 AKS,J & VRKR,J

appellant and respondent No.6. Only to harass respondent No.6,

the appellant has filed the subject Writ Petition. The appellant has

also got interest in respondent No.6-company, which means, he has

rival interest in the case. Therefore, the subject Writ Petition could not

have been filed by the appellant. On this count also, the Writ Appeal

is liable to be dismissed.

10. This Court, having considered the rival submissions made by

the learned counsel for the parties, is of the view that respondent No.6

has given an undertaking before this Court that it would rectify the

shortfalls as pointed out by GHMC vide proceedings, dated 03.12.2024

and 11.05.2025, and only thereafter, it would seek revised building

permission for construction of three additional floors. When

respondent No.6 gives such an undertaking before this Court, this

Court is of the considered view that the Writ Appeal can be disposed

of with an observation that respondent No.6 shall make endeavour to

rectify/comply with the shortfalls as pointed out by GHMC vide

proceedings, dated 03.12.2024 and 11.05.2025, and thereafter only,

respondent No.6 shall take steps for securing revised building 8 AKS,J & VRKR,J

permission for construction of three additional floors, which it

intends to construct.

11. With the above observations and recording the undertaking

given by respondent No.6, the Writ Appeal is disposed of. It is made

clear that Occupancy Right Certificate shall not be issued to

respondent No.6 unless and until it complies with the sanctioned plan

and the GHMC officials shall monitor the construction work of

respondent No.6 from time to time. There shall be no order as to

costs.

Miscellaneous Applications, if any, pending in this appeal shall

stand closed.

________________________________ ABHINAND KUMAR SHAVILI, J

___________________________________ VAKITI RAMAKRISHNA REDDY, J Date: 04.09.2025.

MD

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter