Friday, 08, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Telangana Mineral Development ... vs Gkr Infracon India Private Limited.
2025 Latest Caselaw 3458 Tel

Citation : 2025 Latest Caselaw 3458 Tel
Judgement Date : 27 March, 2025

Telangana High Court

Telangana Mineral Development ... vs Gkr Infracon India Private Limited. on 27 March, 2025

     THE HON'BLE THE ACTING CHIEF JUSTICE SUJOY PAUL
                            AND
           THE HON'BLE SMT. JUSTICE RENUKA YARA

                      WRIT APPEAL No.180 OF 2025

JUDGMENT:

(Per Hon'ble Smt. Justice Renuka Yara)

Heard Sri T.Rajinikanth Reddy, learned Additional Advocate

General appearing for the appellants and Sri Tarun G.Reddy, learned

counsel for respondent Nos.1 and 2. Perused the record.

2. This is an intra-court appeal filed by the appellants/respondent

Nos.1 and 2 aggrieved by the order dated 28.10.2024 passed in

W.P.No.21975 of 2024 by the learned Single Judge of this Court

declaring the action of the appellants/respondent Nos.1 and 2 in

rejecting the tender bid of the respondents/writ petitioners in respect

of tender No.TGMDC/S&M/DSLT/JB/2024/225, dated 14.06.2024

for de-siltation of 6,00,283.55 MT of sand from Mahadevpur/2024/2

sand reach at Jayashankar Bhupalpally District as illegal for not

assigning reasons, the award of tender No.TGMDC/S&M/DSLT/

JB/2024/225, dated 14.06.2024 in favour of respondent No.3 has

been set aside and the writ appellants are directed to call for fresh

bids in respect of tender No.TGMDC/S&M/DSLT/JB/2024/225,

dated 14.06.2024.

3. The background facts of the case are that the writ appellant

No.2 floated tender No.TGMDC/S&M/DSLT/JB/2024/225, dated

14.06.2024 for de-siltation of 6,00,283.55 MT of sand from

Mahadevpur/2024/2 sand reach at Jayashankar Bhupalpally

District and that the said tender was floated for a contract value of

approximately Rs.5,82,27,504/-. Respondent No.1 represented by

respondent No.2 and respondent No.3 participated in the bid. The

bid was awarded in favour of respondent No.3 as per the award dated

19.07.2024. The bid submitted by respondent No.1 has been

rejected as per the information provided in the Telangana

e-procurement portal.

4. The rejection of their bid is challenged by respondent Nos.1 and

2 on the premise that the writ appellants did not conduct the tender

process and awarding of the tender in fair and transparent manner

by referring to the legal ratios laid down by the Hon'ble Supreme

Court of India in Dharmapal Satyapal Limited v. Deputy

Commissioner of Central Excise, Gauhati and others 1, PKF

Sridhar and Santhanam v. Airports Economic Regulatory

Authority of India (WP(C) No.12385 of 2021), Swadeshi Cotton

Mills v. Union of India 2 and Punjab State Power Corporation

Limited and another v. EMTA Coal Limited and others 3.

Respondent Nos.1 and 2 primarily questioned the action of writ

appellants in rejecting the tender without assigning reasons and

(2015)8 SCC 519

AIR 1981 SCC 818

(2022)2 SCC 1

without giving them hearing for giving clarification on their Work

Done Certificate. The learned Single Judge allowed the writ petition

referring to various judgments of the Hon'ble Supreme Court of India

holding that decision making process adopted by the writ appellants

is contrary to principles of natural justice and lacking in

transparency in the tender process. It is held that no reason is

assigned for rejecting respondent No.1's bid as failing to have fulfilled

clause 3.2 tender conditions. In the light of the respondent No.1's

specific case that it fulfilled the requirement under clause 3.2 of the

tender conditions. It is held that as per the entry made in

e-procurement web portal on 19.07.2024, the writ appellants have

clearly observed that respondent No.1 has fulfilled the eligibility

criteria referring to the contents of Remarks column which are

extracted and produced below:

Remarks As per Tender Document

5. Further, the learned Single Judge held that the writ appellants

have failed to give an opportunity to respondent No.1 to give

clarification in case of any ambiguity about the contents of the Work

Done Certificate. Lastly, the learned Single Judge also referred to the

writ appellants issuing Letter of Intent to respondent No.3 on

10.07.2024 and the award of tender to respondent No.3 took place on

19.07.2024. Thus, the writ petition was allowed leading to filing of

the writ appeal.

6. The learned Additional Advocate General would submit that the

Government followed correct procedure as spelled out in the

procurement manual and the tender notification. It is emphasized

that respondent No.1 failed to meet the tender condition No.3.2,

which reads as follows:

"The bidder shall have satisfactorily completed at least one work of Mining/Civil/Irrigation work of value not less than Rs.4,65,82,003/- (Rupees Four crore Sixty Five lakhs Eighty Two thousand and Three only) (80% of value of work) involving excavation and removal any Earth/mineral including sand in State/Central Government Undertakings during the last three (3) years."

7. In this regard referring to the Work Done Certificates vide

Ref.Nos.KGM/JVR OC-II/2023/338C/608 and KGM/JVR OC-

II/2023/338D/609, both dated 12/16.05.2023 submitted by

respondent No.1, it is argued that said certificates clearly

demonstrate that respondent No.1 did not complete the contracts but

rather the work is still in progress in "Present status of work"

column.

8. In that context, it is argued that any bidder has to produce

certificate showing satisfactorily completed work of value not less

than Rs.4,65,82,003/- during the last three years of the bid. It is

argued that among 15 technical qualified bidders, 9 were rejected for

not complying tender clause 3.2 and the same was informed through

e-procurement website on 08.07.2024. Respondent No.1 is one

among 9 bidders whose tender was rejected for failing to meet the

criteria. The learned Additional Advocate General argued that the

Hon'ble Supreme Court in various judgments held that in contractual

matters the scope of judicial review or interference under Article 226

of Constitution of India is available in exceptional circumstances,

such as, on account of mala fides, arbitrariness and illegalities.

Whereas, in the instant case, no specific instance of malice is made

out. Only because respondent No.1 failed to satisfy the condition

under clause 3.2 of tender condition its bid was rejected which is not

arbitrary. The learned Additional Advocate General referred to the

judgment of the Hon'ble Supreme Court in Agmatel India Private

Limited v. Resourys Telecom and others 4, wherein it is held that

"The above mentioned statements of law make it amply clear that the author of the tender document is taken to be the best person to understand and appreciate its requirements; and if its interpretation is manifestly in consonance with the language of the tender document or subserving the purchase of the tender, the Court would prefer to keep restraint. Further to that, the technical evaluation or comparison by the Court is impermissible; and even if the interpretation given to the tender document by the person inviting offers is not as such acceptable to the constitutional court, that, by itself, would not be a reason for interfering with the interpretation given."

9. The contention of respondent No.1 about giving opportunity

under clause 21 to provide clarification with respect to Work Done

(2022)5 SCC 362

Certificate, it is argued that the employer can seek clarification at its

discretion. When the Work Done Certificate itself clearly reflected

that respondent No.1 did not complete the work, there is no need to

seek any clarification. Lastly, it is argued that the learned Single

Judge erred in observing that the letter of intent dated 10.07.2024

was issued in favour of respondent No.2 and the same is contrary to

the information on the web site which shows tender was awarded on

19.07.2024. According to the learned Additional Advocate General,

after the bids were submitted by prospective bidders, the bids were

evaluated by the Tender Evaluation Committee on 08.07.2024 to

ascertain the conditions stipulated and successful bidder was issued

the letter of intent on 10.07.2024 and said information was uploaded

on 19.07.2024. In the entire process, there is no mala fide or lack of

transparency. Learned Additional Advocate General referred to

judgment in W.A.Nos.116 and 117 of 2025, dated 13.02.2025

wherein it was held that:

"16. A careful reading of Clause 17.0 reproduced hereinabove shows that if bidder has been banned by any other body and has disclosed this fact clearly in his bid, as a rule of thumb, SCCL management will not disqualify him. The SCCL management reserves right to take appropriate decision in such eventuality. The language employed in the aforesaid clause shows that it enables the SCCL management to take an appropriate decision in such cases where disclosure of banning is there. The decision taken by SCCL management in the present case is to disqualify the petitioner. At this stage, we are not inclined to put the clock back and direct the Singareni Collieries Company Limited to undertake the entire exercise afresh. The Singareni Collieries Company Limited is serving public interest. For the smooth production and running of Singareni Collieries Company Limited, supply of bulk explosive is essential. Any interference by us at this juncture, will hamper the activity of the industry and consequently will have an adverse impact on public

interest. Thus, in the peculiar facts of these cases, we are not inclined to interfere in the matter. More-so, after passing of impugned order, third party rights are created and contracts have been granted to nine (9) contractors and they are not parties before us."

10. On the basis of above judgment, it is argued that this Court in

similar cases on earlier occasions declined to interfere with the

decision made by the Government while awarding tenders.

11. Learned counsel for respondent Nos.1 and 2 argued that it has

fulfilled condition under clause 3.2 of tender conditions and therefore

it was found to have qualified as per the entry in web portal dated

19.07.2024. It is argued that the learned Single Judge had assessed

the tender process adopted by the writ appellants in proper

perspective with respect to meeting the clause 3.2 of tender

conditions, not providing opportunity under tender clause 21 for

giving clarification about the Work Done Certificates and rejecting the

tender without assigning reasons. In that regard, learned counsel for

respondent Nos.1 and 2 referred to judgment of the Hon'ble Supreme

Court of India in M/s. Kasturi Lal Lakshi Reddy, rep. by its

partner Shri Kasturi Lal and others v. State of Jammu and

Kahsmir and another 5, wherein it is held that

"15.........Where the government is dealing with the public, whether by way of giving jobs or entering into contracts or granting other forms of largess. the Government cannot act arbitrarily at its, sweet will and, like a private individual, deal with any person it pleases, but its action must be in conformity with some standard or norm which is not arbitrary, irrational or irrelevant. The governmental action must not be

(1980)4 SCC 1

arbitrary or capricious, but must be based on some principle which meets the test of reason and relevance..."

12. Learned counsel for the respondents vehemently argued that

no reasons are assigned for rejecting its bid and thereby there is

violation of principles of natural justice. In that context, learned

counsel for the respondents referred to judgment of the Hon'ble

Supreme Court of India in Dharmapal's case (1 supra) and relevant

portion is extracted and produced below:

"The principles of natural justice developed over a period of time and which is still in vogue and valid even today were: (i) rule against bias, i.e. nemo iudex in causa sua; and (ii) opportunity of being heard to the concerned party, i.e. audi alteram partem. These are known as principles of natural justice. To these principles a third principle is added, which is of recent origin. It is duty to give reasons in support of decision, namely, passing of a 'reasoned order'.

13. Analysis by the Court:

A perusal of the record and the arguments of both the counsel

show that the crux of the dispute is with respect to whether or not

respondent No.1 met the criteria under clause 3.2 of tender

conditions, whether the writ appellants acted with mala fides in not

providing an opportunity to respondent No.1 to give clarification

about its Work Done Certificate and lastly whether the writ

appellants did not give a reasoned order for rejection of bid submitted

by respondent No.1 and thereby the tender process lacks

transparency.

14. First and foremost tender under clause 3.2 makes it

mandatory for the bidders to submit Work Done Certificate showing

satisfactory completion of at least one work of mining/civil/irrigation

of value not less than Rs.4,65,82,003/- (80% of value of work)

involving excavation and removal any earth/mineral including sand

in State/Central Government Undertakings during the last three

years. The aforementioned condition requires that the bidder shall

complete at least one work of required monitory value, complete

satisfactorily that too within last three years of the date of the bid.

While so, the Work Done Certificate submitted by respondent No.1

shows that the said company has taken up the work of Singareni

Collieries through work order No.7600009282, dated 21.10.2022 and

has completed certain work upto March 2023 and the status of the

work is "work in progress". Similarly, respondent No.1 has taken up

another work from Singareni Collieries Company Limited and the

certificate shows that the work is still in progress. The contents of

the Work Done Certificates submitted by respondent No.1 failed to

meet two criteria, i.e. completion of work and completion of work

satisfactorily. Only when the entire work is completed that too to the

satisfaction of the employer, it can be said that respondent No.1 has

successfully fulfilled the criteria under clause 3.2 of tender

conditions and not otherwise. The contents of the Work Done

Certificate speak for themselves and cannot be given any other

interpretation. The respondents would contend that the contracts

awarded are for a period of 11 months and 17 months respectively

and each component of work done is a separate piece work which is

to be treated as completed satisfactorily. Such interpretation of the

contents of the Work Done Certificates is not acceptable.

15. Coming to the aspect of seeking clarification from the bidder as

per clause 21 of tender conditions, said tender condition itself clearly

shows that the clarification may be sought at the discretion of the

employer. In case, the employer after perusing the contents Work

Done Certificate has come to the conclusion that the work is still in

progress and that has not been completed, no fault can be found

with the employer. A conjoint reading of clause 3.2 and 21 of the

tender conditions together with the contents of Work Done

Certificates does not make out a positive case in favour of respondent

No.1.

16. Coming to the contention of respondent Nos.1 and 2 that as

per clause 22.1, the eligibility criteria is as per definition ITB clause 3

and only when the eligibility criteria is met, the further evaluation

takes place. To ascertain the case of respondent Nos.1 and 2, said

entry in the web portal is produced below:

Technical parameters list:

Para Parameter Operat Date Min Max Parameter Fulfill Remarks Evaluation meter Description or Type Value value ed comments value name As per As per Text 0.00 0.00 Yes Yes As per Clause 3.2 tender tender Tender of Tender docu document Document conditions ment not fulfilled

17. A reference is made to the contents of above award of tender

dated 19.07.2024 to the "Remarks" column wherein it is entered as

"As per Tender document". This entry in the Remarks column is mis-

interpreted by respondent No.1 to mean that respondent No.1 has

met the eligibility criteria as per 3.2. To the contrary, the meaning of

the contents of "Remarks" column can be construed as that

respondent No.1 qualified for further evaluation of the bid as it has

met the eligibility criteria by filing all the required tender documents

including the Work Done Certificate. The title of the column is

"Remarks". Remarks with respect to whether the bidders have filed

all the documents or not. Only such bidders who have filed all the

documents are eligible for evaluation of their bids and further steps.

18. The next column is titled "evaluation comments", wherein it is

clearly mentioned as "clause 3.2 of Tender conditions not fulfilled".

Therefore, a close scrutiny of the contents of "Remarks" column and

the contents of "evaluation comments" column shows that the

contents of the Remarks column are meant for noting down the

eligibility of a bidder prima facie on account to filing of required

documents as per tender notification and not on the basis of contents

of said documents. Only after the documents filed for the evaluation

of the bid are in order, the contents are examined and an evaluation

is made as to the eligibility of the bidders and thereby respondent

No.1 has been found to be lacking to have met the conditions under

clause 3.2. However, respondent No.1 is mis-interpreting the

contents of "Remarks" column and the "evaluation comments"

column and the same has been erroneously relied upon by the

learned Single Judge while passing the impugned order.

19. Coming to the aspect of observing principles of natural justice,

about passing a reasoned order while rejecting an application, a

reasoned order is passed when there is an adjudication process,

where there are two or more rival contestants, each person is heard

and an evaluation is made of the rival contentions and reasoned

order is passed. In the instant case, the entire tender process took

place online wherein the bids are submitted online and the result

also has been declared online. A reason for rejection is the criteria

for meeting the requirements of principles of natural justice. The

said reasoned order could be one word, one line or a paragraph or

more. In the instant case, the employer has given the reason for

rejecting bid of respondent No.1 by stating that respondent No.1

failed to meet the conditions of clause 3.2 of tender conditions. The

said reason when written in one line or in an elaborate manner

would convey the same meaning. Thus, there is no ground to accuse

the writ appellants of not observing the principles of natural justice.

20. Lastly, mala fides are attributed to the writ appellants on the

basis of issuance of letter of intent dated 10.07.2024 while the

information was made available by the writ appellants on e-

procurement website indicated that respondent No.3 was declared

the successful bidder and awarded the tender only on 19.07.2024.

In this regard, it is seen that the said allegation was not made by

respondent No.1 in the writ petition but was raised only at the time

of filing a rejoinder to the counter filed by respondent No.3.

21. In this regard, as per judgment of the Hon'ble Supreme Court

in Arti Sapru v. State of Jammu and Kashmir 6, the allegations

made for the first time in the rejoinder affidavit do not give scope for

reasonable opportunity to the respondents to give reply and therefore

cannot form basis for a finding in favour of the petitioner. Likewise

in the matter of Ashok Lanka v. Rishi Dikshit 7, the Hon'ble

Supreme Court held that when the allegations are made in the

rejoinder, when no new plea can be permitted in the rejoinder,

without the leave of the Court, such allegations cannot be relied

upon. While legal precedents do not support respondent No.1's

(1981)2SCC 484

(2006)9SCC 90

allegations made in the rejoinder for the first time attributing mala

fides, we are of the considered opinion that the contents of the web

portal dated 19.07.2024 are also mis-interpreted on account of the

fact that the tender evaluation process has been completed by

08.07.2024 and the letter of intent was issued to the successful

bidder on 10.07.2024 and said information was uploaded in the

website on 19.07.2024. Last but not least, after the bids are

evaluated, the eligible bidder has been selected by way of lottery in

the presence of all the bidders. The learned Additional Advocate

General pointed out that even respondent No.1 participated in the

lottery process that took place on 10.07.2024 and therefore, no mala

fides can be attributed to reference Nos.1 and 2, as the entire process

has been conducted in transparent manner as per the tender process

contemplated in the tender conditions as well as notification. When

the successful bidder is selected through the process of drawing lots

in the presence of all the eligible bidders, no mala fides can be

attributed to the writ appellants in conducting the tender process in

fair and transparent manner.

22. For the foregoing reasons, we are of the considered opinion that

the learned Single Judge erred in reading the contents of the Work

Done Certificates, the e-procurement award dated 19.07.2024 and

the factum of issuance of letter of intent dated 10.07.2024 and

publishing said information on 19.07.2024 in the e-procurement

online website and therefore the said impugned of the learned Single

Judge is liable to be set aside.

23. In the result, the Writ Appeal is allowed setting aside the order

dated 28.10.2024 in W.P.No.21975 of 2024 passed by the learned

Single Judge. There shall be no order as to costs.

Miscellaneous applications, if any, pending in this appeal, shall

stand closed.

___________________ SUJOY PAUL, ACJ

____________________ RENUKA YARA, J Date: 27.03.2025 ssp

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter