Citation : 2025 Latest Caselaw 3085 Tel
Judgement Date : 13 March, 2025
HON'BLE SRI JUSTICE ABHINAND KUMAR SHAVILI
AND
HON'BLE SMT. JUSTICE TIRUMALA DEVI EADA
CITY CIVIL COURT APPEAL NOs.154 AND 234 OF 2007
COMMON JUDGMENT:
(per Hon'ble Smt. Justice Tirumala Devi Eada)
These two appeals are filed by the appellants aggrieved by the
judgment and decree dated 26.12.2006 passed in O.S.No.334 of
2002 by the learned XIV Additional Chief Judge, City Civil Court,
Fast Track Court at Hyderabad (hereinafter referred to as 'the trial
Court').
2. For convenience and clarity, the parties herein are referred to
as they were arrayed before the trial Court.
3. The case of the plaintiff before the trial Court is that the
Deccan Enterprises Private Limited is a company carrying business
in manufacturing of rubber products, located at Balanagar. It is
their case that it has taken two insurance policies of "Standard Fire
and Special Perils" with the defendant vide policy
Nos.550100/11/2000/34/00080 and 550100/11/2000/13/2000.
Item No.6 of the policy covers loss due to "storm, Cyclone, Typhon,
Hurricane, Tornado, Flood and inundation". While so on
23.08.2000 due to sudden and unforeseen downpour of rain, the
storm water drains overflowed, as a result of which, the entire area
of Balanagar and other areas of twin cities were inundated with AKS,J & ETD,J
water. The plaintiff factory which is located at Balanagar also got
inundated to a height of about 5 to 6 feet causing extensive damage
to building, plant and machinery, lab equipment, raw materials and
that the said loss was covered under the insurance policies. That
the plaintiff has immediately informed the insurance company and
the insurance company has also sent surveyor by name
N.V.P.Sharma Associates Pvt.Ltd., and that the said surveyor has
inspected the factory and submitted his report. Initially, they raised
a claim amounting to Rs.102.50 Lakhs and thereafter, after detailed
examination of the damages with the contractors, the total
estimation of loss was reduced by the plaintiff to Rs.85,85,000/-.
After submitting the claim, the plaintiff has time and again
requested the defendant company to settle their claim but in vain,
getting vexed with the attitude of the defendant, the present suit is
filed.
4. Defendant has filed its written statement. The defendant
company has admitted that the plaintiff is insured with it under two
policies, but has denied the other averments in the plaint stating
that their policy is restricted subject to the terms and conditions
laid down under it and that the plaintiff has played fraud in arriving
at the claim and that he tried to claim exorbitant amounts and
initially he submitted his claim to Rs.25,00,000/- for repairs to AKS,J & ETD,J
plant and machinery and when a letter was addressed to them, in
reply, he has again reduced the claim to Rs.21,26,882/- and that
the surveyor, while submitting his report has mentioned that the
plaintiff tried to claim exorbitant amounts. His total claim was
Rs.102.50 lakhs initially which was later on reduced to
Rs.85,85,000/-. Therefore, all these discrepancies prove the
fraudulent attitude of the plaintiff and thus, as per the condition
No.8 of the policy, their company is not liable to pay any claim of
the plaintiff and that the alleged claim is not tenable under the
policy. That the purchases alleged to have been made by the
plaintiff company from M/s.Deccan Industrial Products Private
Limited (DIPPL) during the month of August, 2000 are without sales
tax and excise duty and that the Deputy Managing Director of
DIPPL i.e. Vikas Jalan and his wife Richa Jalan are the son and
daughter-in-law of the director of the plaintiff company, O.P.Jalan,
it is nothing but a sister concern of the plaintiff company and thus,
those invoices are raised fraudulently to make a false claim with the
insurance company. Another strong contention made by the
defendant in his written statement is that machinery repair bills
submitted by the M/s.Makvy Engineering Services are fraudulent
and that the proprietor of the company SriY.V.M.M.K.Murthy @
Murali is employed by the plaintiff company as Works Manager, and
by DIPPL as plant manager and that just because he is a known AKS,J & ETD,J
person they have raised false invoices for repairs and cooked up the
claim, therefore, the defendants prayed to dismiss the suit filed by
the plaintiff.
5. Based on the above pleadings, the trial Court has framed the
following issues:
"1. Whether the plaintiff is entitled for various claims made by him in the plaint?
2. Whether the plaintiff is entitled for interest as well as loss of profits due to non-settlement of claims?
3. Whether the plaintiff is entitled for future profits?
4. To what relief?"
6. At the time of trial, the plaintiff got examined PWs 1 to 3 and
got marked Exs.A1 to A92. On behalf of the defendants, DWs1 to 3
were examined and Exs.B1 to B8 were marked.
7. Based on the evidence on record, the trial Court has decreed
the suit for Rs.21,81,736/- and also for the amount of labour
charges deducted by the surveyor towards depreciation with interest
@ 12% per annum on the said amounts from 25.08.2000 till the
date of payment and with proportionate costs.
8. Aggrieved by the said judgment and decree, both the parties
i.e. the plaintiff company has preferred CCCA No.234 of 2007 AKS,J & ETD,J
seeking enhancement while the defendant company has filed CCCA
No.154 of 2007, seeking total exoneration.
9. Heard the submissions of learned counsel for the appellant
and learned counsel for the respondent.
10. Learned counsel for the Deccan Enterprises Private
Limited/plaintiff has submitted that their policies were subsisting
as on the date of the calamity and that the entire loss suffered by
them is covered under the policy and that the defendant is liable to
pay the entire suit claim while the trial Court has erred in assessing
the suit claim. He further submitted that the trial Court ought to
have granted them the entire suit claim of Rs.1,85,98,261/- and
that the surveyor himself has wrongly assessed the damage by not
including the entire loss suffered by them and that he deducted
huge amounts towards depreciation on all items and has arrived at
a very meager amount of loss that occurred due to the damage
caused by the floods and inundation. Further, the trial Court has
not looked into all the evidence that is adduced by the plaintiff and
the cross examination of surveyor is also not taken into
consideration and therefore, the counsel has prayed to allow their
appeal i.e. CCCA No.234 of 2007 by setting aside the judgment and
decree passed by the trial Court.
AKS,J & ETD,J
11. On the other hand, the counsel for the Insurance
Company/Defendant has submitted that their company is not at all
liable to pay the suit claim and that though their company has
issued policies to the plaintiff, the condition No.8 stipulated in the
policy says that any claim raised fraudulently need not be honoured
and that the plaintiff company has fraudulently raised the present
claim based on false invoices alleging that they had purchased the
raw material from DIPPL which is its sister concern and also that
the plaintiff company has raised false repair bills through a known
source i.e M/s.Makvy Engineering Services and has arrived at
exorbitant amount. When the intention of the plaintiff itself is
fraudulent in raising the claim, their company need not honour the
same in view of the said condition, hence, he prayed to dismiss the
claim against them by allowing their appeal i.e. CCCA No.154 of
2007.
12. Based on the above rival submissions, the following points
arise for determination:
1. Whether the plaintiff is entitled to recover the amount claimed in the suit from the defendant?
2. Whether the judgment and decree passed by the trial Court is sustainable under law and in facts?
3. To what relief?
AKS,J & ETD,J
13. POINT NOS.1 AND 2:
a) The admitted facts in this case are that the plaintiff is a
registered company which is into manufacturing rubber products
and that it has obtained two insurance policies from the defendant
company i.e. "Standard Fire and Special Perils" in the year 2000
vide policy Nos.550100/11/2000/34/00080 and
550100/11/2000/13/2000. It is also admitted that item No.6 of
the policy No.2 covers "storm, Cyclone, Typhon, Hurricane,
Tornado, Flood and Unundation" and that on 23.08.2000 there was
a flood in Hyderabad and Secunderabd due to incessant rains and
that the plaintiff company got inundated with water to a height of
about 5 to 6 feet and that there was some damage to the building,
plant and machinery, lab equipment, furniture etc., It is also
admitted that the plaintiff has informed about the damage to the
insurance company and the company has appointed a surveyor
M/s. N.V.P.Sharma Associated Pvt.Ltd., on 26.08.2000 and on
06.09.2000 the plaintiff made a claim of Rs.1,02,50,000/-
subsequently, on receiving a letter from the surveyor as well as the
company, the plaintiff has reassessed its loss and submitted a claim
for Rs.85,85,000/-.
b) The dispute is with regard to the question of liability. The
insurance company contends that though the policies are valid, the
condition No.8 stipulated in the policy prohibits the honouring of AKS,J & ETD,J
fraudulent claims. A perusal of Ex.A3, the policy reveals that the
condition No.8 reads as follows:
"If the claim be in any respect fraudulent, or if any false declaration be made or used in support thereof or of any fraudulent means or devices are used by the Insured or any one acting on his behalf to obtain any benefit under the policy or if the loss or damage be occasioned by the willful act, or with the connivance of the Insured, all benefits under this policy shall be forfeited"
c) Thus, any claim is fraudulent or if any false declaration is
made or if any fraudulent means or devices are used by the Insured
to obtain any benefit under the policy, then the company is not
liable to honour such claims.
d) It is the case of the defendant that, the plaintiff has played
fraud in submitting the claim and so their company is not liable to
honour the claim. Its contention is mainly based on two counts.
Firstly, the purchases alleged to have been made by the plaintiff
company from M/s.Deccan Industrial Products Private Limited
(DIPPL) during the month of August, 2000 are without sales tax and
excise duty and that the Deputy Managing Director of the plaintiff
i.e. Vikas Jalan and his wife Richa Jalan are the son and daughter-
in-law of the director of the plaintiff company, O.P.Jalan, therefore,
it is nothing but a sister concern of the plaintiff company and thus,
the invoices are raised fraudulently to make a false claim with the AKS,J & ETD,J
insurance company. Secondly, it is another specific contention of
the defendant that the machinery repair bills submitted by the
M/s.Makvy Engineering Services are fraudulent and that the
proprietor of the company SriY.V.M.M.K.Murthy @ Murali is being
employed by the plaintiff company as Works Manager and by DIPPL
as plant manager and that no company with the said address as
given on the bills could be located in that area.
e) It is the burden of the plaintiff to prove that their claim is
genuine and is not hit by this fraudulent clause. Plaintiff got
examined PWs 1 to 3 and got marked 98 exhibits to prove their
claim. There are certain facts brought out in the evidence on record
which throw light on the above contentions. Once, the surveyor was
appointed he has examined all the details of the claim and it is
brought on record that most of the raw materials have been
purchased only during August, 2000 just before floods. Almost all
the stocks claimed to be washed away in the floods are shown to
have been purchased from DIPPL. It is particularly averred by the
defendant that the sale invoices for the month of August, 2000
pertaining to the plaintiff are without sales tax or excise duty and in
most cases the sale prices are lower than the purchase cost of
DIPPL and that DIPPL is not a regular supplier of raw material to
the plaintiff.
AKS,J & ETD,J
f) PW1/O.P.Jalan is the Director of plaintiff company. In his
cross examination it is elicited that his son Vikas Jalan and his
daughter-in-law Richa Jalan are the directors of DIPPL and that the
said company is located at Miyapur and it manufactures rubber
components for usage in railways and also rubber floor tiles, while
the plaintiff company manufactures rubber components used for
railways but not floor tiles. He also stated that DIPPL supplied raw
material to the plaintiff company earlier to this incident. But no
such proof is filed in this regard. It is also brought out in his
evidence that no inward register is produced by them. Ex.A48 is an
inward register but according to PW1, it is a kaccha register which
is maintained by the gateman for his own purpose and he does not
even know the reason for maintaining the same. It is further
elicited through him that the reason for filing the said register in the
Court is just because surveyor has referred the same as inward
register in his report. A perusal of Ex.A48 reveals that it portrays
the daily entries of the materials received at the gate.
g) When there was a specific contention by the defendant that
the plaintiff tried to show false invoices towards its purchase from
DIPPL, the burden was on the plaintiff to prove the fact that it is not
a fraudulent claim and that he had been purchasing the raw
material from DIPPL that means he could have shown the entries AKS,J & ETD,J
prior to August, 2000 also and further he could have produced the
inward register as well, which is not done.
h) It is further elicited through his evidence that whatever
material that was in powder form or granule form was washed away
partly due to inundation. But at one point of time he has conceded
saying that the powder and granules available in factory are not
soluble in water and that he did not take any expert to the factory
and obtain a report as to whether the powder and granules got
mixed with mud in the factory premises. The reason expressed by
him is that the surveyor was appointed by the defendant and that
the surveyor did not ask for any expert's opinion and that is why he
could not obtain the same. It is alleged by him that 1300 kg of
Silica, 140 kgs of TMT, 900 kgs of Aluminum Silicate, 950 kgs of
Calicium Carbonate and 940 kgs of whiting got washed away in the
flood and that the opening balance as on 01.08.2000 is shown in
Ex.A27 but a perusal of Ex.A27 reveals that the opening balance of
the stock available as on 01.08.2000 is very meager. It is further
stated by him that certain entries made in Exs.A18, 27, 32, 73 and
79 got washed away in the floods. The said entries pertain to the
purchases stated to have been made from DIPPL.
AKS,J & ETD,J
i) PW2 is a Commercial Manager in the plaintiff company, it is
elicited through his evidence that he visited Visakhapatnam on his
company's work and that he met the investigator Mr.Sisir of "Sisir
and Ravi Associates" and that he handedover an unsigned copy of
Addendum Report dated 10.09.2001 (Ex.A84) prepared by him. The
evidence of PW2 does not aid the plaintiff in proving his claim.
j) DW1 is the surveyor appointed by the insurance company
and his evidence reveals that he visited the plaintiff company and
that he has asked the plaintiff to take the photographs of damaged
parts, clear the debris and proceed with the repairs of the plant and
machinery. It is further elicited through him that initially the
damages were assessed by the plaintiff company through the letter
under Ex.A10 to an amount of Rs.1,02,50,000/- and that
subsequently on repeated communication, the plaintiff has reduced
its claim to Rs.85,85,000/-.
k) The defence taken by the plaintiff to the contention of
increased purchases during August is that the railways have
restored the production by placing orders in the last week of June
or 1st week of July and the same is informed to the defendant under
Ex.A37. It is their contention that their main customer is the
railways and when it has slowed down its consumption, the plaintiff
has reduced their work and on the increased requirement by the AKS,J & ETD,J
railways, they have increased their purchases. But it is to be
observed that when the railways have restored the production and
have placed an indent during last week of June or 1st week of July,
the plaintiff must have increased its purchases during the month of
July also but it is nowhere placed on record and moreover from the
documents placed by the plaintiff company, it is elicited that only
during the month of August i.e. 15 days prior to the inundation the
indent of the company was increased multifold.
l) A perusal of the surveyor's report under Ex.B6 reveals the
quantity of raw material available at the plaintiff's premises after the
flood. The said document is prepared by the surveyor-DW1. In his
cross examination, it is elicited that a part of the material
purchased from DIPPL also may be there in the said inventory
under Ex.B6. His inventory under Ex.B6 shows the material that is
in good condition and the material which is washed away. The
contention of the appellant's counsel is that the surveyor has not
investigated into the issue independently and that he has relied
upon the Auditor's report. The counsel wanted to emphasize upon
the cross examination of DW1 by highlighting the statement made
by DW1 that he has not investigated independently. But the cross
examination cannot be looked into as bits and pieces, it has to be
taken as a whole. He has clearly stated that he did not verify the AKS,J & ETD,J
source of purchase so far as the items allowed by him in Annexure-
II of Ex.B6. It is further elicited through him that the Research
Designs and Standard Organization of Railways instructed the
plaintiff to stop the work with immediate effect by addressing
Ex.A28 dated 04.02.2000 and that the production in the plaintiff
factory was suspended from February, 2000 to July, 2000 as per
the letter of RDSO. Even if this statement is taken into
consideration, the plaintiff has other customers apart from railways,
though railways is stated to be the major customer. Another point
is, the plaintiff has not purchased any items during the month of
July though the production was started. As per the statement of
PW1, the production started again in July but the purchases
reflected in the documents do not show any purchases during the
month of July, the glut of purchase is only during the first 15 days
of August i.e. prior to floods.
m) It is elicited through DW2 who is the Chartered Accountant
that the invoices are available with the plaintiff company but there
are certain discrepancies and that excise duty, service tax and sales
tax were not collected from the plaintiff as seen from the invoices
and he further stated that the plaintiffs have not purchased any
material from DIPPL earlier to 1st August or subsequent to 16th
August, 2000 upto the date of his inspection. It is further elicited AKS,J & ETD,J
from him that the material purchased under delivery challan No.48
from DIPPL is included in the stores ledger on 16.08.2000. All the
sales transactions that were said to have taken place between 1st to
16th of August, 2000 find a place in stores ledger. He has also
stated that the plaintiff has not purchased any material from DIPPL
from August of 2000 to 31.03.2001. Annexure-8 to his report under
Ex.B7 is the delivery challan No.93 dated 07.12.2000 which shows
the supply of raw material worth Rs.28,139/- by DIPPL to the
plaintiff. He stated that he did not rely upon the said Annexure-8
as he has good grounds to suspect the genuineness of this
transaction and that such a transaction can be brought into
existence at any time because the management is the same for both
the companies. But through Annexure-8 of Ex.B7 it is established
that there was supply of raw material from DIPPL subsequent to the
floods also. It is further elicited from DW2 that the invoices do not
disclose payments of sales tax and excise duty on the said
transactions and therefore, he could not verify the sales tax returns
or the excise duty returns. This again casts a shadow on the
genuineness of the invoices put-forth by the plaintiff. However,
Ex.A27 reveals that there was some stock available in the premises
as on 01.08.2000. Then even if the alleged false invoices are
ignored, there was some stock in the company at the time of
inundation.
AKS,J & ETD,J
n) With regard to the bills of repairs, PW1 has admitted that at
the relevant time YVMMK Murthy is working in DIPPL as plant
manager. It is also brought out in the evidence of DW1 that he met
said Murthy in the premises of plaintiff company and he was
working as works manager in the plaintiff company at the time of
his visit and it was informed by Murthy that he does not know
anything about the repairs and that he has just joined the company
on 15.02.2001. The plaintiff has never chosen to examine
Mr.Murthy as a witness.
o) PW3 is a Retired Engineer of IDPL. His evidence reveals that
he was approached by Mr.YVMMK Murthy, the proprietor of Makvy
Engineering Services to assist him and supervise the execution of a
service contract undertaken by him with M/s.Deccan Enterprises
Private Limited and that the equipment was severely damaged due
to flood and inundation of water, mud, sand and scrap and other
foreign materials on 23.08.2000 and that he has more than 20
years of experience and that he accepted the said assignment and
Mr.Murthy agreed to pay him a lumpsum amount of Rs.50,000/-.
It is elicited during his cross examination that he was an employee
of the plaintiff company from 1974 to 1977 before joining IDPL. He
also signed on Ex.A66. He admitted that the proprietor of Makvy
Engineering Services worked in DIPPL earlier and that there is no AKS,J & ETD,J
proof that Makvy Engineering Services employed him as consultant.
Ex.A66 is the declaration given by him at the request of plaintiff.
This again proves the contention of the defendant that the DIPPL
and plaintiff were sister concerns and also that the proprietor of
Makvy Engineering Services is known to plaintiff.
p) DW3 is the Assistant Divisional Manager of National
insurance Company. Apart from protecting the interest of the
company there are few facts that are elicited from his evidence, he
has stated during his cross examination that the repair bills of the
machinery pertaining to J.K.S.Electrical Works under Ex.B3 and
Kode Electricals & Controls under Ex.B4 were picked up for detailed
examination and that neither of the repairers were found to have
the capability or competence to undertake the jobs stated to have
been done by them and further he stated that the address of Makvy
Engineering Services as mentioned in Ex.B5 could not be located
and that the alleged proprietor of Makvy Engineering Services by
name Mr.Murthy was officiating as works manager in the plaintiffs
company and was also employed by DIPPL as plant manager. It is
further elicited that Murthy denied of any knowledge of the repairs
on the plea that he has just joined the plaintiff's company but he
was the person who submitted the bills for the repairs carried out
by Makvy Engineering Services. Therefore, the entire bills raised for AKS,J & ETD,J
repairs by the plaintiff cannot be believed to be totally true. But
inundation of the plaintiff factory upto a height of 5 feet is an
admitted fact. DW1/surveyor also suggested repairs to plant and
machinery after inspecting the premises.
q) Thus, an overall perusal of the entire evidence on record
reveals that there was inundation in the plaintiff company due to
the incessant rains and floods in the twin cities on the intervening
night of 23/24 August, and that there was certain damage in the
plaintiff company but the discrepancy is with regard to the extent of
damage that has taken place. The plaintiff averred that he has
incurred Rs.85,85,000/- but could not place clinching evidence to
prove the loss to the said extent. The insurance company has
appointed a surveyor as it is usually done in such cases, the
surveyor on thorough investigation has submitted his report under
Ex.B6 so also the investigator appointed by the company has
submitted his report under Ex.B7. As per the surveyors report, the
company has sustained loss to an extent of Rs.21,81,736/-.
Therefore, since it is an admitted fact that the plaintiff company has
sustained some loss due to the inundation, once the surveyors
report establishes the loss to an extent of Rs.21,81,736/-, then it
can be safely held that the plaintiff has sustained loss to an extent
of Rs.21,81,736/-. Now the next question is whether the defendant
insurance company is liable to pay the said amount in view of the AKS,J & ETD,J
condition No.8 stipulated in the policy under Ex.A3. It is an
admitted fact that the plaintiff suffered some loss due to the floods,
therefore the claim itself cannot be held to be fraudulent. For
convenience and clarity, condition No.8 of Ex.A3/policy is reiterated
extracted hereunder:
"If the claim be in any respect fraudulent, or if any false declaration be made or used in support thereof or of any fraudulent means or devices are used by the Insured or any one acting on his behalf to obtain any benefit under the policy or if the loss or damage be occasioned by the willful act, or with the connivance of the Insured, all benefits under this policy shall be forfeited"
r) If the said condition is examined under the facts and
circumstances of the case, there are discrepancies to the extent of
damage which are brought out and elaborately discussed in the
evidence supra, but an attempt to exaggerate the claim cannot be
held to make the entire claim itself to be fraudulent in nature. It is
for the insurance company to assess the actual damage and arrive
at the loss sustained so that it can honour the claim. A surveyor
was appointed and the loss was assessed by him. The defendant
also does not say that the plaintiff has not suffered any loss due to
inundation. It is a clear admission by the defendant company that
the plaintiff has sustained loss due to inundation and it is only to
the extent of loss that the discrepancy lies. Therefore, it is held that
the plaintiff company has suffered loss due to inundation to an
extent of Rs.21,81,736/- which has to be paid by the insurance AKS,J & ETD,J
company as the loss sustained is covered under the policy
mentioned at Ex.A3. The appellants counsel in C.C.C.A.No.154 of
2007 has contended that the suit should not be kept open and that
the trial Court was wrong in asking both the parties to file a
calculation memo with regard to the depreciation charges deducted
by the surveyor and that finality should have been expressed by the
trial Court. It is borne out by record that there was a calculation
memo filed by the plaintiff correcting the errors in surveyor's report
after which it has filed a memo to the effect that Rs.21,81,736/- is
the loss incurred. Surveyor is appointed by the insurance company
for assessing the loss, the said loss is admitted by the plaintiff.
Once the surveyor report is placed on record, there is no other
amount to add, over and above the assessment made by the
surveyor. If this is allowed, it would again lead to discrepancies and
multiplicity of proceedings.
s) The record depict that initially the surveyor has submitted a
report under Ex.B6 wherein he assessed the loss as Rs.22,58,039/-
after deducting certain purchases and depreciation amounts. Then,
through a memo, the plaintiff filed a re-computation of surveyor's
assessment after rectifying the arithmetical errors to an extent of
Rs.21,81,736/- as per surveyor's report. Therefore, it is held that
once the surveyors report is filed and the plaintiff has re-computed
the same and rectified it, the plaintiff is entitled to recover the same AKS,J & ETD,J
from the defendant company. Point Nos.1 and 2 are answered
accordingly.
14. POINT NO.3:
In view of the reasoned finding arrived at under point Nos.1
and 2, it is held that the judgment and decree dated 26.12.2006 of
the trial Court need to be modified to the extent of granting
depreciation charges that are deducted by the surveyor, is set aside.
15. POINT NO.4:
In the result, C.C.C.A.No.234 of 2007 filed by the plaintiff
company is dismissed and the C.C.C.A.No.154 of 2007 filed by the
defendant - Insurance Company is partly allowed by setting aside
the judgment and decree dated 26.12.2006 of the trial Court to the
extent of granting depreciation charges that are deducted by the
surveyor towards labour charges. No costs.
Miscellaneous Petitions pending, if any, shall stand closed.
________________________________ ABHINAND KUMAR SHAVILI, J
___________________________ TIRUMALA DEVI EADA, J Date: 13.03.2025 ns
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!