Citation : 2025 Latest Caselaw 4159 Tel
Judgement Date : 23 June, 2025
THE HON'BLE SRI JUSTICE B. VIJAYSEN REDDY
WRIT PETITION No.4098 of 2025
ORDER:
This writ petition is filed seeking a direction from this Court
to declare the to issue an appropriate writ order or direction more
particularly one in the nature of Writ of Prohibition (A) prohibiting
the respondent No.2 from proceeding further with Complaint
No.187 of 2024 by declaring that the respondent No.2 has no
jurisdiction to entertain, hear or decide Complaint No.187 of 2024
pending before it filed under Section 31 of the Real Estate
(Regulation and Development) Act, 2016 (RERA Act) by the
respondent No.4 against the petitioners as being patently illegal,
in contravention of Rule 2(J) of the Telangana State Real Estate
(Regulation and Development) Rules, 2017 ('RERA Rules') and
(B)consequently dismiss the Complaint No.187 of 2024 pending
before the respondent No.2 as not maintainable and
(C) pass such other order or orders.
2. The petitioners are absolute owners of the land admeasuring
Ac.24.11 guntas in Survey Nos.159/Part and 162/Part, Gopanpally
Village, Serilingampally Mandal, Ranga Reddy District, Telangana
(schedule property). The petitioners applied for building permission
from the Greater Hyderabad Municipal Corporation (GHMC) and the
same was granted vide Permit No.2581/HO/WZ/Cir-11/2010 dated
08.06.2011 for development of gated community with
105 independent houses along with 6 units for LIG and 6 units for
EWS. The building permission was originally valid for a period of
3 years till 07.06.2014, which was later extended for a period of six
years as per Rule 19(d) of G.O.Ms.No.168 dated 07.04.2012 and
amended Rule 19(d) vide G.O.Ms.No.7 dated 05.01.2016.
3. It is submitted that pursuant to the building permit,
the petitioners developed the schedule property land into a layout
with plotted area and several plots were sold under registered sale
deeds. There is no dispute with respect to sale of plots by the
petitioners. Some of the plot owners entered into independent
construction contracts with the petitioner No.1 for construction or
completion of under-construction villas. The said independent
contracts were entered with individuals by the petitioner No.1 alone
and therefore, cannot be brought within the purview of Telangana
State Real Estate Regulatory Authority (TSRERA).
4. It is submitted that the RERA Act was enacted by the
Parliament, which came into effect from 01.05.2016. Section 3 of
the RERA Act provides for registration of real estate projects.
The proviso to Section 3 of the Act provides that the projects that
are ongoing on the date of commencement of the RERA Act and for
which the completion certificate has not been issued, the promoter
shall make an application to the Authority for registration of the
said project within a period of three months from the date of
commencement of the RERA Act. As per the RERA Act,
the Government of Telangana enacted the RERA Rules, which were
published vide G.O.Ms.No.202 dated 31.07.2017. Rule 2(j) of the
Rules, 2017 defines 'ongoing project'. The term 'ongoing project'
is not defined under the RERA Act.
5. It is submitted that the petitioners' project 'Pristine Estates'
is exempt from registration under RERA Act in view of the Rule 2(j)
and thereby, the provisions of RERA Act will not apply to the project
permitted vide GHMC Building Permit Order No:2581/HO/MZ/Cir-
11/2010, dated 08.06.2011. As the project was approved before
01.01.2017, the provisions of the RERA Act would not apply and
therefore, no complaint can be entertained by the respondent No.2
against the petitioners.
6. It is submitted that the respondent No.4 was registered with
ill-motive by some of the owners on 21.10.2022. The Respondent
No.4 is not representing the owners of entire community of Pristine
Estates. The respondent No.4 - association was formed without
intimation to all owners with ulterior motive. The members of
respondent No.4 are defaulters of payment of maintenance charges
and deposits to the owners and to avoid payments they formed into
an association and they are liable to pay an amount of
Rs.12,72,62,808/- (Twelve Crores and Seventy Two Lakhs and
Sixty Two Thousand Eight hundred and Eight Only) towards costs of
external electrification and external main water line for the
occupied 74 Villas. The respondent No.4 had been demanding its
members to pay membership fee even to join the Association,
which is against the conditions of the Registered Deeds/Agreements
entered between the owner and the buyer.
7. It is submitted that the respondent No.4 filed Complaint
No.187 of 2024 before the respondent No.2 making certain
allegations against the respondent No.3 and the petitioners. In the
complaint it is alleged that the petitioners, allegedly, advertised and
sold villas in a gated community called 'Pristine Estates' with
promises of state-of-the-art facilities, but failed to deliver on those
promises. The petitioners allegedly kept the water and electricity
supply under a commercial rate instead of residential and
threatened to cut off the essential services if maintenance fees
were not paid. The petitioners and others attempted to form
another association of villa owners and demanded backlog
maintenance charges, despite the existing association already
handling the community's upkeep. The project was not registered
with the TSRERA, despite the building permissions expired on
07.06.2014 (3 years from the date of original building permit) and
continued to advertise the project. Further, that the Club-House is
under a registered lease agreement vide document No.8193/2021
dated 13.08.2021 with certain terms and conditions, with a third-
party entity.
8. It is submitted that the petitioners filed a counter before
TSRERA questioning the jurisdiction of the respondent No.2 to
entertain the complaint filed by the respondent No.4. The RERA Act
and RERA Rules are applicable only to real estate projects whose
building permissions are approved on or after 01.01.2017 by the
Competent Authorities. In other words, the RERA Rules will be
inapplicable to projects whose building permissions were approved
prior to 01.01.2017 or up to 31.12.2016 and hence, the complaint
filed by the Respondent No.4 is not maintainable. It is submitted
that despite specific objection regarding jurisdiction of the
respondent No.2 raised by the petitioners regarding jurisdiction, the
respondent No.2 proceeded with hearing of the complaint and as
such, the petitioners were constrained to approach this Court.
9. The respondent No.4 filed counter affidavit, inter alia, stating
that the respondent No.1 has passed G.O.Ms.No.60 dated
04.03.2025 along with a Circular No.607/2025/TGRERA dated
04.03.2025 amending the RERA Rules, to be in line with the RERA.
As per amended Rule 1(2) and 2(j) of the RERA Rules, the Real
Estate Projects for which the completion certificate has not been
issued as on the date of coming into force of the RERA Act and the
project where development is going on and for which Occupancy
Certificate or Completion Certificate from the Competent Authority
has not been issued, are defined as ongoing project. The project of
the petitioners 'Pristine Estates' has not been issued
occupancy/completion certificate and therefore, the grievance of
the petitioners is no longer valid. In view of the amendment, this
writ petition has become has infructuous.
10. Mr. P. Sri Raghu Ram, learned senior counsel appearing for
Mr. K. Kiran Kumar, learned counsel for the petitioners, fairly
submitted that in view of amendment to Rule 1(2) and Rul2(1)(j) of
the RERA Rules, there is no ambiguity insofar as ongoing project is
concerned, which means, a project for which occupancy certificate
or completion certificate is not issued by the competent authority.
Learned senior counsel further submitted that, admittedly, Pristine
Estates was not issued occupancy certificate. Thus, under the new
Rules, prima facie, the complaint filed against the developers of
Pristine Estates is maintainable.
11. However, learned senior counsel submitted that the
complaint of the respondent No.4 was registered on 13.09.2024
and the amendment to the provisions of Rule 21(j) was on
04.03.2025. The complaint is not maintainable on the date when it
was filed. Thus, the RERA does not have jurisdiction to entertain the
complaint. What is relevant to be seen is the right vested with the
parties on the date of the complaint i.e. 13.09.2024 and as the
complaint could not have been entertained against the Pristine
Estates, such vested right cannot be divested. Alternatively, learned
senior counsel submitted that assuming as per the amended Rules,
the complaint is maintainable, it may be left open to the respondent
No.4 to file a fresh complaint, which will be defended by the
petitioners in accordance with law.
12. Mr. Srinivas Iyengar, learned senior counsel appearing for
Mr. Hirendranath, learned counsel for the respondent No.4,
submitted that the issue in this lis is no more res integra. The same
issue has arisen for consideration before the Supreme Court in
NEWTECH PROMOTERS AND DEVELOPERS PRIVATE LIMITED
v. STATE OF UTTAR PRADESH 1 wherein it was held that RERA Act
is retroactive and that projects, already completed for which
completion certificates are no granted, come within the fold of the
RERA Act.
13. Learned senior counsel for the petitioners, in reply, submitted
that the judgment in NEWTECH PROMOTERS AND DEVELOPERS
PRIVATE LIMITED's case (1 supra) is not applicable to the
(2021) 8 SCC 1
present case because it arises under the Uttar Pradesh Real Estate
(Regulation and Development) Rules, 2016, wherein the definition
of ongoing project is different as compared to RERA Rules.
14. The Supreme Court in NEWTECH PROMOTERS AND
DEVELOPERS PRIVATE LIMITED's case (1 supra) framed
"Question No.1: Whether the 2016 Act is retrospective or
retroactive in its operation and what will be its legal consequence if
tested on the anvil of the constitution of India" and held as under:
"40. The clear and unambiguous language of the statute is retroactive in operation and by applying purposive interpretation rule of statutory construction, only one result is possible, i.e., the legislature consciously enacted a retroactive statute to ensure sale of plot, apartment or building, real estate project is done in an efficient and transparent manner so that the interest of consumers in the real estate sector is protected by all means and Sections 13, 18(1) and 19(4) are all beneficial provisions for safeguarding the pecuniary interest of the consumers/allottees.
...
47. The distinction between retrospective and retroactive has been explained by this Court in Jay Mahakal Rolling Mills v. Union of India [(2007) 12 SCC 198] "8. "Retrospective" means looking backward, contemplating what is past, having reference to a statute or things existing before the statute in question. Retrospective law means a law which looks backward or contemplates the past; one, which is made to affect or facts occurring, or right occurring,
before it comes into force. Retroactive statue means a statues, which creates a new obligation on transactions or considerations or destroys or impairs vested rights."
48. Further, this Court in Shanti Conductors (P) Ltd. v. Assam SEB [(2019) 19 SCC 529], held as under:
"67. Retroactivity in the context of the statute consists of application of new rule to an act or transaction which has been completed before, the rule was promulgated.
...
...
...
53. From the scheme of the Act 2016, its application is retroactive in character and it can safely be observed that the projects already completed or to which the completion certificate has been granted are not under its fold and therefore, vested or accrued rights, if any, in no manner are affected. At the same time, it will apply after getting the ongoing projects and future projects registered under Section 3 to prospectively follow the mandate of the Act 2016."
15. The definition of 'ongoing project' under Rule 2(1)(h) of
the Uttar Pradesh Real Estate (Regulation and Development)
Rules, 2016, is exhaustive as compared to the definition of 'ongoing
project' under Rule 2(1)(j) of RERA Rules. However, from a reading
of both the provisions, there is no ambiguity that 'ongoing project'
means a project where development is going on and for which
completion certificate has not been issued. Thus, in the opinion of
this Court, the judgment in NEWTECH PROMOTERS AND
DEVELOPERS PRIVATE LIMITED's case (1 supra) is squarely
applicable to the facts of the present case.
16. Rules 1(2) and 2(1)(j) of the RERA Rules prior to and after
amendment are as under:
Sl. Rule Prior to Amendment After Amendment
No.
1. Rule 1(2) These Rules are applicable to These Rules are applicable to
all Real Estate Projects whose all Real Estate Projects for
building permissions approved which the completion
on or after 01.012017 by the certificate has not been
Competent Authorities viz., issued as on the date of
UDAs/DTCP/Municipal coming into force as
Corporations/Municipalities/ stipulated in sub-section (1)
Nagar Panchayats/TSIIC. of section 3 of the Real Estate
(Regulation & Development)
Act, 2016 by the Competent
Authorities viz., UDAs/DTCP/
Municipal Corporations/
Municipalities/Nagar
Panchayats /TSIIC.
2. Rule "Ongoing Project" means, a "Ongoing Project" means a
2(1)(j) Project where development is Project where development is
going on and for which going on and for which
Occupancy Certificate or Occupancy Certificate or
Completion Certificate has not Completion Certificate from
been issued but excludes such the Competent Authority has
Projects for which building not been issued as on the
permissions were approved date of coming into force as
prior to 01.01.2017 by per sub-section (1) of section
the Competent Authorities 3 of the Real Estate
viz., UDAs / DTCP / Municipal (Regulation & Development)
Corporations / Municipalities/ Act, 2016.
Nagar Panchayats / TSIIC as
the case may be.
17. On a reading of the above amended Rules, it is clear that
ongoing project means a project for which occupancy certificate or
completion certificate has not been issued. It is not in dispute that
Pristine Estates has not been issued occupancy certificate.
Thus, with effect from 04.03.2025, as per amendment to the above
provisions, Pristine Estates comes within the fold of the RERA Act
and RERA Rules.
18. Assuming that the complaint lodged by the respondent No.4
on 13.09.2024 is not maintainable, I do not have any hesitation to
hold that, by operation of law, the complaint is now maintainable
with effect from 04.03.2025 as per the amendments to Rule 1(2)
and Rule 2(1)(j) of the RERA Rules.
19. The contention of the learned senior counsel for the
petitioners that the maintainability of the complaint has to be
decided with reference to its date of filing even after amendment of
the Rules, cannot be accepted. Such contention is hyper-technical
and would not sub-serve the real cause of justice. Even if the
complaint were to be returned on its date of filing or rejected due to
objection of jurisdiction raised by the petitioners, before rules were
amended, nothing would prevent the respondent No.4 from lodging
a fresh complaint. Therefore, it would not be in the interest of
justice to return the complaint and only to be filed under the
amended rules.
20. For the above reasons, this Court holds that there are no
merits in the writ petition. Accordingly, the writ petition is
dismissed. However, the petitioners are at liberty to raise all issues
including jurisdiction of the respondent No.2 in entertaining the
complaint of the respondent No.4, which shall be considered by the
respondent No.2, by giving opportunity of hearing to the
petitioners, the respondent No.4 and others concerned parties.
The miscellaneous petitions pending, if any, shall stand
closed. There shall be no order as to costs.
____________________ B. VIJAYSEN REDDY, J June 23, 2025 Note: LR Copy to be marked (B/o) DSK
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!