Tuesday, 12, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

M/S Spectrum Power Generation Limited vs M/S United India Insurance Company ...
2025 Latest Caselaw 706 Tel

Citation : 2025 Latest Caselaw 706 Tel
Judgement Date : 2 January, 2025

Telangana High Court

M/S Spectrum Power Generation Limited vs M/S United India Insurance Company ... on 2 January, 2025

          THE HON'BLE THE CHIEF JUSTICE ALOK ARADHE
                                        AND
            THE HON'BLE SRI JUSTICE J.SREENIVAS RAO

             COMMERICAL COURT APPEAL No.26 OF 2022

JUDGMENT:

(Per the Hon'ble Sri Justice J. Sreenivas Rao)

This appeal has been filed aggrieved by the judgment and decree

dated 05.10.2021 in C.O.S.No.134 of 2017 (old O.S.No.451 of 2008)

passed by the Special Court for trial and disposal of Commercial

Disputes at Hyderabad (hereinafter referred to as 'the Special Court')

invoking the provisions of Section 13 of the Commercial Courts Act,

2015 (hereinafter referred to as 'the Act').

2. The appellant is the plaintiff and respondents are the defendants

in C.O.S.No.134 of 2017. For the sake of convenience, the parties

herein are referred to as they arrayed in the suit before the Special

Court.

3. Heard Ms.Meenakshi Aurora, learned Senior Counsel appearing

for Mr.M.Naga Deepak, learned counsel for the appellant, and

Mr.A.Venkatesh, learned Senior Counsel appearing for Mr.Srinivas

Rao Pachwa, learned counsel for respondent Nos.1 and 2.

3. Brief facts of case:

3.1. The plaintiff - Spectrum Power Generation Limited has filed suit

in O.S.No.451 of 2008 before the III Additional Chief Judge, City Civil

Court, Hyderabad, seeking the following reliefs:

"(a) Declaring that the insurance claim comprising of material damage and Business Interruption losses preferred by the plaintiff relating to the Steam Turbine Generator incident which occurred on 05.11.2002 at the facility is admissible under the IAR Policy No. 050100/11/02/059/2002 dated 31.07.2002 pertaining to the period from 01.07.2002 to 30.06.2003; and consequently, direct the defendant Nos.1 to 3, to jointly and severally pay the plaintiff the sum of Rs.166,88,71,981/- (Rupees One hundred Sixty Six Crores Eighty Eight Lakhs Seventy One Thousand Nine hundred and Eighty One only) being Material Damage loss and Business Interruption loss suffered by the plaintiff.

(b) Direct the defendant Nos. 1 to 3 jointly and severally to pay the plaintiff a sum of Rs.1,00,000/- as consequential damages.

(c) Direct the defendant Nos. 1 to 3 jointly and severally to pay pendente lite interest @ 12% p.a. or such higher rate as this Court may decide from the date of filing of the suit till the date of decree on the amount of Rs 166,88,71,981/-.

(d) Direct the defendants 1 to 3 to pay future interest @ 12% p.a. or such higher rate as this Court may decide from the date of decree till the realization of the amount.

(e) To award costs of the suit."

3.2. The said suit was transferred to the Special Court and it was

renumbered as C.O.S.No.134 of 2017. In the above said suit, it is

averred that the plaintiff Company is registered under the provisions of

the Companies Act, 1956 on 26.10.1992 and the main object is that to

generate, harness, develop, accumulate, distribute and supply

electricity by setting up thermal power plants by using liquid, gaseous

or solid fuels for the purpose of light, heat etc., The plaintiff had

entered into an Operation and Maintenance Agreement (for short, 'O &

M Agreement') on 14.03.1995 and thereafter, it had entered Amended

and Restated Power Purchase Agreement (for short, 'PPA') dated

23.01.1997 with the erstwhile Andhra Pradesh State Electricity Board

(A.P.S.E.B.) and subsequently the same was changed into Andhra

Pradesh State Transmission Corporation (APTRANSCO), for the

purpose of generating electricity from the operations of all Gas

Turbines and Steam Turbines. The plaintiff was operating 208 MW

combined gas based power station at Kakinada of Andhra Pradesh

State and the facility comprises of three Gas Turbines and one Steam

Turbine Generator (for short 'STG') and the commercial operations

were commenced on 19.04.1988. The plaintiff further averred that

defendant No.1 is the lead insurer, defendant Nos.2 and 3 are the co-

insurers, defendant No.4 is the Contractor for operation and

maintenance of the facility and defendant No.5 is the original

manufacturer of the equipment.

3.3. The plaintiff further averred that it has originally entered into an

O & M Agreement with defendant No.4 for operation of the facility on

14.03.1995 and purchased an Industrial All Risk Policy (for short 'IAR

Policy') in the joint names of the plaintiff, defendant Nos.4 and 5 for

coverage of Rs.854.24 crores. The said IAR Policy was issued on

31.03.1998 and the same was renewed from time to time till

30.06.2005. The relevant IAR Policy for the period between

01.07.2002 to 30.06.2003 is IARP No.050100/11/02/059/2002 dated

31.07.2002. In the O & M Agreement between the plaintiff and

defendant No.4, there was a condition that the plaintiff shall obtain

various insurance policies in the names of the plaintiff, defendant

Nos.4 and 5 for insurance cover for property as well as for

indemnifying against the loss of business interruption. The condition

13.2 in the O & M Agreement stipulates that the "insurance shall cover

real and personal property at the facility and the site on a 100%

replacement costs basis against all risks of direct physical loss or

damage to facility and cover shall include business interruption and

extra expense cover for loss of revenues and any additional and

continuous expenses".

3.4. The plaintiff further averred that Section I of the IAR Policy

provides for an insurance cover for the material damage to the insured

property of the facility due to accidental, physical loss, destruction or

damage for any reason other than the reasons specifically excluded

and Section II of the IAR Policy made a provision for business

interruption risks/consequential losses arising out of the shutdown of

machines/units to facilitate repairs/replacements due to the damages

caused to the facility and the causes for the same are with reference to

the causes mentioned in Section I of the IAR Policy.

3.5. The Plaintiff also averred that defendant No.4 had been

observing an abnormal increase in the Thrust Pad Temperature of the

STG for the past few weeks before 05.11.2002 and the original

equipment manufacturer i.e., defendant No.5 had recommended

defendant No.4 to conduct a detailed wear particle analysis by drawing

an oil sample from the STG and to collect the oil sample from the

nearest point of the drain point. It is also averred that a detailed

inspection was conducted by defendant No.5 and found that Rotor

Shaft of the STG and the damaged part was sent to M/s. ABB Aisthom

Works, Vadodara for repair and STG was shut down on 05.11.2002.

According to the plaintiff, repair works of the damaged Rotor Shaft

completed by M/s.ABB Aistom Works and the Rotor Shaft reached to

the plaintiff site on 23.10.2003 and finally the STG was put to operate

on full load with the grid on 17.12.2003 after gap of 13 ½ months.

3.6. The plaintiff further averred that defendant No.4 through letter

dated 06.11.2002 forwarded the report on the above incident to the

plaintiff notifying the same to the insurance company and the plaintiff

has forwarded the same to defendant No.1 with letter dated

07.11.2002. On receipt of the said communication, defendant No.1

along with Surveyor M/s. NVP Sharma Associates Private Limited

visited the site on 15.11.2002 and higher officials of defendant No.1

visited the site along with another Surveyor M/s. Mentha & Padamsay

Private Limited on 28.11.2002 and 29.11.2002. The Surveyors visited

the site on 18.12.2002 for collection of information and data relating to

the loss estimate. Accordingly, the plaintiff furnished entire

information to the Surveyors and sought for release of on account

payment pending final settlement for claims for losses caused to the

STG. On 21.01.2003 a meeting was held between the Regional

Manager of defendant No.1 and officials of the plaintiff at Hyderabad

for settlement of issue relating to on account payment and the

Regional Manager of defendant No.1 has assured the plaintiff that on

account of loss to the STG would be released shortly.

3.7. Thereafter, the plaintiff submitted several letters on 21.03.2003,

26.03.2003 and 02.05.2003 for furnishing the copy of the interim

survey report, however, defendant No.1 has not furnished the same,

on the other hand rejected the claim of the plaintiff through letters

dated 13.05.2005 and 09.11.2005. Questioning the above said

rejection letters, the plaintiff filed W.P.No.2195 of 2006 before the High

Court of Andhra Pradesh at Hyderabad. In the said writ petition, the

plaintiff sought interim direction in W.P.M.P.No.2195 of 2006 directing

defendant No.1 to furnish the interim survey report and pursuant to

the interim direction dated 07.02.2006, defendant No.1 furnished the

interim survey report dated 05.02.2003 to the plaintiff. Despite of

recommendation made in the survey report, defendant No.1 has not

made payments to the plaintiff, as such, the plaintiff addressed letters

dated 12.11.2003, 11.12.2003 and 22.01.2004. After 2½ years,

defendant No.1 rejected the insurance claim made by the plaintiff for

the damage to the STG through letter dated 13.05.2005. Thereafter,

the plaintiff addressed a letter dated 31.05.2005 to defendant No.3

seeking for views and opinion on rejection of insurance claim.

Accordingly, defendant No.3 in its letter dated 17.06.2005 opined that

IAR Policy covers all risks except those covered in the exclusions and

the unintentional errors of defendant No.4 in the course of business

are within the coverage of policy.

3.8. When defendant No.1 failed to consider the claims, the plaintiff

filed suit claiming an amount of Rs.166,88,71,981/- against defendant

Nos.1 to 3 towards its insurance claim for material damage and loss

suffered due to the business interruptions and Rs.1,00,000/- towards

consequential damages and pendente lite and post decretal interest on

the above said amount @ 12% per annum and costs.

4. Defendant No.1 filed written statement denying the averments

made by the plaintiff inter alia contending that the original insurance

policy was issued in the year 1998-99 to the plaintiff and renewed

periodically, as the sole insured, and later in terms of the O & M

Agreement dated 14.03.1995, the names of defendant Nos.4 and 5

were included as co-insured or joint injured parties. Defendant Nos.4

and 5 have no insurable interest in the subject of insurance and

defendant No.1 had issued policy after considering all the terms and

conditions of O & M Agreement and strictly subject to their rights

synchronizing with the rights of the plaintiff. It is further averred that

defendant Nos.4 and 5 are exclusively liable as per the terms and

conditions of O & M Agreement and the same was referred in the letter

dated 28.08.1998 as well as reply letter dated 09.09.1998 regarding

inclusion of names of defendant Nos.4 and 5.

4.1. It is also averred that the IAR Policy was issued in the joint

names of the plaintiff, defendant Nos.4 and 5 only basing on the

representation made by the plaintiff regarding O & M Agreement and

the same proves through correspondence. It is further averred that

admissibility of the liability under Section I of the policy, the plaintiff

will be entitled for claiming the insurance under Section II of the

policy. The right to sue for the plaintiff survives till expiry of 12

months from the date of disclaiming the liability as per the condition 5

(ii) of IAR Policy and as the disclaimer was made on 13.05.2005 by

defendant No.1, the plaintiff shall exercise the right to file the suit

within 12.05.2006, failing which it shall be considered that the

plaintiff has abandoned the claim. It is averred that as per clause 5(ii)

of the IAR Policy, even right of defendant No.4 to make any claim stood

expired after lapse of 12 months of the incident and the suit is bad for

non-joinder of financier/banker as the benefit if any payable is only to

the banker and not to the plaintiff, as per the terms of the IAR Policy.

Defendant No.1 further averred that the IAR Policy does not cover the

liability of the Contractor (defendant No.4) under O & M Agreement.

The liability arising out of wilful negligence or wilful act by the plaintiff

or anyone acting on behalf of the plaintiff is excluded from the cover

and as defendant No.4 is acting on behalf of the plaintiff, the liability

out of wilful act or wilful negligence of defendant No.4 stands

excluded.

4.2. Defendant No.1 also averred that the damage occurred due to

the wilful negligence of the employees of defendant No.4 and as such,

damage falls within the exclusion clause of the policy and therefore,

defendant No.1 is not liable to indemnify the loss. As per the terms

and conditions of O & M Agreement, any negligence on the part of

defendant No.4 will render the policy exception effective and operable

and thereby disentitle any of the insured, the right to make the claim

under the policy. Accordingly, defendant No.1 rightly rejected the

claim of the plaintiff.

4.3. Defendant No.1 further averred that in order to check the

functioning of the facility, defendant No.5 has suggested, drawing of

sample for wear particle analysis from the near point to the bearing,

contrary to the suggestion, instead of drawing sample from nearest

point of bearing, staff of the plaintiff has drawn sample from flushing

box by opening it, which resulted in splashing out of oil and the cover

of flushing box could be fixed after some time and the damage

occurred to the rotor shaft of the STG and the same is purely

negligence on the part of the staff of the plaintiff only. Defendant No.1

addressed a letter to Surveyors asking them to clarify the issues

relating to method of collection of sample and surveyors gave clean

chit to the engineers who had drawn the samples.

4.4. Defendant No.1 also averred that the observation of the

Surveyors giving clean chit to the employees of defendant No.4 is not

correct. The Surveyors in their previous reports have stated that the

wear particle analysis was carried out with the help of electronic

microscope by examining the samples drawn from purifier strainer

drain, during pre-accident and post-accident situation. The employees

of defendant No.4 are supposed to have well acquainted with all

features of the STG and the features of flushing box and velocity of

return oil in it. In the letter dated 07.11.2002, the plaintiff has not

stated anything about meeting in the morning or deliberations and

they have not given any reasons for not mentioning about the facts in

the said reporting letter and also averred that survey report dated

05.02.2003, the report given by Mr.Raju was extracted which makes it

clear that he has drawn oil sample by wilful negligent act.

4.5. Defendant No.1 also averred that as per clause 13.2.2 of the O &

M Agreement, defendant No.4 is responsible for direct physical loss or

damage to the facility and the said liability of defendant No.4 is not

subject matter of the IAR Policy. As per clause 3.2.10 of the O & M

Agreement, defendant No.4 shall adhere to all the safety precautions in

operating the facility and qualified safety representatives are to be

employed for the purpose of running the facility by taking all the

precautions.

4.6. Defendant No.1 further averred that as per 22.1 of the O & M

Agreement, defendant No.4 is not entitled to any damages which arise

out of any other contract or written agreement between the plaintiff

and third parties including erection contract and defendant No.4 being

the erection contractor, it is also debarred from making any claim.

The plaintiff has suppressed the material facts regarding the incident

in the plaint and there is no obligation to honour the insurance claim

made by the plaintiff in the absence of proper survey report, in view of

Section 64 UM (2) of the Insurance Act. The role of surveyor is only to

assess the loss and not to decide admissibility of liability. The interim

survey report is not conclusive one. Basing on the interim survey

report, the plaintiff is not entitled to make any claim against defendant

No.1, especially, the plant between 05.05.2003 to 17.12.2003 was not

in operation only on account of the failure of the repairer in properly

affecting the repair and defendant No.1 cannot be made accountable

for the same.

4.7. Defendant No.1 further averred that the property at the site was

insured, the liability of defendant No.4 under O & M Agreement is not

the subject matter of the insurance at all and nowhere in the policy, it

is stated that there is negligence on the part of the operator i.e.

defendant No.4, it is termed as a risk covered under the policy. The

loss is occurred due to non-adhering of the safety programme by

defendant No.4 as per clause 3 and 3.2.10 of the O & M Agreement.

He further stated the suit is filed beyond limitation and the same is

liable to be dismissed and also for non-joinder of banker/financier as a

party to the suit.

5. Defendant No.3 filed written statement denying the claim of the

plaintiff and also letter said to have been issued by it to the plaintiff

giving opinion on admissibility of the claim of the plaintiff. According

to defendant No.3, being a co-insurer, it has to be abide by the

decision of the lead insurer i.e. defendant No.1 and it is the

responsibility of defendant No.1 to admit or deny the claim of the

plaintiff. It is further stated that they adopted all the contentions of

the written statement of defendant No.1.

6. Defendant No.4 has supported the claim of the plaintiff under

the IAR Policy and stated that the incident is the subject matter of the

claim by the plaintiff and further stated that there is no negligence on

the part of the plaintiff or on the part of its employees in operation of

the facility and the claim of the plaintiff does not fall under any of the

exclusion clauses and the IAR Policy is an independent and separate

contract and it cannot be read in conjunction with the terms of O & M

Agreement. He further stated that the plaintiff has rightly claimed the

amount in the suit and the same is to be allowed.

7. Defendant No.5 filed written statement stating that the trial

Court has no jurisdiction to entertain the suit as the plaintiff do not

have office or carry on business within the jurisdiction of the trial

Court and the suit is liable to be dismissed on the ground of

jurisdiction alone.

8. Basing upon the pleadings of the respective parties, the trial

Court framed the following issues:

1. Whether the Plaintiff is entitled for recovery of the amount as prayed for?

2. Whether the Plaintiff is entitled for consequential damages as prayed for?

3. Whether the Plaintiff is entitled to pendente lite and future Interest as claimed?

4. Whether the defendants 1 to 3 are jointly and severally liable to pay the claims made by the plaintiff in the suit?

5. Whether the rejection of the insurance claim of the Plaintiff under all insurance risk policy by defendant No.1 is misconceived, improper, illegal, untenable and against the provisions of all Insurance risk policy?

6. Whether the defendant No.1 has correctly relied on the O & M contract for rejection of the claim of the plaintiff under the all insurance risk policy?

7. Whether the plaintiff sought an endorsement for Including the defendants 4 and 5 as insured in the Industrial all risk policy, dt.31-7-2002 on account of the O & M Contract between the plaintiff and the defendants 4 and 5?

8. Whether the plaintiff's right to sue was abandoned on account of breach of policy condition No.5(ii) as contended by the defendants 1 and 2?

9. Whether the suit filed by the plaintiff is maintainable in respect of reported loss resulting operation of the machine by the O & M contract?

10. Whether the suit filed by the plaintiff is not maintainable for non joinder of necessary party on account of the agreed bank clause as found in industrial all risk policy?

11. Whether the plaintiff is entitled to claim any amount on behalf of defendant No.4, O & M Contract in view of the clause 17.6 of the O & M contract?

12. Whether the loss caused by the plaintiff due to acts of the O & M Contractor is covered under the industrial all risk policy?

13. Whether the negligent and wilful acts and mal-operation of the O&M Contractor exclude the peril under the industrial all risk policy?

14. Whether the findings of the survey report is binding on the defendant No.1 U/s, 64-UM of the Insurance Act?

15. To what relief?

9. On behalf of the plaintiff, PWs.1 and 2 were examined and

Exs.A.1 to A.60 documents were marked and on behalf of the

defendants, DWs.1 and 2 were examined and Exs.B.1 to B.90

documents were marked.

10. The trial Court taking into consideration the oral and

documentary evidence on record and after hearing the parties decreed

the suit in part and directed defendant No.1 (lead insurer), defendant

Nos.2 and 3 (co-insurers) to pay, in proportion to their respective

liability under the IAR Policy i.e., 70%, 10% and 20% respectively, an

amount of Rs.17,79,49,946/- with interest @ 12% per annum from

12.05.2003 till the realization of the suit debt and directed the

defendants to pay a sum of Rs.2,38,15,070/- towards costs of the suit

to the plaintiff and rest of the claim of the plaintiff is dismissed by its

judgment and decree dated 05.10.2021.

11. Aggrieved by above said judgment and decree, the plaintiff filed

the present appeal.

12. Submissions of the learned counsel for the appellant/plaintiff:

12.1. Ms.Meenakshi Aurora, learned Senior Counsel representing Mr.

M.Naga Deepak, learned counsel for the appellant/plaintiff submitted

that the trial Court without properly appreciating the oral and

documentary evidence on record dismissed the suit and not granted

the relief in respect of the business interruption loss for the period of

407 days. She further submitted that in the interim survey

report/Ex.A.12 = Ex.B.43, it is specifically mentioned that the plaintiff

sustained Rs.24.66 crores towards business interruption loss for 105

days. In such circumstances, the trial Court ought to have decreed

the suit in toto.

12.2. Learned counsel also submitted that as per Section II of IAR

Policy, when the business carried by the insurer was interrupted

consequent to the occurrence of damage to the STG as a consequence

to the material damage under Section I of Ex.A.5 policy. The insurer is

entitled to claim amount in respect of business interruption loss. The

Court below without properly considering the conditions mentioned

under Ex.A.5 erroneously rejected the claim of the plaintiff in respect

of business interruption loss.

12.3. Learned counsel further submitted that the trial Court failed to

appreciate that the business interruption loss is a natural/obvious

consequence of material damage. Therefore, denying the claim of

business interruption loss after duly adjudicating the material damage

claim in favour of the plaintiff is contrary to the evidence on record.

She also submitted that the trial Court ought to have considered that

the steam turbine damage and its consequent shut down (material

damage), the plaintiff incurred revenue losses, as in a combined cycle

plant (comprising of Gas Turbines and Steam Turbine) electricity is

produced by the gas turbine exhaust contains lots of amount and

waste heat, which is recovered by the heat recovery steam generator.

She further submitted that the trial Court has not appreciated

Ex.A.13, wherein it is specifically mentioned that the loss of about

50% in the electricity production capacity of the plaintiff's Combined

Cycle Power Plant due to the Steam Turbine Damage and its

consequential shut down. She also submitted that basing upon the

very same material and oral documents adduced by the parties, the

trial Court decreed the suit in respect of the material damages,

however, dismissed the claim insofar as the business interruption loss

in the absence of any reasons, much less valid reasons.

12.4. Learned counsel vehemently contended that defendant Nos.1

and 2 have not placed any evidence denying the claim of the plaintiff

in respect of the business interruption loss even though the plaintiff

proved its initial burden by adducing oral and documentary evidence.

In such circumstances, the trial Court ought to have decreed the suit

in toto. She submitted that defendant Nos.1 and 2 have not filed

appeal or cross-appeal in respect of granting decree in favour of the

plaintiff for an amount of Rs.17,79,49,946/- in respect of claim of

material damage/loss along with interest and the same has become

final. She further submitted that defendant No.1 has not furnished

the survey report in spite of repeated reminders. At that stage, the

plaintiff filed W.P.No.2195 of 2006 and only pursuant to the interim

order dated 07.02.2006, defendant No.1 furnished the interim survey

report and the defendants have not taken any steps to conduct final

survey to determine the business interruption loss.

12.5. In support of the aforesaid submissions, reliance has been

placed on the decisions of the Supreme Court in M/s.Bihari Ganga

Hydro Power Ltd. v. New India Assurance Co.Ltd., 1, Uttar Bharat Hydro

Power Private Limited v. Oriental Insurance Co. Ltd. and another 2 ,

United Phosphorous Limited vs. United India Insurance Company Ltd., 3,

Wilson Home Appliances v. New India Assurance Co. Ltd. and another 4,

Sikka Papers Limited v. National Insurance Company Limited and

others 5 , Sri Venkateswara Syndicate v. Oriental Insurance Company

2020 SCC Online 1093

2022 SCC OnLine NCDRC 758

2019 SCC OnLine Bom 391

2020 SCC OnLine NCDRC 493

(2009) 7 SCC 777

Limited and another 6 , and National Insurance Company Limited v.

Hareshwar Enterprises Private Limited and others 7.

13. Submissions of learned counsel for the defendants/respondents:

13.1. Per contra, Sri A.Venkatesh, learned Senior Counsel, submitted

that the plaintiff has not made any pleading in the plaint in respect of

business interruption loss. He further submitted that the burden lies

upon the party who approaches the Court to prove the claim by

adducing evidence. The plaintiff has not discharged the burden and

not proved the factum of sustaining business interruption loss by

adducing any evidence. In the absence of pleading/evidence, the

plaintiff is not entitled to claim any relief, much less the relief of

business interruption loss. The trial Court after considering the

contentions of the parties and after going through the oral and

documentary evidence on record rightly passed the judgment and

decree by giving cogent findings.

13.2. Learned Senior Counsel further submitted that the trial Court

has given a specific finding that mere claiming material damage loss

does not entitle the plaintiff to claim the loss due to business

interruption. The plaintiff has failed to prove the actual loss suffered

by it due to interruption in the business due to the material damage.

(2009) 8 SCC 507

(2021) 17 SCC 682

He further submitted that the interim survey report/Ex.A.12 = Ex.B.43

do not contain any details regarding the loss on account of business

interruption and the said document is not conclusive proof and basing

on the said report, the plaintiff is not entitled to claim any amount

under the business interruption loss. The trial Court rightly held that

the said document Ex.A.12 = Ex.B.43 is not a conclusive document.

13.3. He further submitted that the trial Court has given a specific

finding that the plaintiff has not filed any income tax statement and

other such statement to establish that it sustained business

interruption loss for a period of 407 days and also held that the

plaintiff has not filed any iota of evidence including income tax returns

for the previous years to prove the factum of sustaining business

interruption loss. He further submitted that the trial Court rightly

rejected the claim of the plaintiff in respect of the business

interruption loss and decreed the suit in part and there are no

grounds in the appeal filed by the plaintiff.

14. In view of the rival contentions raised by the respective parties

and material on record, the following points that emerge for

consideration in this appeal are:

(i) Whether the judgment and decree passed by the trial Court in part for an amount of Rs.17,79,49,946/-, out of an amount of Rs.166,88,71,981/- and dismissing the rest of the claims is sustainable under law?

(ii) Whether the judgment and decree passed by the trial Court is in accordance with law?

(iii) Whether the plaintiff is entitled any relief in this appeal? If so, what relief?

Analysis :

Point Nos.(i), (ii) and (iii):

15. Admittedly, the plaintiff filed suit on 31.05.2008 against the

defendants declaring that the insurance claim comprising of material

damage and business interruption loss relating to the STG incident

which occurred on 05.11.2002 at the facility is admissible under the

IAR Policy dated 31.07.2002 pertaining to the period from 01.07.2002

to 30.06.2003 and consequently, direct defendant Nos.1 to 3 to pay a

sum of Rs.166,88,71,981/- being material damage loss and Business

Interruption loss and claiming an amount of Rs.1,00,000/- as

consequential damages along with interest @ 12% p.a. and other

reliefs. The trial Court after taking into consideration the oral and

documentary evidence adduced by the respective parties decreed the

suit in part directing defendant Nos.1 to 3 to pay an amount of

Rs.17,79,49,946/- in proportionate to their respective liability under

Ex.A.5 - IAR Policy dated 31.07.2022 with interest @ 12% p.a. from

12.05.2003 till the realization along with costs of Rs.2,38,15,070/-

and the rest of the claim of the plaintiff especially in respect of the

business interruption loss was dismissed holding that the plaintiff has

not produced any evidence that the plaintiff sustained the business

interruption loss during the said period.

16. The contention of the learned counsel for the plaintiff is that

once the trial Court has come to the conclusion that the plaintiff is

entitled to claim in respect of material damage under Ex.A.5, the trial

Court ought to have decreed the suit in respect of the business

interruption loss under the very same Ex.A.5. Mere decreeing the suit

in respect of material damage, the plaintiff is not entitled to seek the

claim under business interruption loss in the absence of establishing

the claim by producing necessary evidence, especially the burden lies

upon the plaintiff to prove the claim that the plaintiff sustained

business interruption loss for the period from 01.07.2002 to

30.06.2003.

17. It is pertinent to mention that the plaintiff relying upon the

interim survey report under Ex.A.12 dated 05.02.2003 has made claim

under the business interruption loss, especially when the defendants

are disputing the same and the said interim survey report is not final

and not a conclusive report. The plaintiff has not taken any steps

prior to institution of suit or subsequent to filing of suit for conducting

survey and submission of final survey report, on the other hand the

plaintiff filed application, vide I.A.No.1 of 2024, in the present appeal

seeking appointment of surveyor to compute the business interruption

loss after lapse of nearly more than 22 years.

18. Insofar as the contention of the learned counsel for the appellant

that pursuant to the interim surveyor report under Ex.A.12, the trial

Court ought to have directed the defendants to pay an amount of

Rs.24.66 crores is concerned, the document under Ex.A.12 itself was

disputed by defendants Nos.1 and 2 on the ground that the said

document is not conclusive proof and it is only interim survey. It is

pertinent to mention that the trial Court has given specific finding in

respect of Ex.A.12 holding that in the absence of any final survey

report, the same cannot be taken into consideration and the plaintiff is

not entitled to claim business interruption loss pursuant to the interim

survey report as the same is not conclusive one.

19. It is also pertinent to mention that the interim survey which was

conducted by the surveyor is only for limited purpose and subsequent

to that no final survey was conducted by defendant Nos.1 and 2 and

the plaintiff has not made any effort to conduct final survey or

produced any other evidence that the plaintiff sustained business

interruption loss for the period from 01.07.2002 to 30.06.2003. In

such circumstances, this Court is of the considered view that the trial

Court has rightly not considered Ex.A.12-interim survey report to

grant business interruption loss in favour of the plaintiff.

20. It is pertinent to mention that the plaintiff has addressed

Ex.A.35 and Ex.A.36 for payment of insurance for business

interruption loss. Defendant No.1 has rejected the claim of the

plaintiff under Exs.A.37 and A.38 and also not considered the

vouchers and other documents sent by the plaintiff in support of the

expenditure incurred by it on the ground of non-coverage of the IAR

Policy. According to combined statement Ex.A.27, the entire claim in

which Sl.No.8 relates to claim on account of business interruption for

Rs.101,97,57,237/-. However, the plaintiff has not placed any

evidence to support the claim on the loss of amount of business

interruption is based on Ex.A.35, Ex.A.36 and Ex.A.4 documents.

21. In Bihari Ganga Hydro Power Ltd. (supra), the National

Consumer Disputes Redress Commission citing the Supreme Court's

decisions in United India Insurance Co. Ltd. v. Pushpalaya

Printers, (2004 CTJ 421 (Supreme Court) (CP)) and a Constitution

Bench of Supreme Court in General Assurance Society Ltd. v.

Chandumull Jain ((1966) 3 SCR 500), held that commission under an

industrial all-risk insurance policy, a claim for business interruption

caused by machinery breakdown is valid even without a separate

material damage claim, provided the breakdown is indemnifiable. It is

a settled legal principle that in insurance contracts, uberrima fides

(utmost good faith) requires the assured to act in good faith and contra

proferentem rule, i.e., against the insurer. This ensures that any

ambiguity or term capable of multiple interpretations is resolved in

favor of the insured, aligning with the policy's purpose of providing

risk coverage and ensuring fairness.

22. In Uttar Bharat Hydro Power (P) Ltd. (supra), the National

Consumer Disputes Redressal Commission held that while the

complainant failed to notify the business interruption loss within the

required timeframe, the insurer's exclusion of 42 days in calculating

the business interruption loss was unjustified, as the plant had been

operational before the flood. The complainant was entitled to a

business interruption period of 77 days for loss calculation. The

principle of fair assessment in insurance contracts was emphasized,

ensuring that insured parties are compensated in alignment with the

policy's intent to indemnify reasonable losses.

23. The National Consumer Disputes Redressal Commission in

Wilson Home Appliances (supra), and the Supreme Court in Sri

Venkateswara Syndicate (supra), and Sikka Papers Ltd. (supra)

held that while insurance companies are required to appoint surveyors

for claims exceeding Rs 20,000 or more, the surveyor's report is not

binding or conclusive. It was emphasized that the survey report cannot

be disregarded without valid reasons and insurers cannot repeatedly

appoint surveyors to suit their preferences. It further held that Sikka

Papers Ltd., relying on the judgment of Supreme Court in New India

Assurance Co. Ltd. v. Pradeep Kumar ((2009) 7 SCC 787), confirmed

that the insurer may settle the claim for the loss suffered by insured at

any amount or pays to the insured an amount different from the

amount assessed by the approved surveyor. The report, therefore, is

not the final word and can be departed from by the insurer.

24. In National Insurance Co. Ltd., (supra), the Supreme Court

held that while a surveyor's report holds statutory recognition and is

essential in insurance claims, it is not sacrosanct and can be

contested by other evidence, such as an investigation report. Referring

to decision of Supreme Court in National Insurance Co. Ltd. v.

Harjeet Rice Mills (2005) 6 SCC 45, the Supreme Court further held

that insurers should be given an opportunity to present an

investigation report, especially when the nature of the incident is

disputed. The Court concluded that the surveyor's report, if credible

and addressing crucial aspects like stock loss, can serve as the

primary basis for the claim, even in the presence of a delayed

investigation report, provided it inspires confidence in the adjudicating

forum.

25. The judgments relied upon by the learned counsel for the

plaintiff are not applicable to the facts and circumstances of the case

on hand on the ground that the plaintiff failed to notify the business

interruption loss within the required timeframe and it has not

produced any documentary evidence about the business interruption

loss and the trial Court, after considering the oral and documentary

evidence and hearing the parties, passed the judgment and decree

with cogent findings in respect of each issue.

26. It is pertinent to mention that the trial Court specifically held

that the plaintiff has not adduced any evidence to prove that the

plaintiff could not supply the electricity under Power Purchase

Agreement (PPA) nor any demand made by APTRANSCO for supply and

failure to supply the electricity and further held that Ex.A.12-survey

report does not contain any details regarding the loss on account of

business interruption except only made claim under Ex.A.35 and

Ex.A.36. The trial Court further held that the above said documents

containing two papers with one table in each paper with calculations.

The first one is regarding the increase in fuel cost and in column No.13

of it, they have shown Rs.19.70 crores as the receivable amount lost

on account of STG shutdown. The another page containing another

table with calculation shows incentive amount lost for the period

between 19.04.2002 and 19.04.2023 and in column No.15 an amount

of Rs.14.89 crores was shown. The above said two sheets with

calculations are not supported by any other documents to show that

the figures mentioned in the two tables are correct and also stated that

there is no indication in the tables as to whether the amount

mentioned is in "Rupees" or "Lakhs" or "Crores". The trial Court had

inferred the amounts in the above columns as Rs.19.70 crores and

14.89 crores because of the claim made by the plaintiff and

mentioning of the very same figures in the plaint.

27. The trial Court further held that the plaintiff filed statement with

calculation of units billed and the net amount of bill from 10.11.1999

to 10.11.2003 and another table with calculation of incentives earned.

The tables of calculations annexed to Ex.A.36 are not signed and they

are not supported by any other documents and there is no information

as to who did the said compilation and the basis for the said

compilation in the calculation tables annexed to Ex.A.35 and Ex.A.36

and further held that the plaintiff is under an obligation to file proof

profit and loss statements, income tax statements and other such

statements which it has submitted to the government authorities or

taxing authorities to prove its revenue for previous years and it did not

do so. It is also held that the plaintiff did not file any audit report or at

least the documents evidencing the business transaction through

which revenue was gained and the unsigned calculation tables

annexed to Ex.A.35 and Ex.A.36 has not taken into consideration for

the purpose of determination of the loss on account of revenue and

further held that basing upon Ex.A.35 and Ex.A.36, the claim of the

plaintiff cannot be considered as proved that it sustained revenue loss.

28. It is also pertinent to mention that the trial Court by analyzing

oral and documentary evidence on record passed the impugned

judgment by giving cogent findings in respect of each issue and

decreed the suit in part. Hence, we are of the considered opinion that

the trial Court has rightly decreed the suit filed by the plaintiff for

Rs.17,79,49,946/- with interest and costs and dismissed the rest of

the claims. Accordingly, point Nos.(i), (ii) and (iii) are answered.

29. For the foregoing discussion, we are, therefore, not inclined to

disturb the findings of the trial Court. We, therefore, find no merit in

this appeal and the same is liable to be dismissed.

30. In the result, the appeal is dismissed. There shall be no order as

to costs.

Miscellaneous applications, if any pending, shall stand closed.





                                              _______________________
                                                ALOK ARADHE, CJ



                                           _____________________________
                                              J.SREENIVAS RAO, J
Date:       .01.2025.

mar/pgp
 

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter