Citation : 2024 Latest Caselaw 3829 Tel
Judgement Date : 18 September, 2024
HONOURABLE SRI JUSTICE K. LAKSHMAN
ARBITRATION APPLICATON No.22 OF 2024
ORDER:
Heard Mr. G Durga Charan, learned counsel for the applicant
and Mr. Ch. Pushyam Kiran, learned counsel appearing for the
respondent.
2. The applicant, M/s Tiara Infrastructure Private Limited, a
company duly incorporated under the Indian Companies Act, 1956,
engages in various construction-related activities, including the
provision of construction machinery on rent, and undertaking projects
related to factory, warehouse, and building construction.
3. The respondent issued a tender notification, vide No.
TOASX00035/ NIT_46574 dated 29.05.2019, for "Civil, Structural &
Architectural Works for 1 x 3MLD Sewage Treatment Plant at Budha
Talab for RSCL Raipur Chhattisgarh." Upon evaluating the bids, the
respondent was satisfied with the price bid submitted by the applicant
and consequently awarded the contract vide Letter of Award
(LOA)/Work Order bearing No.TOASX00035/PESD/ PUR/CIVIL/
RSCL-3MLD STP /TIL/WO-01 dated 17.07.2019.
4. In compliance with the terms and conditions outlined in the
LOA, the applicant entered into a formal Contract Agreement with the
respondent, vide Agreement No. PESD/HYD/TOARX00035/ RSCL_
Civil-3MLD STP/TIL/CA/01 dated 28.09.2019. The contract, valued
at Rs.4,21,58,701/- was subject to adjustment based on the actual
quantities executed during the project.
5. In accordance with the agreement, the applicant furnished a
bank guarantee amounting to ₹21,08,000/- videreference number
040BG01192130001 dated 01.08.2019, in favor of BHEL PE & SD,
Ramachandrapuram. Following this, the applicant proceeded to install
the requisite plant and machinery, including power installations
necessary for the project's completion, and commenced work on
01.08.2019.
6. However, on 08.12.2019, the respondent abruptly halted the
work without prior notice and directed that the suspension would
remain in effect until further instructions were provided.
Subsequently, on 01.05.2020, the respondent informed the applicant
that a revised plot plan was nearing finalization and assured that
instructions regarding the resumption of work would be
communicated promptly. Thereafter, on 23.07.2020, the respondent
instructed the applicant to extend the bank guarantee, indicating that
the contract was still in force and thus necessitating the extension.
7. Applicant, after initiating work as per the contractual
obligations, awaited response from the respondent, under the
assumption that the suspended work would resume in due course.
During this period of inactivity, the applicant's plant, machinery,
equipment, and manpower remained idle for an extended duration,
leading to significant financial loss. These losses were incurred both
due to the costs associated with the initial installation and subsequent
demobilization of the equipment, as well as the ongoing expense of
maintaining a workforce that could not be deployed effectively.
8. Several attempts were made by the Applicant to reconcile
accounts and settle outstanding disputes with respondent but for no
avail. Consequently, the applicant issued a legal notice dated
17.04.2023, which detailed the investment and expenditures incurred
for the project and demanded payment of ₹1,68,79,630/-. The notice
also proposed the appointment of an arbitrator to resolve the disputes
in accordance with Clause 2.21 of the General Conditions of the
Contract (hereinafter referred to as 'The GCC'). However, the
respondent responded evasively, denying any outstanding dues.
9. According to Clause 2.21 of the GCC, any disputes arising
between the parties must be referred to a sole arbitrator, to be
appointed by the Head of the BHEL Power Sector Region. Given the
circumstances, the applicant has suffered substantial mental anguish
and financial loss, including loss of anticipated profit, estimated to be
Rs.1,68,79,630/-.
10. In response to the disputes that have arisen under the Contract
Agreement No. PESD/HYD/TOARX00035/RSCL_Civil-3 MLD
STP/TIL/CA/01 dated 28.09.2019, and the associated GCC, the
applicant formally invoked the arbitration clause through a legal
notice dated 17.04.2023. The respondent, however, continued with an
evasive stance, failing to address any of the applicant's claims.
11. Learned Counsel for the respondent denied the existence of any
dispute necessitating arbitration between the parties, asserting that the
agreement between the applicant and the respondent had been
mutually terminated on 22.12.2020, with the applicant accepting
₹48,92,947/- as full and final settlement from the respondent.
Subsequently, on 28.12.2020, the applicant issued a "no claim, no
demand" certificate to the respondent, thereby establishing that the
present case was not arbitrable and is deadwood and vexatiously
litigious as there are no arbitral disputes to be referred for arbitration.
12. The work at the site was commenced on 30.08.2019, with a
completion deadline of 29.02.2020. However, following the execution
of certain works, local agitation on 08.12.2019 led to a complete halt
of the project. As a result, all construction activities were suspended,
and work could not be resumed. The cessation of work was attributed
to the local agitation and subsequent instructions from RSCL.
13. The respondent verbally instructed the applicant to demobilize
manpower and shift the Tools and Plants (T&Ps) back to the nearby
Sewage Treatment Plant (STP) project site, to which the applicant
promptly complied on 08.12.2019 owing to the imminent threat of
damage by agitators. It was further submitted that there was no
cement on-site as Ready Mix Concrete had been utilized, and the
required steel for the project had already been exhausted.
Consequently, no material belonging to the applicant remained at the
site.
14. The respondent refuted the applicant's claim that they were
informed of a forthcoming revised plot plan and assured of the work's
resumption. Due to the absence of communication from RSCL, the
respondent did not advise the applicant to restart the work.
15. Furthermore, as per Clause 2.7.8 (b) of the General Conditions
of Contract (GCC), in cases where no significant work had occurred
in the past six months or was expected in the next six months due to
circumstances beyond the respondent's control, the contract could be
short-closed. Following a request from the applicant, joint
measurements were conducted, and the executed work value was
recorded. The particulars of the same were also mentioned by the
respondent.
16. The joint measurement between the parties was formally
documented and signed on 12.10.2020, vide document No.
Tiara/RSCL/Budhatalab/Final bill certification. Following this, in
accordance with the provisions of the GCC clauses 2.7 and 2.7.8(b),
the contract was short-closed. The respondent subsequently issued a
"Letter of Short Closure" on 22.12.2020, under reference
TOASX00035/PESD/PUR/CIVIL/RSCL-3MLD STP/TIL/LOA-short
closure/01, informing the applicant of the contract's termination. In
the said letter, it was explicitly stated that the applicant was not
entitled to any compensation as per clause 2.7, paragraph 1, of the
GCC. The applicant acknowledged and accepted the terms of this
letter by signing and stamping it, indicating unconditional acceptance
to the same.
17. On 28.12.2020, the applicant formally requested the respondent
to release the bank guarantee previously furnished. Along with this
request, the applicant provided a certificate confirming that there were
no outstanding claims or demands related to the contract and that the
payment received would be considered as full and final settlement of
all claims.The respondent then proceeded to release the agreed sum of
Rs.48,92,947/- to the applicant and returned the bank guarantee No.
040BG01192130001 dated 01.09.2019, as well as the extended bank
guarantee dated 06.08.2020, issued by M/s Yes Bank Limited to the
tune of Rs.21,08,000/-.
18. The respondent acknowledged the legal notice dated 17.04.2023
from the applicant containing erroneous claims and demands. In
response, the respondent issued a reply to the said legal notice on
11.05.2023, unequivocally denying the applicant's claims.
19. The respondent emphasized that the sum of Rs.48,92,947/- had
been paid to the applicant as the final settlement for the short closure
of the contract, and a "no claim, no demand" certificate had been
issued by the applicant. However, the applicant contested the
legitimacy of the letter of short closure dated 22.12.2020, submitted as
Ex-R4 by the respondent. The applicant alleged that the said
document, purportedly signed by them, did not bear their signature
and was forged by the respondent with malicious intent to deprive the
applicant of rightful compensation for the losses incurred due to the
respondent's alleged neglect.
20. Considered the rival submissions and perused the record.
Disputes have arisen between the parties and further repeated attempts
to amicably settle the disputes regarding the nonpayment of amounts
due to applicant.
21. The applicants invoking said Clause 2.21 from the GGC
agreement have issued a legal notice dated 17.04.2023. The Clause
2.21 of the subject agreement is relevant and the same is extracted
below:-
"Clause 2.21 Except as provided elsewhere in this Contract, in case amicable settlement is not reached between the Parties, in respect of any dispute or difference; arising out of the formation, breach, termination, validity or execution of the Contract; or, the respective rights and liabilities of the Parties; or, in relation to interpretation of any provision of the Contract; or, in any manner touching upon the Contract, then, either Party may, by a notice in writing to the other Party refer such dispute or difference to the sale arbitration of an arbitrator appointed by Head of the BHEL Power Sector Region issuing the Contract. It shali not be open to the Contractor to object to such arbitrator only on the ground that such arbitrator is an employee/ ex-employee of BHEL or has dealt with or has expressed any opinion on any issue touching upon the Contract.The Arbitrator shall pass a reasoned award and the award of the Arbitrator shall be final and binding upon the Parties."
22. The disputes arose when the machinery and tools were idling
out for over an year. The applicant claims that the respondent failed to
fulfil contractual obligations, resulting in significant financial losses.
The applicant contends that, despite several attempts to resolve the
issue, including a legal notice to initiate arbitration, the respondent
avoided settling the dispute and denied owing any compensation.
23. The respondent contended that there is no dispute requiring
arbitration, asserting that the contract was mutually short-closed vide
letter dated 22.12.2020. The respondent states that the applicant
accepted final payment, issued a "no claim, no demand" certificate,
and requested to release the bank guarantee, thus settling all claims.
The respondent also refutes the applicant's claims by presenting
evidence of a short closure agreement, which the applicant later
challenged as forged.
24. In the light of the above submissions and contentions, the short
question which is posed for the consideration of this Court is:-
Whether the jurisdiction of the referral court at pre-referral stage, when the issue with respect to the existence of any arbitrable disputes between the parties which are already settled by accepting final settlement and issuing 'no claim, no demand certificate' to the respondent, necessitate appointment of a sole Arbitrator as prayed by the applicant?
25. Admittedly, there is no dispute with regard to the existence of
an arbitration agreement between the parties. It is relevant to note that
the scope of Section 11 of the Act, 1996, is extremely limited. The
Court has to only see whether prima facie an arbitration agreement
exists. The Court cannot go into disputed questions of facts which are
to be decided by the arbitrator.
26. It is apt to note that the Apex Court referring to the principle
laid down by it in various judgments including Vidya
Drolia v. Durga Trading Corpn. 1 and scope of Section 11 of the
Act, in NTPC Limited Vs. SPML Infra Limited 2 held as follows:-
Eye of the needle:-
25. The above referred precedents crystallize the position of law that the pre-referral jurisdiction of the Courts under Section 11(6) of the Act is very narrow and inheres two inquiries. The primary inquiry is about the existence and the validity of an arbitration agreement, which also includes an inquiry as to the parties to the agreement and the applicant's privity to the said agreement. These are matters which requires a thorough examination by the Referral Court. The secondary inquiry that may arise at the reference stage itself is with respect to non-arbitrability of the dispute.
26. As a general rule and a principle, the Arbitral Tribunal is the preferred first authority to determine and decide all questions of non-
arbitrability. As an exception to the rule, and rarely as a demurrer, the referral court may reject claims which are manifestly and ex facie non- arbitrable.
27. The standard of scrutiny to examine the non-arbitrability of a claim is only prima facie. Referral courts must not undertake a full review of the contested facts; they must only be confined to a primary first review and let facts speak for themselves. This also requires the courts to examine whether the assertion on arbitrability is bona fide or not. The prima facie scrutiny of the facts must lead to a clear conclusion that there is not even a vestige of doubt that the claim is non-arbitrable. On the other hand, even if there is the slightest doubt, the rule is to refer the dispute to arbitration.
28. The limited scrutiny, through the eye of the needle, is necessary and compelling. It is intertwined with the duty of the Referral court to protect the parties from being forced to arbitrate when the matter is
(2021) 2 SCC 1 : (2021) 1 SCC (Civ) 549
2023 (9) SCC 385
demonstrably non-arbitrable. It has been termed as a legitimate interference by courts to refuse reference in order to prevent wastage of public and private resources. If the said duty within the limited compass is not exercised, and the court becomes too reluctant to intervene, it may undermine the effectiveness of both, arbitration and court. Therefore, This Court or a High Court, as the case may be, while exercising jurisdiction under Section 11(6) of the Act, is not expected to act mechanically, merely to deliver a purported dispute raised by an applicant at the doors of the chosen arbitrator.
27. In the light of the law laid down by the Apex Court, coming to
the facts of the present case, there is no dispute with regard to the
existence of arbitration agreement between the parties.
28. It is also apt to note that the work at the site was commenced on
30.08.2019, with a completion deadline of 29.02.2020. Respondent
directed the applicant to suspend work until further instructions, due
to local agitation. According to the respondents, it has verbally
instructed the applicant to demobilize manpower and shift the Tolls
and Plants (T & Ps) back to the nearby Sewage Treatment Plant (STP)
project site, to which the applicant promptly complied on 08.12.2019
owing to the imminent threat of damage by agitators.
29. Respondent denied the applicant's contention that they were
informed of a forthcoming revised plot plan and assured of the work's
resumption.
30. It is also relevant to note that the details of joint measurement
between the parties were formally documented and signed on
12.10.2020. The subject contract was short-closed in accordance with
Clause No.2.7 and 2.7.8 (b) of the GCC. Subsequently, respondent has
issued a letter of short-closure on 22.12.2020 informing the applicant
of the contract's termination. In the said letter, it was explicitly stated
that the applicant is not entitled to any compensation as per Clause
No.2.7, paragraph No.1 of GCC. The applicant received and
acknowledged the said terms of letter by signing and stamping it,
indicating unconditional acceptance to the same.
31. On 28.12.2020, the applicant formally requested the respondent
to release the bank guarantee previously furnished. Applicant has also
provided a certificate confirming that there were no outstanding
claims or demands related to the contract and that the payment
received would be considered as full and final settlement of all claims.
Then, respondent proceeded to release the agreed sum of
Rs.48,92,947/- to the applicant and returned the bank guarantee
furnished on 01.09.2019 as well as the extended bank guarantee dated
06.08.2020. The applicant received the said amount of Rs.48,92,947/-
as final settlement for the short closure of the contract and a 'no claim,
no demand' certificate has been issued by the applicant. Having
received the said amount, now the applicant is contesting the
legitimacy of the short closure letter dated 22.12.2020 by way of
issuing a legal notice after three years i.e. on 17.04.2023.
32. As discussed supra, having issued a 'no claim, no demand
certificate', on receipt of agreed amount of Rs.48,92,947/-, the
applicant cannot dispute the short closure notice. As discussed supra,
both the applicant and the respondents measured the completed work
and it is a joint measurement. It was documented on 12.10.2020. In
the light of the said case, this Court is of the considered view that
there is no dispute much less arbitrable dispute between the applicant
and respondents.
33. As discussed supra, this Court being referral Court cannot
mechanically refer the matter to the arbitral Tribunal as held by the
Apex Court.
34. Therefore, the petitioner herein is failed to make out any case to
refer the matter to the arbitral Tribunal. Therefore, this application is
liable to be dismissed.
35. In view of the above discussion, this Arbitration Application is
dismissed.
As a sequel thereto, miscellaneous applications, if any, pending
in the Arbitration Application shall stand closed.
________________________ JUSTICE K. LAKSHMAN Date:18.09.2024
Vvr
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!