Saturday, 11, Apr, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Psm Energy Pvt. Ltd vs Zam Engineering And Logistics Pvt. Ltd
2024 Latest Caselaw 4527 Tel

Citation : 2024 Latest Caselaw 4527 Tel
Judgement Date : 22 November, 2024

Telangana High Court

Psm Energy Pvt. Ltd vs Zam Engineering And Logistics Pvt. Ltd on 22 November, 2024

           THE HONOURABLE THE CHIEF JUSTICE ALOK ARADHE
                               AND
            THE HONOURABLE SRI JUSTICE J. SREENIVAS RAO

                + COMMERCIAL COURT APPEAL No.20 OF 2024

     % Dated 22.11.2024

     # PSM Energy Pvt. Ltd.
       A Company incorporated under Companies Act.
       Having registered office at:-
       # 220, MIG Flats, Kautilya Apartments
       Plot No.25, Sector -14, Pocket-B
       Dwarka, New Delhi 110075
       Through its director/Authorized Representative
       Shri Ajay Vishwakarma

                                                               .... Appellant
                                     VERSUS
     $ ZAM Engineering and Logistics Pvt. Ltd.
       A Company incorporated under Companies Act.
       Having its registered office at 25-12-44 & 45,
       Asmagate, Godeyvari Street,
       Vishakhapatnam, Andhra Pradesh
       Rep. by its Managing Director, Mr. Zafar Hosain
       And four others
                                                            ... Respondents

     ! Counsel for petitioner               : Mr. Prasen Gundavaram

     ^ Counsel for Respondent No.1          : Ms. Manjari S. Ganu,


     < GIST:

     > HEAD NOTE:

     ? CITATIONS:

1.   2018) 15 SCC 678
2.   (2021) 9 SCC 732
3.   (1998) 7 SCC 184
4.   (2006) 3 SCC 100
5.   2016 (6) ALD 598 (DB)
                                     2




     THE HON'BLE THE CHIEF JUSTICE ALOK ARADHE
                                 AND
       THE HON'BLE SRI JUSTICE J.SREENIVAS RAO

       COMMERCIAL COURT APPEAL No.20 OF 2024

JUDGMENT:

(Per the Hon'ble Sri Justice J. Sreenivas Rao)

This appeal under Section 13 of the Commercial Courts

Act, 2015 read with Section 37 of the Arbitration and

Conciliation Act, 1996 has been filed against the order dated

10.06.2024 passed in C.O.S.No.31 of 2021 by the Commercial

Court in the Cadre of District Judge for Trial and Disposal of

Commercial Disputes at Hyderabad, (for short, 'Commercial

Court') by which the application filed by appellant/defendant

No.1 seeking rejection of the plaint under Section 8 of the

Arbitration and Conciliation Act, 1996 read with Order VII

Rule 11(a) & (b) read with Section 151 of Code of Civil

Procedure, 1908 (C.P.C.) was dismissed.

2. Heard Sri G. Vidya Sagar, learned Senior Counsel

representing Sri Sai Prasen Gundavaram, learned counsel for

the appellant, and Sri Sunil B. Ganu, learned Senior Counsel

representing Ms. Manjari S. Ganu, learned counsel for

respondent No.1.

3. The appellant herein is defendant No.1 and respondent

No.1 herein is the plaintiff in C.O.S.No.31 of 2021. For the

sake of convenience, the parties shall be referred to in this

order as per their ranking in C.O.S.No.31 of 2021.

4. BRIEF FACTS:

i) The plaintiff is a company registered under the

Companies Act, 1956 and it had entered into an operational

lease agreement dated 16.10.2019 with defendant No.1

company in respect of 30 nos. of Volvo FMX 460 33 Cu.M

Coad Body Tippers and the said operational lease agreement

was executed at Gurugram, Haryana. The defendant No.1

defaulted in payment of monthly lease rental of the Volvo

Tippers from the 1st month itself and failed to pay the rents

from November, 2019 to August, 2020. Subsequent thereto,

the plaintiff and defendant No.1 have entered into

Memorandum of Understanding (MOU) in furtherance of the

operational lease agreement on 05.01.2020, whereby the

original operational lease agreement was modified/revised.

As per MOU, defendant No.1 was agreed to pay the rents from

20.01.2020 along with interest @ 13% p.a. as against the rate

of 18% p.a. as per the operational lease agreement dated

16.10.2019. Despite repeated demands, defendant No.1 did

not perform any part of the obligations. Thereafter, defendant

Nos.1 to 3 approached the plaintiff in the month of February

2020 stating that defendant No.1 was independently awarded

works of contract in Odisha and proposed joint venture with

the plaintiff and offered to share 50% of the profits in the

revenue accrued and also to refund the working capital to the

plaintiff and accordingly, the plaintiff and defendant No.1

entered into joint venture agreement dated 21.02.2020.

According to the said joint venture agreement, the plaintiff is

allowed to withdraw an amount of Rs.3 lakhs every month

from the month of January 2020. However, defendant No.1

did not perform any part of the obligations as agreed and the

joint venture agreement dated 21.02.2020 was never acted

upon. As defendant No.1 failed to pay the rents from

November, 2019 to August, 2020, the plaintiff filed

C.O.S.No.31 of 2021 seeking a direction to the defendants to

jointly and severally pay an amount of Rs.10,93,05,243/- in

respect of the Lease Agreement dated 16.10.2019 along with

future interest @ 13% per annum from the date of suit till

realisation and sought another relief directing defendant No.1

to pay an amount of Rs.33,41,069/- being amounts

refundable by them towards initial capital investment and

other expenses in respect of the joint venture agreement

dated 21.02.2020 along with future interest @ 13% per

annum from the date of suit till realisation.

ii) In the said suit, defendant No.1 filed an application in

I.A.No.73 of 2022 under Section 8 of the Arbitration and

Conciliation Act, 1996 (hereinafter referred to as 'the Act')

read with Order VII Rule 11(a) and (b) of C.P.C. to reject the

plaint on the ground that as per the arbitration clause in the

joint venture agreement dated 21.02.2020, the Commercial

Court is not having jurisdiction to adjudicate the dispute as

well as bar under Section 8 of the Act as there is valid

arbitration clause in the agreement existing between the

parties and also on the ground of cause of action.

iii) The Commercial Court dismissed the said application,

by its order dated 10.06.2024. Aggrieved by the same,

defendant No.1 filed this appeal.

5. Submissions of learned counsel for defendant No.1/appellant:

5.1. Learned Senior Counsel contended that the plaintiff and

defendant No.1 were entered operational lease agreement

dated 16.10.2019 and MOU dated 05.01.2020 as well as joint

venture agreement dated 21.02.2020. In the joint venture

agreement, there is a specific clause enumerated that if any

dispute arises between the parties, the said dispute has to be

resolved through arbitrator. The plaintiff instead of invoking

arbitration clause filed suit in C.O.S.No.31 of 2021 before the

Commercial Court and the same is not maintainable under

law and also there is no cause of action to institute the suit.

In such circumstances, the Commercial Court ought to have

rejected the plaint.

5.2. He further submitted that as per the provisions of

Section 8 of the Act, the Commercial Court ought to have

rejected the plaint and directed the plaintiff to invoke the

proceedings under the Act by virtue of specific arbitration

clause enumerated in the joint venture agreement dated

21.02.2020 and the Commercial Court is not having

jurisdiction to adjudicate the suit proceedings.

5.3. In support of his contention, he relied upon the

following judgments:

1. Ameet Lalchand Shah and others v. Rishabh Enterprises and another 1;

2. Sanjiv Prakash v. Seema Kukreja and others 2; and

3. Order passed by the Division Bench of this Court in C.R.P.No.348 of 2024 dated 22.07.2024.

6. Submissions of learned counsel for the plaintiff/respondent No.1:

6.1. Per contra, learned counsel for the plaintiff submitted

that the operational lease agreement dated 16.10.2019 and

the joint venture agreement dated 21.02.2020 are not inter-

connected and both are different agreements. He further

(2018) 15 SCC 678

(2021) 9 SCC 732

submitted that the operational lease agreement dated

16.10.2019 was executed between the plaintiff and defendant

No.1, whereunder the plaintiff leased out 30 Volvo Tippers to

defendant No.1 for a period of 34 months and MOU dated

05.01.2020 was executed between the parties modifying the

terms of operational lease agreement dated 16.10.2019,

whereunder defendant No.1 agreed to pay the rents from

20.01.2020. Insofar as joint venture agreement dated

21.02.2020 is concerned, it is an independent agreement in

respect of works which were already awarded to defendant

No.1 at Lakhanpur, Odisha at the Mines of Mahanadi Coal

Fields.

6.2. He also submitted that operational agreement and the

MOU do not contain arbitration clause and only joint venture

agreement contains an arbitration clause. Pursuant to the

said clause, defendant No.1 filed Arbitration Application

No.419 of 2022 before the High Court of Delhi seeking

appointment of Sole Arbitrator to resolve the dispute between

the parties and the said arbitration application was allowed,

by its order dated 12.08.2024 referring the dispute under

joint venture agreement dated 21.02.2020 and referred to

arbitration. Aggrieved by the same, defendant No.1 filed

S.L.P. (Civil) Diary No.39966 of 2024 before the Hon'ble

Supreme Court of India and the same was dismissed as

withdrawn on 18.11.2024.

6.3. He further contended that before the Hon'ble Supreme

Court, defendant No.1 specifically raised a ground that even

before execution of joint venture agreement dated 21.02.2020,

the plaintiff and defendant No.1 were carrying out the joint

business by utilisation and operatinalisation of the

equipment/vehicles/ tippers which are the subject matter of

the operational lease agreement. Defendant No.1 further

raised a ground that the High Court of Delhi had erroneously

held that there is no connection between the subject matter of

the operational lease agreement read with MOU and the joint

venture agreement as recorded in its previous order dated

21.03.2023 is contrary to law and the said grounds were not

accepted by the Hon'ble Supreme Court of India and S.L.P.

was dismissed and defendant No.1 is not entitled to raise the

very same ground in the present appeal.

6.4. He further submitted that by virtue of the orders dated

12.08.2024 passed by the High Court of Delhi in Arbitration

Application No.419 of 2022, the plaintiff is not pressing the

relief of recovery of an amount of Rs.33,41,069/- in

C.O.S.No.31 of 2021. He also submitted that the Commercial

Court has rightly dismissed the application filed by defendant

No.1.

Analysis:

7. This Court considered the rival submissions made by

the respective parties and perused the material available on

record. The record discloses that the plaintiff filed suit in

C.O.S.No.31 of 2021 in the month of April, 2021 against the

defendants for recovery of an amount of Rs.10,93,05,243/-

along with interest @ 13 % per annum basing on the

operational lease agreement dated 16.10.2019 and MOU

dated 05.01.2020 and also for recovery of Rs.33,41,069/-

along with interest @ 13% per annum, which was paid to

defendant No.1 pursuant to the joint venture agreement

dated 21.02.2020. The plaintiff specifically pleaded in the

plaint that the plaintiff is having 30 Volvo Tippers and the

representative of defendant No.1 had approached the plaintiff

and agreed to purchase the said Volvo Tippers and the

plaintiff and defendant Nos.2, 3 and 5 met at Park Hyatt

Hotel at Hyderabad on 04.10.2019 and negotiations were

taken place and the plaintiff offered to sell the Volvo Tippers

for Rs.65 lakhs per Tipper excluding Goods and Services Tax

(for short, 'GST') and defendant No.2 approached the finance

company for funding and the finance company did not come

forward to finance and defendant No.2 suggested to enter into

operational lease agreement and the same was entered into

on 16.10.2019 between the plaintiff and defendant No.1 and

the plaintiff agreed to lease 30 nos. Volvo Tippers for a lease

period of 34 months and defendant No.1 agreed to pay the

monthly lease/rent of Rs.77,58,621/- excluding GST as per

the schedule annexed to the operational lease agreement

dated 16.10.2019 and the physical possession of the Volvo

Tippers were handed over to defendant No.1 on 17.10.2019

and defendant No.1 defaulted in payment of monthly lease

rental and requested the plaintiff to defer the commencement

of payment by two months i.e., with effect from 05.01.2010

and subsequently MOU was entered on 05.10.2020 and

defendant No.1 agreed to pay the rents from 20.01.2020 and

in spite of the same, defendant No.1 failed to pay the lease

rentals as assured.

8. The plaintiff further averred that defendant Nos.1 to 3

have approached the plaintiff in the month of February, 2020

stating that defendant No.1 was awarded works contracts in

Odisha and defendant No.1 proposed for joint venture

agreement with the plaintiff and offered to share 50% of the

profits and allowed the plaintiff to withdraw Rs.3,00,000/-

every month from January, 2020 and accordingly the parties

entered into joint venture agreement on 21.02.2020 and

further pleaded that plaintiff paid an amount of

Rs.25,00,000/- to defendant No.1 towards contribution of the

working capital and other amounts. However, defendant No.1

failed to take steps for complying with the obligation under

the joint venture agreement dated 21.02.2020 and also

payment of monthly lease rentals from January, 2020

onwards and the plaintiff has withdrawn from the proposed

joint venture. Thereafter, several communications were

addressed to defendant No.1 and it is also pleaded that the

joint venture agreement was never acted upon.

9. During pendency of the suit in C.O.S.No.31 of 2021,

defendant No.1 filed Arbitration Application No.419 of 2022

before the High Court of Delhi on 25.03.2022 under Section

11 of the Act to refer the dispute to the arbitrator. The said

Arbitration Application was allowed on 12.08.2024 referring

the dispute in respect of joint venture agreement dated

21.02.2020 to arbitrator. Aggrieved by the said order,

defendant No.1 filed S.L.P. (Civil) Diary No.39966 of 2024

before the Hon'ble Supreme Court of India and the same was

dismissed as withdrawn, by its order dated 08.11.2024.

10. The record further reveals that during pendency of the

Arbitration Application No.419 of 2022 before High Court of

Delhi, defendant No.1 filed I.A.No.73 of 2022 invoking the

provisions of Section 8 of the Act read with Order VII Rule

11(a) and (b) read with Section 151 of C.P.C. on 20.07.2022 to

reject the plaint in C.O.S.No.31 of 2021 on the ground of

arbitration clause enumerated in joint venture agreement

dated 21.02.2020, as such the Commercial Court is not

having jurisdiction to entertain the suit and also on the

ground of cause of action.

11. It is relevant to extract the arbitration clause mentioned

in the joint venture agreement dated 21.02.2020 here under:

"Settlement of Disputes by Arbitration:

26. In case of any disputes, question of controversy arises between the JV Partners to this Agreement and the same could not be resolved amicably, then in every case, the matter in dispute shall be resolved and finally settled in accordance with the provisions of the Arbitration & Conciliation Act 1996 as may be amended from time to time over its re-enactment. The arbitrator shall be mutually appointed by both parties. The arbitration shall be taken place at Gurgaon, Haryana, India. All questions concerning the construction, validity and interpretation of this Agreement will be governed by the laws of India, and the courts at New Delhi, India, shall have exclusive jurisdiction."

12. Pursuant to the above said clause, defendant No.1 has

filed Arbitration Application No.419 of 2022 before the High

Court of Delhi and the same was allowed on 25.03.2022

referring the dispute arose out of a joint venture agreement

dated 21.02.2020 to the arbitrator and also held that there is

"no connect" between the subject matter of the operational

lease agreement read with MOU and joint venture agreement

and the said order has become final.

13. It is pertinent to mention that the plaintiff filed suit for

recovery of an amount of Rs.10,93,05,243/- against the

defendants basing upon the operational lease agreement

dated 16.10.2019 and MOU dated 05.01.2020 and the said

documents do not contain arbitration clause and basing upon

the arbitration clause enumerated in the joint venture

agreement dated 21.02.2020, defendant No.1 is not entitled to

seek rejection of the plaint, especially the operational lease

agreement, MOU and joint venture agreement are not

interconnected and they are different.

14. Insofar as the relief (b) sought by the plaintiff in

C.O.S.No.31 of 2024 for recovery of an amount of

Rs.33,41,069/- arising out of joint venture agreement dated

21.02.2020 is concerned, the plaintiff filed Memo dated

02.11.2024, vide USR.No.106135 stating that by virtue of the

order of the High Court of Delhi in Arbitration Application

No.419 of 2022 referring the dispute between the parties in

respect of joint venture agreement dated 21.02.2020 to the

arbitrator, the plaintiff is not pressing the relief sought in the

suit in C.O.S.No.31 of 2021 for recovery of Rs.33,41,069/-.

15. In Ameet Lalchand Shah (supra), the Hon'ble Supreme

Court held that where multiple agreements are

interconnected and form part of a single commercial

transaction, the presence of an arbitration clause in one or

more agreements can justify referring all disputes, involving

all agreements and parties, to arbitration. This is true even if

some agreements lack an arbitration clause or some parties

are non-signatories, provided the agreements are integrally

connected to achieving the overall purpose of the transaction.

Courts should interpret such commercial arrangements with

a sense of "business efficacy" and not be restricted by

technicalities or allegations of fraud, unless substantial

grounds exist. The Apex Court also held that the averments

in the plaint also prima facie indicate that all the four

agreement are interconnected.

16. In C.R.P.No.348 of 2024, this Court held that petitioner

No.1 and respondent No.1 entered into two sub-lease

agreements, one of which contained an arbitration clause.

Instead of opting for arbitration, petitioner No.1 filed a suit

seeking the recovery of Rs.3,24,74,899/-. In response,

Respondents No.1 and 2 submitted an application under

Section 8 of the Arbitration and Conciliation Act, which the

Commercial Court accepted. The petitioners challenged this

decision, arguing there was no written agreement. The Court,

after examining Clause 11 of the sub-lease agreement, upheld

the Commercial Court's decision, ruling that the dispute

should be resolved through arbitration as per the agreed

terms. The Court found no error in the Commercial Court's

decision, dismissing the revision petition.

17. In Sanjiv Prakash (supra), the Hon'ble Supreme Court

held that in this case the disputes arose regarding a

Shareholders' Agreement (SHA) and a prior Memorandum of

Understanding (MoU) between family members and Reuters,

which included arbitration clauses. The MoU was claimed to

have been superseded by the SHA, which contained a

novation clause (i,e., Clause 28). When disputes regarding

share transfer pre-emptive rights emerged, the appellant

invoked the arbitration clause in the MoU. The respondents

argued that the MoU was void post-1996 due to novation by

the SHA. The Delhi High Court dismissed the Section 11

petition for appointing an arbitrator. On appeal, the Supreme

Court held that the doctrine of kompetenz-kompetenz and

Section 11(6-A) of the Arbitration and Conciliation Act, 1996,

which limits judicial interference at the referral stage to

verifying the existence of an arbitration agreement, leaving

issues of validity and scope to the arbitral tribunal. The Court

emphasized that the novation of a contract affects its

arbitration clause only if explicitly stated, and any deeper

examination of such issues falls under the tribunal's

jurisdiction.

18. The judgements and order in C.R.P.No.348 of 2024

relied upon by the learned counsel for defendant No.1 are not

applicable to the facts and circumstances of the case on the

ground that in the subject matter operational lease agreement

dated 16.01.2019 and joint venture agreement dated

21.02.2020 are not interconnected. The operational lease

agreement is pertaining to leasing of 30 x Volvo FMX 460

Tippers (33 CUM coal body) for an amount of 91,57,161/-

and for a term of 34 months and whereas the joint venture

agreement dated 21.02.2020 in respect of works which were

awarded to defendant No.1 in Lakhanpur, Odisha at the

Mines of Mahanadi Coal Fields.

19. Insofar as the other ground raised by defendant No.1

that there is no cause of action and jurisdiction to file suit

before the Commercial Court, Hyderabad, is concerned, the

plaintiff specifically pleaded at paras 29 and 30 of the plaint

that negotiations between the plaintiff and defendants for

entering into operational lease agreement took place on

04.10.2019 at Park Hyatt Hotel, Hyderabad and Clause 25 of

the operational lease agreement dated 16.10.2019 provides

for Hyderabad as the place of jurisdiction to initiate legal

proceedings in case of disputes between the parties. Basing

on the said pleadings, the Commercial Court has entertained

the suit.

20. In Raptakos Brett & Co. Ltd. v. Ganesh Property 3

and Mayar (H.K.) Ltd. v. Vessel M.V. Fortune Express 4, the

(1998) 7 SCC 184

Hon'ble Apex Court held that though in an application under

Order VII Rule 11 of C.P.C., the Court has to look into the

averments made in the plaint and the documents filed along

with the plaint alone. The Court cannot at that stage look

into the written statement or the documents filed along with

the written statement.

21. In Mustigulla @ Namaswamy Hemanth Kumar v.

Abhaya Infrastructure Pvt. Ltd. And others 5, the Division

Bench of erstwhile High Court for the States of Telangana and

Andhra Pradesh held that rejection of plaint on the ground of

res judicata, cause of action, under valuation, limitation have

to be decided on trial but the same cannot be a ground for

rejection of plaint, especially when the parameters of Order

VII Rule 11 of C.P.C. are not satisfied.

22. For the foregoing reasons as well as the plethora of

judgments, this Court does not find any illegality or

irregularity or jurisdictional error in the impugned order

dated 10.06.2024 passed by the Commercial Court in

(2006) 3 SCC 100

2016 (6) ALD 598 (DB)

dismissing the application filed by defendant No.1 to reject

the plaint filed by the plaintiff.

23. Accordingly, the Commercial Court Appeal is dismissed.

No costs.

Miscellaneous petitions, pending if any, shall stand

closed.

_______________________________ ALOK ARADHE, CJ

_______________________________ J.SREENIVAS RAO, J Date: 22.11.2024

L.R. copy to be marked (b/o) mar

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Media

 
 
Latestlaws Newsletter