      IN THE HIGH COURT OF TELANGANA AT HYDERABAD


                    W.P.No.12675 OF 2017


Between:


M/s. Pallavi-Maa-GC-(JV)

                                                   ...     Petitioner

And

The Union of India & others
                                               ...     Respondents


JUDGMENT PRONOUNCED ON: 03.06.2024


THE HON'BLE MRS JUSTICE SUREPALLI NANDA


1. Whether Reporters of Local newspapers   :       Yes
   may be allowed to see the Judgment?

2. Whether the copies of judgment may be   :       Yes
   marked to Law Reporters/Journals?

3. Whether Their Lordships wish to         :       Yes
   see the fair copy of the Judgment?


                                   __________________
                                   SUREPALLI NANDA, J
                                 2                                 SN,J
                                                              wp_12675_2017




          THE HON'BLE MRS JUSTICE SUREPALLI NANDA


                    W.P.No.12675 OF 2017


% 03.06.2024

Between:

# M/s. Pallavi-Maa-GC-(JV)

                                                    ...   Petitioner

     And

$ The Union of India & others

                                                  ... Respondents
< Gist:

> Head Note:

! Counsel for the Petitioner        : Mr.C.Hanumantha Rao

^ Counsel for Respondents           : Mr.P.Bhaskar, Ld.S.C.for
                                      R1 to R5
                                      G.P. for Mines and Geology,
                                      for R6.


? Cases Referred:

      --
                                      3                                         SN,J
                                                                           wp_12675_2017




         THE HON'BLE MRS. JUSTICE SUREPALLI NANDA

                      W.P. No.12675 OF 2017

ORDER:

Heard Mr.C.Hanumantha Rao, learned counsel

appearing on behalf of the petitioner, Mr.P.Bhaskar, learned

Standing Counsel appearing on behalf of respondent Nos.1

to 5 and learned Government Pleader for Mines and Geology

appearing on behalf of respondent No.6.

PRAYER:

2. The petitioner approached the court seeking prayer as

under:

"...to issue writ order or direction especially one in the Nature of Writ of Mandamus declaring the action of the respondents in deducting @ 30% towards District Mineral Foundation Fees and 2% State Mineral Exploration Trust, in total deducting 32% on the seigniorage charges from the running bills payable to the petitioner is illegal, arbitrary and violative of the Article 19(1)(g) of the Constitution of India and consequently direct the respondents not to deduct 30% towards District Mineral Foundation Fees and 2% State Mineral Exploration Trust, in total deducting 32% on the seigniorage charges from the petitioner or in the alternative it 4 SN,J wp_12675_2017

is prayed that this Hon'ble Court may be pleased to direct the Respondents to reimburse the amount deducted towards Mineral Development Fund at 30% of the seigniorage charges and also 2% of the seigniorage charges towards State Mineral Exploration Trust and pass..."

3. PERUSED THE RECORD:

A) Counter affidavit filed by the respondents, in

particular, the relevant paras 3, 4, 5, 6, 7, 8, 9 and 10, read

as under:

"3. I submit that the seigniorage charges, if increased, will be recovered from the contractors "on account" and "final bills" and remitted to state government. However, the reimbursement of the increased seignorage to the contractor will be applicable only in respect of condition 19(3)(a) of the agreement i.e., for seinorage charges and not for condition 19.4 of the agreement which is applicable to all other taxes, duties, levies etc., except for seigniorage charges. The clauses mentioned about seignorage charges in the agreement are reproduced below.

Clause no.19.1 of the agreement condition. "Seigniorage charges/fee for consumption of earth, moorum, sand and other minerals in works execution as fixed by the state government from where the minerals are drawn and payable to them as revised from time to time during currency 5 SN,J wp_12675_2017

of contract will be recovered by the Railway from the contractors, in "on account" and "final bills" and remitted to the State government, unless exemption obtained to the contrary or proof of payment of seigniorage charges submitted as indicated below:

Clause No. 19.3(a) of the agreement condition "For any subsequent increase or decrease in the rates of seigniorage charges, reimbursement / recovery will be effect to/from the contractor as per the following provisions.

a) For increase in the rates of seigniorage charges after the last date of submission of tender the increased amount will be recovered by the Railway from the contractors, in "on account" and "final bills" and remitted to the State Govt., on receipt of state Govt.'s order to that effect. However, the Railway shall reimburse the additional liability to the contractor, provided that the work executed falls in the original completion period of the work or in the extended period granted on administrative grounds i.e., under clause 17-A (i), (ii) or (iii) of IRSGCC.

Clause No.19.4 No additional amount will be paid or claim entertained on this account by the Railway. Contractor shall not have any claim whatsoever as a result of the increase in the rates of all other taxes, duties, octroi or any form of levies etc., even if incurred on the supply/use of minerals indicated above.

6 SN,J wp_12675_2017

Hence DFM, MERIT are to be treated as levies which comes under 19.4 and are to be borne by the contractor.

4. It is submit that the petitioner entered into agreement to deduct seigniorage charges as per the rate prevailing on the date of submitting tenders, i.e., on 14.09.2015, the liability with respect to other taxes, duties, levies etc., as per condition 19.4 of the agreement still persists upon the contractor.

5. I submit that the proceedings vide W.Con.Dy.CPM/ WCSP/NDKD-KHT dt.30.11.2016 was issued based on Assistant Director of Mines and Geology/Guntur letter No.846/DFM/2016 dated 10-11-2016, as per the proceedings, 30% on seigniorage fees will be deducted from contractor's on account and final bills for payment towards District mineral foundation (DMF) However, the reimbursement to the contractor with respect to recovered DMF fees is not applicable as per condition 19.4 of the agreement. It is to state that the additional 30% charged as DMF is not the seignorage charges.

6. I submit that the petitioner entered into agreement with the Railways in which the condition 19.4 of the agreement specifically states that all other taxes, levies, duties etc., are to be borne by the contractor and will be recovered from on account and final bills and will not be reimbursed in future. It is to state that the Railways has no 7 SN,J wp_12675_2017

obligation to pay DMF (30% on seinorage, fees) which is in the nature of levies as per condition 19.4 of the agreement.

7. I submit that the DMF fees so recovered falls under condition 19.4 of the agreement which has agreed upon by the contractor for recovering from running bills without any question of reimbursement. As such, recovery is not illegal and arbitrary and as per the law of the land. The same is applicable to MERIT which is 2% of seignorage fees deduction from running bills with respect of state mineral exploration fund. Hence DFM & MERIT which comes under clause No.19.4 of the agreement.

8. I submit that the Deduction of 30% of seinorage fees towards DMF and 2% of seinorage fees towards State Mineral Exploration Trust is not illegal as the contractor has agreed for recovering any other taxes, fees, duties levies etc., as per condition 19.4 of the agreement.

9. I submit that it is to submit that the DMF @30% is being deducted on the basis of State of AP framed DMF rules and the liability of the payment is upon the contractor who has agreed for the same while entering into agreement. As such, agreeing for reimbursement is violative of condition 19.4 of the agreement and a loss to Public exchequer.

10. I further submit that from the language employed in the GOs, this amount as directed to be recovered is only a 8 SN,J wp_12675_2017

contribution towards DMF and SMETF and the contribution is quantified based on the seigniorage fee. Hence, the said 30% or 2% to be recovered on seigniorage, per se, is not part of seigniorage fee, but it is only an additional amount imposed by the State Government on the Contractors."

B) Interim order of this Court dated 11.04.2017

passed in W.P.M.P.No.15758 of 2017 in W.P.No.12675 of

2017, observed as under:

"Any deduction of the amount towards district mineral fund and state mineral exploration trust fund on the seigniorage charges from the running bills of the petitioner shall be subject to further orders in the writ petition."

Interim orders of this Court dated 11.04.2017 passed

in WPMP No.15758 of 2017 in W.P.No.12675 of 2017

referred to above are in force as on date.

4. The case of the petitioner in brief as per the averments

made by the petitioner in the affidavit filed by the petitioner

in support of the present writ petition, is as under:

i) The petitioner is a partnership firm operating under the

name and style "M/s Pallavi-Maa-GC-(JV)" and in pursuance of

tender notificationNo.24/CAO/C/SC/2015 dated 06.08.2015 issued 9 SN,J wp_12675_2017

by the 3rd respondent inviting sealed tenders for execution of work

'Nadikudi - Srikalahasti New BG line Project-Piduguralla -

Rampicherla Section - Earthwork in embankment and cutting

including construction of Minor bridges and other miscellaneous

works from Ch.4500 to Ch.21300 in Reach-1 between Piduguralla

(New) and Rampicherla (Pro) stations, the petitioner submitted its

sealed tender on 14.09.2015 at 11.00 AM and tenders were opened

on 14.09.2015 at 11:30 AM and finalized on 03.02.2016. The

petitioner being the lowest tenderer, is declared as successful

bidder. Thereafter, the Railway Department issued Letter of

Acceptance dated 15.02.2016.

ii) The petitioner entered into agreement of works dated

28-04-2016 with the 2nd respondent for performance of work

'Nadikudi - Srikalahasti New BG line Project-Piduguralla -

Rampicherla Section - Earthwork in embankment and cutting

including construction of Minor bridges and other miscellaneous

works from Ch.4500 to Ch.21300 in Reach-1 between Piduguralla

(New) and Rampicherla (Pro) stations (Two packet system) and the

petitioner deposited earnest deposit of Rs.24,40,000/- by way of

bankers chequeNo.348636 dated 11.09.2015 drawn on SBH, 10 SN,J wp_12675_2017

Vanasthalipuram Branch. The balance security deposit of

Rs.2,22,92,270/- will be recovered from the running bills at the

rate of 10% till the balance security deposit amount is fully

recovered.

iii) As per the agreement the security deposit shall be

released only after the expiry of the maintenance period and after

passing the final bill based on "No Claim Certificate". The petitioner

also submitted performance guarantee in the form of bank

guarantee No.86431PEBG160012 dated 14.03.2016 for

Rs.2,47,50,000/- issued by Bank of India, Dilsukhnagar Branch

which is valid upto 13th May, 2017.

iv) It is the case of the petitioner that, as per the

agreement the work should be completed within 12 months and

later on, the date of completion of work is extended from

16.02.2017 to 31.10.2017 by the 3rd respondent by executing

subsidiary agreement dated 28.02.2017 and the bank guarantees

were also extended up to 13.05.2018.

v) While this stood thus, the 3rdrespondent issued

proceedings in W.Con.Dy.CPM/WCSP/NDKD-KHT dated 30.11.2016

stating that the State Government of Andhra Pradesh issued rules 11 SN,J wp_12675_2017

for establishment of District Mineral Foundation in terms of

amended Mines and Minerals Regulation and Development Act and

framed rules named as District Mineral Foundation Rules, 2016,

and according to the said rules, Mining lease, Prospecting Licence

or Quarry Lease Holders shall pay the DFM equivalent to 30% of

the seigniorage charges paid to the State Government.

vi) It is the case of the petitioner that, subsequent to

issuance of above said proceedings, the petitioner was informed

that in view of the introduction of District Mineral Foundation Rules,

2016, they will deduct30% of the seigniorage charges in addition to

seigniorage from the petitioner from its running bills and the

3rdrespondent stated that the said charges might not be

reimbursed.

vii) It is the specific case of the petitioner that, the

condition No.19(3)(a) contemplates that if there is increase in the

seigniorage fees, the same will be recovered from the running bills,

however the excess amount which is recovered will be reimbursed

at a later point of time. Thus, when the seigniorage charges were

agreed to be reimbursed, the proposed DMF @ 30% on the 12 SN,J wp_12675_2017

seigniorage charges also should be reimbursed, otherwise the same

would lead to miscarriage of justice.

Therefore, collection of DMF @ 30% on the seigniorage

charges from the running bills payable to the petitioner without any

assurance of repayment/reimbursement, is illegal and arbitrary.

Hence, this Writ Petition.

DISCUSSION AND CONCLUSION:

5. Clause no.19.1 of the agreement condition, is extracted hereunder:

"Seigniorage charges/fee for consumption of earth, moorum, sand and other minerals in works execution as fixed by the state government from where the minerals are drawn and payable to them as revised from time to time during currency of contract will be recovered by the Railway from the contractors, in "on account" and "final bills" and remitted to the State government, unless exemption obtained to the contrary or proof of payment of seigniorage charges submitted as indicated below:

Clause No. 19.3(a) of the agreement condition is extracted hereunder:

"For any subsequent increase or decrease in the rates of seigniorage charges, reimbursement / recovery will be effected to/from the contractor as per the following provisions.

a) For increase in the rates of seigniorage charges after the last date of submission of tender the increased amount will be recovered by the Railway from the contractors, in "on account" and "final bills" and remitted to the State Govt., on

13 SN,J wp_12675_2017

receipt of state Govt.'s order to that effect. However, the Railway shall reimburse the additional liability to the contractor, provided that the work executed falls in the original completion period of the work or in the extended period granted on administrative grounds i.e., under clause 17-A (i), (ii) or (iii) of IRSGCC.

Clause No.19.4: No additional amount will be paid or claim entertained on this account by the Railway. Contractor shall not have any claim whatsoever as a result of the increase in the rates of all other taxes, duties, or any form of levies etc., even if incurred on the supply/use of minerals indicated above."

6. On perusal of clause 19, 19.1, 19.3 (a), 19.4 of the

Agreement it is evident that as per condition No.19 of the

Agreement, the Department is entitled to deduct Seigniorage

Charges per cubic meter as per the rate prevailing on the date of

the bid. However, condition 19(3) (a) of the Agreement indicates

that if there is any increase of rates of seigniorage charges after

the last date of submission of tender, the enhanced amount will be

recovered by the respondents from the contractors "on account"

and "final bills" and remit to State Government on receipt of the

State Government's order to that effect. However, the Railway

Authorities shall reimburse the additional liability to the contractor

i.e., difference between seigniorage as on the date of bid and

enhanced seigniorage charges. Therefore, it is clear that the 14 SN,J wp_12675_2017

petitioner is not liable for any additional burden or additional

payment on the minerals consumed on the ground of change of

policy of the state Government increasing the seigniorage charges.

A bare perusal of the record indicates that the petitioner entered

into agreement for completion of the earthwork subject to only

deduction of seigniorage charges as per the rate prevailing on the

date of submitting tenders i.e., 14.09.2015. Therefore, this Court

opines that no other liability can be cast upon the petitioner on any

ground.

7. This court on perusal of the record and on perusal of Clause

19, 19.1 of the Agreement condition about Seignorage charges in

the Agreement, Clause No.19.3 (a) of the Agreement condition and

clause No.19.4 opines that the petitioner cannot be burdened by

the Railway Authorities for payment of DMF @30% which came into

existence after opening of tenders therefore it is the duty of the

Railway to reimburse the same. This Court opines that petitioner

cannot be burdened with additional taxes if any levied subsequent

to the date of opening/negotiations of the tenders and hence the

said amounts deducted shall be reimbursed to the contractor.

15 SN,J wp_12675_2017

8. The pleas put forth by the learned counsel appearing on

behalf of the respondents are untenable and hence rejected.

9. Taking into consideration:

(I) The aforesaid facts and circumstances of the case,

(II) Duly considering the condition 19.3(a) of the Agreement

(III) The writ petition is allowed as prayed for.

However, there shall be no order as to costs.

Miscellaneous petitions, if any, pending in this Writ Petition,

shall stand closed.

___________________ SUREPALLI NANDA, J

Date: 03.06.2024

Note : L.R. Copy to be marked.

B/o.Yvkr

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Media

 
 
Latestlaws Newsletter