Citation : 2024 Latest Caselaw 2738 Tel
Judgement Date : 18 July, 2024
THE HON'BLE THE CHIEF JUSTICE ALOK ARADHE
AND
THE HON'BLE SHRI JUSTICE ANIL KUMAR JUKANTI
WRIT APPEAL No.831 of 2024
JUDGMENT:
(Per the Hon'ble the Chief Justice Alok Aradhe)
Mr. B.Mayur Reddy, learned Senior Counsel
representing Mr. P.Sathwik Reddy, learned counsel for the
appellant.
Mr. R.Vinod Reddy, learned Standing Counsel for the
Transmission Corporation of Telangana Limited for the
respondents No.1 to 4.
Mr. S.V.Ramana, learned counsel for the respondent
No.5.
2. This intra court appeal is filed against the order
dated 12.03.2024 passed by the learned Single Judge by
which the writ petition preferred by the appellant, namely
W.P.No.15253 of 2023, has been dismissed on the ground
that the appellant has failed to prove its possession as well
as agreement of sale executed in its favour.
3. Facts giving rise to filing of the appeal briefly stated
are that the appellant is engaged in the business of real
estate. The respondents No.6 and 7 were the owners and
possessors of agricultural land bearing Survey Nos.302,
303, 304, 305, 306, 307, 308 and 310 measuring
Acs.42.22 guntas situated at Solipet Village (hereinafter
referred to as, "the subject land"). The appellant had
agreed to purchase the said land for a consideration of
Rs.1,17,12,050/-. In pursuance of the aforesaid
agreement, according to the appellant, it paid a sum of
Rs.64,00,000/- to the respondents No.6 and 7. However,
the appellant was informed that since the subject land has
been mortgaged, the sale deed would be executed once the
said land is redeemed.
4. According to the appellant, it is in possession of the
subject land since 19.05.2005. It was averred in the writ
petition that two buildings were situated at the subject
land and the electricity connection was provided to the
aforesaid buildings. It is the appellant's case that the
respondent No.5 in collusion with the respondents No.6
and 7 started claiming the subject land on the basis of sale
deeds executed in her favour. Thereupon, the appellant
instituted O.S.No.105 of 2021 in which an interim order of
injunction dated 02.11.2021 was granted restraining the
respondents from alienating or creating any third party
interest over the suit property.
5. The respondent No.5 made an application to the
respondents No.1 to 4 to transfer the electricity connection
in her favour which was initially rejected. The aforesaid
order of rejection was challenged by the respondent No.5 in
a writ petition, namely W.P.No.24519 of 2021, which was
disposed of by directing the Telangana State Southern
Power Distribution Company Limited (TGSPDCL) to
consider the documents submitted by the respondent No.5
and to pass appropriate orders. Thereafter, the authorities
of TGSPDCL informed the appellant about the
disconnection of electricity. Thereupon, the appellant filed
the writ petition in which the action of the TGSPDCL in
transferring the power supply in the name of the
respondent No.5 and in threatening to disconnect the
power supply was challenged. The learned Single Judge,
by an order dated 12.03.2024, dismissed the writ petition,
inter alia, on the ground that the appellant has not been
able to prove the agreement of sale executed in its favour
and has also not been able to prove the fact that it is in
possession of the subject land. Hence, this appeal.
6. Learned Senior Counsel for the appellant submitted
that the issue before the learned Single Judge was with
regard to the validity of the action of the TGSPDCL in
transferring the electricity connection in favour of the
respondent No.5 and in threatening the appellant with
disconnection of power supply. The learned Single Judge
has travelled beyond the scope of the writ petition and has
recorded a finding with regard to title and possession of the
appellant over the subject land, which is not permissible
under Article 226 of the Constitution of India.
7. On the other hand, learned Standing Counsel for the
respondents No.1 to 4 has submitted that the action for
supply of electricity and disconnection shall be made in
accordance with Clauses 5.1 and 5.2 of the General Terms
and Conditions of Supply.
8. On the other hand, learned counsel for the
respondent No.5 has supported the order passed by the
learned Single Judge.
9. Heard the learned counsel for the parties and
perused the record.
10. The dispute between the parties emanates from filing
an application seeking electricity connection by the
respondent No.5. Telangana State Electricity Regulatory
Commission has adopted General Terms and Conditions of
Supply approved by Andhra Pradesh Electricity Regulatory
Commission. The General Terms and Conditions of Supply
have been made in pursuance of Clause 21 of the
Distribution and Retail Supply Licence granted by the
Regulatory Commission and in accordance with the
provisions of the Electricity Act, 2003. Clause 5 of the
aforesaid General Terms and Conditions of Supply deals
with supply of electricity. Relevant Clauses 5.1 and 5.2
thereof are extracted below for the facility of reference.
"5. Supply of Electricity
5.1. Company's Duty to Supply
The Company shall, on an application by the owner or occupier of any Premises, located in his area of supply, give supply of electricity to such Premises in accordance with Section 43 of the Act and the APERC ('Licensees' duty for supply of electricity on request) Regulation, 2004 (No.3 of 2004) as well as the APERC ('Licensees' Standards of Performance) Regulation, 2004 (No.7 of 2004). The applicant must however ensure compliance with the procedure specified in the GTCS.
5.2. Requisition for Supply
5.2.1. Requisition for supply for a new connection or additional load must be submitted in the prescribed format of Application for supply of Electricity at Low Tension (LT) (Appendix I) and the Application for supply of Electricity at High Tension (HT) (Appendix II) as the case may be. The Company will make available the prescribed form free of cost at the offices specified by the Company and will also provide the same on the Company's Internet website for free downloading. Photocopies of a blank application form duly filled in, shall also be accepted by the Company.
Any assistance or information required in filling up the application form will be given to the applicant at the offices specified in the Designated Officers' Notification.
5.2.2. The requisition shall be made by the owner or occupier of the premises for which supply is required. The application form complete in all respects and accompanied with the undertaking and prescribed fees, charges and security, shall be submitted at the office of the Officer specified in the Designated Officers Notification. The Company shall verify the application and the enclosed documents at the time of receipt of application, and shall issue a written acknowledgement.
5.2.3 An applicant who is not the owner of the premises he occupies and intending to avail of supply shall submit an Indemnity Bond drawn by the owner of the premises in favour of the company whereby the owner of the premises undertakes to indemnify the company for any loss caused to the company by the applicant (who is the tenant/ occupant of the Premises) arising out of the release of service to the tenant/ occupant. Otherwise he shall be required to pay three times the normal security deposit apart from providing proof of his being in lawful occupation of the premises.
5.2.4. Where the consumer's premises has no frontage on a street and the supply line from the company mains has to go upon, over or under the adjoining premises of any other person (and whether or not the adjoining Premises owned jointly by the consumer and such other person), the consumer shall arrange at his own expense for any necessary way-leave, license or sanction. The Company shall not be bound to afford supply until the way leave or sanction is granted. Any extra expenses incurred in placing the supply line in accordance with the terms of the way leave, license or sanction shall be borne by
the consumer. In the event of the way-leave, license or sanction being cancelled or withdrawn, the consumer shall, at his own cost, arrange for any diversion of the service line or the provision of any new service line thus rendered necessary.
5.2.5. It shall not be incumbent on the Company to ascertain the legality or adequacy of way-leave, license or sanction obtained by the consumer.
5.2.6. A consumer requiring supply for industrial or commercial purposes for new or additional loads shall obtain the necessary license or permission or no-objection certificate from the local authority or any other competent authority as might be required under the statute.
5.2.7. After receipt of the complete application form along with required supporting documentation and charges, the Company takes action to release supply within the time frames prescribed in the APERC ('Licensees' duty for supply of electricity on request) Regulation, 2004 (No.3 of 2004) as well as the APERC ('Licensees' Standards of Performance) Regulation, 2004 (No.7 of 2004) issued by the Commission."
11. The application submitted by any party has to be
dealt with in accordance with the relevant clauses of the
General Terms and Conditions of Supply. The learned
Single Judge has transgressed his jurisdiction in recording
a finding of fact about the possession of the appellant and
with regard to the agreement executed in favour of the
appellant.
12. Therefore, the respondents No.1 to 4 are directed to
take an action in accordance with Clauses 5.1 and 5.2 of
the General Terms and Conditions of Supply on the
application submitted by the respondent No.5 without
being influenced by the observations contained in the order
of the learned Single Judge dated 12.03.2024. Needless to
state that it would be open for the appellant to take
recourse to such remedy as may be available to it in
accordance with law. It is also clarified that the findings
recorded by the learned Single Judge with regard to
possession and execution of the agreement shall not be an
impediment to the appellant in case the appellant decides
to invoke the remedy provided to it by law. The order
passed by the learned Single Judge is set aside.
13. In the result, the appeal is disposed of.
Miscellaneous applications pending, if any, shall
stand closed. However, there shall be no order as to costs.
______________________________________ ALOK ARADHE, CJ
______________________________________ ANIL KUMAR JUKANTI, J
18.07.2024 vs
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!