Monday, 20, May, 2024
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Akshra Townships Private Limited vs L.Renuka
2024 Latest Caselaw 3 Tel

Citation : 2024 Latest Caselaw 3 Tel
Judgement Date : 2 January, 2024

Telangana High Court

Akshra Townships Private Limited vs L.Renuka on 2 January, 2024

Author: B. Vijaysen Reddy

Bench: B. Vijaysen Reddy

         THE HON'BLE SRI JUSTICE B. VIJAYSEN REDDY

           ARBITRATION APPLICATION No.61 of 2021

ORDER:

This application is filed under Section 11(6) of the Arbitration

and Conciliation Act, 1996 (for short 'the Act') to appoint an

arbitrator to resolve the disputes and claims between the applicant

and the respondents in terms of Clause 12 of the Development

Agreement dated 01.01.2018 and Clause 13 of the Development

Agreement dated 22.12.2018 entered into between the parties.

2. It is stated that the applicant is a company registered under

the Companies Act and engaged in real estate business, having

registered office at Warangal and branch offices in different areas.

One of its branch offices is in Siricilla. The applicant executed

several projects and completed ventures under the name and style

of "Akshara Township Private Limited".

3. It is stated that the respondent Nos.1 to 3, having come to

know about the successful projects of the applicant, approached the

applicant and made a proposal to give the land admeasuring

Ac.36.00 situated at Vemulavada for development to the applicant.

It was represented by the respondents that the owners of the said

land, Sri Govrineni Rajeshwar Rao and others and others, expressed

their interest to give their land for development and the 2

respondents No.1 to 3 had been dealing with the said owners.

The respondent No.1 is the wife of respondent No.3 and the

respondent No.3 had been dealing with the affairs of the

respondent No.1.

4. It is stated that with the above understanding,

the respondent No.2, at the first instance, with the oral consent of

the respondents No.1 and 3, entered into Preliminary Agreement

cum Memorandum of Understanding on 09.12.2017 with the

applicant in respect of the land admeasuring Ac.36.00 situated at

Vemulawada for its development i.e. conversion into house site

plots. In furtherance of the above Memorandum of Understanding

dated 09.12.2017, a separate document styled as "Preliminary

Agreement for Development of Property" dated 01.01.2018 was

executed between the respondents No.1 and 2 and the applicant to

develop the land admeasuring Ac.35.32 guntas (land available on

spot measurement) situated at Tippapur village, Vemulawada Urban

Mandal, Rajanna Siricilla District Telangana. As per the terms of the

Preliminary Agreement dated 01.01.2018, the respondents No.1

and 2 agreed to get the above mentioned property into registered

in their names and later, to execute a registered Development

Agreement with the applicant. The applicant and the respondents

No.1 to 3 have also finalized the proposed Approved Layout Plan of

the property.

3

5. It is submitted that the respondents No.1 to 3 informed the

applicant that the pattedars i.e. Govrineni Rajeshwer Rao and

others executed registered Sale Deed vide Document

No.8056/2018 dated 01.11.2018 in respect of land to an extent of

Ac.12.00 guntas in Sy.No.255/9, Sy.No.273/C/అ, Sy.No.273/C/ఆ,

Sy.No.274/1/A, Sy.No.274/1/B1 and Sy.No.274/1/B2 situated at

Tippapur Village, in favour of the respondents No.2 to 5. It was

informed to the applicant that the pattedars would execute another

registered sale deed in favour of the respondents in near future.

That believing the representation of the respondents, the applicant

sent a Draft Development Deed to the respondent No.3, which was

approved, finalized and registered as Development agreement cum

Irrevocable General Power of Attorney executed by the respondents

No.2 to 5 vide document No.9323/2018 dated 22.12.2018 in

respect of Ac.12.00 guntas at Vemulawada, in favour of the

applicant.

6. It is submitted that as per the terms of the development

agreement dated 22.12.2018, if the applicant fails to complete the

work within the stipulated time, the respondents No.2 to 5 have to

complete the work and the balance amount will be paid to the

applicant by them. Further, it was mentioned in page No.7 at para

No.4 of the development agreement dated 22.12.2018 that the

respondents No.2 to 5 shall provide road access to the schedule 4

property covered therein from out of the remaining land

admeasuring Ac.23-22 guntas to enable the applicant to complete

the project. It was made clear that unless and until the respondents

No.2 to 5 carve out a road, the applicant cannot complete its

project as envisaged in development agreement dated 22.12.2018.

7. It is submitted that the applicant has been ready and willing

to perform its obligations covered under Preliminary Agreement

dated 01.01.2018 and development agreement dated 22.12.2018.

But the respondents No.1 to 5, on one pretext or the other,

have failed to perform their obligations in providing road access to

the schedule property covered under development agreement dated

22.12.2018. The applicant issued several e-mails to the respondent

No.3 to provide road access but there is no response from the

respondent No.3.

8. It is submitted that while the matter stood thus,

the applicant came to know that the original pattedars/owners have

executed different sale deeds to an extent Ac.23.22 guntas in the

following manner:

A. The Registered Sale Deed vide Document No. 2906/2019 dated : 29-03-2019 to an extent of Ac 8.00 guntas situated at Vemulawada, in which the respondents No 3 and respondent No 5 are shown as the purchasers. B. The Registered Sale Deed vide document number 7110/2019 dated : 03-08-2019 to an extent of Ac 3.33 5

guntas situated at Vemulawada, in which the respondents No 3 and Respondent No. 9 are shown as the purchasers.

C. The Registered Sale Deed vide document number 7111/2019 dated : 03-08-2019 to an extent of Ac 11.39 guntas situated at Vemulawada, in which the respondents No 3,Respondent No.6 to 8 were shown as the purchasers.

9. It is stated that thereafter, the respondents No.3, 5, 7 and 8

have executed a registered Development Agreement cum General

Power of Attorney to M/s NRR Infra i.e. respondents No.5 and 10

for development of land to an extent of Ac.19.32 guntas vide

document No.7766/2019 dated 23.08.2019, which is breach of

development agreement dated 01.01.2018 and 22-12-2018.

The execution of the development agreement in favour of the

respondents No.5 and 10 would hamper the project of development

of land i.e. conversion to house sites for total extent of Ac 35.32

guntas.

10. It is stated that the respondents No.2 to 5 have issued a

notice to the applicant on 14.12.2019 alleging non-completion of

the project and invoked clause 13 of agreement dated 22.12.2018

and sought consent for appointment of sole arbitrator.

On 05.02.2020, the applicant sent a reply to the respondents No.2

to 5 by not accepting the name suggested by the respondents No. 2

to 5 and suggested the name of another person to act as sole 6

arbitrator to resolve dispute and differences. Later, on 04.12.2020,

the applicant sent a notice to the respondents seeking consent of

named Arbitrator invoking the arbitration clause to resolve disputes

and other differences between the applicant and the respondents.

The applicant had also invoked Section 9 of Act for interim relief as

the respondents did not come forward to appoint an arbitrator.

In the circumstances, the instant application is filed for

appointment of arbitrator as per clause 12 of the development

agreement dated 01.01.2018 and clause 13 of the development

agreement dated 22.12.2018.

11. In the counter filed by the respondents No.1 to 3, inter alia,

it is stated that the agreement dated 01.01.2018 had no nexus with

the preliminary agreement dated 09.02.2017. It was denied that

the respondents No.1 to 3 introduced themselves and proposed for

development of land claiming that its owners, Govrineni Rajeshwer

Rao and others, intended to develop the same and the respondent

No.3 is dealing with the said owners. As per clause 19 of the

development agreement dated 22.12.2018, the said agreement

supersedes all other agreements and understandings between the

parties or any of them, as such, the parties to the preliminary

agreement, more particularly, the applicant was conscious of the

fact that the preliminary agreement dated 01.01.2018 was

superseded by development agreement dated 22.12.2018 and 7

consequently, the preliminary agreement would no longer be valid.

As such, invocation of arbitration clause under the superseded

preliminary agreement is invalid. The applicant did not initiate any

steps for developing the schedule property. The agreement of sale

dated 22.10.2017 entered into between the owners of the land and

the respondents No.1 and 2 could not be fructified for certain

unforeseen circumstances.

12. It is admitted that respondents No.2 to 5 have issued notices

dated 14.12.2019 invoking clause 13 of the development

agreement dated 22.12.2018 requesting the applicant to give

consent to the name suggested by them to be appointed as an

arbitrator to adjudicate the disputes between the parties and that

and that the applicant gave reply on 05.02.2020 refusing to give

consent and in turn, proposed to appoint one Md. Habeeb Ali,

Advocate, as an arbitrator. It is submitted that the present

application filed seeking appointment of arbitrator under two

different agreements, which are unconnected, is liable to be

rejected.

13. The respondent No.2 adopted the counter of respondents

No.1 and 3. In the counter filed by the respondents No.4 and 5, it is

stated that they are not parties to the agreement dated 01.01.2018

and there was no breach on the part of the respondents No.4 and 5 8

in performing the terms of the agreement dated 22.12.2018.

In the counter filed by the respondents No.6, 8 and 9, it is stated

that they are unnecessarily arraigned as respondents in the instant

application and they are not aware of the purported agreements

dated 01.01.2018 and 22.12.2018. In the counter of respondents

No.7 and 10, it is stated that they are not parties to the

agreements dated 01.01.2018 and 22.12.2018 and they are not

binding on them.

14. Mr. Alladi Ravinder, learned senior counsel appearing for the

applicant, submitted that the preliminary agreement dated

01.01.2018 and development agreement dated 22.12.2018 are

binding on the respondents. The respondents No.2 to 5 are parties

to the development agreement dated 22.12.2018 and a refundable

deposit of Rs.1.5 crores was deposited at the time of preliminary

agreement dated 01.01.2018. The preliminary agreement was

entered in favour of the applicant in respect of Ac.32.35 guntas of

land with an understanding that the respondents No.1 and 2 would

complete the sale transactions and executed development

agreements in favour of the applicant from time to time. As sale

deed was finalized for an extent of Ac.12.00 guntas,

the development agreement dated 22.12.2018 was entered into for

Ac.12.00 guntas by the respondents No.2 and 3. The respondent 9

No.3 is the husband of the respondent No.1 and had been dealing

on her behalf.

15. Mr. M. Srinivas Reddy, learned counsel appearing for the

respondents No.1 and 3, submitted that the respondent No.3 is not

a party to the agreement dated 01.01.2018 and it was entered into

only by the respondents No.1 and 2. The development agreement

dated 22.12.2018 was signed by four parties (respondents No.2 to

5) and the respondent No.2 is common to the two agreements.

However, the remaining parties are not signatories in two

agreements. As per clause 19 of the development agreement dated

22.12.2018, the agreement dated 01.01.2018 stood novated.

16. Learned counsel for the respondents No.4 and 5, while

reiterating the submissions made by the respondents No.1 and 3,

submitted that the respondents No.4 and 5 are not parties to the

agreement dated 01.01.2018. The respondents No.7 and 10 are

subsequent purchasers and developers of different extents of land.

Further, the respondents No.6, 8 and 9 are not parties to both the

agreements.

17. In reply to the arguments of the learned counsel for the

respondents, learned senior counsel for the petitioner submitted

that the agreement dated 01.01.2018 is the main agreement.

The development agreement dated 22.12.2018 is made in 10

pursuance of the agreement dated 01.01.2018. Both the

agreements are interconnected. By applying the doctrine of group

companies, both the agreements are binding on the respondents.

The respondents No.4 and 5 consented for appointment of

arbitrator and consented for initiating the arbitration proceedings.

18. Heard learned senior counsel for the petitioner and learned

counsel for the respondents. Perused the material on record.

19. Clause 12 of the preliminary agreement dated 01.01.2018

provides for arbitration in case of dispute on differences arising

between the parties. The respondents No.1 and 2 have entered into

preliminary agreement dated 01.01.2018 with the applicant in

respect of an extent of Ac.32.35 guntas of land situated in

Sy.No.251 (Ac.7.31 guntas), Sy.No.253 (Ac.8.22 guntas),

Sy.No.254 (Ac.6.28 guntas), Sy.No.255 (Ac.2.23 guntas),

Sy.No.273 (Ac.4.16 guntas) and Sy.No.274 (Ac.5.32 guntas) of

Tippapur Village, Vemulawada Urban Mandal, Rajanna Sircilla

District. As per Clause B of the said agreement, the respondents

No.1 and 2 represented that they are going to get the sale deeds

registered in their favour from the site owners of the schedule

property. It is not in dispute that in furtherance of the preliminary

agreement dated 01.01.2018, the development agreement dated

22.12.2018 was entered into for an extent of Ac.12.00 guntas, 11

which forms part of Ac.32.35 guntas covered under preliminary

agreement dated 01.01.2018. The development agreement dated

22.12.2018 also contains arbitration at Clause 13 wherein the

parties have agreed to refer the matter to a sole arbitrator in the

event of disputes or difference arisen between them.

20. The contention of the learned counsel appearing for the

respondents is that novation of the agreement dated 01.01.2018 in

terms of the clause 19 of the development agreement dated

22.12.2018 cannot be decided in the instant application filed under

Section 11(6) of the Act. Whether there is novation of earlier

agreement dated 01.02.2018 or not, is a matter to be adjudicated

by the arbitrator. In the instant application, for appointment of an

arbitrator, this Court would be only concerned with prima facie

claims of the parties and would see whether there is a valid

agreement containing arbitrator clause and if disputes have arisen

between the parties, which need to be referred to an arbitrator.

Though respondents No.6 to 10 are not parties to the agreement

dated 01.01.2018, the said point would not fall for consideration in

this application. The respondents No.6 to 10 claim interest in the

subject property through the respondents No.1 to 5 and whether

the agreement is binding on the respondents No.6 to 10 is a matter

to be looked into by the arbitrator.

12

21. The judgment of the Supreme Court in YOUNG ACHIEVERS

v. IMS LEARNING RESOURCES PRIVATE LIMITED 1, relied upon

by the learned counsel for the respondents No.1 and 3, is not

applicable to the facts of the present case. In the said case, it was

held that new agreement dated 01.02.2011 was entered into, which

does not contain arbitration clause. The Supreme Court held that

the agreements dated 01.04.2007 and 01.04.2010 containing

arbitration clauses could not survive as they have been superseded

by the new agreement dated 01.02.2011. The facts of the present

case are totally different and the transaction between the parties is

relating to immovable property. The first agreement was entered

into on 01.01.2018 and followed by development agreement dated

22.12.2018 and both the agreements are interconnected and both

the agreements contain arbitration clauses. Thus, the contention of

the learned counsel for the respondents that the arbitration clauses

in both the agreements are not binding on the respondents is not

sustainable.

22. In view of the above, the arbitration application is allowed.

Sir Justice G.V. Seethapathy, Former Judge of the erstwhile High

Court of Andhra Pradesh, is appointed as arbitrator to adjudicate

the claims and disputes between the parties and to pass an award

1 (2013) 10 SCC 535 13

in accordance with law. The parties are at liberty to raise all factual

and legal grounds in support of their respective claims.

23. The learned Arbitrator is entitled to fees as per the rates

specified in the Fourth Schedule to the Act of 1996, inserted by

Act 3 of 2016 with effect from 23.10.2015, which shall be borne by

both parties in equal shares.

The miscellaneous petitions pending, if any, shall stand

closed. There shall be no order as to costs.

____________________ B. VIJAYSEN REDDY, J January 2, 2024 DSK

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 
 
Latestlaws Newsletter
 
 
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2024

 

LatestLaws.com presents 'Lexidem Online Internship, 2024', Apply Now!

 
 
 
 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

Publish Your Article

Campus Ambassador

Media Partner

Campus Buzz