Monday, 20, May, 2024
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

East Hyderabad Expressway Limited vs The Hyderabad Metropolitan ...
2024 Latest Caselaw 244 Tel

Citation : 2024 Latest Caselaw 244 Tel
Judgement Date : 22 January, 2024

Telangana High Court

East Hyderabad Expressway Limited vs The Hyderabad Metropolitan ... on 22 January, 2024

         HIGH COURT FOR THE STATE OF TELANGANA

                               *****

           ARBITRATION APPLICATION No.170 OF 2022

Between:
East Hyderabad Expressway Limited
Through its Authorised representative
Mr. Shaik Masthan Bovine.
                                                     ... Applicant

                               AND

The Hyderabad Metropolitan Development Authority
previously known as Hyderabad Urban Development Authority
Through its Authorised Representative
and another.
                                                 ... Respondents


! Counsel for Applicant       : Sri S. Ram Babu.

^ Counsel for Respondents     : Sri Y. Rama Rao,
                               learned Standing Counsel for HMDA
> HEAD NOTE:

? Cases referred:

  1) (2017) 9 SCC 729

  2)   (2018) 17 SCC 95

  3) (2008) 10 SCC 240

  4) (2009) 8 SCC 520

  5) (2014) 9 SCC 288

  6) (2017) 14 SCC 187
                                     2



     THE HONOURABLE SRI JUSTICE C.V. BHASKAR REDDY

            ARBITRATION APPLICATION No.170 OF 2022

ORDER:

This application, under Section 11(6)(a) of the Arbitration and

Conciliation Act, 1996 (for short "the Act") is filed by the applicant

seeking to intervene into the matter and appoint a nominee

Arbitrator of Respondents to resolve the dispute.

2. The applicant is a Company incorporated under the

provisions of Companies Act, 1956. The respondent No.1 is a

statutory body constituted under the provisions of Andhra Pradesh

Urban Areas (Development) Act, 1975 and respondent No.2 is a

company registered under the Companies Act, 1956. It is stated

that respondent No.1 invited proposals under a single stage process

from bidders and prescribed commercial terms and conditions for

selection of a successful bidder vide Notice Inviting Proposal

No.HGC/CGM(T)/ORR/6/2006-07 dated 22.02.2007 inter alia for

"Design, Construction, Development, Finance, Operation and

Maintenance of eight lane access controlled expressway under

Phase IIA programme as an extension of Phase I of ORR to

Hyderabad city, for the package from Pedda Amberpet to Bongulur

from 95.00 KM to 108.00 KM on Build, Operation and Transfer

(BOT) (Annuity) Basis" (for short "Project"). In response to the same, 3

a consortium of (i) M/s. IL & FS Transportation Networks Limited

("ITNL") and (ii) M/s.KMC Constructions Limited, was constituted

with ITNL as its lead member for undertaking the project work. The

said consortium submitted its Bid for the Project and the same was

accepted by the respondents and a letter of acceptance was issued

by the respondent No.1 vide its letter dated 14.06.2007. A

Concession Agreement dated 03.08.2007 was executed between the

applicant and the respondents, containing the detailed terms and

conditions in relation to the Project. The said Agreement was

subsequently amended vide Supplementary Agreement dated

05.01.2022, whereby Clause 39.2 (arbitration clause) was added

with a view to refer the disputes in question to Arbitration. Clause

39.2 (as amended) reads as follows:

"39.2.1 Any Dispute, which is not resolved amicably as provided in Clause 39.1 above shall be finally decided by reference to Arbitration by a Board of Arbitrators, appointed pursuant to Clause 39.2.2. Such arbitration shall be held in accordance with and shall be subject to the provisions of the Arbitration and Conciliation Act, 1996 and amendments thereto.

39.2.2 Arbitration shall be conducted by a panel of three Arbitrators each party shall appoint one Arbitrator and the two Arbitrators shall mutually appoint the Presiding Arbitrator. The Arbitration process shall be governed by the Arbitration and Conciliation Act, 1996, and amendments thereto.

39.2.3 The arbitrators shall issue a reasoned Award.

39.2.4 The seat of such arbitration shall be at Hyderabad, India.

39.2.5 The language of arbitration shall be English.

4

39.2.6 The arbitration fee shall be governed by the Fourth Schedule to the Arbitration & Conciliation Act, 1996 and amendments thereto, with a maximum ceiling of Rs. 30 Lakhs payable to each arbitrator, maximum of Rs. 90 Lakhs for entire three members Tribunal. The above fee shall be shared in equal proportion by both the Concessionaire and the Employer"

3. It is further case of the applicant that "Project Completion

Schedule" had to be met not later than 30 months from the

Commencement Date, and the period ending on 30th month from

the Commencement Date was referred to as the "Schedule Project

Completion Date" ("SPCD"), which, in the present case, had to fall

on or before 09.06.2010. The said condition was subject to the

Respondents being able to handover Right of Way ("ROW") for the

Site to the Applicant in a timely manner as stipulated under Article

13.5 of the Concession Agreement dated 03.08.2007. It is further

case of the applicant that respondents materially failed to handover

the Site as stipulated under the Concession Agreement dated

03.08.2007. The abnormal delay in handing over the Site/Right of

Way by the respondents severely affected the completion of the

Project within the stipulated timeline. According to the applicant,

Schedule G of the Concession Agreement dated 03.08.2007, which

provides for an Annuity Payment Schedule, entitles the Applicant

for 25 Annuities, spread across 12.5 years of the Operations Period.

The first and second Annuity Payment Dates, as prescribed in the

said Schedule G, were 27.09.2010 and 26.03.2011. Notably,

however, R-2, vide its letter dated 05.11.2011 had revised Schedule 5

G, given the belated declaration of the Commencement Date in the

Project. Consequent to the said revision, the first and second

Annuity Payment Dates stood amended to 09.12.2010 and

08.06.2011, respectively. It is the specific case of applicant that

consequent to delay in handing over the land by the respondents,

construction works of the Project witnessed delays and the

Applicant was, as such, entitled to an extension of time under the

Concession Agreement dt.3.8.2007. It is stated that the

correspondence exchanged between the parties reveal that the

Applicant made numerous requests to the respondents seeking

extension of time. It is further case of the applicant that even after

categorical recommendations of the Independent Consultant, the

respondents never intimated an extension of time to the applicant.

The applicant has referred various correspondences between the

applicant and the respondents from 08.01.2009 to 23.06.2017. The

respondent No.2 has issued letter dated 23.01.2018 to the

applicant's banker directing the bank to release a sum of Rs.29.39

crores to respondent No.2, failing which threatened to recover the

said amount from the applicant's 15th Annuity Payments, which was

payable on 09.12.2017. It is further case of the applicant that in the

Proceedings dated 06.03.2018, the respondent No.2 has specifically

recorded that I.C verified the Invoice and recommended for payment

of Rs.33.3 crores, but the respondent No.2 illegally and in contrary 6

to the express provisions of the Concession Agreement dated

3.8.2007 deducted Rs.29.39 crores and accorded for payment of

Rs.2,99,35,000/- as opposed to Rs.33.30 crores. It is the specific

case of the applicant that it has issued a letter dated 16.05.2018 to

the respondent No.2, requesting not to recover the said amount and

pleaded the respondent to release the 15th Annuity, in entirety,

besides the Bonus and the 1st Annuity which had been due since

long time. Despite the applicant's request, the respondents went

ahead and illegally recovered a sum of Rs.29.39 crores from 15th

Annuity. It is the case of applicant that correspondence with the

respondents from mid-2018 onwards, clearly establish that both

parties were in active consideration of amicably resolving the issues

pertaining to release of Bonus, 1st Annuity, interest on delayed

release of bonus, as well as reimbursement of illegal recoveries from

the 15th annuity. It is the case of the applicant that even after

several meetings and elaborate discussions, the respondents have

not accepted to pay the differential amount as per the Agreement

and therefore, the applicant was constrained to issue a letter dated

05.10.2020 to the respondents reiterating the demand and for

amicable resolution of the matter. It is further case of the applicant

that acting on the said representation, a meeting was held on

06.11.2020, wherein respondents admitted that the issue of Bonus

and X-factor was being considered by them and that the matter 7

would be discussed with the Metropolitan Commissioner of

respondent No.1. It is further case of the applicant that in the said

meeting held on 06.11.2020, the respondents actively considered

the applicant's claim for Bonus. Despite so, the respondents did

not release the amounts to the applicant. Thereafter, the applicant

issued another letter dated 23.06.2021 to the respondents

requesting for amicable resolution of the claims i.e, a) bonus,

b)reimbursement of monies illegally deducted by the respondents

from the 15th Annuity c) interest on delayed payment of Annuities

and d) release of certain monies withheld by the respondents from

the 1st Annuity. It is the specific case of the applicant that

respondents vide letter dated 13.08.2021 had taken U-turn from

their commitments and assurances given in the earlier meetings

held on various dates with regard to applicant's claims. It is the

case of the applicant that applicant accepted the proposal of

respondent No.2 and signed the supplementary agreement dated

05.01.2022 exclusively for amendment of Article 39 of Concession

Agreement, wherein the parties shall choose the arbitrators from the

Indian Council of Arbitration (ICA) panel in a time bound manner

failing which the ICA will nominate the arbitrators. Since the

respondents have not come forward to settle the disputes, the

applicant issued a letter dated 25.03.2022 to the respondents

invoking the arbitration clause between the parties and nominated 8

Mr.Justice Devinder Gupta, Former Chief Justice of Andhra

Pradesh High Court, as its nominee Arbitrator and requested the

respondents to nominate an arbitrator on their behalf within a

period of 15 days, so that the Arbitral Tribunal may be constituted

expeditiously. But the respondents issued a reply letter dated

23.04.2022 disagreeing with the applicant's request stating that the

same is barred by limitation. Hence the present arbitration

application under Section 11(6) of the Act is filed by the applicant

seeking to appoint a nominee Arbitrator on behalf of respondents.

4. A counter affidavit has been filed by the respondents, wherein

inter alia it is stated that the claims raised by the applicant in the

notice invoking clause 39.2 of the Concession Agreement is barred

by limitation. It is submitted that Clause 39 of the Concession

Agreement provides mechanism for Dispute Resolution between the

parties. The said Clause states several steps that need to be done

before proceeding with arbitration. Therefore, the Applicant has to

meet the requirements as stated under Clause 39.1 of the

Concession Agreement and shall mandatorily follow the procedure

as agreed to, by the Parties, i.e, Applicant and the Respondents

herein and non-compliance of such pre-mandated mechanism will

lead to pre-mature Application. It is stated that in the present

application, the Applicant only mentioned that the parties were in

active consideration of amicably resolving the disputes which arose 9

in the years 2010, 2011 and further in 2018, but has not disclosed

whether the pre-mandated resolution mechanism was followed or

not. The Applicant failed to adhere to the terms and conditions of

the agreement and also failed to follow the dispute resolution

mechanism contemplated under the agreement, which is evident

from the letter dated 13.08.2021 issued by the Respondents to the

Applicant. In fact, the correspondence also mentions that the claims

raised by the Applicant are barred by limitation. It is further

submitted that the Applicant did not mention the clause under

which it was seeking amicable resolution and failed to refer the

disputes to the Independent Consultant. There is no mention about

the disputes being referred to the Vice-Chairman of HUDA and the

Chairman of the Board or Directors of the Concessionaire. The

applicant had raised claims which are merely illustrative and

indicative and therefore such vague claims cannot be referred to

Arbitration for the reason that any disputes raised should be

specific and notified to the other side. It is further stated in the

counter affidavit that the Applicant approached this Court without

adhering to the terms and conditions of the agreement and without

complying the dispute resolution mechanism contemplated under

Clause 39 of the Agreement and therefore, the present Application

deserves to be dismissed in limine.

10

5. Considered the submissions of the respective counsel and

perused the record.

6. It is well settled principle of law that while considering the

application filed under Section 11(6) of the Arbitration and

Conciliation Act, 1996, this Court has to see whether there is an

arbitral dispute between the parties and whether the agreement

entered between the parties contains an arbitration clause or not.

Further, it is also well-settled law that while deciding the question of

appointment of arbitrator, the Court should not touch the merits of

the case as it may cause prejudice to the case of the parties.

7. In Duro Felguera, S.A. v. Gangavaram Port Ltd., 1 the

Hon'ble Supreme Court, at para 59, has held as under:

"The scope of the power under Section 11(6) of the 1996 Act was considerably wide in view of the decisions in SBP and Co. [SBP and Co. v. Patel Engg. Ltd., (2005) 8 SCC 618] and Boghara Polyfab [National Insurance Co.Ltd. v. Boghara Polyfab (P) Ltd., (2009) 1 SCC 267 : (2009) 1 SCC (Civ) 117]. This position continued till the amendment brought about in 2015. After the amendment, all that the courts need to see is whether an arbitration agreement exists nothing more, nothing less. The legislative policy and purpose is essentially to minimise the Court's intervention at the stage of appointing the arbitrator and this intention as incorporated in Section 11(6-A) ought to be respected."

8. In IBI Consultancy (India) (P) Ltd. v. DSC Ltd. 2, the Hon'ble

Supreme Court while dealing with the Arbitration Application filed

1 (2017) 9 SCC 729 2 (2018) 17 SCC 95 11

under Section 11(6) read with Section 11(9) of the Arbitration and

Conciliation Act, 1996 for appointment of arbitrator to adjudicate

the disputes that have arisen between the parties therein in

connection with the contracts in question, has held, at Para 8, as

under:

8. The first and the foremost thing is the existence of an arbitration agreement between the parties to the petition under Section 11 of the Act and the existence of dispute(s) to be referred to arbitrator is condition precedent for appointing an arbitrator under Section 11 of the Act. It is also a well-settled law that while deciding the question of appointment of arbitrator, the court has not to touch the merits of the case as it may cause prejudice to the case of the parties. The scope under Section 11(6) read with Section 11(9) is very limited to the extent of appointment of arbitrator. This Court has to see whether there exists an arbitration agreement between the parties and if the answer is in the affirmative then whether the applicant has made out a case for the appointment of arbitrator.

9. In Northern Railway Administration, Ministry of Railway,

New Delhi v. Patel Engineering Company Limited 3, a three-

Judge Bench of Hon'ble Supreme Court held that the Hon'ble Chief

Justice or the designated Judge, if required, is free to deviate from

the arbitration clause and nominate an independent person; but

while doing so, due regard shall be given to the qualifications

prescribed in the arbitration agreement, as required under Section

11(8) of the Arbitration and Conciliation Act.

3 (2008) 10 SCC 240 12

10. In Indian Oil Corporation and others v. Raja Transport

Private Limited 4 the Hon'ble Supreme Court has elaborately

discussed the scope of Section 11 of the Act and held that if the

circumstances so warrant, the Hon'ble Chief Justice or the

designated Judge can ignore the specified arbitrator as stipulated in

the agreement. Paras 45 and 48, to the extent relevant, reads as

follows:

"45. If the arbitration agreement provides for arbitration by a named arbitrator, the courts should normally give effect to the provisions of the arbitration agreement. But as clarified by Northern Railway Admn., where there is material to create a reasonable apprehension that the person mentioned in the arbitration agreement as the arbitrator is not likely to act independently or impartially, or if the named person is not available, then the Chief Justice or his designate may, after recording reasons for not following the agreed procedure of referring the dispute to the named arbitrator, appoint an independent arbitrator in accordance with Section 11(8) of the Act. In other words, referring the disputes to the named arbitrator shall be the rule. The Chief Justice or his designate will have to merely reiterate the arbitration agreement by referring the parties to the named arbitrator or named Arbitral Tribunal. Ignoring the named arbitrator/Arbitral Tribunal and nominating an independent arbitrator shall be the exception to the rule, to be resorted for valid reasons.

xxxx xxxx xxxx xxxx xxxx

48. In the light of the above discussion, the scope of Section 11 of the Act containing the scheme of appointment of arbitrators may be summarised thus:

(i) Where the agreement provides for arbitration with three arbitrators (each party to appoint one arbitrator and the two

4 (2009) 8 SCC 520 13

appointed arbitrators to appoint a third arbitrator), in the event of a party failing to appoint an arbitrator within 30 days from the receipt of a request from the other party (or the two nominated arbitrators failing to agree on the third arbitrator within 30 days from the date of the appointment), the Chief Justice or his designate will exercise power under sub-section (4) of Section 11 of the Act.

(ii) Where the agreement provides for arbitration by a sole arbitrator and the parties have not agreed upon any appointment procedure, the Chief Justice or his designate will exercise power under sub-section (5) of Section 11, if the parties fail to agree on the arbitration within thirty days from the receipt of a request by a party from the other party.

(iii) Where the arbitration agreement specifies the appointment procedure, then irrespective of whether the arbitration is by a sole arbitrator or by a three-member Tribunal, the Chief Justice or his designate will exercise power under sub-section (6) of Section 11, if a party fails to act as required under the agreed procedure (or the parties or the two appointed arbitrators fail to reach an agreement expected of them under the agreed procedure or any person/institution fails to perform any function entrusted to him/it under that procedure).

(iv) While failure of the other party to act within 30 days will furnish a cause of action to the party seeking arbitration to approach the Chief Justice or his designate in cases falling under sub-sections (4) and (5), such a time-bound requirement is not found in sub-section (6) of Section 11. The failure to act as per the agreed procedure within the time-limit prescribed by the arbitration agreement, or in the absence of any prescribed time-limit, within a reasonable time, will enable the aggrieved party to file a petition under Section 11(6) of the Act.

(v) Where the appointment procedure has been agreed between the parties, but the cause of action for invoking the jurisdiction of the Chief Justice or his designate under clauses (a), (b) or (c) of sub-

section (6) has not arisen, then the question of the Chief Justice or 14

his designate exercising power under sub-section (6) does not arise. The condition precedent for approaching the Chief Justice or his designate for taking necessary measures under sub-section (6) is that

(i) a party failing to act as required under the agreed appointment procedure; or

(ii) the parties (or the two appointed arbitrators) failing to reach an agreement expected of them under the agreed appointment procedure; or

(iii) a person/institution who has been entrusted with any function under the agreed appointment procedure, failing to perform such function.

(vi) The Chief Justice or his designate while exercising power under sub-section (6) of Section 11 shall endeavour to give effect to the appointment procedure prescribed in the arbitration clause.

(vii) If circumstances exist, giving rise to justifiable doubts as to the independence and impartiality of the person nominated, or if other circumstances warrant appointment of an independent arbitrator by ignoring the procedure prescribed, the Chief Justice or his designate may, for reasons to be recorded ignore the designated arbitrator and appoint someone else."

11. In North Eastern Railway and others vs. Tripple

Engineering Works 5 also the Hon'ble Supreme Court reiterated the

position that the Hon'ble Chief Justice or the designated Judge was

free to deviate from the terms of the contract. Paragraphs-6 and 7 of

the said judgment read as follows:

"6. The "classical notion" that the High Court while exercising its power under Section 11 of the Arbitration and Conciliation Act, 1996 (hereinafter for short "the Act") must appoint the arbitrator as per the

5 (2014) 9 SCC 288 15

contract between the parties saw a significant erosion in ACE Pipeline Contracts (P) Ltd. v. Bharat Petroleum Corpn. Ltd. wherein this Court had taken the view that though the contract between the parties must be adhered to, deviations therefrom in exceptional circumstances would be permissible. A more significant development had come in a decision that followed soon thereafter in Union of India v. Bharat Battery Mfg.

Co. (P) Ltd. wherein following a three-Judge Bench decision in Punj Lloyd Ltd. v. Petronet MHB Ltd. it was held that once an aggrieved party files an application under Section 11(6) of the Act to the High Court, the opposite party would lose its right of appointment of the arbitrator(s) as per the terms of the contract. The implication that the Court would be free to deviate from the terms of the contract is obvious.

7. The apparent dichotomy in ACE Pipeline and Bharat Battery Mfg. Co. (P) Ltd. was reconciled by a three-Judge Bench of this Court in Northern Railway Admn. v. Patel Engg. Co. Ltd. wherein the jurisdiction of the High Court under Section 11(6) of the Act was sought to be emphasised by taking into account the expression "to take the necessary measure" appearing in sub-section (6) of Section 11 and by further laying down that the said expression has to be read along with the requirement of sub-section (8) of Section 11 of the Act. The position was further clarified in Indian Oil Corpn. Ltd. v. Raja Transport (P) Ltd. Para 48 of the Report wherein the scope of Section 11 of the Act was summarised may be quoted by reproducing sub-paras (vi) and (vii) herein below: (Indian Oil case, SCC p. 537)

"48. (vi) The Chief Justice or his designate while exercising power under sub-section (6) of Section 11 shall endeavour to give effect to the appointment procedure prescribed in the arbitration clause.

(vii) If circumstances exist, giving rise to justifiable doubts as to the independence and impartiality of the person nominated, or if other circumstances warrant appointment of an independent arbitrator by ignoring the procedure prescribed, the Chief Justice or his designate may, for reasons to be recorded ignore the designated arbitrator and appoint someone else."

(emphasis in original)"

16

12. The decision in Indian Oil Corporation and others v. Raja

Transport Private Limited (supra), was upheld by the Hon'ble

Supreme Court in a subsequent decision reported in Union of

India vs. Besco Limited 6.

13. In the case on hand, it is the case of applicant that it had

issued a letter dated 25.03.2022 to the respondents invoking the

arbitration clause between the parties and nominated Mr.Justice

Devinder Gupta, Former Chief Justice of Andhra Pradesh High

Court, as its nominee Arbitrator and requested the respondents to

nominate an arbitrator on their behalf within a period of 15 days, so

that the Arbitral Tribunal may be constituted expeditiously. But the

respondents vide reply letter dated 23.04.2022 rejected the request

of the applicant stating that the same is barred by limitation. There

is no provision in the Arbitration and Conciliation Act, 1996

specifying the period of limitation for filing an application under

Section 11 of the Act and therefore, one would have to take recourse

to the Limitation Act, 1963. Section 43 of the Arbitration and

Conciliation Act, 1996 provides that the Limitation Act shall apply

to arbitrators, as it applies to proceedings in Court. Since none of

the Articles in Schedule to the Limitation Act, 1963 provide a time

period for filing an application for appointment of arbitrator under

Section 11 of the Act, it would be covered by the residual provision

6 (2017) 14 SCC 187 17

under Article 137 of the Limitation Act which provides that the

period of limitation is three years for any other application for which

no period of limitation is provided elsewhere in the division.

Therefore, the limitation period of three years for filing an

arbitration application would commence from the date when the

cause of action arose. Admittedly, in the instant case, the applicant

has issued a letter dated 25.03.2022 to the respondents nominating

Mr.Justice Devinder Gupta, Former Chief Justice of Andhra

Pradesh High Court, as its nominee Arbitrator as per Clause 39 of

the Supplementary Agreement dated 05.01.2022 and requested the

respondents to nominate an arbitrator on their behalf within a

period of 15 days, so that the Arbitral Tribunal may be constituted

expeditiously. The respondents have rejected the request of the

applicant vide letter dated 23.04.2022. For the purpose of cause of

action, limitation has to be calculated from the date of assertion of

claim. Once the applicant has asserted its claim and the

respondents fails to respond to such claim, such failure will be

treated as a denial of the applicant's claim giving rise to a dispute.

Whether the applicant's claim is barred by lapse of time is a matter

which requires to be decided by the Arbitral Tribunal at the time of

making an order under Section 20 of the Arbitration and

Conciliation Act, 1996.

18

14. Pending adjudication of the arbitration application, the

respondents have filed a memo dated 27.06.2023 suggesting the

name of Sri M.Krishna Murthy, Retd. Chief Engineer, R & B

Department, as nominee Arbitrator on their behalf. The applicant

has taken serious objection to the name proposed by the Arbitrator

stating that in view of Fifth Schedule of the Arbitration and

Conciliation Act, 1996 he is disqualified to be appointed as

Arbitrator, as he was an Ex-employee of the organization. Thus

there is no unanimity among the parties in appointing nominee

Arbitrator on behalf of respondents. As per Clause 39.2.2 of the

contract, arbitration shall be conducted by a panel of three

Arbitrators, each party shall appoint one Arbitrator and the two

Arbitrators shall mutually appoint the Presiding Arbitrator. The

applicant has already proposed the name of Mr. Justice Devinder

Gupta, Former Chief Justice of Andhra Pradesh High Court

(resident of Flat No.A-61, 3rd Floor, South Extension, Part-II, New

Delhi-110 049) as its nominee Arbitrator on its behalf. Therefore,

Mr.Justice Devinder Gupta, Former Chief Justice of Andhra Pradesh

High Court, shall be the nominee Arbitrator on behalf of applicant.

15. Since the respondents failed to appoint the nominee arbitrator

on their behalf within a period of fifteen 15 days from the date of

request from the applicant, this Court deems it appropriate to

appoint nominee Arbitrator on behalf of respondents under Section 19

11(6) of the Arbitration and Conciliation Act. Therefore, Sri Justice

V.V.S.Rao, Former Judge of Andhra Pradesh High Court (resident of

H.No.165/3, Street No.6, Baghlingampally, Hyderabad-44) is

appointed as nominee Arbitrator on behalf of respondents.

16. Both the nominee Arbitrator on behalf of applicant and the

nominee Arbitrator on behalf of respondents, shall mutually appoint

the Presiding Arbitrator. The Arbitration process shall be governed

by the provisions of Arbitration and Conciliation Act, 1996, and

amendments thereto. Needless to state that the parties are at liberty

to raise all such objections as are permissible to be raised under the

provisions of the Arbitration and Conciliation Act, 1996.

17. Registry to inform and communicate a copy of this order to

the learned Arbitrators.

18. Accordingly, this Arbitration Application is disposed of.

Miscellaneous Applications, if any, pending in the Arbitration

Application shall stand closed.

___________________________ C.V. BHASKAR REDDY, J Date: 22.01.2024 Note: L.R Copy to be marked: YES/ NO (b/o) scs

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 
 
Latestlaws Newsletter
 
 
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2024

 

LatestLaws.com presents 'Lexidem Online Internship, 2024', Apply Now!

 
 
 
 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

Publish Your Article

Campus Ambassador

Media Partner

Campus Buzz