Citation : 2024 Latest Caselaw 1647 Tel
Judgement Date : 23 April, 2024
HON'BLE MRS JUSTICE SUREPALLI NANDA
WRIT PETITION No.13573 of 2011
ORDER:
Heard Mr. D.V.Nagarjuna Babu, learned counsel
appearing on behalf of petitioner and Mr.P.Prasad,
learned Standing Counsel for TSERC, appearing on
behalf of respondent No.1, Sri R.Vinod Reddy, learned
Standing Counsel for TSSPDCL, appearing on behalf of
respondent Nos.2 to 4.
2. The petitioner approached the Court seeking the
prayer as follows:
"......to issue a writ or order or direction more particularly on in the nature of Writ of Mandamus declaring (a) the order passed by the 1st respondent in O.P. Nos. 1 to 4/2004 dated 24.08.2005; (b) Condition No.5.3.3 of the General terms and conditions of supply of the 1st respondent and (c) the action of the respondents 2 to 4 in levying and collecting development charges for the release 200 KVA CMD (Additional Load) to the Petitioner and as highly illegal, arbitrary, unjust and contrary to Sections 43, 46, 181 and 182 of the Electricity Act, 2003 and consequently set aside the order dated 24-08-2005 of the 1st respondent in O.P.Nos. 1 to 4/2004 and pass such other order or orders as this Honourable Court may deem fit and proper in the circumstances of the case."
SN,J WP_13573_2011
PERUSED THE RECORD
3. It is represented by the learned counsel appearing
on behalf of the petitioner and Mr.R.Vinod Reddy,
learned Standing Counsel appearing on behalf of
respondent Nos. 2 to 4 that, the subject issue in the
present writ petition is squarely covered by the order of
this Court dated 05.10.2010 passed in WP.No.4010 of
2005 and batch and the relevant portion of the above
said judgment reads as under:
"From the above, it is clear that Clauses 5 to 11 stand deleted from the date of Regulation 3 of 2004 i.e. with retrospective effect. It is settled principle of law that a subordinate legislation can never be made with retrospective effect even assuming that the said deletion amounts to amendment of the rules/regulations. Further, the Distribution Companies were directed to file all relevant data with the Commission within 60 days of the issue of the order, till a separate regulation under Section 46 of the Act is made. Since the clauses in question are not notified as required under Section 181 and were not placed before the Legislature of the State for its approval, the deletion shall be treated as nonest in the eye of law. Therefore, applying such a law and making demands for payment of notional developmental charges for new connections and for additional loads is arbitrary and illegal.
SN,J WP_13573_2011
4. It is further represented by the learned counsel
for the petitioner and the learned Standing Counsel
appearing on behalf of respondent Nos. 2 to 4 that, the
order dated 05.10.2010 passed in W.P.No.4010 of 2005
and batch had been confirmed by the Division Bench of
this Court dated 19.04.2022 passed in W.A.No.857 of
2011 and batch, and in particular, paragraph Nos. 16 to
19 of the said Judgment reads as under:
"16. In the considered opinion of this Court, once Regulation No.4 of 2013 has already been issued repealing Regulation No.3 of 2004, the appellant company cannot demand the charges based upon the order passed by the Regulatory Commission in Review Petitions. The Review Petitions were preferred in respect of Regulation No.3 of 2004, the Regulation No.3 of 2004 has already been repealed and therefore, the present writ appeals have become infructuous and there cannot be any demand on the basis of Regulation No.3 of 2004, which is not in existence at all.
17. In the considered opinion of this Court, even though it is presumed for a moment that the Commission was having power to review the Regulation, the procedure prescribed was required to be followed and the same was not done at all. Meaning thereby, there was total non-compliance of Section 181 of the Electricity Act, 2003 and therefore, the Order passed in Review Petitions could not be given effect to, as has been done in the present cases.
18. The learned Single Judge was, therefore, justified in allowing the writ petitions and once Regulation No.4 of 2013 has been framed and
SN,J WP_13573_2011
published in the Official Gazette, the question of permitting the appellant company to raise the demand based upon the repealed Regulation No.3 of 2004, which has been struck down by this Court, does not arise.
19. In the light of the aforesaid, all the writ appeals deserve to be dismissed and are accordingly dismissed."
5. Mr.R.Vinod Reddy, learned Standing Counsel for
TSSPDCL, appearing on behalf of respondent Nos.2 to 4
submits that the Writ petition could be allowed with the
stipulations that the respondent Nos.2 to 4s may be directed
to adjust the development charges already paid by the
petitioner in their future bills.
6. Taking into consideration the submissions of both
the learned counsel on record and the order passed by
this Court vide its order dated 05.10.2010 passed in
W.P.No.4010 of 2005 and batch which had been
confirmed by the Division Bench of this Court vide its
judgment dated 19.04.2022 passed in W.A.No.857 of
2011 and batch, the Writ Petition is allowed directing
the respondent Nos.2 to 4 to adjust the development
charges already paid by the petitioner herein in their
SN,J WP_13573_2011
future bills to be levied by the respondent Nos.2 to 4
herein. However, there shall be no order as to costs.
Miscellaneous petitions, if any, pending shall stand closed.
__________________________ MRS JUSTICE SUREPALLI NANDA
Date: 23rd April, 2024 ksl.
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!