Sunday, 12, Apr, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Keytrade Ag vs Nagarjuna Fertilizers And ...
2023 Latest Caselaw 3092 Tel

Citation : 2023 Latest Caselaw 3092 Tel
Judgement Date : 12 October, 2023

Telangana High Court
Keytrade Ag vs Nagarjuna Fertilizers And ... on 12 October, 2023
Bench: C.V. Bhaskar Reddy
        IN THE HIGH COURT OF JUDICATURE AT HYDERABAD

   FOR THE STATE OF TELENGANA AND THE STATE OF ANDHARA
                         PRADESH

                                     ***

                            EXEP.No.3 of 2017
Between:


Keytrade AG,
Zurcherstrasse 68, CH-8800 Thalwil,
Switzerland
Through General Power of Attorney Holder
Mr.Mayank Kashirsagar, Advocate,
24, Firoze Gandhi Road, Flat No.4,
Lajpat Nagar-III, New Delhi.

                                               ......... Decree Holder/Petitioner

                                     And


Nagarjuna Fertilizers & Chemicals Ltd.
D.No.8-2-248, Nagarjuna Hills,
Punjagutta, Hyderabad - 500082,
Telangana.

                                             .......Judgment Debtor/Respondent

Date of Judgment pronounced on      : 27-11-2018



            HON'BLE SRI JUSTICE M.S.RAMACHANDRA RAO


1. Whether Reporters of Local newspapers                : Yes/No
   May be allowed to see the judgments?

2. Whether the copies of judgment may be marked         : Yes
   to Law Reporters/Journals:

3. Whether The Lordship wishes to see the fair copy     : Yes/No
   Of the Judgment?
                                          2                               MSR,J
                                                                   exep_3_ 2017




  THE HON'BLE SRI JUSTICE M.S. RAMACHANDRA RAO


                               EXEP.No.3 of 2017
%27-11-2018
# Keytrade AG,
Zurcherstrasse 68, CH-8800 Thalwil,
Switzerland
Through General Power of Attorney Holder
Mr.Mayank Kashirsagar, Advocate,
24, Firoze Gandhi Road, Flat No.4,
Lajpat Nagar-III, New Delhi.

                                                ......... Decree Holder/Petitioner


Versus

$ Nagarjuna Fertilizers & Chemicals Ltd.
D.No.8-2-248, Nagarjuna Hills,
Punjagutta, Hyderabad - 500082,
Telangana.

                                              .......Judgment Debtor/Respondent


< GIST:

> HEAD NOTE:

!Counsel for the Petitioner      :   Sri K.Vivek Reddy

^Counsel for the respondent      :   Sri N.Ashwani Kumar

? Cases referred
1. (2014) 2 SCC 433
2. (1976) 4 SCC 89 at Para 6
3. AIR 1994 SC 860
4. AIR 1959 SC 781
5. MANU/DE/0965/2017
6. (2018) 12 SCC 471
7. (2001) 6 SCC 356
8. AIR 1951 SC 177
9. AIR 1943 PC 29
10. 2004(2) ALD 635 (DB)
11. (2018) UKSC 24
12. AIR 1958 SC 512
13. (2005) 12 SCC 764
14. (1976) 4 SCC 89
15. (2015) 3 SCC 49
                                     3                                  MSR,J
                                                                 exep_3_ 2017




     HON'BLE SRI JUSTICE M.S.RAMACHANDRA RAO

                          EXEP.No.3 of 2017

ORDER:

This Execution Petition is filed under Section 47 of the

Arbitration and Conciliation Act, 1996 read with provisions of Section

2(1)(c), 7 and 10(i) of the Commercial Courts, Commercial Division

and Commercial Appellate Division of the High Courts Act, 2015

(Act 4 of 2016) to recover a sum of US $ 2,143,168 equivalent to INR

14,27,75,708.87ps pursuant to an Arbitral Award passed in London on

05.04.2016 by a Three-Member Arbitration Tribunal (for short 'the

Tribunal') after adjudicating the dispute between the parties.

THE BACKGROUND FACTS

2. The petitioner herein is a Company incorporated in Switzerland

and is engaged in the business of trading in fertilizers.

3. The respondent is a Company registered under the Companies

Act, 1956 having its registered office at Hyderabad, India, which is

also engaged in the business of trading in fertilizers.

4. The petitioner and respondent entered into a contract 'KTS

201310338' dt.30-4-2013 whereby the petitioner agreed to sell and the

respondent agreed to by 50,000 Metric Tonnes (M.T.) of

Di Ammonium Phosphate (for short, 'D.A.P.') (later split into two

contracts) with a shipping tolerance of ±10% at the option of the

petitioner at a price of US $ 515 per M.T. on C.F.R. basis. The value 4 MSR,J exep_3_ 2017

of this contract is US $ 25.75 Million equivalent to Rs.167.37 crores.

It provided that payment was to be by irrevocable confirmed Letter of

Credit (for short 'LC') payment at sight and the LC was to be

established by State Bank of India or another bank acceptable to

sellers.

5. Subsequently, on 28.05.2013, the above contract was split into

two contracts (KTS201310338.1 and KTS201310338.2) of 25,000

M.T. each at the option of the petitioner. All other terms and

conditions including the price which was US $ 515 M.T. remained the

same. In this split contract the mode of payment was by an

irrevocable LC established by State Bank of India or any Bank

acceptable to petitioner. It provided that the governing Law was to be

English Law and in the event of disputes, the arbitration was to be

held in London under the L.C.I.A. Rules by a panel of three arbitrators

who shall be commercial men.

6. After the contracts were signed, petitioner nominated a vessel

'MV Bulk Leo' with a capacity of 50,000 M.T. The respondent

however requested for extension of the shipping date on the ground

that they were waiting for payment of a Government subsidy, and in

the meantime was not in a good enough financial condition to open

the required LCs. So the petitioner agreed to the respondent's request.

7. Later parties entered into four different amendments by

extending the shipping dates from time to time as mentioned below.

                                      5                              MSR,J
                                                              exep_3_ 2017




8. According to petitioner, these amendments were pursuant to

respondent's request due to different reasons.

9. Under the Amendment No.1, reflecting the delayed shipping

date until 2nd half of June, 2013 the petitioner nominated a vessel 'MV

Aoyama' of capacity 50,000 M.T. on 12.6.2013 and requested the

respondent for opening of the L.C.

10. This was not acted upon in view of the respondent's request on

12-6-2013 to delay the shipping date until July, 2013 citing the non

receipt of anticipated government subsidy as well as falling value of

the Indian Rupee vis-a-vis the US $. This was agreed to by the

petitioner.

11. On 20.6.2013, petitioner again nominated a vessel 'MV

Harrier' with Laycan 4/10 July,2013, but the respondent again

requested for extension of the shipping date stating that their Banker

was refusing to open the LCs.

12. In view of the said request, the parties entered into Amendment

No.2 on 20.6.2013 reflecting the revised shipping dates pushing them

back to 25/30 July, 2013 , but all other terms of contract remained the

same. Though the above vessel's nomination was accepted by

respondent on 21.6.2013, respondent sought reduction in price,

credit/usance to the maximum possible. Petitioner at that time refused

to reduce the price, but offered to modify the payment clause allowing

the LCs to be paid 60 days from the Bill of Lading date.

                                    6                                MSR,J
                                                              exep_3_ 2017




13. Thereafter, the parties entered on 10.07.2013 into an

Amendment No.3 as per the request of the respondent incorporating

the deviation in payment clause as above.

14. It is not in dispute that on 03.05.2013 the Government of India

issued an Office Memorandum reducing the price for availing subsidy

for D.A.P. to Rs.24,000 per M.T. and on 26.06.2013, it issued another

Office Memorandum reiterating the same.

15. On 08.07.2013, the respondent's representative sent an e-mail

to the petitioner informing it about the challenges faced by the

respondent due to the formulation of policies relating to the fertilizer

industry.

16. After the Amendment no.3 was signed, on 11.07.2013, the

petitioner nominated a vessel 'Nikolaos A' to load 50,000 M.T. with

Laycan put on 21/28 July 2013, but the respondent contacted the

petitioner and rejected petitioner's vessel nomination by sending an

e-mail on 11.07.2013.

17. On 12.07.2013, discussion took place between the parties

through a conference call wherein the respondent referred to its

financial problems, and in addition, asked for more time proposing a

number of other destinations for the cargo including a proposal for

sale by the petitioner of the cargo to some third party albeit at the

lower current market price to which petitioner's representative

responded that loss should be borne by the respondent if such a 7 MSR,J exep_3_ 2017

mitigation sale took place. The petitioner in turn proposed that if

respondent honoured the parties' contracts at the agreed price of $ 515

per M.T., it could possibly sell the cargo at $ 470 Dollars per M.T.

and submitted on 13.07.2013 the Amendment No.4 for respondent's

counter-signature pushing the shipment dates to mid- September,

2013 and requiring the respondent to open L.C.s by five days prior to

the vessel's Laycan.

18. The 4th amendment was counter-signed by the respondent on

06.08.2013.

19. Before that on 19.07.2013, the petitioner's representatives met

the respondent's representatives at New Delhi and in the said meeting,

the respondent stated that it is in receipt of subsidy money and was in

a position to open L.C.s, but the Fertilizer Association of India warned

it against importing the cargo at a price well above the current market

value. According to the petitioner, the respondent's representative

Mr.Bhaskaran, while acknowledging that a contract is a contract,

allegedly made a request to the petitioner for reducing price as well as

the quantity of D.A.P. to 40,000 M.T. which would help the

respondent to reduce its loss. This is disputed by respondent.

20. On 22.7.3013, petitioner proposed Amendment No.5 reducing

the price to $ 505 and the quantity to 40,000 MT and providing

payment through LC 60 days, with LC to be established by 16.8.2013

and shipment by 15.9.2013. This according to the petitioner is the 8 MSR,J exep_3_ 2017

Amendment No.5 and it is contended by petitioner that this was

agreed to by respondent and is binding on the respondent.

21. The respondent however did not return the same to petitioner

after it was signed by it's representative. The respondent contends that

it had never signed Amendment No.5 to the contract, and contends

that the petitioner cannot place any reliance on it and that the

proposals contained in the said Amendment did not bind it.

22. On 12.08.2013, the petitioner nominated a vessel "MV Navios

Arc' of 40,000 M.T. in terms of agreement which had a laycan of

23/30 August 2013.

23. On 13.08.2013, the respondent informed the petitioner on

telephone that it would be hard to accept the vessel's nomination

unless directed by their legal team; and through an email that it has

not been receiving a favorable response from it's bankers in view of

the price not being in accordance with the prevailing market prices

and it's bankers are prohibiting them from proceeding further on the

contracts; that the Government of India will also not consider

favorably for release of subsidy at the prevailing prices in the

agreement; that it wants to relocate the product to other markets and

give it time to complete the transaction on FOB Tampa basis. It

therefore requested petitioner to keep the vessel's nomination on hold.

24. On 16.08.2013, the petitioner requested respondent to confirm

if they intended to reject the nomination of the vessel pointing out that 9 MSR,J exep_3_ 2017

in the event the respondent was rejecting the nomination, it should

explain why the nomination of the vessel was not in accordance with

the agreement. The respondent did not respond to this request. The

petitioner therefore contends that the respondent failed to open the

requisite L.C.s within the stipulated time period and committed breach

of contract.

25. The matter was referred to Arbitration by the Three-Member

Arbitration panel as provided in the contract.

THE AWARD OF THE ARBITRATORS

26. The arbitrators rendered a unanimous Award on 05.04.2016

holding that petitioner is entitled to US $ 1,840,000 with interest at the

rate of 5% per annum compounded at three monthly intervals

commencing from 12.09.2013 until the date of the Award and

thereafter at the same rate compounded on the same basis until the

date of payment.

27. The Arbitral Tribunal:

(a) accepted the evidence of the petitioner's witness

Mr. Seth that on 19.07.2013 at a meeting in New Delhi, the

respondent requested for reduction in price as well as reduction

in quantity to 40,000 M.T. in order to reduce its loss and

rejected the contention of the respondent that it never requested

or agreed to a change in the quantity of the D.A.P.;

                             10                               MSR,J
                                                       exep_3_ 2017




(b)    rejected the contention of the respondents that it was the

petitioner who made the offer or proposal on 22.07.2013, that

the respondent was not obliged to accept the said proposal, and

that it had not done so and so no contract on the premise of the

Amendment No.5 proposal dt.22.07.2013 arose;

(c) also rejected the respondent's contention that there could

not have been a breach of contract which never existed under

the 22.07.2013 proposal;

(d) took note of the statement made by the petitioner in its

letters dt.17.08.2013 addressed to the State Bank of India,

Corporate Accounts Group Branch, Punjagutta, Hyderabad that

the respondent had entered into a sale contract with the

petitioner for import of 20,000 M.T. of D.A.P. in bulk, and it

was enclosing applications for establishing L.C. for US

$ 10,100,000 together with copy of the sale contract

dt.30.04.2013 requesting arrangement of the L.C. at the earliest.

It also relied upon the petitioner's nomination of the vessel

NAVIOS ARC to ship 39,000 to 40,000 M.T. On the basis of

this evidence, it concluded that there was no merit in the

respondent's contentions referred to above;

(e) noted in para 172 the respondent's contention that the

Amendment No.5 dt. 22.07.2013 proposal did not take effect as

a binding contractual agreement and observed that petitioner's

case in this regard was somewhat opaque, but yet what really

mattered was what the oral and written evidence showed, i.e., 11 MSR,J exep_3_ 2017

that there was in fact a binding agreement on 22.07.2013 to

vary the contract quantity to 40,000 M.T., conditional upon the

respondent actually moving forward with the deal and there was

no option to the respondent to decide whether to perform or not.

It held that if the respondent did not perform, then it would be

in breach of contract;

(f) rejected the contention of respondent that since

petitioner pressed for return of the Amendment No.4 which

was prior to the 22.07.2013 proposal, the parties had intended

that unless there was an agreement in writing there would not

be a binding contract. It observed that the request of the

petitioner for the return of the Amendment No.4 to the contract

duly signed by the respondent only reflected good

post-contractual practice in ensuring that all the documentation

was signed off properly and that it showed nothing more than

good house-keeping;

(g) accepted the petitioner's submission that the evidence

supports petitioner's argument of a bilateral agreement to revise

the quantity sold and supports also their case that the

respondent's obligation to pay for the subject cargo was

triggered.

(h) also rejected the argument of the respondent based on the

I.C.C. Force Majeure Clause, 2003. The contention of the

respondent was that under Sections 10(4) and 10(5) of the

Foreign Exchange Management Act, 1999, the State Bank of 12 MSR,J exep_3_ 2017

India was required to satisfy itself of the bona fides of the

transaction between the petitioner and the respondent in order

to ensure that the transaction did not contravene the provisions

of the said Act and the refusal of the Bank to issue L.C. would

be a force majeure event excusing the respondent to discharge

its obligation under the proposal dt.22.07.2013.

The Tribunal concluded that there was no intervening

Governmental order, rule, regulation or direction falling within

the scope of the force majeure Clause that prevented the

respondents from opening the L.C., that the contracts were

bona fide transactions and the State Bank of India never raised

any doubt about compliance with Section 10(4) of the F.E.M.A.

or about the bona fides of the subject contracts in general. It

noted that the State Bank of India's concern was only about

opening L.C.s for transactions and purchase prices greater than

the market price (as can be seen from the letter dt.08.07.2013

written by the State Bank of India which indicated that doing so

would create a risk of further defaults when the respondent had

been consistently defaulting on their L.Cs. which was also

reiterated in the State Bank of India's second letter

dt.24.08.2013). It concluded that the respondent's bad credit

caused by their failure to honour its obligations towards State

Bank of India did not give rise to a force majeur defence. It

rejected the evidence of respondent's witness that the State

Bank of India was not satisfied with the bona fides of the 13 MSR,J exep_3_ 2017

transaction and accepted petitioner's submission that the

respondent could have approached another bank acceptable to

petitioner to open L.Cs. in accordance with the contracts if the

State Bank of India did not agree to do so;

(i) held that it was a classic case of a party attempting to excuse

its breach of contract on force majeure grounds where the

market had moved against them; and the respondent took no

steps to open L.C.s after receiving State Bank of India's letter

dt.24.08.2013 because the respondents believed that at that time

it had became a bad deal;

(j) rejected the defence of frustration raised by the respondent

on the ground that considerations for the said defence were, in

effect, identical to those arising in relation to force majeure;

(k) concluded that the measure of the petitioner's loss was to be

determined pursuant to Section 50 of the English Sale of Goods

Act, 1979.

On that basis, since the respondent also agreed that the correct

approach was to take the relevant F.O.B. Tampa Price and add

allowance for freight to India, it then applied mid-point price of

$ 402 per M.T. for the F.O.B. Tampa Price as at 12.09.2013, and

computed the difference between the baseline C.F.R. Price of

$ 505 per M.T. with F.O.B. Tampa plus freight $ 459 and arrived at

difference of $ 46. This figure was multiplied with 40,000 M.T.

which was the quantity under the 22.07.2013 proposal, and 14 MSR,J exep_3_ 2017

determined that $1,840,000 is to be paid by respondent to petitioner. It

also granted interest and costs thereon.

28. No petition was filed in any English Court under Sec.68 of the

English Arbitration Act, 1996 challenging the said Award.

29. Alleging that the respondent did not satisfy the decree in spite

of the Award, the present E.P. is filed under Order XXI Rule 11

C.P.C. for realization of the Award amount with interest by

(i) attaching the properties mentioned in the Schedule under Order

XXI Rule 43 and (ii) by sale of such properties under Order XXI Rule

54 r/w Order XXI Rule 64 and 66 read with Section 49 of the Indian

Arbitration and Conciliation Act, 1996.

30. Notice was ordered in the E.P. on 16.06.2017.

COUNTER/OBJECTIONS FILED BY RESPONDENT TO THE EXECUTION PETITION FILED BY THE PETITIONER.

31. In the counter filed by the respondent, the following objections

to Execution of the Arbitral award dt.05-04-2016 are raised:

(a) The present petition as framed for execution of the award, is

not maintainable without there being any relief sought for a

declaration that the subject award is enforceable under Section

47 of the Arbitration and Conciliation Act, 1996; that the

foreign award could not be treated as a decree and ; it is

capable of execution only after the Court concludes that the

award is enforceable under Chapter I of Part II of the 15 MSR,J exep_3_ 2017

Arbitration and Conciliation Act, 1996; in the absence of the

petitioner setting out and evidencing compliance with Section

47 of the Act and a prayer for declaring that the said foreign

award is enforceable, the Execution Petition simpliciter cannot

be maintained in law; the adjudication as regards enforceability

of a foreign award is a step in aid for the purposes of

adjudication of the EP and thus it is a condition precedent

before the matter is taken up for Execution as urged by the

petitioner.

(b) According to respondent, Government of India provided

subsidies to Fertilizer Companies in relation to their activities

in the DAP sector and the Urea sector and this allowed

businesses to remain commercially viable and were therefore a

necessary component of the respondent's cash flow; in addition

to the DAP subsidy, payments to respondent were outstanding

in relation to Urea subsidy receivable from the Government of

India; and Banks were unwilling to open LCs for respondent.

(c) For the above reason, nominations made of vessels by

petitioner pursuant to the Amendment No.1 to the contract on

31-05-2013, Amendment No.2 to the Contract on 12-06-2013

were not accepted.

(d) According to respondent, unforeseen difficulties arose in regard

to opening of LC due to a Maximum Retail Price directive

issued by the Government of India in June, 2013 compelling 16 MSR,J exep_3_ 2017

Indian Fertilizer Companies to sell DAP less than or equal to a

maximum price fixed by the Government; on account of the

said directive, Banks in India were, more than ever, careful to

open LCs only when the contract price was in accordance with

the market price: firstly, to ensure statutory compliance with

the Foreign Exchange Management Act, 1999 which regulated

their ability to extend credit only to bonafide transactions; and

secondly to ensure that the Company seeking LC would be able

to meet their payment obligations under the relevant LC. It

contended that continued delays in the receipt of Government

subsidies, combined with the effect of the MRP directive,

meant that respondent continued to face obstacles when

attempting to open LCs and therefore rejected the nomination

of the vessel by petitioner pursuant to the Amendment No.3. It

is further stated that the prevailing market price of the DAP

continued to fall because of which the State Bank of India and

alternative Banks would not open an LC at the instance of the

respondent in favour of the petitioner.

(e) Respondent claimed that it endeavored to find alternative

purchasers for the DAP under the contracts, with the intention

of securing a favorable outcome for both parties. On

12-07-2013, the parties held a teleconference where the

possibility of selling the DAP to a third party identified by

respondent was discussed and this sale would have resulted in a 17 MSR,J exep_3_ 2017

loss of $ 15 per MT to respondent, but no loss or cost to

petitioner. The respondent continued to search for viable

solutions for reallocating the DAP throughout July and August,

2013, but petitioner withheld its permission to allow respondent

to sell the DAP on its behalf.

(f) Respondent contends that on 13-07-2013, petitioner sent

Amendment No.4 to the contracts for respondent's signature

which was done on 06-08-2013 and by this amendment, the

shipment date was postponed to 15 or 20-09-2013 depending

on the shipment origin on the same payment terms that were

included in Amendment No.3.

(g) According to the respondent, the Amendment no.4 signed by it

on 06-08-2013 superseded all prior amendments to the contract;

and the obligations of the parties were framed only by the

agreements dt.30-04-2013 whereby it had agreed to purchase

50,000 MT of D.A.P. with a shipping tolerance of +/- 10% in

petitioner's option at $ 515 per MT CFR and amendment No.4

signed by it on 06-08-2013.

(h) Respondent contends that though there was nomination of the

vessel MV Navios Arc to load 39000/40000 MT on 12-08-2013

made by petitioner pursuant to Amendment No.4, its capacity

was less than the contracted quantity of 50000 MT and so on

13-08-2013, respondent informed petitioner that the nomination

"would be hard to accept" without a favourable response from 18 MSR,J exep_3_ 2017

their Bankers and requested petitioner to hold the vessel

nomination.

(i) It is the contention of the respondent that obligation to open LC

as per valid contract (Amendment No.4) starts with petitioner

nominating a vessel of 50000 MT, and since there was no such

nomination by petitioner, it had no obligation to open LC.

(j) According to the respondent, vide e.mail dt.22-07-2013,

petitioner offered revision of the contracts reducing the quantity

to 40000 MT +/- 10%, reducing the price to $ 505 per MT and

LC of 60 days subject to LC being established by 16-08-2013;

but this offer of the petitioner was not accepted by respondent;

and so there was no occasion or obligation for respondent to

accept the nominated vessel MV Navios Arc.

(k) It is contended that it was the petitioner who was in breach of

its contractual obligation by not nominating vessel in

accordance with the terms and agreement (since the said vessel

MV Navios Arc had less than the required capacity of 50000

MT) and this resulted in the respondent unable to fulfill its

obligations to supply DAP for onward sale to customers.

(l) According to the respondent, the basis of the claim of the

petitioner is the alleged breach of contract by respondent of

purchase of 50000 MT whereas, the alleged cause of action

arose out of alleged breach of proposal for 40000 MT which 19 MSR,J exep_3_ 2017

was never accepted by it, and so the award passed on the basis

that respondent did not purchase 40000 MT, cannot be

executed and enforced.

(m) It is contended that the State Bank of India, which was

approached by the respondent to open the LC, was unable to

open the LC in favour of the petitioner since it was an

"authorized dealer" under Section 10(4) of FEMA, 1999 which

required compliance with general or special directions or orders

imposed by RBI; and the Master Circular issued by RBI on

Import of Goods and Services on 01-07-2014 directed the

authorized dealer such as SBI to be satisfied with the bonafides

of the transactions.

LEGAL SUBMISSIONS

(n) Relying on clauses 3(a) to (g) of the ICC Force Majeure

Clause, 2003, it is contended that the finding of the Arbitrators

regarding applicability of the said Clauses violates

"fundamental policy of Indian law" (as per Section 48 of the

Act) and "basic notions of morality or justice"; and that it is the

fundamental policy of India law not to enforce contractual

obligations, when the obligations of one of the parties to the

contract turned impossible of performance, on application of

the above clauses and also Section 56 of the Contract Act;

                                20                                MSR,J
                                                           exep_3_ 2017




(o) In the present case, the price of the contracted commodity had

come down due to market forces, which was not the reason

why the respondent could not perform its obligations. Having

regard to the policy of Government of India in relation to

subsidy in respect of fertilizer products and having regard to the

credit policy framed by the SBI, on policy directive from the

Union of India, the SBI, a nationalized bank, did not agree for

opening the LC, on account of huge variance in the market

price at the time of the request and the contracted price. Such a

variance and the refusal of the SBI in that regard, were not

within the reasonable control, anticipation of the respondent

and the SBI, having been guided by a policy formulation of the

Union of India, refused to open the LC.

(p) The finding of the Arbitral Tribunal at para-189 that

"Nagarjuna's bad credit caused by their failure to honour their

separate obligations towards the SBI does not give rise to a

force majeure defence" is clearly erroneous and contrary to

record and does not disclose a judicial approach to the

determination of the subject matter by the Arbitral Tribunal.

Findings based on surmises and conjectures and which are

contrary to record, perverse and irrational, have been given by

the Arbitral Tribunal to the prejudice of the respondent.

(q) It is clear that the principle of a 'judicial approach" demands

that a decision be fair, reasonable and objective. On the 21 MSR,J exep_3_ 2017

obverse side, anything arbitrary and whimsical would

obviously not be a determination which would either be fair,

reasonable or objective.

(r) The finding of the Arbitral Tribunal that the respondent is

guilty of breach of contract by its conduct of not securing the

LC from SBI, is vitiated in law for lacking in judicial approach

and is utterly perverse.

(s) The award is patently antithetical to the concept of law,

morality and justice in Indian context, and enforcement of such

awarded monies on such basis, would fall foul of the

parameters ingrained in Section 48 of the Arbitration and

Conciliation Act, 1996 in as much as it has ignored that the

doctrine of frustration is a part of law where discharge of

contract occurs by reason of supervening impossibility or

illegality of the act agreed to be done.

(t) The Arbitral Tribunal created a contract between the parties

that did not exist. Such an exercise by the Arbitral Tribunal is

contrary to Indian law, morality and justice. Therefore the

award falls foul of Section 44 of the Arbitration and

Reconciliation Act, 1996 r/w S.7 and S.2(e)(ii) of the said Act

for this Court to be a 'Court' for exercising powers under

Section 49 for enforcement. The Award cannot be enforced as

being contrary to public policy, morality and justice.

                                       22                             MSR,J
                                                               exep_3_ 2017




(u) In such situation, it would be opposed to the tenets of justice

and morality to hold the respondent liable to pay the awarded

damages to the petitioner. The petitioner has clearly not made

out any case for enforceability of the subject award in the

Indian Jurisdiction and consequently, the present Execution

Petition filed by the petitioner is not tenable in law and

deserves to be dismissed.

REPLY OF PETITIONER                  TO    ABOVE   CONTENTIONS         OF
RESPONDENT

30. In reply to the above contentions of the respondent, the

petitioner contended:

(1) The Office Memorandum dt.03.05.2013 issued by the

Government of India reducing the price for availing subsidy for the

product D.A.P. is applicable only to those companies who chose to

avail of the Nutrient-Based subsidy policy for fertilizers which is

sought to be implemented under it, and it would not apply to an

import transaction like the transaction between the petitioner and

respondent; that Office Memorandum did not put a cap on the import

prices; and it was issued even prior to the execution of the twin

contracts between the parties on 28.05.2013, when the original

contract dt.30.04.2013 to buy 50,000 M.T. of D.A.P. was split into

two contracts of 25,000 M.T. each.

(2) The split contracts do not even mention the word 'subsidy' or

that the respondent was to avail of the same, and so there is no link 23 MSR,J exep_3_ 2017

between the contract price of the D.A.P. fertilizer and the respondent

availing the subsidy.

(3) The respondent, having executed the split contracts on

28.05.2013 after the publication of the Office Memorandum

dt.03.05.2013, was fully aware of the said Office Memorandum and

still chose to enter into contracts at US $ 515 per M.T.

(4) The Office Memorandum dt.26.06.2013 issued by the

Government of India merely reiterated the fixation of subsidy of

D.A.P. made under the Office Memorandum dt.03.05.2013 fixing

Rs.24,000 per M.T. for D.A.P. and did not change the price.

(5) The State Bank of India which was approached by the

respondent addressed a letter dt.08.07.2013 to the respondent stating

that it had been "consistently defaulting on the L.C.s" and also stating

that "unless the procurement prices are equal to or lower to current

market prices, it would be difficult for the Bank to approve the L.C.s,

despite the company having L.C. limits as there is a risk of further

defaults". The said letter did not refer to any legal impediment for

issuing L.C.s. It is clear from the said letter that it was the conduct of

the respondent which prevented the S.B.I. from issuing L.C.s to avoid

further defaults and not because of any force majeure event. Thus, the

real reason is the poor credit rating of the petitioner because of the

past history of defaults.

                                     24                               MSR,J
                                                               exep_3_ 2017




(6)    Having stated in its two letters dt.17.08.2013 addressed to the

State Bank of India admitting that it had entered into sale contracts

with petitioner for import of 20,000 M.T. of D.A.P. (total 40,000

MT), the respondent cannot contend that it had not agreed to the

5th amendment to the contract dt.22.07.2013 reducing the quantity

under the contracts to 40,000 M.T. at a price of US $ 505 C.F.R. per

M.T.

(7) The petitioner's conduct in searching for a vessel for delivery of

40,000 M.T. as opposed to four prior nominations of vessels for

50,000 M.T. as well as the oral evidence of the parties that the

contract was entered into for the reduced quantity which was subject

to cross-examination, was rightly relied upon by the Arbitrators to

reject the respondent's contention that the 5th amendment had not

come into effect and it was still at the proposal stage.

(8) On 24.08.2013, admittedly the State Bank of India returned

respondent's application for L.C. stating that it was unable to honour

the respondent's request in view of the difference in the application of

the L.C. and Amendment No.4, and the contract price not being in

accordance with the market price.

(9) The findings of the Arbitral Tribunal are based on evidence

adduced by the parties, and the respondent, in this application under

Section 48 of the Act, cannot request this Court to go into the merits

of the dispute and review the evidence which is prohibited by

Explanation 2 to Section 48(2).

                                    25                               MSR,J
                                                              exep_3_ 2017




(10) The contention of the respondent that the Arbitral Tribunal

failed to take into account certain e-mails is liable for rejection in

view of the judgment in Shri Lal Mahal v. Progetto Grano1 which

held that procedural defects (like taking into consideration

inadmissible evidence or ignoring / rejecting the evidence which may

be of binding nature) in the course of foreign arbitration do not lead

necessarily to excuse an Award from enforcement on the ground of

public policy; and Section 48 does not give an opportunity to have a

second look at the foreign award in the award enforcement stage.

(11) If the respondent is aggrieved by the findings of fact of the

Tribunal relating to the coming into effect of the 5th amendment, the

respondent ought to have challenged the Award under Section 68 of

the English Arbitration Act, 1996 before an English Court, and having

failed to do so, it cannot oppose its enforcement in India.

(12) The respondent had not raised any contention before the

Tribunal that even if the 5th amendment had been agreed to orally,

such oral amendment to a written contract / amendment is not valid in

English Law, and therefore it is precluded from raising the same under

Section 48, and in fact, this objection was not even pleaded before this

Court specifically.

(13) Without prejudice to the above plea, the petitioner contended

that Indian Law did not prohibit an oral amendment to a written

contract and 4th Proviso to Section 92 of the Evidence Act, 1872

(2014) 2 SCC 433 26 MSR,J exep_3_ 2017

expressly permitted parties to adduce evidence of any distinct

subsequent oral agreement modifying any written agreement and the

Supreme Court in Niranjan Kumar v. Dhyan Singh2 held that an

oral amendment to a written agreement is permissible.

(14) Alternatively, even under English Law an oral amendment to a

written contract is permissible unless a contract categorically states

that the amendment has to be in writing and there is no such clause in

the instant case.

(15) The respondent cannot raise any objection on English Law

before this Court stating that if the Award was contrary to English

Law, the proper and contractually agreed remedy would have been to

challenge the Award on merits before the seat court, i.e., the Courts in

London. But, in the present case, since the Award has attained

finality before the seat court, it cannot be challenged on English Law

before the executing Court, i.e., this Court.

(16) Force Majeure is a question of interpretation of contract. The

Supreme Court in Shri Lal Mahal (1 supra) held that erroneous

interpretation of contract is not a public policy violation under Section

48.

(17) Force Majeure clause in the contract can be invoked if the

following conditions are satisfied:

(1976) 4 SCC 89 at Para 6 27 MSR,J exep_3_ 2017

(i) If the impediment is listed in S.3(a) to 3(g) of I.C.C.

Force Majeure Clause 2003 or any other similar event of the

same class, AND

(ii) By due diligence, the party invoking, was unable to

prevent or overcome the said event.

(18) The Arbitral Tribunal found that the second condition was not

satisfied (See Para 184 of Award at page 2098 of Vol.V). This

finding of fact and which is on the "merits of the dispute" cannot be

challenged under Section 48 of the Act.

(19) The petitioner also pointed out that the Respondent had relied

on the Government of India Office Memorandum dt.26.06.2013 fixing

the subsidy price as Rs.24,000/- per M.T, but this Office

Memorandum was issued pursuant to 3rd May, 2013 Office

Memorandum. This was prior to the execution of contracts by the

respondent and so there cannot be a force majeure event if the so-

called unforeseeable event occurred prior to the execution of the

contract.

(20) Further, the Office Memorandum was confined to fixing the

price at which the Company can avail subsidy and there was no cap

on the price for importing fertilizer. If the respondent were to import

fertilizer at the contractual price, it would not be in violation of any

law.

                                    28                                MSR,J
                                                               exep_3_ 2017




(21) SBI's refusal to issue the L.C. was not in view of Section 10(4)

and 10(5) of FEMA and therefore it does not give rise to a force

majeure event.

(22) SBI gave two letters declining to give L.Cs., viz., (i) First letter

dt.08.07.2013 Vol.III at page 990, and (ii) Second letter,

dt.24.08.2013, Vol.III at page 1009; that the first letter of SBI does

not make any reference to Sections 10(4) and 10(5) of FEMA; and the

second letter of SBI also does not decline the L.C. because of Sections

10(4) and 10(5) of FEMA. It is evident from the letters that the SBI

declined to provide the L.C. in view of the continuous defaults by

respondent. It was a business decision. The Arbitral record also

shows that the respondent was part of CDR mechanism (Corporate

Debt Restructuring). It was the basis for its Counter Claim. A

Corporate Entity is in C.D.R. when it defaults on its loan obligations

to the consortium of banks; this supports the SBI's assessment that

respondent would be unable to honour L.C.s, if they were invoked;

and Section 10(4) only states that the Authorized Person shall act in

accordance with the general or special directions or orders of RBI.

(23) The respondent has not shown how the import of D.A.P. at U.S.

$ 505 is in violation of any R.B.I. direction or order. Section 10(5) of

F.E.M.A. states that the authorized person (i.e., a person who deals

with foreign exchange) shall not undertake any transaction on foreign

exchange on behalf of any person until that person gives a declaration

that the transaction is not in violation of the F.E.M.A. or any rules / 29 MSR,J exep_3_ 2017

regulation / notification / director or order made under the F.E.M.A.

In the present case, the respondent has not pointed out as to how

import of D.A.P. at U.S. $ 505 is in violation of any provision of the

F.E.M.A. or Rules and Regulations. This is consistent with the S.B.I.

not referring to the F.E.M.A. at all in its two letters. This is simply

because there was no violation of F.E.M.A. whatsoever.

(24) The Arbitral Tribunal also found that the respondent did not

make any efforts to obtain L.C. from another bank, which it was

required to do under the Contract. In fact, the respondent is in breach

of the contract for not having obtained the L.C. from another bank.

The respondent did not challenge this finding.

(25) None of the objections raised by the respondent fall within the

framework of sub-section (2)(b) of Section 48 of the Act.

(26) The Supreme Court in Renusagar Power Co. v. General

Electric Co3 dealt with phrase "public policy" as follows:

(a) The Supreme Court relied on the 'narrow view' approach

upheld in Gherulal Parakh v. Mahdeodas Maiya4 in the

context of enforcement of foreign award, wherein it was held

that public policy ground can be invoked in clear and

incontestable cases of harm to public.

(b) The narrow view would facilitate international trade and

commerce.



    AIR 1994 SC 860

    AIR 1959 SC 781
                                       30                                  MSR,J
                                                                    exep_3_ 2017




         (c)    Since   foreign    awards   are   governed    by      private

international law, the narrow view of public policy as

applicable in private international law must be applied.

(d) Contravention of law alone will not attract the bar of

public policy and something more than contravention of law is

required.

(e) To represent 'narrow view' on public policy, the

Supreme Court used the phrase 'fundamental policy of Indian

law'. The scope of 'public policy' would be limited to: (i)

Fundamental policy of Indian Law; (ii) The interests of India;

and (iii) Justice and morality.

(27) After the amendment to the Act, the Delhi High Court in Cruz

City 1 Mauritius Holdings v. Unitech Limited5 dealt with the

meaning of 'fundamental policy' and held that it connotes the basic

and substratal rationale, values and principles which form the bedrock

of laws in our country. It further held that the objections to

enforcement on ground of public must offend the core values of a

member State's national policy and which it cannot be expected to

compromise. It also held that one of the principle object of the New

York Convention is to ensure enforcement of awards notwithstanding

that the awards are not rendered in conformity to the national laws.






    MANU/DE/0965/2017
                                        31                                      MSR,J
                                                                         exep_3_ 2017




THE CONSIDERATION BY THE COURT


31. Enforcement of Foreign Arbitral Awards is dealt with by Part-II

of the Arbitration and Conciliation Act, 1996.

32. Section 47 requires a party applying for enforcement of a

Foreign Award to file the copy of the Award and the original

Agreement for Arbitration or copies thereof.

33. Section 48 sets out the conditions for enforcement of Awards.

It states:

"Section 48 -Conditions for enforcement of foreign awards. - (1) Enforcement of a foreign award may be refused, at the request of the party against whom it is invoked, only if that party furnishes to the court proof that-

(a) The parties to the agreement referred to in section 44 were, under the law applicable to them, under some incapacity, or the said agreement is not valid under the law to which the parties have subjected it or, failing any indication thereon, under the law of the country where the award was made; or

(b) The party against whom the award is invoked was not given proper notice of the appointment of the arbitrator or of the arbitral proceedings or was otherwise unable to present his case; or

(c) The award deals with a difference not contemplated by or not falling within the terms of the submission to arbitration, or it contains decisions on matters beyond the scope of the submission to arbitration:

Provided that, if the decisions on matters submitted to arbitration can be separated from those not so submitted, that part of the award which contains 32 MSR,J exep_3_ 2017

decisions on matters submitted to arbitration may be enforced; or

(d) The composition of the arbitral authority or the arbitral procedure was not in accordance with the agreement of the parties, or, failing such agreement, was not in accordance with the law of the country where the arbitration took place; or

(e) The award has not yet become binding on the parties, or has been set aside or suspended by a competent authority of the country in which, or under the law of which, that award was made.

(2) Enforcement of an arbitral award may also be refused if the court finds that-

(a) The subject-matter of the difference is not capable of settlement by arbitration under the law of India; or

(b) The enforcement of the award would be contrary to the public policy of India.

[Explanation. 1- For the avoidance of any doubt, it is clarified that an award is in conflict with the public policy of India, only if, -

(i) the making of the award was induced or affected by fraud or corruption or was in violation of section 75 or section 81; or

(ii) it is in contravention with the fundamental policy of Indian Law; or

(iii) it is in conflict with the most basic notions of morality or justice.] [Explanation 2.- For the avoidance of doubt, the test as to whether there is a contravention with the fundamental policy of Indian law shall not entail a review on the merits of the dispute.]

(3) If an application for the setting aside or suspension of the award has been made to a competent authority referred to in clause (e) of sub-section (1) the court may, if it considers it proper, adjourn the decision on the enforcement of the award and may also, on the application of the party claiming enforcement of the award, order the other party to give suitable security. "

                                    33                                 MSR,J
                                                                exep_3_ 2017




34. Thus under Section 48(1)(a) of the Act, enforcement of an

award may be refused, at the request of the party against whom it is

invoked, only if that party furnishes to the Court proof that the parties

to the agreement were, under the law applicable to them, under some

incapacity, or the said agreement is not valid under law to which the

parties have subjected it or, failing any indication thereon, under the

law of the country where the award was made.

35. Under Section 48(2)(b) of the Act, enforcement of foreign

awards may be refused if its enforcement would be contrary to public

policy of India. Explanation I thereto clarifies that an award is in

conflict with public policy of India only if (i) the making of the

Award was induced or affected by fraud or corruption or was in

violation of Section 75 of Section 81; or (ii) it is in contravention with

the fundamental policy of Indian Law; or (iii) it is in conflict with the

most basic notions of morality or justice. Explanation II states that

the test as to whether there is a contravention with the fundamental

policy of Indian Law shall not entail a review on the merits of the

dispute.

36. In Shri Lal Mahal (1 supra), the Supreme Court followed

Renusagar (3 supra) and held that for the purposes of Section

48(2)(b), the expression "public policy of India" must be given a

narrow meaning and the enforcement of the foreign award would be

refused on the ground that it is contrary to the public policy of India if

it is covered by one of the three categories enumerated in Renusagar 34 MSR,J exep_3_ 2017

(3 supra), i.e., (i) fundamental policy of Indian law; or (ii) interests of

India; or (iii) justice or morality. It also declared that Section 48 does

not give an opportunity to have a "second look" at the foreign award

in the award enforcement stage and the scope of enquiry under

Section 48 does not permit review of the foreign award on merits. In

particular, it held that procedural defects like taking into

consideration inadmissible evidence or ignoring / rejecting the

evidence which may be of binding nature, in the course of foreign

arbitration, does not lead necessarily to excuse an award from

enforcement on the ground of public policy.

37. In H.R.D. Corporation v. GAIL (India) Ltd.6, the Supreme

Court held that after amendment to Section 48 and Section 34, "public

policy" will now include only "fundamental policy of Indian Law"

and "justice or morality" and the ground "interest of India" is no

longer available; and the term "justice or morality" is now to be

understood as meaning only basic notions of justice and morality, i.e.,

such notions as would shock the conscience of the Court. It further

held that construction of the terms of the contract is primarily for the

arbitrator to decide unless it is found that such a construction is not a

possible one; and for Part I awards arising out of arbitration other than

an international commercial arbitration, one more ground of challenge

is available, i.e., patent illegality appearing on the face of the award.

It held that the ground of patent illegality would not be established,

(2018) 12 SCC 471 35 MSR,J exep_3_ 2017

if there is merely an erroneous application of the Law or a re-

appreciation of evidence.

38. These principles will be kept in mind while considering the

contentions of both sides.

A. Whether the petitioner should have filed an application to declare that the foreign award is enforceable before seeking its execution

39. I shall first deal with the respondent's objection that the present

petition as framed for execution of the award, is not maintainable

without there being any relief sought for a declaration that the subject

award is enforceable under Section 47 of the Arbitration and

Conciliation Act, 1996; that the foreign award could not be treated as

a decree and ; it is capable of execution only after the Court

concludes that the award is enforceable under Chapter I of Part II of

the Arbitration and Conciliation Act, 1996; in the absence of the

petitioner setting out and evidencing compliance with Section 47 of

the Act and a prayer for declaring that the said foreign award is

enforceable, the Execution Petition simpliciter cannot be maintained

in law; the adjudication as regards enforceability of a foreign award is

a step in aid for the purposes of adjudication of the EP and thus it is a

condition precedent before the matter is taken up for Execution as

urged by the petitioner.

40. Under Section 49 of the Arbitration and Conciliation Act, 1996

where the Court is satisfied that the foreign award is enforceable

under Chapter I of Part II of the Act, the award shall be deemed to be 36 MSR,J exep_3_ 2017

a decree of the Court. Thus, what the law requires is the satisfaction

of the Court that the foreign award is enforceable and there is no

necessity for the successful party in the foreign arbitration to seek a

declaration that the award is enforceable under Section 47 of the Act.

41. In Feurst Day Lawson Ltd. v. Jindal Exports Ltd.7, the

Supreme Court, after considering the provisions of Part II of the

Arbitration and Conciliation Act, 1996 rejected the contention that a

party holding a foreign award has to file a separate application and

produce evidence as contemplated under Section 47 and also satisfy

the conditions laid down under Section 48 and it is only after the

Court decides about the enforceability of the Award, it should be

deemed to be a decree under Section 49 as available for execution. It

held that the object of the Act is to minimize the supervisory role of

the Courts in the arbitral process and to give speedy justice and this

would be defeated if it is held that a party must separately apply

before filing an application for execution of a foreign award; that if

separate proceedings are to be taken, one for deciding the

enforceability of a foreign award and the other thereafter for

execution, it would only contribute to protracting the litigation. It

held that a party holding a foreign award can apply for enforcement

of it but the Court, before taking further effective steps for the

execution of the Award has to proceed in accordance with Sections 47

to 49; in one proceeding there may be different stages; in the first

stage the Court may have to decide about the enforceability of the

(2001) 6 SCC 356 37 MSR,J exep_3_ 2017

Award and with regard to the requirement of the said provisions and

once the Court decides that the foreign award is enforceable, it can

proceed to take further effective steps for execution of the same; and

there arises no question of making foreign award a rule of Court /

decree again.

42. This judgment is a complete answer to the contention of the

respondent.

B. Whether the arbitration clause is attracted to the dispute

43. Counsel for respondent also contended that petitioner's claim

before the arbitrators arose out of Amendment No.5 proposed by it

which did not take the shape of a concluded contract; that the

respondent did not accept the modification in writing; and the

arbitrators could not have inferred that there is a concluded contract

on the basis of conduct of parties; and consequently, the arbitration

clause is not attracted to such a dispute.

44. The Arbitration Clause contained in the contracts dt.30.04.2013

is very wide and it contemplated that "any dispute, controversy or

claim arising out of or relating to this contract, or the breach,

termination or validity thereof, shall be referred to arbitration ... ...".

45. In view of the fact that any dispute, controversy or claim

relating to the contracts would be covered by the arbitration clause,

I see no merit in this contention of the counsel for respondent.

                                       38                                  MSR,J
                                                                    exep_3_ 2017




C. Whether the arbitrators erred in law in granting relief to the petitioner on the basis of Amendment no.5 dt.22.07.2013 ?

46. The counsel for the respondent stated that the proposal

contained in the e-mail dt.22.07.2013 (the Amendment No.5

proposed) was not an agreement under English Law, that it was only a

proposal and without unconditional acceptance, either expressly or by

conduct, of the respondent, there was no agreement valid under law;

that there was no plea of estoppel raised by petitioner; that the Arbitral

Award could not have been based on the proposal for Amendment

No.5; and the Award therefore should be refused enforcement.

47. It is not in dispute that before the Arbitral Tribunal the

petitioner's claim was in fact on the original quantity of 50,000 MT

as per the original contract dt.30.04.2013 and during the course of

arbitration, the petitioner appears to have made a claim pursuant to the

proposal contained in the e-mail dt.22.07.2013 (Amendment No.5

proposal) for a reduced quantity of 40,000 MTs at $ 505 per MT.

48. The Arbitral Tribunal noted in para 172 of its Award that

petitioner's case on the 22.07.2013 proposal "was rather opaque", but

what really mattered, according to the Tribunal, was what the oral and

written evidence showed and it found that there was evidence of a

binding agreement on 22.07.2013 to vary the contract quantity to

40,000 MT conditional upon the respondent actually moving forward

with the deal.

                                            39                                    MSR,J
                                                                           exep_3_ 2017




49. In law, a plaintiff who made a claim in the plaint against the

defendant is not precluded from making an alternative claim if there is

foundation laid in the pleading.

50. In Firm Sriniwas Ram Kumar v. Mahabir Prasad8 a suit for

specific performance of a contract was filed and plaintiff alleged that

in part performance he paid the defendant some money. The

defendant denied the contract and pleaded that the money was taken

by him as a loan. The Supreme Court held that Court can pass a

decree for recovery of the loan in favour of the plaintiff even if he

failed to prove the contract and even though he failed to plead and

claim relief on the alternative case. It explained :

"A plaintiff may rely upon different rights alternatively and there is nothing in the Civil Procedure Code to prevent a party from making two or more inconsistent sets of allegations and claiming relief thereunder in the alternative. The question, however, arises whether, in the absence of any such alternative case in the plaint it is open to the court to give him relief on that basis. The rule undoubtedly is that the court cannot grant relief to the plaintiff on a case for which there was no foundation in the pleadings and which the other side was not called upon or had an opportunity to meet. But when the alternative case, which the plaintiff could have made, was not only admitted by the defendant in his written statement but was expressly put forward as an answer to the claim which the plaintiff made in the suit, there would be nothing improper in giving the plaintiff a decree upon the case which the defendant himself makes. A demand of the plaintiff based on the defendant's own plea cannot possibly be regarded with surprise by the latter and no question of adducing evidence on these facts would arise when they were expressly admitted by the defendant in his pleadings. In such circumstances, when no injustice can possibly result to the defendant, it may not be

AIR 1951 SC 177 40 MSR,J exep_3_ 2017

proper to drive the plaintiff to a separate suit. As an illustration of this principle, reference may be made to the pronouncement of the Judicial Committee in Babu Raja Mohan Manucha v. Babu Manzoor9. This appeal arose out of a suit commenced by the plaintiff appellant to enforce a mortgage security. The plea of the defendant was that the mortgage was void. This plea was given effect to by both the lower courts as well as by the Privy Council. But the Privy Council held that it was open in such circumstances to the plaintiff to repudiate the transaction altogether and claim a relief outside it in the form of restitution under Section 65 of the Indian Contract Act. Although no such alternative claim was made in the plaint, the Privy Council allowed it to be advanced and gave a decree on the ground that the respondent could not be prejudiced by such a claim at all and the matter ought not to be left to a separate suit. It may be noted that this relief was allowed to the appellant even though the appeal was heard ex parte in the absence of the respondent."

51. This principle was followed by the Division Bench of this

Court in Kusam Satyanarayana Reddy and Ors. Vs. Kusam

Sambrajyamma (died) by LRs. and Ors.10 It was held:

"It may also be, however, noted that under Order 7, Rule 7 of the Code although the Court can grant a relief which has not been asked for, but it cannot grant a relief which is larger than the relief claimed by the plaintiff, but where the relief claimed by the plaintiff is larger and the Court grants a relief which is smaller than the one claimed, it would be legal. In the present case the plaintiffs claimed whole property, but on facts the Trial Court found that they could claim part of the property as legal representatives of the original owner along with some of the defendants. Therefore, in our view, the Trial Court was right in granting the decree of partition."

52. Thus, there is no bar for the Arbitral Tribunal to grant a relief

on an alternative basis if there is no surprise to the defendant and

AIR 1943 PC 29

2004(2) ALD 635 (DB) 41 MSR,J exep_3_ 2017

when there is a foundation in the pleading, and if the petitioner makes

out a case for grant of the alternative relief.

53. Therefore, it cannot be said that the Arbitral Tribunal

committed any error in law in granting relief to the petitioner on the

basis of Amendment no.5 dt.22.07.2013 instead of granting relief on

the original quantity of 50,000 M.T. and price of US $ 515 after

finding that the petitioner established such a claim.

D. Whether the Arbitral Award's enforcement ought to be refused under Section 48 :

(a) Whether enforcement of the award can be refused under Section 48(1)(a) of

the Act ?

54. It is the contention of the respondent that Section 48(1) of the

Act gives power to the Court to adjudicate on the award and ascertain

for itself, whether there has been a proper application of law which

the parties have subjected themselves to and the Court can come to the

conclusion whether the agreement was valid under the law governing

the contract i.e. English law in the instant case.

55. Elaborating the same, counsel for the respondent contended that

the award was based on the proposal contained in the e.mail

dt.22-07-2013 of the petitioner (Amendment No.5) and the arbitrators

were not correct in holding that the proposal contained in the e.mail

dt.22-07-2013 constituted a valid contract under English law.

                                      42                             MSR,J
                                                              exep_3_ 2017




56. Admittedly, the contract between the parties is governed by

English law.

57. There is no dispute that the original contract signed by the

parties on 30-04-2013 whereby the petitioner agreed to sell to the

respondent 50,000 MT of DAP at $ 515 per MT is valid under English

law.

58. The questions therefore are:

(i) whether the e.mail dt.22-07-2013 containing Amendment No.5

proposed by the respondent varying the quantity under the contract to

40,000 MT at $ 505 per MT was accepted by the respondent ? and

(ii) whether such a modification is valid under English law, when the

initial contract was signed by the parties but there is no document

signed by respondent accepting the terms of Amendment No.5

contained in the e.mail dt.22-07-2013 proposed by the petitioner?

THE LEGAL POSITION IN ENGLAND

59. In Rock Advertising Limited Vs. M.W.B. Business

Exchange Centers Limited11, the United Kingdom Supreme Court

considered (a) whether a contractual term prescribing that an

agreement may not be amended save in writing signed on behalf of

the parties (commonly called a "No Oral Modification" clause) is

legally effective and (b) whether an agreement whose sole effect is to

(2018) UKSC 24 43 MSR,J exep_3_ 2017

vary a contract to pay money by substituting an obligation to pay less

money or the same money later, is supported by consideration.

60. In that case, clause 7.6 of the agreement ( referred to as the 'No

Oral Modification' clause) between the parties provided:

"This Licence sets out all of the terms as agreed between MWB and Licensee. No other representations or terms shall apply or form part of this Licence. All variations to this Licence must be agreed, set out in writing and signed on behalf of both parties before they take effect."

61. The Court accepted that the position in England was equivocal

but held that the law should and does give effect to a contractual

provision requiring specified formalities to be observed for a

variation; but held that parties cannot validly bind themselves as to

the manner in which future changes in their legal relations are to be

achieved, however clearly they express their intention to do so. It

held that nevertheless No Oral Modification clauses are commonly

included in written agreements; there are legitimate commercial

reasons for agreeing a clause like 7.6; and the law of contract does not

normally obstruct the legitimate intentions of businessmen, except for

overriding reasons of public policy. Therefore there is no mischief in

No Oral Modification clauses, nor do they frustrate or contravene any

policy of the law.

62. It held that No Oral Modification clauses like Entire Agreement

clauses achieve contractual certainty about the terms agreed.

                                     44                               MSR,J
                                                               exep_3_ 2017




63. Then it considered the question "what if the parties make a

collateral agreement any way and would it otherwise bind them?"

64. The Court answered the said question stating that what the

parties to a No Oral Modification clause have agreed is not that oral

variations are forbidden, but that they will be invalid. The mere fact

of agreeing to an oral variation is not therefore a contravention of the

clause. It is simply the situation to which the clause applies. It is not

difficult to record a variation in writing, except perhaps in cases where

the variation is so complex that no sensible businessmen would do

anything else. The natural inference from the parties' failure to

observe the formal requirements of a No Oral Modification clause is

not that they intended to dispense with it but that they overlooked it.

If, on the other hand, they had it in mind, then they were courting

invalidity with their eyes open.

65. More importantly it held that the enforcement of No Oral

Modification clauses carries with it the risk that a party may act on

the contract as varied, for example by performing it, and then find

itself unable to enforce it. The Court referred to the Vienna

Convention and the UNIDROIT Model Code and stated that they

qualify the principle that effect is to be given to No Oral Modification

clauses, by stating that a party may be precluded by his conduct

from relying on such a provision to the extent that the other party

has relied (or reasonably relied) on that conduct; in some legal

systems this result would follow from the concepts of contractual 45 MSR,J exep_3_ 2017

good faith or abuse of rights; and in England, the safeguard against

injustice lies in the various doctrines of estoppel. It stated that the

scope of the estoppel is that (i) at the very least there would have to be

some words or conduct unequivocally representing that the variation

was valid notwithstanding its informality; and (ii) something more

would be required for this purpose than the informal promise itself. It

also held that it is unnecessary to deal with existence of

'consideration' for the variation and is undesirable to do so.

66. Thus, according to English law as decided in Rock Advertising

Limited (11 supra), normally No Oral Modification clauses would

be enforced except where a party acts on the contract as varied, for

example by performing it. In such an event, the doctrine of estoppel

is applied.

67. It is important to note that before the Arbitral Tribunal, no

contention was raised by the respondent that even if an oral

agreement/amendment had occurred pursuant to the e.mail

dt.22-07-2013 (Amendment No.5), such oral amendment to the

written contract is impermissible under English law. Without raising

the said contention before the Arbitrators or filing a petition under

Section 68 of the English Arbitration Act, 1996 before the English

Court, I am of the opinion that the respondent cannot be allowed to

raise it before this Court in proceedings to execute the award.

68. Assuming that it is entitled to raise the said plea, it is important

to note that, in the instant case, there is no clause prohibiting oral 46 MSR,J exep_3_ 2017

modification to the contracts. There was no clause akin to clause 7.6

in Rock Advertising (11 supra). In such circumstances it cannot be

said that an oral modification vide e.mail dt.22-07-2013 to the written

contract dt.30-04-2013, if proved to have occurred by consent of both

sides and their conduct, is prohibited by law or impermissible in law.

THE LEGAL POSITION IN INDIA

69. In Indian law, there is no prohibition for a promisee to accept as

performance of a promise made to him, part performance of it, or

some other satisfaction of the said promise. Even if there is no later

agreement in writing, this can be established by him through oral

evidence or by evidence of conduct of parties.

70. Sec.63 of the Contract Act, 1872 states that every promisee

may dispense with or remit, wholly or in part, the performance of the

promise made to him, or may extend the time for such performance,

or may accept instead of it any satisfaction which he thinks fit.

Illustration (b) thereto states "A owes B Rs.5000/-. A pays to B, and B

accepts, in satisfaction of the whole debt Rs.2000/-, paid at the time

and place at which Rs.5000/- were payable. The whole debt is

discharged."

71. The Supreme Court has held that under Section 63, extension of

time for performance of a contract (which is usually one of the terms

of a contract/promise) may even be orally agreed or may be inferred 47 MSR,J exep_3_ 2017

from conduct. In Keshavlal Lallubhai Patel v. Lalbhai Trikumlal

Mills Ltd12. the Court explained::

"8. The true legal position in regard to the extension of time for the performance of a contract is quite clear under Section 63 of the Indian Contract Act. Every promisee, as the section provides, may extend time for the performance of the contract. The question as to how extension of time may be agreed upon by the parties has been the subject-matter of some argument at the Bar in the present appeal. There can be no doubt, we think, that both the buyer and the seller must agree to extend time for the delivery of goods. It would not be open to the promisee by his unilateral act to extend the time for performance of his own accord for his own benefit. It is true that the agreement to extend time need not necessarily be reduced to writing. It may be proved by oral evidence. In some cases it may be proved by evidence of conduct. Forbearance on the part of the buyer to make a demand for the delivery of goods on the due date as fixed in the original contract may conceivably be relevant on the question of the intention of the buyer to accept the seller's proposal to extend time. It would be difficult to lay down any hard and fast Rule about the requirements of proof of such an agreement. It would naturally be a question of fact in each case to be determined in the light of evidence adduced by the parties. Having regard to the probabilities in this case, and to the conduct of the parties at the relevant time, we think the appellants are entitled to urge that their oral evidence about the acceptance of the respondent's proposal for the extension of time should be believed and the finding of the learned trial Judge on this question should be confirmed."(emphasis supplied)

72. This principle was reiterated in S. Brahmanand v. K.R.

Muthugopal13, where the Court held :

"34. Thus, this was a situation where the original agreement of 10-3-1989 had a "fixed date" for performance, but by the subsequent letter of 18-6-1992 the defendants made a request for

AIR 1958 SC 512

(2005) 12 SCC 764 48 MSR,J exep_3_ 2017

postponing the performance to a future date without fixing any further date for performance. This was accepted by the plaintiffs by their act of forbearance and not insisting on performance forthwith. There is nothing strange in time for performance being extended, even though originally the agreement had a fixed date. Section 63 of the Contract Act, 1872 provides that every promisee may extend time for the performance of the contract. Such an agreement to extend time need not necessarily be reduced to writing, but may be proved by oral evidence or, in some cases, even by evidence of conduct including forbearance on the part of the other party."(emphasis supplied)

73. Also proviso (4) to Section 92 of the Evidence Act, 1872

permits parties to prove the existence of any distinct subsequent oral

agreement to rescind or modify a contract except where such contract

is by law required to be in writing, or has been registered according to

the law in force for the time being as to the registration of documents.

This is an exception to the general principle contained in Section 92

that when terms of any contract are required by law to be reduced to

the form of a document, no evidence of any oral agreement or

statement shall be admitted, as between the parties to such contract for

the purpose of contradicting, varying, adding to or subtracting from,

its terms.

74. In Niranjan Kumar and others Vs. Dhyan Singh and

another14, the Supreme Court applied the above principle in a case

where the 1st respondent gave a shop on rent to 2nd respondent for 11

months by executing a rent note. A partnership firm occupied the

shop on the authority of the rent note and continued its business in the

(1976) 4 SCC 89 49 MSR,J exep_3_ 2017

shop even after the expiry of the period of the rent note. The

respondent No.2 also retired from the firm under a deed of dissolution

and the other persons continued in the same premises under a

reconstituted partnership. The respondent No.1 sought possession of

the shop from respondent No.2 and partners of the firm, who were

appellants before the Supreme Court under the East Punjab Urban

Rent Restriction Act, 1949 alleging that respondent No.2 was the

tenant of the shop in his personal capacity and had unlawfully sublet

the shop to the firm. The appellants contended that respondent No.2

did not take the shop on rent in his personal capacity but as partner of

the firm and there was no subletting in favour of the firm or its

partners. The Rent Controller accepted this contention and dismissed

the application, but the District Judge on appeal reversed this finding

accepting the plea of respondent No.1. This was confirmed by the

High Court. The Supreme Court held that under proviso (4) to Section

92, it was open to the appellants to lead evidence to show that there

was, apart from the rent note, a distinct subsequent oral agreement

under which the terms of the original contract or grant were modified

and that the partners of the firm, both before and after its

recomposition, were the real tenants of the shop. After considering

the evidence on record, the Supreme Court dismissed the appeal

stating that there is no evidence to accept the appellant's case that

respondent No.2 had taken the premises from respondent No.1 on

behalf of the firm and not in his personal capacity.

                                     50                                  MSR,J
                                                                  exep_3_ 2017




75. Therefore, both under English law and Indian law, it was

permissible for the petitioner to prove that the original contract was in

fact modified by an oral agreement whose terms were contained in the

e.mail dt.22-07-2013 (Amendment No.5). This can be done by

relying on oral evidence or by evidence of conduct of parties.

Whether in the facts of the case, the Arbitral Tribunal was right in holding that Amendment No.5 proposed by the petitioner was accepted by respondent

76. It is the contention of the petitioner that in a meeting held at

New Delhi on 19-07-2013, the respondent requested for a quantity

reduction to 40,000 MT from 50,000 MT and a price reduction as

well.

77. In the pre-hearing brief submitted by petitioner before the

arbitrators, at para 26 there is a specific plea by the petitioner that

after the meeting held at New Delhi on 19.7.2013, petitioner stood by

the respondent and, on 22.7.2013 accepted the respondent's offer to

reduce the quantity and price. But this acceptance was conditional

upon the respondent moving forward with the deal. It is also pleaded

that in addition petitioner agreed to accept payment on basis of LC to

be established by 16.8.2013 and payable 60 days from Bill of Lading

Date and to extend the shipment periods to 15.9.2013; that for more

than a week thereafter there was no substantive response by

respondent confirming this proposal; that in a telecom with Ravindra

(respondent) on 31.7.2013, he again requested to sell cargo

somewhere else and promised to pay the difference; but the next day 51 MSR,J exep_3_ 2017

i.e 1.8.2013, Bhaskaran ( respondent) called Seth ( petitioner) and

informed that his legal department had asked him not to take a

decision and matter would be referred to respondent's Board on

9.8.2013; that on 5.8.2013, in a conference call, the respondent 's

representatives expressed that they were committed and wanted to

fulfill all their obligations under the contract, and to do so "ethically";

this was noted in the diary of the petitioner's representative

Mr.Keyman; but after the Board meeting of respondent , petitioner did

not hear anything. So petitioner nominated on 12.8.2013, the vessel

"MV Navios Arc" with lay/can 24/30 August, 2013 and which could

carry cargo of 39,000/40,000 MT and only on the next day,

respondent flatly refused to move forward on the contracts. It was

contended that respondent's plea that there was no agreement to

reduce the quantity did not make sense as the respondent had several

times confirmed it, and once petitioner agreed to reduce the quantity,

everything they did and said afterwards was framed in terms of 40,000

MT for both contracts. In para 58 a specific plea was raised by

petitioner stating that the nomination of the vessel with reduced

capacity of 40,000 MT was only at the request of the respondent on

19.7.2013 which was acquiesced on 22.7.2013; that there was no

reason for petitioner to nominate a vessel with 10000 MT more than

the quantity the parties intended to load and incur substantial dead

load freight charges; and having requested for reduction of quantity,

the respondent should be estopped from contending that petitioner's

nomination of the vessel capable of carrying 40000 MT was not in 52 MSR,J exep_3_ 2017

accordance with the contracts. In para 61, reference was also made to

respondent's admission in the two letters addressed to State Bank of

India about the reduced quantity. Thus the plea of estoppel by conduct

of respondent was also specifically raised by petitioner and the

counsel for respondent is not correct in contending that there was no

such contention raised by the petitioner before the tribunal. The

statement of respondent's witness Mr.Ravindra that the respondent

never requested or agreed to a change in the quantity of DAP was

denied in para-24 of the petitioner's pre-hearing brief.

78. To buttress these contentions, e.mail dt.19-07-2013 addressed

by Mr.Aditya Seth (for short 'Mr.Seth') of petitioner to others in

petitioner Company is relied upon as also the oral evidence given by

Mr.Seth before the Arbitral Tribunal.

79. The evidence on record shows that petitioner's representative

sent the e.mail dt.22-07-2013 reducing the quantity to 40,000 MT and

price to $ 505 MT permitting LC to be established by 16-08-2013.

On 25-07-2013, the petitioner's representative Mr.Seth by e.mail

requested Mr.Ravindra of the respondent to respond to its e.mail

dt.22-07-2013. The respondent's representative Mr.Ravindra did not

dispute or disagree with the proposal contained in the e.mail

dt.22-07-2013 and merely stated that "we have discussed the proposal

with our Bankers, in view of the concerns raised by them. We have

already initiated the dialogue with them and shall revert to you." The

petitioner's representative Mr.Seth again wrote an e.mail on 53 MSR,J exep_3_ 2017

26-07-2013 requesting prompt action from the respondent and

followed it up with another e.mail on 29-07-2013 sent by it's

President Melih Keyman.

80. It is not in dispute that the respondent addressed two letters both

dated 17-08-2013 to the State Bank of India, Panjagutta Branch

stating that "we have entered into a sale contract with Keytrade AG,

Switzerland, for import of 20,000 MT of Di Ammonium Phosphate in

bulk", that the shipment was scheduled for the 3rd week of September,

2013 and LC has to be established in favour of petitioner at the

earliest. The quantity of DAP covered by these two letters is 40,000

MT and not 50,000 MT.

81. If the respondent had not accepted Amendment No.5 and

intended to act on it, they would not have written those letters. This

indicates that the Amendment No.5 proposed by the petitioner by

e.mail dt.22-07-2013 was not only accepted by the respondent, but

also acted upon by it. It cannot now turn around and contend that it

had never accepted it, and liability cannot be imposed on it by treating

it as a modification to the written contracts dt.30-04-2013 and the

subsequent written modifications thereto.

82. Though counsel for the respondent contended that the petitioner

was not aware of the letters dt.17-08-2013 addressed by the

respondent to the State Bank of India until much later and so cannot

rely on the said conduct, I do not agree with the said contention.

When the question is whether respondent had accepted the 54 MSR,J exep_3_ 2017

Amendment No.5 proposal containing lesser quantity and lesser price,

what the respondent did after it received Amendment No.5 through

email dt.22-7-2013 is critical and has a direct bearing, and cannot be

ignored merely because the petitioner at that time was not aware of it.

83. Inter alia the circumstance about nomination by petitioner of

the vessel "Navios Arc" which can carry cargo upto 40,000 MT i.e the

petitioner acting on the Amendment No.5, triggering an estoppel, is

also mentioned in the order of the Arbitral Tribunal in support of its

finding that there is a bilateral agreement to revise the quantity sold

and its conclusion that the respondent's obligation to pay for the

subject cargo was triggered.

84. These circumstances cannot be said to be irrelevant to support

the said conclusion of the Arbitral Tribunal nor can the conclusion be

said to be perverse.

85. Thus, I hold that the Arbitral Tribunal committed no error in

holding that there was a binding agreement between the parties on the

terms contained in e.mail dt.22-07-2013 (the Amendment No.5)

which was an independent agreement and which was acted upon by

both parties i.e. by the petitioner by nominating the vessel "Novios

Arc" and by the respondent by writing letter to the State Bank of India

on 17-08-2013 that there it had in fact accepted such an agreement.

86. In view of the above, the contention of respondent that there

was no valid agreement in the eye of English law on the basis of the 55 MSR,J exep_3_ 2017

proposal contained in the e.mail dt.22-07-2013 between the parties is

rejected.

87. Respondent's plea that by conduct of parties in relation to

amendment nos.1 to 4 (form and format with signatures of both

parties), both parties have agreed to a 'No Oral Modification' clause

in their contractual relationship, cannot be accepted because if the

parties really wanted such a clause, they would have specifically

incorporated it, but admittedly, there is no such clause.

88. It's further plea that the prior amendments were all put in

writing and signed by it and absence of such written document as

regards Amendment No.5 indicate that it was only a proposal which

was never accepted, also cannot be countenanced. The reasoning of

the Arbitral Tribunal that signing and returning of earlier amendments

is nothing more than good post contractual practice in ensuring that all

the documentation was signed off properly and that it is nothing more

than good house keeping, is unexceptionable.

89. Therefore I hold (i) that the Arbitral Tribunal was right in

rejecting the respondent's contention that nomination on 12-08-2013

of the vessel "Navios Arc" with minimum/maximum cargo of

39,000/40,000 MT was not in accordance with the terms of the

contracts (as amended by Amendment No.4) which contemplated

purchase of 50,000 MT; and (ii) that the agreement inferred by the

Arbitral Tribunal on the basis of the terms contained in Amendment 56 MSR,J exep_3_ 2017

no.5 contained in the e-mail dt.22.07.2013 was valid under English

Law.

90. The respondent is also not correct in it's plea that the initial

claim of the petitioner is based on the Amendment no.4 only before

the Arbitral Tribunal and its alternative plea was based on the

proposal in e-mail dt.22.07.2013 on the basis of facts which came into

record during the course of arbitration (such as the two letters

addressed to State Bank of India by the petitioner on 17.08.2013

mentioning that it had a sale contract with petitioner to import 20,000

M.T. of D.A.P.) and so estoppel by conduct cannot be applied on the

basis of events which the petitioner was not aware of at that time.

91. According to respondent, there was in fact a request by the

petitioner to reduce the quantity and price in the meeting between the

representatives of both parties held at New Delhi on 19.07.2013 at

which the respondent, while acknowledging that "a contract is a

contract" requested for price reduction and quantity reduction too.

Ex.69-email dt.19.07.2013 of Mr. Seth addressed to Mr. Keyman

Melih corroborates this. It was in response to this request of the

respondent, Amendment no.5 contained in e-mail dt.22.07.2013

emanated from the petitioner reducing the quantity and price.

92. In the e-mail dt.25.07.2013, the respondent merely stated that it

has to discuss the proposal with its bankers (Ex.72) and would revert.

                                      57                               MSR,J
                                                                exep_3_ 2017




93. The conduct of the respondent in not refusing the Amendment

no.5, and after the vessel 'M.V. Navios Arc' was nominated on

12.08.2013 (Ex.82), not rejecting its nomination immediately but

merely requesting through its e-mail dt.13.08.2013 "to hold the vessel

nomination" are all factors on the basis of which the petitioner

believed that there was an agreement in terms of Amendment No.5.

The conduct of the respondent in addressing letters dt.17.08.2013 to

S.B.I. is an additional circumstance which supports the petitioner's

case since those letters contained an admission by the respondent that

it had entered into a sale contract for 40,000 M.T. with petitioner.

94. For the aforesaid reasons, I am of the view that the

enforcement of the award of the Arbitral Tribunal cannot be refused

under Section 48(1)(a) of the Act.

Whether the Award lacks a judicial approach?

95. It is also the contention of the counsel for petitioner that certain

other e-mails/correspondence exchanged between the parties indicate

that it never agreed to Amendment No.5 and they were not taken into

account by the Arbitrators and this indicates absence of judicial

approach by the Arbitral Tribunal and renders the award in conflict

with basic notions of justice attracting Explanation (1) (iii) clarifying

'conflict with public policy of India'.

96. This contention is without any merit in view of the principle

laid down in Shri Lal Mahal (1 supra) that procedural defects like 58 MSR,J exep_3_ 2017

ignoring/rejecting the evidence in the course of a foreign arbitration

do not lead necessarily to excuse an award from enforcement on the

ground of public policy.

97. Also, the e-mails on which reliance is placed by the respondent

do not in any way reduce the effect of the conduct of the respondent in

writing to the State Bank of India on 17-08-2013 seeking LCs by

stating that it had entered into two agreements to purchase 20,000 MT

each (in all for only 40,000 MT modifying the earlier quantity of

50,000 MT) from the petitioner. No prejudice therefore can be said to

have been caused to the respondent by not referring to the other

e-mails exchanged between the parties.

Whether the award is contrary to the public policy of India? and

Whether the Arbitrators were right in holding that the respondent cannot plead force majeure ?

98. It is the contention of the respondent that the contract

contemplated an LC to be given by State Bank of India, but the said

Bank refused to provide LC facility to the respondent relying on

policy of the Union of India with regard to Fertilizer Price Control

Order under the Essential Commodities Act, 1955.

99. Counsel contended that for 2012-13, the Government approved

proposal for fixation of rates of subsidy on DAP at Rs.14,350/- per

MT in order to make them available at a price lower than its delivered

cost, but for 2013-14, there was a further change made on

03-05-2013/25-06-2013 reducing the subsidy on DAP to Rs.12,350/-

per MT and this was done because of the falling International prices 59 MSR,J exep_3_ 2017

having no corresponding decrease in domestic prices. According to

him, it became mandatory for all Fertilizer Companies to submit

certified Cost Data while claiming subsidy and if MRP is not found

reasonable, the Government would restrict or deny subsidy.

According to him, the State Bank of India was reluctant to open LCs

for the above reason.

100. It is not in dispute that the State Bank of India addressed two

letters to the respondent on 08-07-2013 and 24-08-2013 in response to

the request of the respondent for opening LC to buy the cargo of DAP

from the petitioner.

101. The first letter dt.08-07-2013 gives two reasons for not opening

LC as per the respondent's request: (a) that respondent was

consistently defaulting on its LCs that year and (b) its procurement

price is higher than the current market price and so it would be

difficult for the Bank to approve LCs despite the respondent having

LC limits as there is a risk of further defaults.

102. The second letter dt.24-08-2013 also states that the contract

price was not in accordance with the prevailing market price. No

doubt another reason viz., that there is a difference in the application

of LC (which was made for 40,000 MT DAP purchase) and the

agreement dt.30-04-2013 and Amendment No.4 dt.12-06-2013 (which

mentioned 50,000 MT DAP purchase). There is no mention of the

Government of India Fertilizer Policy at all in this letter.

                                    60                               MSR,J
                                                              exep_3_ 2017




103. In my opinion, the main anxiety of the State Bank of India

appears to be the fact that there was a delay in receipt of Government

subsidy and if there is a high cost of import, it would push up the

respondent's selling cost and increase the subsidy receivables. It

therefore advised in its letter dt.08-07-2013 to the respondent to

reduce input cost and expedite realizations so that there will not be

any risk of further defaults on the LCs. Thus the refusal of the Bank

to open LCs appears to be a purely commercial decision of the Bank

based on bad credit history of the respondent.

104. Moreover, the Office Memorandums dt.03-05-2013 and 26-06-

2013 relied upon by the respondent deal with the price at which a

Company can avail subsidy on DAP, but do not deal with import of

DAP nor do they prohibit it's import. They also did not put any cap on

the price for importing fertilizer. So respondent can still import the

DAP and sell it, but it cannot claim subsidy. So if the respondent

were to import fertilizer at the contractual price, it would not be

committing violation of any law.

105. Also, no where in the contracts entered into between the parties

or four amendments thereto is there any mention about performance

of the contracts being subject to the respondent availing subsidy.

106. A further contention was raised by the respondent that the State

Bank of India refused to open LC in its letter dt.24.08.2013 in view of

the policy change enunciated by the Government of India contained in 61 MSR,J exep_3_ 2017

the notification issued on 03.05.2013 with regard to reduction in the

subsidy of fertilizers and this constituted a force majeure event

absolving the respondent of any liability.

107. This contention is not tenable as the Office Memorandum

dt.03-05-2013 providing subsidy for 2013-14 was issued by the

Government of India much prior to Amendment No.5 dt.22-07-2013.

It therefore cannot be said to be a force majeure event which was

unforeseeable at the time when Amendment No.5 was agreed between

the parties.

108. Counsel for respondent sought to link the conduct of the SBI

also to Sections 10(4) and 10(5) of the Foreign Exchange

Management Act, 1999 (F.E.M.A.) and sought to contend that

pursuant to Section 10(5) of the F.E.M.A., the SBI was required to

satisfy itself of the bona fides of the transaction between the parties in

order to ensure that the transaction did not contravene the provisions

of F.E.M.A. and the letter dt.24.08.2013 of SBI addressed to the

respondent indicated that SBI was not satisfied with the bona fides of

the transaction.

109. Before dealing with the above contention, I shall consider the

provisions of Section 10(4) and 10(5) of the FEMA.

110. Section 10(4) of FEMA requires an authorized person dealing

with Foreign Exchange to comply with the directions and orders of

the Reserve Bank and prohibits him from engaging in any transaction 62 MSR,J exep_3_ 2017

involving Foreign Exchange except with the previous permission of

the Reserve Bank.

111. Section 10(5) requires an authorized person, before undertaking

any transaction in Foreign Exchange on behalf of any person, require

that person to make a declaration and to give such information as will

reasonably satisfy him that the transaction will not involve, and is not

designed for the purpose of any contravention or evasion of the

F.E.M.A. Act or rules and regulations made thereunder, and if such

person refuses to comply with such a requirement or makes only

unsatisfactory compliance therewith, the authorized person shall

refuse in writing to undertake the transaction and shall, if he has

reason to believe that any such transaction or evasion as aforesaid is

contemplated by the person, report the matter to the Reserve Bank.

112. In other words, these provisions require the SBI (the authorized

person) to follow the directions of the Reserve Bank and require any

person approaching it for Foreign Exchange to give a declaration that

the transaction will not involve and is not designed for purpose of any

contravention or evasion of the F.E.M.A. Act. If such person refuses

to give declaration, it can refuse to undertake the Foreign Exchange

transaction and may also report it to the Reserve Bank that it has

reason to believe that such contravention or evasion is contemplated

by the person who approached it.

                                   63                               MSR,J
                                                             exep_3_ 2017




113. In the instant case, the refusal to open LCs by SBI is not on any

of the above grounds, as can be seen from the letters dt.8.07.2013 and

24.08.2013.

The decision in Cruz City 1 Mauritius Holdings (5 supra)

114. More importantly, the Delhi High Court in Cruz City 1

Mauritius Holdings (5 supra) considered the question whether

violation of any regulation or any provision of F.E.M.A. would ipso

jure offend the public policy of India. After considering the decisions

in Renusagar Power Company (3 supra), Shri Lal Mahal (1 supra)

and others, the Delhi High Court held that a contravention of a

provision of law is insufficient to invoke the defence of public policy

when it comes to enforcement of a foreign award; contravention of

any provision of an enactment is not synonymous to contravention of

fundamental policy of Indian Law; the expression "fundamental

policy" connotes the basic and substratal rationale, values and

principles which form the bedrock of laws in our country. It held that

a foreign award may be based on foreign law, which may be at

variance with a corresponding Indian statute and if the expression

"fundamental policy of Indian Law" is considered as a reference to a

provision of the Indian statute, the basic purpose of the New York

Convention to enforce foreign awards would stand frustrated. It

explained that the principal objective of the New York Convention is

to ensure enforcement of Awards notwithstanding that the Awards are

not conformity to the national laws and the objections to enforcement 64 MSR,J exep_3_ 2017

on the ground of public policy must be such that offend the core

values of a Member State's national policy and which it cannot be

expected to compromise and not a provision of any enactment.

115. It held that there is a material change in the fundamental policy

of exchange control as enacted under the Foreign Exchange

Regulation Act, 1993 and the Foreign Exchange Management Act,

1999; that the former was enacted at a time when India's economy

was a closed economy and the accent was to conserve foreign

exchange by effectively prohibiting transactions in foreign exchange

unless permitted; but after liberalization of the economy, it was felt

that it should be repealed and thereafter F.E.M.A. was enacted in

1999. It held that events since 1993 such as substantial increase in the

Foreign Exchange reserves, growth in foreign trade, rationalization of

tariffs, current account convertibility, liberalization of Indian

investments abroad, increased access to external commercial

borrowings by Indian Corporate and participation of Foreign

Institutional Investors in the Stock markets created a paradigm shift in

the statutory policy; and the focus shifted from prohibiting

transactions to a more permissible environment.

116. It explained that the fundamental policy of F.E.M.A. no longer

proscribes or prohibits Indian entities from expanding their business

overseas and accepting risks in relation to transactions carried out

outside India, that the policy now is to manage foreign exchange;

under F.E.M.A. all foreign account transactions are permissible 65 MSR,J exep_3_ 2017

subject to any reasonable restriction which the Government may

impose in consultation with R.B.I.; and it is now permissible not only

to compound irregularities but also seek ex post facto permission. It

therefore held that the question of declining enforcement of a

foreign Award on the ground of any regulatory compliance or

violation of a provision of F.E.M.A. would not be warranted.

117. I respectfully agree with the view expressed by the Delhi High

Court in the above decision.

118. I am of the opinion that firstly, violation of any regulation or

any provision of F.E.M.A. would not ipso jure offend the public

policy of India; and the term "fundamental policy of Indian law" in

Section 48 (2)(b) of the Act permitting an executing Court to refuse

enforcement of a foreign award would not be attracted to the instant

case, not only for the reason that FEMA does not prohibit entering

into oversees transactions provided there is compliance with the

reasonable restrictions imposed by the Government of India in

consultation with the RBI, but also because no evidence is placed on

record by respondent to show that any alleged violation of FEMA was

the cause for its refusal to open LCs. Alternatively, the instant foreign

award based on English law cannot be tested on the basis of an Indian

statute like FEMA and if it is so tested, it would frustrate the basic

purpose of the New York Convention to enforce foreign awards.

119. The Arbitrators held that the contracts were bona fide

transactions, that SBI never raised any doubt about the bona fides of 66 MSR,J exep_3_ 2017

the subject contracts in general, there was no force majeure event

which by due diligence the respondent was unable to prevent or

overcome, and price decline of D.A.P. was not unforeseen or

unforeseeable to the extent that it was a relevant consideration. They

also held that it was a classic case of the respondent attempting to

excuse its breach of contract on force majeure grounds where the

market had moved against it; that Section 10(5) did not make any

mention of the concept of bona fides at all; and the respondent

deliberately did not take steps to obtain LCs on receipt of the SBI

letter dt.24.08.2013 because it wanted to avoid moving forward with

the contracts, as by then, they had become a bad deal. These are all

findings of fact based on appreciation of evidence by the Arbitrators

and are unexceptionable.

WHETHER THE AWARD IS CONTRARY TO MORALITY AND

JUSTICE?

120. In HRD Corporation (6 supra), the Supreme Court has

explained that the terms "morality or justice" occurring in explanation

(1) to Section 48(2)(b) of the Act have been tightened and they have

to be understood as meaning only basic notions of justice and morality

i.e. such notions as would shock the conscience of the Court as

understood in Associate Builders Vs. DDA15. Instance mentioned in

the Associate Builders (15 supra) case of an award being contrary to

justice is one where much larger sum than what was sought is

awarded without any acceptable reason or justification; and

(2015) 3 SCC 49 67 MSR,J exep_3_ 2017

illustration about an award being contrary to morality were confined

to sexual morality only.

121. Applying these tests to the instant award show that it cannot be

said to be contrary to justice or morality and its enforcement cannot be

refused on the said ground.

122. For the reasons given by me in para nos. 98 to 121, I find that

the subject award is not contrary to the 'public policy of India'; that

there factually no violation of F.E.M.A.; and enforcement of a foreign

Award like the subject Award ought not to be declined on any of the

grounds raised by the respondent.

123. Moreover, Explanation 2 to Sec.48(2) of the Arbitration and

Conciliation Act,1996 prohibits a review on merits of the dispute

when considering the question of alleged contravention of

fundamental policy of Indian law. As already noted by me earlier, in

Shri Lal Mahal (1 supra), the Supreme Court followed Renusagar

(3 supra) and held that for the purposes of Section 48(2)(b), the

expression "public policy of India" must be given a narrow meaning

and the enforcement of the foreign award would be refused on the

ground that it is contrary to the public policy of India if it is covered

by one of the three categories enumerated in Renusagar (3 supra),

i.e., (i) fundamental policy of Indian law; or (ii) interests of India; or

(iii) justice or morality. It also declared that Section 48 does not give

an opportunity to have a "second look" at the foreign award in the 68 MSR,J exep_3_ 2017

award enforcement stage and the scope of enquiry under Section 48

does not permit review of the foreign award on merits.

124. Accordingly, I reject all the contentions raised by the

respondent opposing the execution of the Award dt.05.04.2016 passed

by the Arbitral Tribunal and hold that it is executable.

125. Consequently, there shall be an order attaching the building

with D.No.8-2-248, Nagarjuna Hills, Punjagutta, Hyderabad - 500082

as well as shares in Jaiprakash Engineering and Steel Company

Limited (JESCO) owned by the respondent for recovery of US $

2,143,168 which was awarded to the petitioner under the said Award

under Order XXI Rule 46 and 54 of Civil Procedure Code, 1908.

126. For further steps, list on 29.11.2018

__________________________________ JUSTICE M.S.RAMACHANDRA RAO Date: 27-11-2018

Note :- L.R. Copy to be marked.

B/o.

Ndr/Vsv

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Media

 
 
Latestlaws Newsletter