Citation : 2023 Latest Caselaw 3977 Tel
Judgement Date : 15 November, 2023
THE HONOURABLE SMT. JUSTICE M.G.PRIYADARSINI
Civil Miscellaneous Appeal No.1007 OF 2008
JUDGMENT:
Aggrieved by the judgment dated 05.05.2006 (hereinafter
will be referred as 'impugned judgment') in O.P.No.1929 of 2002
on the file of learned XIV Additional Chief Judge, City Civil
Court, Hyderabad, the respondents filed the present Civil
Miscellaneous Appeal to set aside the impugned judgment.
2. For the sake of convenience, hereinafter, the parties will
be referred as per their array before the learned XIV Additional
Chief Judge, City Civil Court, Hyderabad.
3. The brief facts of the case as can be seen from the record
available before this Court are as under:
a) The claimant undertook a contract from the department
to repair and re-erect the sheds in military campus for
Rs.15,77,944.22 paise. The claimant commenced the work on
14.07.1997 and he has to complete the work by 13.07.1998.
However, the respondent extended the time twice i.e., by
31.08.1998 and 28.09.1998. However, the claimant stopped
the work, as such the department issued notices calling up the
claimant to execute the remaining work and threatening to 2 MGP,J CMA_1007_2008
cancel the contract. The department requested the claimant to
start the work and complete the same but the claimant failed to
do so, however, indulging in correspondence. Ultimately, the
contract was cancelled by the department under clause 54 of
the General Conditions of the Contract with effect from
08.02.1999 by the first respondent. An instruction was given to
the claimant to be present for taking inventory of the material
from the spot. The claimant protested the cancellation of
contract and sought for payment of final bill. The department
took inventory of material and entrusted the remaining work to
a third party. The department did not even pay the final bill of
the claimant as they have got a right to recover any loss suffered
by them by entrusting the work to third party. Though the
claimant requested the department to appoint an Arbitrator, the
Department failed to appoint Arbitrator, as such, the Claimant
approached the High Court for appointment of Arbitrator by
Arbitration Application No.40/2000. The respondent No.4 was
appointed by this Court as an Arbitrator, wherein the claimant
filed claim statement alleging that the department committed
breach of contract and that he is entitled to claim of
Rs.18,00,000/-. The Department filed counter denying that
they are responsible for breach of contract and alleging that
claimant himself was responsible for breach of contract. Apart 3 MGP,J CMA_1007_2008
from denying the averments of the claimant in the claim
application, the department has made eight counter claims
under different heads. the learned Arbitrator framed as many as
20 issues and awarded some amounts in favour of the claimant
and some amounts in favour of the department and after
adjusting the claim and counter claims, it was held that the
claimant himself has to pay Rs.4,29,355/- with interest @ 6%
per annum from 31.01.2001 till realization in favour of the
department, Rs.5,000/- towards costs of reference in favour of
the department, Rs.2,500/- towards reimbursement of share of
the secretarial expenses in favour of the department,
Rs.75,000/- towards Arbitrator's fee and Rs.2,500/- towards his
share of secretarial expenses.
4. Aggrieved by the Award, dated 24.06.2002 passed by the
Respondent No.4, the claimant has filed O.P.No.1929 of 2002
under Section 34 of the Arbitration and Conciliation Act, 1996
(hereinafter will be referred as 'the Act'), which was allowed in
part by ordering that the amount payable by the claimant to the
department is reduced to Rs.2,79,355/- with interest @ 6% per
annum from 31.01.2001 till the date of realization. Aggrieved
by the same, the Department filed the present Civil
Miscellaneous Appeal to set aside the impugned order.
4 MGP,J
CMA_1007_2008
5. Heard both sides and perused the record.
6. The first and foremost contention of the learned counsel
for the Department/Appellant is that learned Judge erred in
holding that the Arbitrator is not justified in awarding
Rs.1,50,000/- as damages for the delay in execution of the
work, which is contrary to the condition No.50 of the General
Conditions of Contract and the Arbitrator after considering all
the aspects only awarded Rs.1,50,000/- towards damages. It is
seen that the learned Arbitrator i.e., Respondent No.4 in his
Award dated 24.06.2002 has directed the claimant to pay
Rs.4,29,355/- which includes the damages to a tune of
Rs.1,50,000/-. Thereafter, the learned XIV Additional Chief
Judge, Hyderabad has set aside the said award to the extent of
awarding Rs.1,50,000/- and thereby reduced the amount
payable by the claimant to the department from Rs.4,29,355/-
to Rs.2,79,355/-. Thus, the only grievance of the Department
in this appeal is setting aside the Award passed by respondent
No.4 to the extent of awarding Rs.1,50,000/-.
7. The Arbitrator i.e., respondent No.4 in his Award observed
that there was default on the part of claimant in concluding the
contract within specific time in spite of extending the time to
complete the work. Even the learned XIV Additional Chief 5 MGP,J CMA_1007_2008
Judge, Hyderabad in the impugned judgment observed that the
claimant could not complete the work in the schedule time and
there is negligence on the part of the claimant, who has
committed breach of contract. However, learned XIV Additional
Chief Judge, Hyderabad in the impugned judgment opined that
the quantum of damages to a tune of Rs.1,50,000/- awarded by
the learned Arbitrator was not justified as the Department failed
to submit any proof to show that it suffered damages to the
extent of Rs.1,50,000/-. It is to be seen that learned XIV
Additional Chief Judge, Hyderabad has not reduced the
damages but in fact completely exonerated the claimant from
paying damages. There is no explanation in the impugned order
as to why the claimant was completely exonerated from paying
damages, more particularly, when the learned XIV Additional
Chief Judge, Hyderabad observed in the impugned judgment
that the department suffered loss by re-entrusting the work to
third party.
8. Merely because the Arbitrator has awarded
Rs.2,04,052.60 paise towards extra expenditure incurred by the
Department for getting the left work completed through third
party, the claimant cannot be exonerated entirely from payment
of liquidated damages. As can be seen from the record, 6 MGP,J CMA_1007_2008
Condition No.50 of the General Conditions of contract between
the parties, there is a specific clause for fixing the liquidated
damages. No doubt, compensation payable under Sections 73,
74, 75 of the Contract Act is only for loss or damage caused by
the breach and not on account of the mere act of breach. If in
any case the breach has not resulted in or caused any loss or
damage to a party, compensation cannot be claimed. But in the
case on hand, there was breach of contract on the part of
claimant and the Department has also suffered loss to a tune of
Rs.2,04,052.60 paise.
9. Damages are a type of compensation granted to the party,
who has been harmed to allow them to reclaim their position
before the breach. Damages are claimed in different contracts
for a variety of reasons, including loss of profit, opportunity,
overheads, and so on. There are two sorts of damages i.e.,
liquidated and un-liquidated. The court may award un-
liquidated damages, the amount of which is not known ahead of
time. The term 'liquidated damage' is not specified in the Indian
Contract Act, 1872, however, Section 74 defines the parts that
make up the definition of liquidated damage. So, if a contract
states that a certain number will be awarded in the case of a
breach, the innocent party will be allowed to recover damages 7 MGP,J CMA_1007_2008
equal to or less than that amount, based on the facts and
circumstances of each case, up to the maximum amount stated
in the contract. As stated supra, there is specific condition
No.50 of the General Conditions of contract fixed the liquidated
damages. In such circumstances, the claimant is liable to pay
damages to the Department for breach of contract. Damages
are granted to compensate the injured party and, as a result, it
places the aggrieved party in the very same situation as it would
have been if the breach had not occurred. Thus, there is no
irregularity or infirmity in the Award passed by the learned
Arbitration while granting damages to a tune of Rs.1,50,000/-
in the Award, dated 24.06.2002.
10. The other contention of learned Government Pleader for
Arbitration representing the Department/appellant is that the
learned Judge agreed with the findings of Arbitrator, however,
interfered and set aside the award of Arbitrator exceeding the
scope for setting aside award under Section 34 of the
Arbitration and Conciliation Act as if he is sitting in appeal over
arbitrator award. It is further contented that the learned Judge
erred in observing that Apex Court in Oil and Nvatural Gas
Company Limited (ONGC) v. Saw Pipes Limited 1 certain
AIR 2003 SC Page 2629 8 MGP,J CMA_1007_2008
grounds for setting aside the award were added besides
whatever mentioned in Section 34 of the Arbitration and
Conciliation Act. In support of above contention, the learned
Government Pleader for Arbitration relied upon a decision in
the Project Director, National Highways No.45 E and 220
National Highways Authority of India v. M. Hakeem 2, the
Apex Court at paragraph Nos.40 and 46 held as follows:
"40. It can therefore be said that this question has now been settled finally by at least 3 decisions of this Court. Even otherwise, to state that the judicial trend appears to favour an interpretation that would read into Section 34 a power to modify, revise or vary the award would be to ignore the previous law contained in the 1940 Act; as also to ignore the fact that the 1996 Act was enacted based on the UNCITRAL Model Law on International Commercial Arbitration, 1985 which, as has been pointed out in Redfern and Hunter on International Arbitration, makes it clear that, given the limited judicial interference on extremely limited grounds not dealing with the merits of an award, the 'limited remedy' under Section 34 is co-terminus with the 'limited right', namely, either to set aside an award or remand the matter under the circumstances mentioned in Section 34 of the Arbitration Act, 1996.
46. Quite obviously if one were to include the power to modify an award in Section 34, one would be crossing the Lakshman Rekha and doing what, according to the justice of a case, ought to be done. In interpreting a statutory provision, a Judge must put himself in the shoes of Parliament and then ask whether Parliament intended this result. Parliament very clearly intended that no power of modification of an award exists in Section 34 of the Arbitration Act, 1996. It is only for Parliament
Laws (SC) 2021 7 20 9 MGP,J CMA_1007_2008
to amend the aforesaid provision in the light of the experience of the courts in the working of the Arbitration Act, 1996, and bring it in line with other legislations the world over."
11. The Apex Court in ONGC's case (supra) has enumerated
certain grounds to set aside the award passed by an Arbitrator
under Section 34 of the Act. However, in the case on hand,
none of the grounds mentioned in ONGC's case (supra) are
available for the learned XIV Additional Chief Judge, City Civil
Court, Hyderabad to set aside the Award passed by the
respondent No.4, more particularly with regard to damages
when there is specific condition that in case of default by either
of the parties, the party, which suffered loss is entitled for
damages. No doubt the Arbitrator awarded Rs.2,04,052.60
paise in favour of the Department as amount found due towards
extra expenditure incurred for getting left over work completed.
But there is no explanation as to what was the loss suffered by
the Department for non completion of the work within
stipulated period. In such circumstances, Condition No.50 of
the General Conditions of contract comes into picture and the
said condition stipulates that if the contractor fails to complete
the work within the time, the aggrieved is entitled for 10% of the
contract as liquidated damages. Therefore, the learned XIV
Additional Chief Judge, City Civil Court, Hyderabad ought not 10 MGP,J CMA_1007_2008
to have interfered with the findings of the learned Arbitrator so
far as awarding damages to the extent of Rs.1,50,000/- is
concerned, more particularly, when the scope and ambit of the
Court under Section 34 of the Act to interfere with Award
passed by the Arbitrator is limited until and unless the
irregularity goes to the root of the matter. In the case on hand,
there is no dispute that the contractor has committed breach of
contract for which the Arbitrator has awarded liquidated
damages in favour of the Department. Thus, on the face of the
record, there is no patent irregularity in the Award passed by
the learned Arbitrator.
12. In view of the above discussion, viewed from any angle,
there are no grounds at all to interfere with the findings of the
learned Arbitrator in the Award, dated 24.06.2002. Thus, the
learned XIV Additional Chief Judge, City Civil Court, Hyderabad
has committed an irregularity in modifying the Award, dated
24.06.2002, more particularly, when the scope and ambit of
interfering with the Award under Section 34 of the Act is very
restricted as stated supra. Hence, the Department is entitled
for liquidated damages to the tune of Rs.1,50,000/- towards
liquidated damages as rightly awarded by the learned
Arbitrator.
11 MGP,J
CMA_1007_2008
13. Accordingly, the Civil Miscellaneous Appeal is allowed by
setting aside the judgment dated 05.05.2006 in O.P.No.1929 of
2002 on the file of learned XIV Additional Chief Judge, City Civil
Court, Hyderabad to the extent of exonerating the
claimant/contractor from paying liquidated damages of
Rs.1,50,000/- and thereby the Award dated 24.06.2002 passed
by the respondent No.4/learned Arbitrator is confirmed. There
shall be no order as to costs.
Pending Miscellaneous applications, if any, shall stand
closed.
_______________________________
JUSTICE M.G.PRIYADARSINI
Date: 15.11.2023
AS
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!