Monday, 13, Apr, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Manda Prakash, vs Bobbalaraji Reddy,
2023 Latest Caselaw 428 Tel

Citation : 2023 Latest Caselaw 428 Tel
Judgement Date : 30 January, 2023

Telangana High Court
Manda Prakash, vs Bobbalaraji Reddy, on 30 January, 2023
Bench: Ujjal Bhuyan, N.Tukaramji
         THE HON'BLE THE CHIEF JUSTICE UJJAL BHUYAN
                                       AND
              THE HON'BLE SRI JUSTICE N. TUKARAMJI


                   WRIT APPEAL No.121 of 2023

JUDGMENT: (Per the Hon'ble the Chief Justice Ujjal Bhuyan)


       Heard Mr. G.Kishore Kumar, learned counsel for the

appellant and Mr. P.Sri Raghu Ram, learned Senior

Counsel for respondent No.1.                       We have also heard

Ms. Borra Lakshmi Kanakavalli, learned Assistant

Government Pleader for Municipal Administration & Urban

Development Department for respondent No.2 and

Mr. S.Surender Reddy, learned counsel for respondents

No.3 and 4.

2. This appeal is directed against the order dated

06.12.2022 passed by the learned Single Judge allowing

W.P.No.40836 of 2022 filed by respondent No.1 as the writ

petitioner.

3. Respondent No.1 had taken exception to the

proceedings of Greater Warangal Municipal Corporation

(briefly, 'the Corporation' hereinafter) dated 22.07.2022

cancelling the building permission granted on 19.04.2022.

4. Respondent No.1 contended before the learned Single

Judge that he along with one Satyapal Reddy had

purchased land admeasuring Ac.1.20 guntas in Survey

Nos.561 and 564 situated at Ursu Village, Khila Warangal

Mandal in the district of Warangal (briefly, 'the subject

land' hereinafter) through a registered sale deed dated

19.02.1999. The said Satyapal Reddy sold his share of the

land in favour of respondent No.1 by registered sale deed

dated 18.10.2021. Thus, respondent No.1 became the

absolute owner and possessor of the entire subject land.

He made an application before the Corporation for seeking

permission for construction of residential house. By

proceedings dated 19.04.2022, permission was granted to

an extent of 4749.85 square yards.

5. When respondent No.1 started construction of the

compound wall, show cause notice dated 10.06.2022 was

issued by the Corporation calling upon respondent No.1 to

show cause as to why building permission granted earlier

should not be cancelled. The show cause notice was

issued on the basis of representation submitted by the

appellant and respondent No.5 ('objectors' hereinafter).

The objectors had pointed out that building permission

was obtained suppressing order passed in W.P.No.26340 of

2003 as well as pendency of O.S.No.82 of 2019. It was

contended by respondent No.1 before the learned Single

Judge that respondent No.1 was not a party to

W.P.No.26340 of 2003. Thus, there was no suppression of

material facts, besides there was no statutory violation of

any provision of the Telangana Municipalities Act, 2019, to

warrant issuance of show cause notice for cancellation of

building permission granted.

6. On behalf of the Corporation, it was submitted before

the learned Single Judge that in view of status quo order

passed in W.P.No.26340 of 2003, Corporation had revoked

the building permission.

7. Insofar appellant is concerned, learned Single Judge

noted that appellant had refused to receive the notice

issued by the Court and therefore he would be deemed to

have been served. On the other hand, learned counsel for

respondent No.5 was found to be not present.

8. This has been clarified by learned counsel for the

appellant stating that appellant had appeared through

counsel, but the counsel was delayed in reaching the

Court.

9. Learned Single Judge by the order dated 06.12.2022

allowed the writ petition in the following manner:

4. In the impugned order dated 22.02.2022, the respondents have repeatedly mentioned about the status-quo orders passed by this court in W.P.No.26340 of 2003. This court has disposed of the said writ petition by order dated 29.08.2017 wherein this court has observed that the aggrieved person shall invoke the common law remedy claiming the title over the said land and also seek appropriate orders, if any, from the court and till such time, status-quo obtained as on that date shall be maintained with regard to possession and entries made in the record. Admittedly, the petitioners therein have already filed a civil suit i.e.O.S.No.82 of

20l9. Hence, the respondents cannot say that there is a status-quo order and the same was suppressed by the petitioner and all the more, the petitioner is not a party to the said writ petition. Further, there no restraint orders are passed in O.S.No.82 of 20l9 either restraining the petitioner or the respondents from going ahead with the construction. As the 4th respondent has refused to receive the notice, it amounts to deemed service of notice and learned counsel for the 5th respondent is not present. Taking into consideration all the above aspects, the proceedings dated 22.07.2022 and intimation letter dated 02.11.2022 are liable to be set aside.

5. The writ petition is accordingly allowed setting aside the proceedings dated 22.07.2022 and intimation letter dated 02.11.2022 passed by the respondents. There shall be no order as to costs.

10. From the above, it is seen that learned Single Judge

found from the record that W.P.No.26340 of 2003 was

disposed of by this Court on 29.08.2017 relegating the

parties therein to the forum of civil Court and till such time

status quo as regards possession was directed to be

maintained. Thereafter, appellant filed civil suit, being

O.S.No.82 of 2019. There is no injunction order passed in

the civil suit. Once, the civil suit was instituted by the

appellant, the status quo order passed by this Court in

W.P.No.26340 of 2003 ceased to operate. Therefore, there

was no status quo order restraining the Corporation from

considering the request of respondent No.1 for building

permission. That apart, respondent No.1 was not a party

to W.P.No.26340 of 2003. Therefore, learned Single Judge

set aside the proceedings dated 22.07.2022 and

consequential letter dated 02.11.2022.

11. Prima facie, a view can be taken that once building

permission is granted, the same should not be cancelled

unless it was obtained fraudulently or there is any violation

of the building permission or of the statute.

12. However, considering the fact that appellant, who

had lodged objection before the Corporation leading to

cancellation of building permission, did not get an

adequate opportunity to contest the proceedings, we are of

the view that it would be in the interest of justice, if the

matter is remanded back to the learned Single Judge to

give an opportunity of hearing to the appellant as well as

respondent No.5 and thereafter pass a fresh order in

accordance with law. In the meanwhile, having regard to

the substance of the order dated 06.12.2022 and the view

that we have taken, proceedings dated 22.07.2022 as well

as the consequential letter dated 02.11.2022 shall remain

stayed for a period of 6 (six) weeks whereafter the same

shall be subject to such order as may be passed by the

learned Single Judge.

13. Ordered accordingly.

14. Writ appeal is accordingly disposed of.

Miscellaneous applications pending, if any, shall

stand closed. However, there shall be no order as to costs.

______________________________________ UJJAL BHUYAN, CJ

______________________________________ N. TUKARAMJI, J 30.01.2023 vs

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IDRC

 
 
Latestlaws Newsletter