Sunday, 12, Apr, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

M/S Abhishek Business Private Limited vs M/S Blue Nile Developers Pvt Ltd
2023 Latest Caselaw 4423 Tel

Citation : 2023 Latest Caselaw 4423 Tel
Judgement Date : 29 December, 2023

Telangana High Court

M/S Abhishek Business Private Limited vs M/S Blue Nile Developers Pvt Ltd on 29 December, 2023

          THE HONOURABLEJUSTICE SRI J. SREENIVASRAO

                      ARB.APPL.No.190 OF 2022

ORDER:

The Applicant filed this application under Section 11 (5) and (6) of

the Arbitration and Conciliation Act, 1996 (R/w settlement of appointment

of arbitrator), 1996 (for short "the Act") to appoint a sole arbitrator to

adjudicate the claims and disputes between the applicant and respondent

pursuant to the "Memorandum of Understanding" (brevity "MOU") dated

19.07.2012.

Factual Matrix:

2. The Applicant is a company incorporated under the Indian

Companies Act, 1956, engaged in various business activities, such as,

supply of industrial goods, commercial goods, household goods,

construction material, agriculture and wholesale trading. The applicant

submits that in 2012, the Respondent had approached the Applicant for

investment in a real estate project named "Pebble Beach Villas" in

Visakhapatnam. Accordingly, "MOU" was entered by both the parties on

19.07.2012, stipulating the joint development of the project with a 25%

equity investment by the Applicant. The project has to be completed within

a period of 24 months. The Applicant invested an amount of more than Rs.

7,50,00,000/- crores in the said project in three tranches. But, disputes

were arose with regard to land documentation, delays in approvals, and

JSR, J

discrepancies arose. The Respondent failed to provide required project

information. Upon scrutiny, it was discovered that project funds were

misappropriated by the directors. The Applicant initiated insolvency

proceedings before NCLT (National Company Law Tribunal), which were

later withdrawn with a liberty to approach appropriate tribunal by its

order dated 08.09.2022.

2.1 That the applicant has demanded the respondent to return back the

investment made by it along with interest and further stated that it is no

longer interested in jointly developing the said project with the respondent

and also issued legal notice dated 14.04.2020 demanding the respondent

to pay a sum of Rs.2,25,00,000/- with interest on the ground that

respondent failed to adhere to the terms and conditions mentioned in

"MOU". Despite of several promises, respondent did not repay the full

investment made by the applicant and the project was also stalled. At that

stage, applicant got issued notice dated 14.07.2022 invoking the

arbitration clause IV-9 of "MOU" nominating Sri. B.Prakash Rao Retd.

High Court Judge, as the sole arbitrator. However, respondent has not

given consent nor issued any reply. Hence, the applicant filed present

application.

3. Respondent filed counter denying the allegations inter alia

contending that the claim made by the applicant for repayment of Rs.

JSR, J

2,25,00,000/- with interest @18% from 2015, is time barred and the cause

of action arose in 2015 and suit for recovery of money shall be filed within

3 years, i,e., on and before 2018. The "MOU" is not properly stamped as

per the provisions of Indian Stamp Act, 1899 (for short, 'the Act') unless

and until such deficit stamp duty paid through proper procedure under

the Act. Applicant is not entitled to seek any relief much less the relief of

appointment of arbitrator basing upon the above said document.

4. Heard Sri Sheelam Ashok Reddy, learned counsel for the

applicant and Sri. P. Ramesh babu, learned counsel for the

respondent.

5. Learned counsel for the applicant submits that the applicant

company has entered into "Memorandum of Understanding" on

19th July, 2012 with the respondent intending to jointly develop the

project under the name and style of "Peddle Beach Villas" with a 25%

equity investment by the Applicant. The completion of said project within

24 months from the date of granting of plan of approval. The respondent

has committed several illegal activities, including gross mismanagement

and also misappropriation of funds and the respondent failed to repay the

principal amount of Rs. 1,20,73,000/- along with 18% interest from 2015.

In 2018, the respondent made a partial payment of Rs. 80,00,000/- which

was credited towards the interest on the principal amount. Thereafter, the

JSR, J

respondent has not paid any further payment, resulting in default on both

the principal and accrued interest and the respondent liable to pay a total

amount of Rs. 2,25,00,000/- inclusive of the principal sum and interest at

the rate of 18%.

6. He further contended that in spite of several requests made by the

applicant through mails, respondent did not repay the amounts and at

that stage, the applicant got issued a legal notice dated 14.04.2020

demanding the respondent to pay a sum of Rs. 2,25,00,000/- including

interest. Regardless of the said notice, the respondent has neither

complied with the said demands nor replied to the said notice. Having left

with no other alternative, the applicant had issued notice dated

14.07.2022 invoking arbitration clause IV-9 of "MOU" nominating retired

High Court Judge as arbitrator. However, the respondent neither given

consent nor issued any reply. He further contented whether claim made by

the applicants within the period of limitation or not and whether the

"MOU" is required stamp duty or not those aspects will be decided by the

arbitral tribunal and the application under section 11(5)&(6) is

maintainable.

7. Per contra, learned counsel for respondent contented that the claim

made by the applicant in the application is barred by limitation and

JSR, J

"MOU" is not properly stamped and required stamp duty and basing upon

such document the applicant cannot seek appointment of arbitrator.

8. Having considered the rival submissions made by the respective

parties and after perusal of the material available on record, it reveals that

the applicant company and the respondent have entered into a "MOU" on

19.07.2012, for a joint development of project styled and named "Peddle

Beach Villas". The specific claim of the applicant is that the respondent is

carrying out illegal activities, mismanagement and misappropriation of

funds, violating the terms and conditions of "MOU". The applicant got

issued legal notice dated 14.04.2020 demanding the respondent to return

back the investment made by it along with interest amount of

Rs.2,25,00,000/- on the ground that the respondent failed to adhere to

the "MOU" terms and stated in the said notice that the applicant is no

longer interest in jointly developing the said project with the respondent.

Despite of several promises, the respondent did not repay the full

investment and the project stalled. The applicant claims non-repayment of

principal amount of Rs.1,20,73,000/- with 18% interest since 2015.

When the respondent failed to repay the said amount, the applicant issued

notice dated 04.07.2022 invoking the arbitration clause IV-9 of "MOU"

dated 19.07.2012 seeking resolution for outstanding amounts by

nominating retired High Court Judge, as a sole arbitrator, to adjudicate

JSR, J

the disputes between the parties. However, respondent has not given

consent nor issued any reply.

9. It is very much relevant to extract the clause IV-9 of the

Memorandum of Understanding dated 19.07.2012 which reads as follows:

9. This MOU supersedes any other oral or written agreement between the First and Second Party. Any dispute between the parties regarding matters contained in this MOU shall be resolved by arbitration as per the Arbitration and Conciliation Act, 1996. The Place of Arbitration shall be at Hyderabad, Andhra Pradesh and the proceedings shall be in English. The Place of legal jurisdiction shall be Hyderabad, Andhra Pradesh.

10. The objection raised by the respondent that the claim made by the

applicant is barred by limitation and the "MOU" was not properly stamped,

these aspects can gone into by the arbitral tribunal, as purview of section

11 or 8 of the Act is very limited, whether there is any arbitral disputes

between the parties or not. Admittedly, the parties have entered "MOU"

dated 19.07.2012 and disputes were arose between the parties. As per

clause IV-9 of "MOU" the parties agreed to settle the disputes through

arbitration. Hence, the view of this Court is that there is arbitral dispute

between the parties.

11. It is also relevant to place on record of the seven bench Judges of

the Hon'ble Apex court In M/s Bhaskar Raju and Brothers and Anr v.

M/s Dharmaratnakara Rai Bahadur Arcot Narainswamy Mudaliar

JSR, J

Chattram & Other Charities and Ors 1 , overruling the earlier the

judgments of N. N. Gobal mercantile (p) ltd. V. Indo Unique Flame

ltd. 2 and SMS Tea Estates (P) Ltd. v. Chandmari Tea Co. (P) Ltd., 3

holding that Non-stamping or inadequate stamping is a curable defect and

an objection as to stamping does not fall for determination under Section 8

or 11 of the Arbitration Act. The concerned court must examine whether

the arbitration agreement is exist between the parties or not and all the

other objections and disputes including stamping of agreement falls within

the ambit of arbitral tribunal only.

12. It is already stated 'supra' that the objection raised by the

respondent that the claim made by the applicant is barred by limitation

and document "MOU" is not stamped properly, these aspects have to be

adjudicated by the arbitral tribunal and the application filed by the

applicant for seeking appointment arbitrator invoking clause IV-9 of

"MOU" dated 19.07.2012 is very much maintainable under Section 11 (5)

or (6) of the Act.

13. For the foregoing reasons as well as the law laid down by the

Hon'ble Apex Court, Sri. P. Naveen Rao, Retired High Court Judge,

H.No.3001, My Home Bhooja, Block-A, Plot Nos.22-24 & 31-33,

Raidurgam, K.V Raga Reddy District, Telangana state-500081 is

Curative Petition (C) No. 44 of 2023 (2023INSC1066) 2 2023 (7) SCC 1 3 (2011) 14 SCC 66

JSR, J

appointed as sole Arbitrator, who will adjudicate the dispute between the

parties arising out of the "MOU" dated 19.07.2012.

14. The learned Arbitrator shall fix his own remuneration upon

deliberation and consultation with the parties. He shall also estimate the

cost and expenses for the secretarial assistance and other incidental

expenditure of the arbitration proceedings. The parties will bear the

expenses of the arbitration proceedings in equal share.

15. Accordingly, the Arbitration Application is allowed. No

costs.

As a sequel there to, miscellaneous applications, if any,

pending in this arbitration application, shall stand closed.

______________________ J. SREENIVAS RAO, J

Date: 29.12.2023

mar

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Media

 
 
Latestlaws Newsletter