Sunday, 12, Apr, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Md, Apcpdcl, Hyderabad And 3 Others vs Director, M/S Suguna Metals Pvt Ltd, ...
2023 Latest Caselaw 4342 Tel

Citation : 2023 Latest Caselaw 4342 Tel
Judgement Date : 16 December, 2023

Telangana High Court

Md, Apcpdcl, Hyderabad And 3 Others vs Director, M/S Suguna Metals Pvt Ltd, ... on 16 December, 2023

  THE HON'BLE THE CHIEF JUSTICE ALOK ARADHE

                             AND

 THE HON'BLE SHRI JUSTICE ANIL KUMAR JUKANTI


              WRIT APPEAL No.1006 of 2012


JUDGMENT:

(Per the Hon'ble the Chief Justice Alok Aradhe)

Mr. R.Vinod Reddy, learned counsel representing

Mr. O.Manohar Reddy, learned counsel for the appellants.

Mr. D.V.Nagarjuna Babu, learned counsel for the

respondent.

2. This intra court appeal is filed against an order

dated 11.04.2012 passed by the learned Single Judge in

W.P.No.17287 of 2009, by which writ petition preferred by

the respondent has been allowed.

3. Facts giving rise to filing of this appeal briefly

stated are that the respondent is a private limited

company, which has established an industrial unit for

manufacture of M.S. Billets. The respondent obtained

high tension power supply from the appellants with

contracted maximum demand of 4900 KVA. Thereupon by ::2::

an order dated 13.11.2007, the same was sanctioned. The

respondent paid a sum of Rs.51,21,620.00 towards service

line charges for laying an independent line from Parigi sub-

station to the respondent's factory at Narayanapur Village,

covering distance of about 7.5 kilometers. It is not a

disputed fact that the respondent carried out the work of

laying the service line at its own cost and the appellants

accepted 10% of the service line charges i.e., a sum of

Rs.5,12,162.00 towards supervision charges. The

respondent got the load of independent 33 KV feeder from

Parigi sub-station to its factory under the supervision of

the officers of appellant No.1. It is also not in dispute that

the respondent had paid a sum of Rs.49,89,750.00 towards

development charges at the rate of Rs.1,200.00 per KVA

and an amount of Rs.73,50,000.00 towards security

deposit. The power supply was released to the

respondent's unit on 22.11.2008.

4. Subsequently, the respondent submitted an

application seeking additional load of 1100 KVA which was

released on 14.05.2009. It is also not in dispute that ::3::

except the respondent's unit, the feeder does not serve any

other consumer. The feeder was laid by the respondent at

its cost under the supervision of officers of appellant No.1

duly paying supervision charges.

5. However, the appellants by a notice dated

10.08.2009 raised a demand levying voltage surcharge for

the months of December, 2008 and January, March, April

and May, 2009. The appellants thereupon challenged the

aforesaid notice in a writ petition. The learned Single

Judge has allowed the writ petition inter alia on the ground

that the feeder in question is a dedicated feeder and

therefore, no voltage surcharge can be levied on the

respondent. In the aforesaid factual background, this intra

court appeal has been filed.

6. Learned counsel for the appellants has

submitted that learned Single Judge erred in allowing the

writ petition and ought to have appreciated that the

correspondence between the officers of the Department

cannot be taken into consideration for holding that the

respondent is drawing power from a dedicated feeder.

::4::

7. On the other hand, learned counsel for the

respondent has supported the order passed by learned

Single Judge.

8. We have considered the submissions made on

both sides and have perused the record.

9. The fact that the subject feeder was an

independent feeder, which has not been disputed by the

appellants. It is also not in dispute that the said feeder

was laid down by the respondent at its cost under the

supervision of officers of appellant No.1 by duly paying the

supervision charges and after depositing all the required

amounts either towards service line charges or

development charges or security deposit, etc. It is also not

in dispute that the said feeder is not serving any other unit

or the consumer and is exclusively supplying power to the

respondent's unit.

10. In view of the aforesaid admitted facts emerging

from the record, which even otherwise have not been

disputed by the appellants in their counter, the learned ::5::

Single Judge has rightly recorded the finding that no

voltage surcharge could have been demanded from the

respondent.

11. For the aforementioned reasons, we do not find

any ground to differ with the view taken by learned Single

Judge.

12. In the result, the writ appeal fails and is hereby

dismissed. There shall be no order as to costs.

Miscellaneous applications, if any pending, shall

stand closed.

_______________________________ ALOK ARADHE, CJ

_______________________________ ANIL KUMAR JUKANTI, J Date: 16.12.2023 KL

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Media

 
 
Latestlaws Newsletter