Friday, 08, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Itd Cementation India Limted vs Madhucon Projects Limted
2022 Latest Caselaw 979 Tel

Citation : 2022 Latest Caselaw 979 Tel
Judgement Date : 3 March, 2022

Telangana High Court
Itd Cementation India Limted vs Madhucon Projects Limted on 3 March, 2022
Bench: Satish Chandra Sharma, Abhinand Kumar Shavili
THE HON'BLE CHIEF JUSTICE SATISH CHANDRA SHARMA
                              AND
 THE HON'BLE SRI JUSTICE ABHINAND KUMAR SHAVILI
      Commercial Court Appeal No.63 of 2019

JUDGMENT:     (Per Hon'ble Justice Abhinand Kumar Shavili)


     This Commercial Appeal is filed under Section

13(1) of the Commercial Courts, Commercial Division

and Commercial Appellate Division of High Court's Act,

2015 aggrieved by the order dated 11.06.2018 passed

in C.O.S.S.R.No.483 of 2018 by the Commercial Court

- cum - XXIV Additional Chief Judge, City Civil Court,

Hyderabad.

2.   Heard    Mr.    M.S.      Srinivasa       Iyengar,      learned

counsel for the appellant and Mr. S. Srinivasa Reddy,

learned counsel for the respondent.

3. The above suit had been filed by the appellant

against the respondent for recovery of a sum of

Rs.1,47,57,653/- together with interest at the rate of

13.5% from the date of suit till the date of realisation.

                            ::2::                   HC,J & AKS,J
                                                 comca_63_2019




4. It is the case of the appellant that he had

entrusted sub-contract work to the respondent in the

year 2015. Prior to that, M/s. Barasat Krishnagar

Expressways Ltd. (BKEL) was entrusted contract by

the respondent. It further contended that the Bills

pertaining to the contract, i.e., the last RA Bills were

presented on 22.07.2015; and that the contract

between him and the respondent was terminated w.e.f.

03.05.2016. According to the appellant, the cause of

action arose on 03.05.2016 when the contract was

terminated and the suit was filed on 01.06.2017 well

within time and the same is not barred by limitation.

But the Court below by order dated 11.06.2018,

rejected the suit at the admission stage holding that

the cause of action arose on 06.12.2013; that plaintiff

had also filed a memo stating that it had entered into a

Letter of Intent dated 06.12.2013 with the defendant

and also contract agreement in the year, 2015, and

that the said contract was terminated w.e.f.

                             ::3::                      HC,J & AKS,J
                                                     comca_63_2019




16.03.2016 itself. The court further held that in view

of the termination of the contract w.e.f. 16.03.2016,

the claim ought to have been filed within one year as

per the terms of the contract; that this has not been

done by the plaintiff; and therefore, it held that the

suit itself is barred by limitation.

5. Assailing the same, the present Appeal is filed.

6. Learned counsel for the appellant contended that

the court below erroneously came to conclusion that

the claim made by the appellant before the court below

is barred by limitation as the cause of action for filing

a suit arose on 16.12.2013, and the suit has been filed

after expiry of three (03) years which is beyond the

period of limitation, i.e., 01.06.2017. It is further

contended by the appellant that when the contract was

terminated w.e.f. 03.05.2016, the suit ought to have

been filed by 16.03.2017, but it was filed on

01.06.2017. He further contended that the Court

below rejected the original suit filed by the appellant at ::4:: HC,J & AKS,J comca_63_2019

the preliminary stage without going into the merits of

the case.

7. Learned counsel for the appellant further

contended that Court below erroneously came to a

conclusion that the claims made by the appellant are

barred by limitation, as the cause of action arose for

the appellant on 16-12-2013 and the suit has been

filed after expiry of three years of limitation i.e., on

16-12-2016; and on that sole ground, the plaint

preferred by the appellant was mechanically rejected.

8. The learned counsel for the appellant further

contended that if there was delay, the Court below

ought to have framed an issue to that effect while

adjudicating the suit itself at the time of hearing, and

an opportunity ought to have been given to the

appellant to satisfy the court that there was no delay.

But, without giving an opportunity, the Court below

had mechanically rejected the plaint preferred by the

appellant and, therefore, prayed that appropriate ::5:: HC,J & AKS,J comca_63_2019

orders be passed by setting aside the orders passed in

COSSR No. 483 of 2018, dated 11-06-2018, and to

further direct the Court below to entertain the plaint

submitted by the appellant and after adjudicating the

same on merits, pass appropriate orders in accordance

with law.

9. Learned counsel for the respondent filed counter-

affidavit stating that the contentions raised in the

appeal are baseless, and the Court below had rightly

rejected the plaint on the ground of limitation, and

prayed for dismissal of the appeal.

10. This Court after considering the rival

submissions of the parties, is of the considered view

that the plaint was rejected at the threshold without

giving an opportunity to the appellant. Even though

the court below was not satisfied about the

maintainability of plaint on the aspect of delay and

laches, it ought to have framed an issue while

adjudicating the main suit itself. Therefore, we are of ::6:: HC,J & AKS,J comca_63_2019

the view that the Court below erred in rejecting the

plaint filed by appellant at the threshold without giving

an opportunity to the appellant.

11. Accordingly, we set aside the order dated

11-06-2018 passed by the court below in

C.O.S.S.R.No.483 of 2018, and the Court below is

directed to entertain the plaint/suit preferred by the

appellant; and, if necessary frame a specific issue

about the maintainability of the suit on the ground of

delay and laches, and adjudicate the same on merits.

Appeal is disposed of with the above directions. No

costs.

12. As a sequel, miscellaneous applications pending

if any in this Appeal, shall stand closed.

___________________________________ SATISH CHANDRA SHARMA, CJ

_________________________________ ABHINAND KUMAR SHAVILI, J Date : 03.03.2022 NDR /ASR

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter