Citation : 2022 Latest Caselaw 89 Tel
Judgement Date : 7 January, 2022
HON'BLE SRI JUSTICE P.NAVEEN RAO
AND
HON'BLE SMT. JUSTICE P.SREE SUDHA
CIVIL MISCELLANEOUS APPEAL NOs.358 AND 164 OF 2013
COMMON JUDGMENT
(per Justice P.Sree Sudha)
1. C.M.A.No.358 of 2013 is filed by M/s.Siri Homes, a partnership
firm, represented by its Managing Partner-petitioner in the A.O.P.
against the orders in A.O.P.No.325 of 2009 dated 06.11.2012 on the
file of the learned II Additional District Judge, Ranga Reddy, insofar
as denying the relief of specific performance of contract dated
26.02.2004 in confirming the order dated 06.02.2009 passed in
A.A.No.39 of 2006 on the file of the learned Arbitrator.
2. C.M.A.No.164 of 2013 is also filed by Sri Kasu Ram Reddy,
Smt. Kasu Madhavi and M/s.Maruthi Hemanth Housing Private
Limited - respondents in A.O.P. against partial modification of
refunding of Rs.35,00,000/- in A.O.P.No.325 of 2009.
3. The parties in these appeals are hereinafter referred to as they
were arrayed in the AOP for the sake of convenience.
4. The brief facts of the case are that originally respondents
purchased agricultural lands in Sy,Nos.234, 235, 236, 240 and 241
situated at Mangalpalli Village, Patelguda Gram Panchayat,
Ibrahimpatnam Mandal, Rangareddy District, between the years
1992-98. They divided the land into plots for construction of houses
and got the layout approved by the Gram Panchayat. They sold 118
plots measuring an extent of 34,000 square yards to different persons
and the balance left out in the said land was about 72,000 square
yards. The third respondent-M/s.Maruthi Hemanth Housing Private
Limited, agreed to sell the same land measuring 72,000 square yards
to the petitioner at the rate of Rs.300/- per square yard for a total
amount of Rs.2,16,00,000/-, to which an agreement of sale was
executed on 26.05.2004 and on the date of agreement and amount of
Rs.35,00,000/- was paid and the balance amount of
Rs.1,81,00,000/- was agreed to be paid in five quarterly instalments
commencing from 25.05.2004 as indicated below.
Instalment Due Date Amount
First Instalment 25-05-2004 Rs.43,20,000/-
Second Instalment 25-08-2004 Rs.38,20,000/-
Third Instalment 25-11-2004 Rs.33,20,000/-
Fourth Instalment 25-02-2005 Rs.33,20,000/-
Fifth Instalment 25-05-2005 Rs.33,20,000/-
The petitioner did not pay the abovementioned instalments and there
was correspondence between the petitioner and the respondents
through letters and legal notices and the claimant-petitioner filed
O.P.No.182 of 2006 under Section 9 of the Arbitration and
Conciliation Act, and obtained interim orders on 28.04.2006
restraining the respondents from alienating the said property. He also
filed an application for appointment of an Arbitrator for adjudication
of the dispute and it was allowed on 13.10.2006.
5. The learned Arbitrator after considering the evidence of both
sides and documents on record, arrived at the conclusion that the
petitioner-claimant committed a breach of the agreement and held
that the amount of Rs.35,00,000/- already paid by claimant-
petitioner is liable to be forfeited.
6. Aggrieved by the said order, an Appeal is preferred by M/s. Siri
Homes-petitioner in A.O.P.No.325 of 2009 and the learned
II Additional District Judge allowed the appeal in part holding that
the petitioner is entitled for refund of the amount of Rs.35,00,000/-
which was paid by it along with interest at the rate of 6% per annum
from the date of the Agreement of Sale till the date of refund, with a
charge over the property covered under the Agreement of Sale, if any,
left unsold. C.M.A.No.358 of 2013 is filed against the said order, and
the petitioner is seeking for the relief of specific performance.
8. The C.M.A.No.164 of 2013 is preferred by the respondents
against the same order contending that the Court does not have any
grounds to interfere with, modify or set aside the well-reasoned
findings of the learned Arbitrator within the grounds mentioned in
Section 34(2) and (3) of the Arbitration and Conciliation Act; and that
there was no prayer for refund of Rs.35,00,000/- made by M/s.Siri
Homes Private Limited and hence the same cannot be granted.
9. Now the point for consideration before this Court is
(1) whether the petitioner is entitled for the relief of specific
performance of contract, (2) whether the refund of Rs.35,00,000/-
with an interest at the rate of 6% per annum granted by the
II Additional District Judge is valid or not, and (3) whether the order
of the learned Arbitrator was rightly interfered by the Court.
10. The agreement of sale for an extent of 72,000 square yards at
the rate of Rs.300/- square yards was entered on 26.02.2004. The
petitioner paid an amount of Rs.35,00,000/- in cash and by way of
cheques on the same day and agreed to pay the balance in five
instalments as indicated before. The petitioner asked for a dispute-
free vacant possession of the 72,000 square yards of land before
payment of the first instalment through letter marked as Ex.A-4, he
demanded the link documents and original approved plan of the
layout. Under Ex.A-5, the respondent stated that the original layout
was misplaced and applied to the Gram Panchayat for a copy and as
soon as it is received, they can furnish a copy of the same. PW-1 in
his evidence stated that copy of layout and copies of link document
were furnished even before the said agreement was entered into. The
petitioner also stated that the extent of land possessed by the
respondents does not exceed more than 35,000 square yards and
that they had also suppressed the sale of some plots to third parties
while entering into the agreement.
13. The petitioner would submit that in accordance with the terms
of the agreement, he cleared the debris on the land, fixed survey
stones on the basis of the plan, displayed sign boards and
advertisement boards on the sides. He also laid the roads, planted
avenue trees, erected fencing around the land, employed a watchman
and incurred an amount of Rs.40,00,000/- for the development of the
said land. He further stated, that as the respondents had transferred
portion of the property to third parties, the petitioner negotiated with
them and purchased plots from them to avoid complications, and
thus, spent a further amount of Rs.30,00,000/-. The petitioner has
not filed a statement of expenditure incurred for development of land
and did not file the report of surveyor and he has not mentioned
about the expenditure incurred by him for development and
purchase of the said lands in the notice issued to the respondents in
November 2004 through their counsel and also in Exs.A-6 and A-8
letters written by him on 21.05.2004 and 03.06.2004. Although he
stated that the respondents disturbed the signs and advertisement
boards and he gave compliant against them, the copy of complaint is
not produced before the Court or the learned Arbitrator.
16. As per the terms of the agreement, the respondents have to
execute sale deeds as and when each instalment is paid in any
portion of the land as desired by the petitioner for such extent in
proportion to the consideration paid by him and the said condition is
admitted by the petitioner in rejoinder. In spite of such a condition,
the petitioner contended that the respondents should deliver dispute
free vacant possession of 72,000 square yards of lands as a condition
precedent for payment of the first instalment. This demand for
possession of entire extent even before payment of first instalment is
contrary to the terms of the agreement.
17. The petitioner addressed a letter dated 10.05.2004 and
respondent gave reply on 12.05.2004. The petitioner wrote another
letter on 21.05.2004 and the third respondent sent a reply on
26.05.2004 in which he categorically stated that he will cancel the
agreement if the amount is not paid within the time specified in the
agreement. The respondents got issued a legal notice on 27.10.2004
and also published general notice in Eenadu on 29.10.2004, for
which the petitioner gave reply notice on 09.11.2004 requesting them
to receive the instalments, but they did not cooperate with him.
18. The petitioner stated that he was always ready and willing to
perform his part of the contract, but the respondents stated that they
wrote a letter under Ex.A-7 on 26.05.2004 giving five days time for
payment of the first instalment to the petitioner, and also stated that
if he fails to do so, it would be deemed that he has no objection for
repudiation. Subsequently in a Lawyer's notice marked Ex.A-9, the
respondents stated that the amount of Rs.35,00,000/- is liable to be
forfeited in view of cancellation of the agreement.
19. The respondents contended that after repudiating the contract
the petitioner kept quiet for more than a year and approached this
Court for appointment of an Arbitrator in the year 2006. If at all the
petitioner was really interested in the specific performance of the
contract, he would not have kept quiet for such a long time after
repudiating the contract and stating that the advance paid will be
forfeited. It is also submitted that it appears that he now came up
with this relief of specific performance only to get a refund of the
advance paid.
20. The respondents stated that they received notices from the
State Financial Corporation (SFC) for auction of the cold storage.
Ex.B14 to 17 were the notices received prior to agreement of sale. As
such the respondents entered into an agreement of sale with a view
to settle the amount due to the State Financial Corporation and
agreed to receive the consideration in instalments. In fact, they
agreed to sell, in order to discharge their liability towards State
Financial Corporation. As the petitioner committed default in paying
first instalment, they could not discharge their liability. As per Ex.B-
19, the valuation of the cold storage was Rs.1,75,00,000/-, but they
sold it for a meagre amount of Rs.76,00,000/- in order to discharge
the aforesaid loan.
21. The respondents not only cancelled the agreement but also
requested the learned Arbitrator for forfeiture of the paid-up amount
of Rs.35,00,000/- and for further damages. The learned Arbitrator
concluded that the petitioner committed breach and thereby the
respondents were forced to sell the cold storage unit for a meagre
amount for discharge of their liabilities and thereby ordered for the
forfeiture of the amount of Rs.35,00,000/- in favour of the
respondents. However, he rejected the damages as the said forfeiture
is sufficient to cover the same.
22. The petitioner preferred an appeal against the arbitration
award, in AOP No.325 of 2009 in which the learned District Judge
supported the version of the petitioner and observed that at no point
of time the respondent issued notice to the petitioner stating their
urgency and their needs and thereby demanding him to pay the
amount. The learned Judge further observed that though petitioner
was in possession of the property, the respondents have not taken
any steps for getting back the possession and he deferred with the
finding of the learned Arbitrator and held that the petitioner is
entitled to a refund of Rs.35,00,000/- with an interest at the rate of
6% per annum and also observed that the respondents have no right
to forfeit the amount without putting a notice to the petitioner.
23. Aggrieved by the said order, the petitioner approached this
Court and claimed the relief of specific performance. As per the
agreement, he has to pay the balance amount in five instalments on
the dates mentioned in the agreement but the petitioner miserably
failed to pay even the first instalment. Though he stated that he was
ready and willing to perform his part of the contract, he failed to pay
the instalment amount even after receiving notice from the third
respondent regarding the repudiation and forfeiture of the amount
paid by him on the date of agreement of sale. He kept quiet for more
than one and half years and filed O.P.No.182 of 2006 for
appointment of Arbitrator. Even after this, he has not deposited
amount before the Arbitrator to show his bona fides.
24. In the agreement, it was specifically mentioned that the first
instalment is to be paid on 25.05.2004 and the last on 25.05.2005
and it clearly reflects that time is the essence of the contract.
Moreover, respondents stated that they sold the land at the rate of
Rs.300/- per square yard only to discharge their liability to the State
Financial Corporation. In spite of having knowledge about the
requirements of the respondents, the petitioner never complied with
the conditions of the contract. Therefore, his version that he is ready
and willing to perform his part of the contract is not tenable.
25. In the arbitration award, the learned Arbitrator, on detailed
discussion, in para 26 held that the remaining extent of land is
72,000 square yards. The respondents also stated that they already
sold 118 plots prior to the agreement. Though the petitioner stated
that he spent Rs.40,00,000/- for development and Rs.30,00,000/- for
purchasing the said lands from several persons, he has not filed a
scrap of paper showing the same. Instead of paying the first
instalment, he raised an objection regarding the extent of land,
demanded for link documents and copy of the layout, though the said
documents were furnished prior to the agreement of sale. On the
date of agreement, he paid Rs.35,00,000/- and he has not paid the
first instalment on one or the other pretext and thus he violated the
terms and conditions of the contract. He has not approached the
Court with clean hands as such, he is not entitled for the equitable
relief of specific performance.
26. In C.M.A.No.164 of 2013, the respondents contended that there
is no prayer for a refund of Rs.35,00,000/- made by M/s.Siri Homes.
They further stated that the award can not be modified or set aside
except for grounds mentioned in Section 34(2) and (3) of the
Arbitration and Conciliation Act. They also stated that in
Ex.A-7 it was clearly stated that if Siri Homes Private Limited failed to
pay the first instalment in five days from 26.05.2004, the agreement
between the parties stands cancelled and the advance amount paid
by them will be forfeited. But the Court below erred in modifying the
reasoned findings of the learned Arbitrator and thus requested the
Court to set aside the order of A.O.P.No.325 of 2009, dated
06.11.2012.
27. Section 22 of Specific Relief Act, 1963 - Power to grant relief for
possession, partition, refund of earnest money, etc.--(1)
Notwithstanding anything to the contrary contained in the Code of
Civil Procedure, 1908 (5 of 1908), any person suing for the specific
performance of a contract for the transfer of immovable property
may, in an appropriate case, ask for -
(a) possession, or partition and separate possession, of the property, in addition to such performance; or
(b) any other relief to which he may be entitled, including the refund of any earnest money or deposit paid or made by him, in case his claim for specific performance is refused.
(2) No relief under clause (a) or clause (b) of sub-section (1) shall be granted by the court unless it has been specifically claimed.
As per Section 22(2) of the Specific Relief Act, refund of earnest
money cannot be granted in the absence of specific claim. Petitioner
never claimed for refund of Rs.35,00,000/- in A.O.P.No.358 of 2013,
and thus, he is not entitled for the said amount.
28. Learned counsel for the respondents relied on a case reported
in ASSOCIATE BUILDERS V/s. DELHI DEVELOPMENT
AUTHORITY1, the Apex Court held that an Arbitral award cannot be
interfered with unless it was assailed that the findings of the
arbitrator are arbitrary, capricious or perverse. The Court shall not
interfere with the arbitrary award when merely another view is
possible. The Award can be interfered only when in the following
circumstances:
i. Not in compliance with statutes or judicial precedents;
ii. Violated the principle of judicial approach;
iii. Not in compliance with the principles of natural justice;
or
iv. Violates the principle of Wednesbury reasonableness i.e., the award is perverse.
29. The counsel for the petitioner relied upon the case reported in
OIL AND NATURAL GAS CORPORATION V/s. WESTERN GECO
INTERNATIONAL LTD.2, wherein the Apex Court held that an award
can be set aside if it is contrary to the following:
i. Fundamental policy of Indian law;
ii. Interest of India;
iii. Justice or morality; or
iv. Patently illegal
30. The appellate Court cannot sit in appeal and re-appreciate the
evidence in the award of the learned Arbitrator. It can interfere with
only when it is patently illegal. But in the case on hand, the learned
Arbitrator passed a well-reasoned award. Therefore, the interference
2015 (3) SCC 49
2014 (9) SCC 263
of the appellate Court is not warranted and thus, the order of the
trial Court in A.O.P.No.325 of 2009 dated 06.11.2012 is liable to be
set aside by duly confirming the award of the learned Arbitrator.
31. Accordingly, C.M.A.No.164 of 2013 is allowed and
C.M.A.No.358 of 2018 is dismissed. There shall be no order as to
costs.
32. Miscellaneous Petitions, if any, pending in this appeal shall
stand closed in the light of this final order.
___________________ P.NAVEEN RAO,J
___________________ P.SREE SUDHA,J
7th JANUARY, 2022
pgs
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!