Citation : 2021 Latest Caselaw 298 Tel
Judgement Date : 5 February, 2021
HON'BLE SRI JUSTICE A.RAJASHEKER REDDY
ARBITRATION APPLICATION Nos.132, 133 and 134 OF 2014
COMMON ORDER:
Since the issue involved in all these Arbitration Applications
is one and the same, they are being heard together and disposed
of by way of this Common Order.
2. These Arbitration Applications are filed under Section 11(6) of the
Arbitration and Conciliation Act, 1996 (for short 'the Act') for
appointment of an Arbitrator to resolve the disputes that arose between
the parties in respect of different works under separate Sub Contract
Agreements dated 30.07.2012 in all these Arbitration Applications.
3. For the sake of convenience, the facts in Arbitration Application
No.132 of 2014 are considered for disposal of these Applications. Brief
facts which are necessary for disposal of the Arbitration Application are
as follows:
The respondent was awarded a work pertaining to Sardar
Sarovar Narmada Nigam Limited for the Design, Construction, Testing,
Commissioning and operation and Maintenance for five years of Kutchh
Branch Canal Package-I on Engineering, Procurement, Construction
and Commissioning (EPC) basis between Ch.82.300 kms to Ch.112.50
kms including earthwork, structures, lining, service road,
CR/HR/Escape, Gates, Stop Locks, Control Cabins etc., by Executive
Engineer, Sardar Sarovar Narmada Nigam Limited, vide agreement
No.KBC/EPC/Package/1/EPC-I of 2011-2012, dated 07.02.2011. The
respondent sub-contracted a portion of the work i.e.,98.00 km to
100.100 km, which forms part of the above mentioned package
awarded by Executive Engineer, Sardar Sarovar Narmada Nigam
Limited on item rate work basis including materials vide Sub-Contract
Agreement dated 30.07.2012 (for short 'SCA'), which is valued at
Rs.36,51,64,687.58 ps and as per the said agreement, the work shall
be completed on or before 30.07.2013. Pursuant to the award of the
contract, the applicant had mobilized its men and machinery in right
earnest so as to execute the work under SCA and complete the
execution before the designated date. However, for the reasons which
are beyond the control of the applicant and for the reasons attributable
to the respondent, the entire planning schedule of the applicant got
disturbed and thus the execution of the work got unduly delayed. The
issues that are encountered by the applicant while executing the work
have been brought to the notice of the respondent for resolving the
same so as to complete the work within the time schedule, but in vain.
The subject work could not be progressed due to frequent obstructions
by the Forest Department and though the same was brought to the
notice of the respondent for it's intervention, they turned a deaf ear, as
such, the work got unduly delayed. That apart, the respondent failed to
pay amounts under RA Bills, which were raised from time to time.
Thereafter, the Applicant was constrained to address letter
No.SRRCIPL/KBC.PKG.1/2014-15/No.73, dated 11.08.2014
demanding an amount of Rs.16,79,13,904/- along with interest at 18%
per annum. As disputes arose between the applicant and the
respondent, the applicant got issued notice dated 28.07.2014 invoking
arbitration clause No.34 contained under the SCA dated 30.07.2012 for
settlement of claims amicably in the first place and to take further
suitable action i.e., appointing an Arbitrator, if they failed to agree for
any amicable settlement. In response thereto, the respondent replied
through letter vide Ref.No.NCC/HO-Irri/KBC Pkg-I/SRRC/2014-15/07,
dated 08.08.2014 stating that the claims raised by the applicant are
beyond the ambit of the contract and that same are excepted matters
and there are no disputes existing for the purpose of any settlement.
Thereafter, the respondent called upon the applicant for amicable
settlement on 14.08.2014 to resolve the issues, if any, within the ambit
of the contract. On receipt of the said letter, the applicant addressed
letter dated 10.08.2014 requesting the respondent to give details of the
meeting, to which the respondent replied through letter dated
12.08.2014 giving the particulars and also named the authorized
representative i.e., S.Srinivasa Rao, AGM, Irrigation. As the person
proposed is far less in hierarchy than Mr.B.A.N.Raju, Vice President,
the applicant addressed letter dated 14.08.2014 expressing
reservations as regard the said nominated person. On 14.08.2014, the
applicant represented by its Managing Director attended the meeting.
While reiterating their stand in the letter dated 08.08.2014, the
respondent called upon the applicant to come up with fresh proposal in
terms of the contract. In the said meeting, the disputes/claims raised
by the applicant through letter dated 11.08.2014 was also considered.
As the respondent was not willing to consider the claims of the
applicant, the applicant requested the respondent to appoint an
arbitrator for resolving the disputes raised by the applicant in their
letter dated 11.08.2014. Thus, the so called amicable settlement fell
through, as such, the respondent ought to have appointed arbitrator
and that instead of appointing an Arbitrator, the respondent addressed
letter dated 16.08.2014 fixing a fresh date of meeting as 23.08.2014
falsely alleging that the applicant agreed to submit a reasonable
proposal within the terms of the agreement. The applicant represented
by its Managing Director attended the meeting on 23.08.2014 to
question the same and also to discuss if there would be any
consideration of the issues raised by them in respect of two other
contracts. However, on the said date, almost a new team has come to
the meeting and they reiterated their stand taken in their letter dated
08.08.2014 for all the works/contracts, which are under execution by
the applicant, thereby refusing to entertain the said issues.
Subsequently, there is exchange of correspondence between the
parties. As the respondent did not come forward to appoint an
Arbitrator as requested by the applicant vide letter dated 11.08.2014,
this Application is filed.
4. Counter affidavit is filed by the respondent denying the
averments in the affidavit filed in support of the Arbitration Application
stating that application filed by the applicant is liable to be dismissed
in limine on the ground that; a) the Application is premature as it is
filed within 30 days and b) the Application is not maintainable either in
law or on facts and same has become infructous. That the claim of the
applicant for Rs.16,79,13,904/- along with interest at 18% per annum
is exorbitant and beyond the ambit of the SCA dated 30.07.2012. It is
asserted that the applicant by letter dated 10.08.2014 acknowledged
the receipt of letter dated 08.08.2014 and had given consent for the
amicable settlement as provided under Clause 34 of the SCA.
Accordingly, on 14.08.2014, a meeting was held between the
representatives of the applicant and the respondent at the office of
respondent and that after discussions, it was agreed that the applicant
would submit a reasonable proposal for settlement of issues on or
before the next meeting i.e., on 16.08.2014. However, the scheduled
meeting was rescheduled to 23.08.2014. On the said date, a second
meeting was held between the representatives of the applicant and the
respondent at the office of the respondent. The applicant submitted a
settlement proposal for which, the respondent requested for some time
to review ad revert with their views. On 03.09.2014, the respondent
addressed a letter to the applicant and informed that settlement
proposal submitted by the applicant was not agreeable to the
respondent as the excess amount of Rs.2,23,98,021/- proposed by the
applicant was already paid. The respondent vide letter dated
03.09.2014 expressed its intent to appoint a Sole Arbitrator under
Clause 34 of the SCA for adjudication of all the claims and counter
claims of the parties. Thereafter, the respondent addressed a letter
dated 05.09.2014 to Mr.Inder Mohan Singh, who retired as Chief
Engineer seeking his consent to act as an Arbitrator to arbitrate on the
dispute between the parties. On 15.09.2014, Mr.Inder Mohan Singh
addressed a letter to the respondent wherein he confirmed his
willingness to act as a Arbitrator to arbitrate the dispute between the
parties. On 22.09.2014, the respondent prepared a draft letter to be
issued to the Applicant informing the appointment of Arbitrator and the
said letter was internally circulated to the officers of the respondent for
their approval by e mail. Pursuant to the letter dated 03.09.2014, the
respondent vide letter dated 22.09.2014 intimated to the applicant that
the respondent had appointed Mr.Inder Mohan Singh as Sole Arbitrator
under the Clause 34 of the SCA and said letter was emailed to the
applicant with a copy marked to the Arbitrator on 23.09.2014 and hard
copy of the said letter was dispatched on the same day through Courier
and was received by the applicant on 24.09.2014. The respondent is
not aware of the fact of the applicant approaching this Court under
Section 11(6) of the Act praying for an appointment of an Arbitrator.
On the next day i.e., 23.09.2014 at 5.27 pm, the respondent received a
letter from the counsel for the applicant informing the respondent
about filing of present Application praying for an appointment of
Arbitrator. The present Application has been filed before the completion
of the 30 days period as required under Section 11(5) of the Act from
the date of intimation by respondent about failure of the amicable
settlement and that the respondent would appoint an Arbitrator as per
Clause 34 of the Sub-Contract Agreement. From September 2nd, 2014
i.e., from the date of filing of the present application till 23.09.2014 on
receipt of notice dated 21.09.2014 from the counsel appearing for the
applicant, the applicant deliberately suppressed the fact that the
applicant had filed an application before this Court. In response to the
letter dated 22.09.2014 intimating the applicant about appointment of
Mr.Inder Mohan Singh as Sole Arbitrator, the applicant sent a reply
letter dated 25.09.2014 to the respondent and informed about filing of
present Application and disputed the appointment of the Arbitrator by
the respondent. The sole Arbitrator appointed by the respondent
meanwhile fixed a Schedule for Arbitration and issued the same to both
the parties for further action. There is no specific request to the
respondent for appointment of Arbitrator consequent to failure of
amicable settlement and that there is no such time limit prescribed
under Clause 34 of the SCA. The relief sought for by the applicant
cannot be granted as the entire Application is misconceived and has
become infructous. The applicant even without making a request for
appointment of Arbitrator as contemplated under Clause 34 of the SCA,
with a malafide intention approached this Court, even before expiry of
30 days as provided for under Section 11 of the Act. Since the
respondent had already appointed Arbitrator under Clause 34, this
Application is infructous and requires to be dismissed. In Datar
Switchgears Limited v. Tata Finance Limited [2001 Vol.103(1)
Bom.L.R 865 (SC], Ace Pipeline Contracts Private Limited v.
Bharat Petroleum Corporation Limited [(2007) 5 SCC 304 and
Deep Trading Company v. Indian Oil Corporation [(2013) (3) AWC
2984 (SC)], the Hon'ble Supreme Court held that for cases falling under
Section 11(6) are concerned, no time limit has been prescribed under
the Act, whereas a period of 30 days has been prescribed under Section
11(6) is concerned, if one party demands the opposite party to appoint
an Arbitrator and the opposite party does not make an appointment
within 30 days of the demand, the right to appointment does not get
automatically forfeited after expiry of 30 days. If the opposite party
makes an appointment even after 30 days of the demand, but before
the first party has moved the Court under Section 11 that would be
sufficient. In other words, in cases arising under Section 11(6), if the
opposite party has not made an appointment within 30 days of
demand, the right to make appointment is not forfeited but continues,
but an appointment has to be made before the former files Application
under Section 11 seeking appointment of an Arbitrator. Only then the
right of the opposite party ceases. This Application cannot be
entertained as the Sole Arbitrator had already been appointed and the
schedule for submission of Statement of Claim, Statement of Defence &
Counter claims and rejoinder to Statement of Defence & reply to the
Counter Claims was also fixed by the Arbitrator. It is asserted that the
Arbitrator appointed by the respondent retired as a Engineer-in-Chief,
PWD, Government of Delhi and has vast expertise in the Construction
Industry and had dealt with many cases as an Arbitrator and he is
based out of New Delhi. The Arbitrator also issued letter dated
25.09.2014 to the Applicant and the respondent under Section 12 of
the Act, 1996. The respondent followed due process provided under the
Act and the clauses of the SCA in appointing the Sole Arbitrator. The
applicant cannot invoke Section 11(6) of the Act as the respondent had
complied with sub-sections (2), (3) and (4) of Section 11 of the Act. The
respondent appointed Sole Arbitrator within 30 days as contemplated
under sub-section (4)(a) of Section 11 of the Act. The applicant is
precluded from approaching this Court under Section 11(6) of the Act
and as per the applicability of sub-section 6(a) of Section 11 of the Act,
the respondent had acted as required under the procedure
contemplated under the Clause 34 of the Sub-Contract Agreement,
whereas sub-sections 6(b) and (c) of Section 11 of the Act does not
apply for the present case and sought for dismissal of the Application.
6. Heard Sri P.Sree Raghu Ram, learned Senior Counsel appearing
for Sri Krishna Mohan Shikaram, learned counsel for the applicant and
Ms.Altaf Fathima, learned counsel appearing for Sri Gandham Durga
Bose, learned counsel for the respondent.
7. Sri P.Sree Raghu Ram, learned Senior Counsel, while reiterating
the averments in the affidavit filed in support of the Application
submitted that the applicant issued letter dated 28.07.2014 invoking
Clause 34 of the SCA for settlement of claims amicably in the first place
and to take further suitable action for appointing an Arbitrator, if
amicable settlement fails. He submits that though the respondent
issued letter dated 08.08.2014, they did not intend to settle the issues
amicably and replied that the claims made by the applicant are beyond
the ambit of the contract and same are excepted matters and that no
disputes existing for the purpose of settlement, but however, addressed
a letter dated 14.08.2014 calling upon the applicant for resolving the
issues, if any, within the ambit of the contract. He submits that
though the meeting was held on 14.08.2014, no amicable settlement
was arrived at between the parties, as such, present application is filed
for appointment of an Sole Arbitrator. He also submits that when once
the Application is filed by the applicant, the respondent cannot appoint
arbitrator as they lost their right of appointment an Arbitrator. He also
submits that even otherwise, there is no time limit for appointment of
Arbitrator under Section 11(5) of the Act. He submits that even though
30 days period is not required to be maintained for initiating arbitration
proceedings under Section 11(6) of the Act, the present application is
filed after expiry of 30 days after invocation of arbitration Clause 34
contained in SCA. He submits that this Application is filed on
02.09.2014 and by that time, the respondent lost their right to
appointment an Arbitrator. In support of his contention, he relied on
the judgment reported in Datar Switchgars Ltd., v. Tata Finance
Ltd.,[2000 (6) ALT 26 (SC), Judgment of Calcutta High Court in
Great Eastern Shipping Co. Ltd., v. Board of Trustees [(2004) (3)
CHN 37) and Deep Trading Company v. Indian Oil Corporation
(AIR 2013 SC 1479). He also submits that in this application, the
applicant invoked the arbitration clause 34 on 28.07.2014 and also on
11.08.2014 and the present application is filed on 02.09.2014, as such,
30 days period was also complied with.
8. On the other hand, learned counsel for the respondent while
reiterating the averments in the counter affidavit rebutted the
contentions of the learned Senior Counsel for the applicant.
9. There is no dispute with regard to award of SCA in favour of the
applicant by the respondent on 30.07.2012 for the execution of certain
works relating to Sardar Sarovar Narmada Nigam Limited. During the
course of execution of SCA, disputes arose between the parties in
respect of alleged incomplete works and non-payment of certain dues
by the respondent. There was an exchange of correspondence between
parties and one such correspondence is the letter addressed by the
applicant on 28.07.2014 calling upon the respondent for amicable
settlement of the disputes that arose between them. According to the
applicant, even after addressing letter dated 11.08.2014, as there is no
amicable settlement with the respondent, filed the present application
for appointment of an Arbitrator. It is the specific contention of the
respondent that the present application under Section 11(6) of the Act
has already been filed on 02.09.2014, without intimation to the
respondent and without waiting for the amicable settlement.
10. Before considering the rival contentions of the parties, it is
necessary to extract the Clause-34 contained in SCA, which reads as
follows:
"All disputes or differences whatsoever arising between NCC and SRRC out of or relation to the construction, meaning and operation or effect of this Sub Contract Agreement, or any breach thereof, shall be settled amicably by the parties, failing which, it shall be settled by a Sole Arbitrator, to be appointed by NCC, as per the provisions of the Indian Arbitration & Conciliation Act, 1996. The award passed by the Sole Arbitrator shall be final and be binding on the Sub-Contractor and NCC. The Venue of arbitration shall be Hyderabad, Andhra Pradesh."
A perusal of the aforesaid clause goes to show that if at all any
differences or disputes arises between the parties in relation to the
execution of the work or during the course of execution of the work,
initially, both the parties shall try for amicable settlement by issuing a
notice under Clause 34 for amicable settlement. If the amicable
settlement fails, then they have to take steps for appointment of a Sole
Arbitrator, to be appointed by NCC for resolving the disputes between
the parties by issuing notice for appointment of Sole Arbitrator and the
Award passed by the Sole Arbitrator shall be final and binding on both
the parties. Now, we have to examine whether the applicant and the
respondent have taken any steps for resolution of the disputes
amicably or not?
11. It is the specific contention of the learned counsel for the
respondent that the applicant never intimated to the respondent that
there is a failure of amiable settlement between them and that the
applicant also neither requested the respondent for appointment of
arbitrator in accordance with Clause 34 of the SCA nor as per the
provisions of the Act. As per Section 21 of the Act, date of service of
notice by the party for appointment of an Arbitrator would be the
relevant date for the purpose of commencement of the arbitration
proceedings. For the sake of convenience, Section 21 of the Act is
reproduced hereunder:
"21. Commencement of arbitration proceedings: Unless otherwise agreed by the parties, the arbitral proceedings in respect of a particular dispute commence on the date on which a request for that dispute to be referred to arbitration is received by the respondent."
Section 21 of the Act mandates that unless notice of intention for
appointment of arbitrator is issued by one party to the other party, the
question of compliance or non-compliance of the notice requirements
by the other party does not arise. Let us examine as to whether the
applicant has served any notice, as required under Section 21 of the
Act, on the respondent for appointment of Sole Arbitrator or not?
12. Admittedly, the applicant has addressed letters dated
28.07.2014 & 11.08.2014 purportedly under Clause 34 of the SCA for
settlement of disputes in the first place and not for the purpose of
appointment of arbitrator. Even according to the applicant, it is
categorically stated in the affidavit that after receiving correspondence
vide letters dated 08.08.2014 and 12.08.2014, though there was a
meeting held on 14.08.2014 for amicable settlement, but the same was
not successful. It is the contention of the learned Senior Counsel for
the applicant that in the letter dated 11.08.2014, they have requested
the respondent for appointing an Arbitrator. A perusal of the aforesaid
letter dated 11.08.2014, particularly, the concluding paragraph, goes to
show that the said notice was issued only for the purpose of amicable
settlement and not for requesting the respondent for appointment of
Arbitrator. For the sake of convenience, the same is reproduced
hereunder:
"21.00 This is the notice issued under clause 34 of the sub-contract agreement for settlement of claims amicably in the first place and further suitable action deemed fit under the circumstances as laid down in the agreement."
13. The aforesaid concluding paragraph goes to show that it was
only for the purpose of amicable settlement and not for seeking
appointment of a Sole Arbitrator. That apart, on the letter addressed
by the respondent on 16.08.2014, a meeting was held on 23.08.2014
wherein the applicant attended the same, but there was no fruitful
result forthcoming for amicable settlement. In the affidavit, it is also
categorically asserted by the applicant that the respondent is willfully
protracting the matter without appointing the Arbitrator. However, it
is pertinent to note here that the respondent addressed a letter dated
03.09.2014 to the Managing Director of the applicant stating as follows:
"1. Keeping in the view of your correspondence exchanged subsequent to meeting for amicable settlement dated 14.08.2014 and having already paid an excess amount of Rs.2,23,98,021/- as per statement enclosed along with our letter dated 22.08.2014, your proposal is not agreeable.
2. In addition, there was a default on your part by non-
performance and abandonment of work for which we have already invoked clause 9 of the subcontract agreement/work order to execute the balance work at your risk an cost.
3. In these circumstances, attempt for amicable settlement held on 14.08.2014 and 23.08.2014 has failed.
4. Since you have already invoked clause 34, we will appoint the Sole Arbitrator shortly under clause 34 in respect of Sub-Contract Agreements/Work Order; 8A, 8 & 9 for adjudication of all the claims and counter claims of parties."
As rightly contended by the learned counsel for the respondent,
without any prior request or intimation with regard to the
appointment of Sole Arbitrator prior to 30.09.2014, the applicant
straight away filed this Application under Section 11(6) of the Act
seeking appointment of an Arbitrator on 02.09.2014, which is in
violation of the procedure envisaged Clause 34 of the SCA. Therefore,
the applicant has failed to follow the mandate of issuance of notice
under Section 21 of the Act, so also the procedure under Clause 34 of
the Act and that he failed to take steps as required under the
provisions of the Act.
14. It is next contended by the learned Senior Counsel for the
applicant that there is no requirement of 30 days prior notice for filing
an application under Section 11(6) of the Act. As rightly contended by
the learned counsel for the respondent that the said argument was
advanced but there is no whisper about the same in the affidavit filed
in support of the Application. That apart, a perusal of the affidavit also
shows that there is no such averment in the entire affidavit filed by the
applicant. As already observed supra, the applicant neither declared
about the failure of amicable settlement to the respondent nor
requested for appointment of Sole Arbitrator in the correspondence that
exchanged between the applicant and the respondent. On the other
hand, the respondent had addressed a letter dated 03.09.2014 to the
applicant of it's intention to appoint an Arbitrator and in fact had also
appointed one Sole Arbitrator by name Mr.Inder Mohan Singh, for
resolution of disputes between the parties. That apart, the applicant
also failed to follow the mandate of issuance of notice under Section 21
of the Act. When once there is failure on the part of the applicant in
following the procedure under Clause 34 of the SCA by issuing notice
seeking appointment of Sole Arbitrator to the respondent, the present
applicant is not maintainable and liable to be dismissed on this ground
alone.
15. In Hindustan Construction Company Ltd., v. State of Orissa
[2013 (1) ILR-CUT 548], wherein the Orissa High Court held that
arbitration application is not maintainable for the reason that it is not
preceded by a demand notice issued and served to the opposite party
demanding for appointment of an Arbitrator, which is mandatory in
law, as per Section 11(4)(a) of the Act.
16. It is vehemently argued by the learned Senior Counsel for the
applicant that since the Application has been filed by the applicant for
appointment of Sole Arbitrator before this Court, the appointment of
Sole Arbitrator by the respondent is of no consequence and same
cannot be held to be valid.
17. In Man Mohan Kumbhaj v. Union of India [2020 (2) RLW
1331 (Raj.), wherein the Rajasthan High Court held that if a notice for
appointment of Arbitrator in consonance with dispute resolution clause
has not been given, the application can be dismissed on the said
ground itself with the liberty to the applicant to proceed in the matter
in consonance to the terms of the agreement to seek appointment of
arbitrator. It was further held that, when the application under Section
11 of the Act itself is not maintainable, the issue in reference to Section
12(1) and 12(5) of the Amended Act of 2015 remains premature.
As already observed supra, since the applicant has filed the
present Application without following the procedure envisaged under
Clause 34 of the SCA and without issuing any prior notice for
appointing Arbitrator, this Application is premature and not
maintainable, in view of principle of law in the aforesaid judgment of
Rajasthan High Court.
18. Be that as it may, as per Section 11(5) of the Act, a Sole
Arbitrator should be appointed within a period of 30 days upon the
request of other party which intends to initiate arbitration proceedings,
as such, 30 days period for a party to appoint an Arbitrator is
prerequisite condition. Clause 34 of the SCA mandates two stages i.e.,
firstly for amicable settlement and secondly for appointment of
Arbitrator for resolution of disputes between the parties arising out of
SCA. According to the applicant, they have issued two notices i.e.,
28.07.2014 and 11.08.2014 requesting for amicable settlement and
also for appointment of arbitrator, upon failure of the amicable
settlement. As already observed supra, notice dated 11.08.2014 was
only intended for the purpose of amicable settlement as per Clause 34
in the first place and further suitable action deemed fit under the
circumstances as laid down in the agreement. After failure of amicable
settlement, it is the respondent who issued notice of it's intention to
appoint a Sole Arbitrator as per Clause 34 of SCA on 03.09.2014 but
not the applicant. There is no iota of evidence showing that the
applicant has requested the respondent seeking appointment of Sole
Arbitrator upon failure of amicable settlement on 14.08.2014 and
23.08.2014. Thus, it can be presumed that only after failure of
amicable settlement, the respondent issued notice on 03.09.2014 for
appointment of Sole Arbitrator, therefore, the period of 30 days as
required under Section 11(5) would start from 03.09.2014 and not from
28.07.2014 and 11.08.2014, as alleged by the learned Senior Counsel
for applicant. It is also pertinent to note that after 03.09.2014, the
respondent sought willingness of the Arbitrator i.e., Mr. Inder Mohan
Singh on 05.09.2014, who gave his consent on 15.09.2014 and
thereafter, the respondent informed the same to the applicant on
23.09.2014. However, the applicant, without informing the respondent
about failure of amicable settlement and without requesting the
respondent for appointment of Arbitrator in accordance with Clause 34
of SCA, filed this Application on 02.09.2014, that too after respondent
informing it's intention to appoint an Arbitrator on 03.09.2014. As
such, contention of the learned Senior Counsel that 30 days period
shall commence from 28.07.2014 and 11.08.2014 for initiation of
arbitration proceedings under Section 11(6) of the Act and that the said
period of 30 days is not required for filing this application before this
Court, cannot be accepted as on the said dates, the applicant only
sought for amicable settlement with the respondent but not seeking
appointment of Arbitrator. Therefore, the contention of the learned
counsel for the application that there is no requirement to provide 30
days period cannot be accepted.
19. In Ace Pipeline Contracts Private Limited v. Bharat
Petroleum Corporation Limited (2007 (2) ARBLR49 (SC); Datar
Switchgears Ltd., (supra), it has been held by the Hon'ble Supreme
Court that in cases arising under Section 11(6) of the Act, if the
opposite party has not made an appointment within 30 days of
demand, the right to make appointment is not forfeited but continues,
but an appointment has to be made before the former files application
under Section 11 of the Act, seeking appointment of a arbitrator and
only then the right of the opposite party ceases. In the instant, as
already observed supra, the 30 days period would start from the date of
failure of amicable settlement i.e., from 03.09.2014, the date on which,
the respondent addressed letter stating so to the applicant and not
from 28.07.2014 and 11.08.2014, as alleged by the applicant. Though
the applicant had relied on Great Eastern Shipping Company (supra),
but the facts and circumstances therein are quite different from the
facts of the case on hand. In the said case, dispute resolution clause
did not provide for amicable settlement of the dispute and only provides
for Arbitration clause. The applicant therein, even after addressing
several letters to the respondent therein, when there is no response
from the respondent for appointment of an arbitrator, filed an
application under Section 11(6) of the Act, after a period of six months,
which was allowed by the Court. But in the instant facts are otherwise,
as such, the said judgment is not applicable to the facts of the case on
hand.
20. Similarly, the judgment relied on by the learned Senior Counsel
for the applicant in Deep Trading Company v. Indian Oil Corporation
(supra) is also not applicable to the facts of the case on hand. In the
said case, the applicant therein has requested the opposite party to
appoint an arbitrator as per the agreed procedure. Since the opposite
party failed to as per the request of the applicant, the application under
Section 11(6) was filed and thereafter, appointed an arbitrator. The
Hon'ble Supreme Court held that the appointment so made is of no
consequence and the right of the opposite party to appoint is lost once
application for appointment is made to Court. But in instant case, as
already supra, no request was made to the respondent by the applicant
for appointment of arbitrator, as per Clause 34 of the SCA. As such,
this judgment is not applicable to the facts of the instant case.
21. In Simpark Infrastructure Pvt Ltd., v. Jaipur Municipal
Corporation (2013(3) RLW 2133 (Raj.), the arbitration clause
provided that any dispute which is not resolved amicably shall be
referred to a panel of three Arbitrators in terms of the Act. However,
the applicant therein, without attempting to resolve the issue through
amicable settlement approached the Court under Section 11(6) of the
Act. The High Court of Rajasthan observed that (i) Where the parties
have greed to arbitral procedure of dispute resolution, which has been
made a condition precedent for invoking the arbitration clause, then it
is required to be followed before filing an application under Section 11
of the Act, and (ii) Sub-section (6) of Section 11 of the Act cannot be
invoked directly on expiry of thirty days notice under sub-section (4) of
Section 11 of the Act, by the applicant for appointment of the Arbitral
Tribunal ignoring the agreed arbitral procedure. After considering
these observations, the High Court of Rajasthan held that the agreed
arbitral procedure has not been followed by the applicant and
therefore, the arbitration application is premature. In the instant case
also, the applicant has not followed the procedure envisaged under
Clause 34 of SCA, and straight away filed this application, without
intimation or notice to the respondent of its intention to approach this
Court for appointment of an Arbitrator, which is wholly erroneous. In
fact, it is the respondent, who, after failure of amicable settlement,
taken steps for appointment of Sole Arbitrator and also nominated one
Mr.Inder Mohan Singh, as Sole Arbitrator, in compliance of Clause 34
of SCA, as such, this Application for appointment of an arbitrator is not
maintainable.
22. It is pertinent to note that under Section 11(6) of the Act, the
Court has jurisdiction to make the appointment only when the person
including an institution, fails to perform any function entrusted to it
under that procedure. If the jurisdiction of the Court is invoked without
first following the procedure agreed to between the parties, thus no
cause of action would arise to seek the appointment from the High
Court under Section 11(6) of the Act and thus the said petition would
be premature. The parties are required to comply with the procedure of
appointment as agreed to and the defaulting party cannot be allowed to
take advantage of its own wrong. (see National Highways Authority of
India and another v. Bumihiway DDB Ltd.,(JV) [2007 (2) ALT 18
(SC)].
23. Though it is vehemently argued by the learned Senior Counsel for
the applicant that there exists disputes between the parties with regard
to non payment of amount by the respondent, but the same is denied
by the learned counsel for respondent stating that no arbitral dispute
exists between the parties at the first instance, when the applicant
addressed letters dated 28.07.2014 and 11.08.2014. As already
observed supra, on two occasions i.e., on 14.08.2014 and 23.08.2014
amicable settlements failed, then only the respondent addressed letter
to the applicant on 03.09.2014 of it's intention for appointment of an
arbitrator. Since there exists disputes after amicable settlement failed,
the respondent thought it fit to resolve such disputes through
arbitration only, addressed said letter on 03.09.2014 informing the
applicant about proposal for appointment of an arbitrator, as the
respondent did not agree to the proposal made by the applicant, as
such, there exists a dispute, as the same was not resolved amicably.
24. The existence of dispute is essential for appointment for an
arbitrator under Section 8 or a reference under Section 20 of the Act.
There should be a dispute and there can only be a dispute when a
claim is asserted by one party and denied by the other on whatever
grounds. Mere failure or inaction to pay does not lead to the inference
of the existence of dispute. Dispute entails a positive element and
assertion in denying, not merely inaction to accede to a claim or a
request. Whether in particular case a dispute has arisen or not has to
be found out from the facts and circumstances of the case. (see Major
(Retd.) Inder Singh Rekhi v. Delhi Development Authority [AIR
1988 SC 1007]. A reference to Arbitration could only be made
pursuant to the last communication between the parties which
indicates that there is no further possibility of settlement between the
parties. [see Hari Shankar Singhania v. Gaur Hari Singhania [2006
(4)ALT 1 (SC). In the instant, since the respondent communicated
about failure of amicable settlement on 03.09.2014, then any reference
to the arbitration could be made only subsequent to 03.09.2014.
25. It is argued by the learned Senior Counsel for the applicant that
there was no communication marked to the applicant which took place
between the respondent and the so called Sole Arbitrator, appointed by
the respondent. Learned counsel for the respondent submits that as
per Clause 34 of the SCA, the appointment of Sole Arbitrator was to be
done by the respondent and not by the applicant, as such, it was not
necessary nor the contract provided otherwise that the applicant was to
be communicated all the communication between the respondent and
the arbitrator. However, he submits that the applicant was duly
communicated about the appointment of arbitrator vide letter dated
22.09.2014.
26. The communication must be addressed to all the concerned
parties if appointment of Arbitrator is routed through them and/or if
the agreement provides for. It does not consider it necessary that the
communication is addressed to all the concerned parties
simultaneously. It is sufficient if it is communicated in the first
instance to any of them and thereafter to the others. (see Voltas Limited
v. Rolta India Limited [2010 Indlaw MUM 1672].
27. Learned Senior Counsel argued that after amendment of Act
2015, a party to the agreement cannot unilaterally appoint an
arbitrator. It is pertinent to note that even according to the
respondent, arbitrator was appointed on 22.09.2014. The Arbitration
(Amendment) Act, 2015 came into effect from 23.10.2015 i.e, after
appointment of arbitrator by the respondent. Amendment Act, 2015
does not have retrospective effect to the arbitration proceedings
commenced prior to the enactment of the Amendment Act, as such, as
per the Clause 34 of SCA as well as the Act prior to Amendment, the
respondent was entitled appoint an arbitrator unilaterally, and
appointed as such.
28. The provisions of the Amendment Act, 2015 (with effect from
23.10.2015) cannot have retrospective operation in the arbitral
proceedings already commenced unless the parties agree otherwise.
(see Board of Control for Cricket in India v. Kochi Cricket Private
Limited [(2018) 6 SCC 287]. In S.P.Singla Constructions (P) Ltd.,
v. State of Himachal Pradesh [2019 (2) SCC 488], the Hon'ble
Supreme Court, while placing reliance on the judgment of Board of
Control for Cricket in India (supra) held that Section 12(5) of the Act
does not apply to the case therein, since the arbitral proceedings
commenced back in 2013, much prior to the commencement of
Amendment Act on 23.10.2015.
In view of above facts and circumstances, all these Arbitration
Applications are liable to be dismissed and accordingly dismissed. No
order as to costs. As a sequel thereto, miscellaneous applications, if
any, pending in these Arbitration Applications, shall stand dismissed.
____________________________ A.RAJASHEKER REDDY,J
Date:05.02.2021 kvs
HON'BLE SRI JUSTICE A.RAJASHEKER REDDY
ARBITRATION APPLICATION Nos.132, 133 & 134 OF 2014
Date: 05.02.2021
kvs
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!