Saturday, 09, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Kmc Brahmaputra Infrastructure ... vs The Chief Engineer, Road And ...
2022 Latest Caselaw 89 Sikkim

Citation : 2022 Latest Caselaw 89 Sikkim
Judgement Date : 20 December, 2022

Sikkim High Court
Kmc Brahmaputra Infrastructure ... vs The Chief Engineer, Road And ... on 20 December, 2022
Bench: Hon'Ble The Justice, Meenakshi Madan Rai
              THE HIGH COURT OF SIKKIM : GANGTOK
                                      (Civil Appellate Jurisdiction)
                              DATED : 20th December, 2022
--------------------------------------------------------------------------------------------------------------
 DIVISION BENCH : THE HON'BLE MR. JUSTICE BISWANATH SOMADDER, CHIEF JUSTICE
                  THE HON'BLE MRS. JUSTICE MEENAKSHI MADAN RAI, JUDGE
--------------------------------------------------------------------------------------------------------------

                                  Arb.A. No.03 of 2021
         Appellant                :       KMC Brahmaputra Infrastructure Limited

                                                      versus
         Respondent               :       The Chief Engineer, Roads & Bridges Department,
                                          Government of Sikkim

                 Appeal under section 37(1)(c) of the Arbitration
                    and Conciliation Act, 1996 (as amended)
         -----------------------------------------------------------------------------------------
           Appearance
               Mr. Rohan Batra, Advocate with Mr. Dhruv Sethi and Mr. Hemlal
               Manager, Advocates for the appellant.
               Mr. Varun Mishra, Advocate with Mr. Rishab Joshi and Ms.
               Bhawana Rai, Advocates for the respondent.
         -----------------------------------------------------------------------------------------
                                      JUDGMENT

Meenakshi Madan Rai, J.

1. The dispute between the parties before this Court is

confined to the "Loss of Profit" awarded by the Learned Arbitral

Tribunal (hereinafter, "Tribunal") to the appellant, but disallowed

by the Learned Commercial Court (hereinafter, "Commercial

Court") while considering the matter under section 34 of the

Arbitration and Conciliation Act, 1996 (for short, "Arbitration Act").

2. The appellant was to construct a two-lane Gangtok

Bypass Road, from Ranipool to Burtuk in East Sikkim, measuring

23.14 kms., commencing from 22-12-2010, to be completed within

thirty six months. The Project was being developed by the

respondent with the Ministry of Road, Transport and Highways,

Government of India (MoRTH). The appellant's financial bid for

KMC Brahmaputra Infrastructure Limited vs. The Chief Engineer, Roads & Bridges Department, Government of Sikkim

execution of the Project was submitted on 25-06-2010, the

respondent having invited bids on 05-05-2010. On 18-11-2010,

the bid submitted by the appellant, which was about 10% below

the approximate value of the work was accepted, being the lowest

bid. The Letter of Acceptance was issued on the same day. On 22-

12-2010, an Agreement was entered into between the parties

whereby the appellant was to execute the Project within 36 (thirty-

six) months from the date of commencement, i.e., 22-12-2010.

The milestones to be achieved by the appellant was set out in the

Contract which at Clause 25.3 provided that; "The arbitration shall

be conducted in accordance with the arbitration procedure stated in

the Special Conditions of Contract". Clause 59.2(d) of the Contract

provided that "The Employer or the Contractor may terminate the

Contract if the other party causes a fundamental breach of the

Contract. Fundamental breaches of Contract include, but shall not be

limited to the following:";

"(a) .................................................................

(b) .................................................................

(c) .................................................................

(d) a payment certified by the Engineer is not paid by the Employer to the Contractor within 56 days of the date of the Engineer's certificate;

(e) .................................................................

(f) .................................................................

(g) .................................................................

(h) .................................................................

................................................ [emphasis supplied]"

On 26-09-2016, the appellant put forth a proposal to the

respondent to foreclose the Contract, sans adverse consequences

on the appellant and undertaking not to claim compensation if the

foreclosure materialised. Before a response was furnished by the

respondent, the Contract came to be terminated by the appellant

on 18-10-2016 alleging breach of Clause 59.2(d) supra of the

Contract on the failure of the respondent Department to release

KMC Brahmaputra Infrastructure Limited vs. The Chief Engineer, Roads & Bridges Department, Government of Sikkim

payment of Running Account (RA) bills after more than 56 days

from the date of certification. On 25-10-2016, the appellant

invoked the Arbitration Clause in the Contract, while the

respondent by its letter addressed to the appellant dated 29-10-

2016 refuted the basis of termination of Contract. Thereafter, on

the nomination of the Arbitrators the Notice of Preliminary Hearing

was given by the Tribunal on 24-12-2016 and on 12-01-2017 the

first meeting of the Tribunal took place.

3. The Statement of Claim before the Tribunal was filed on

18-02-2017, the appellant inter alia made the following claims;

"1. Release/Return of the following Bank Guarantees

S. No. Particulars of Bank Guarantee Amount (INR)

(a) Performance Bank Guarantee 4,54,30,000 No.01774101PG000041

(b) Performance Bank Guarantee 2,56,27,142 No.69/2015

(c) Performance Bank Guarantee 2,27,15,000 No.01774101PG000044

(d) Equipment Bank Guarantee 3,67,00,000 No.2013/47

2. Damages/Losses being the following:

                                   S. No.      Heads of Claims/Damages                Amount (in INR)
                                      (a)     Outstanding Payments:
                                                                                          1,17,32,363/-
                                                   Certified RA/PA Bills
                                                                                          2,33,65,351/-
                                                   Uncertified RA/PA Bills
                                      (b)     Refund of Security Deposit                  1,80,31,640/-
                                      (c)     Refund      of     amounts                    19,84,000/-
                                              wrongfully              and
                                              unauthorizedly deducted
                                      (d)     Idling costs for machinery                62,36,01,265/-
                                      (e)     Overhead costs                            11,39,80,104/-
                                      (f)     Refund of excess interest                   3,41,17,059/-
                                              charged  on   mobilization
                                              advance
                                      (g)     Loss of profit                            11,49,59,328/-
                                      (h)     Demobilization and              other         75,94,772/-
                                              related expenses


KMC Brahmaputra Infrastructure Limited vs. The Chief Engineer, Roads & Bridges Department, Government of Sikkim

3. Cost of Proceedings under Section 31(8) r/w Section 31A of the Arbitration and Conciliation Act, 1996, Legal Expenses for Court Proceedings and Interest."

4. The respondent filed their Statement of Defence and in

the Counter-Claim put forth a claim of ₹ 101,87,86,714/- (Rupees

one hundred and one crores, eighty seven lakhs, eighty six

thousand, seven hundred and fourteen) only, with rates of interest

as deemed appropriate as detailed in the averments. The break-up

in the Counter-Claim is as hereinbelow;

            Sl. No.                     Counter Claim                                  Amount
             1.        Performance Guarantee                                    Rs.7,10,57,142/-
             2.        Recoveries of outstanding                                Rs.6,39,44,376/-
                       Mobilization/Equipment Advance
                       (or encashment of Bank Guarantee up
                       till the outstanding amount)
             3.        Claims against interest on                                    At 8% Rs.
                       outstanding advances                                         37,68,817/-
                                                                                    At 10% Rs.
                                                                                    47,11,021/-
                                                                                    At 12% Rs.
                                                                                    56,53,226/-
             4.        Liquidated Damages                                      Rs.11,67,66,000/-
             5.        Damage to public properties                                Rs.41,40,540/-
             6.        Maintenance of existing road                               Rs.83,81,900/-
             7.        Claim against 20% of the balance                        Rs.22,99,18,565/-
                       unfinished work
             8.        Cost Over-run                                           Rs.33,33,55,000/-
             9.        Additional overhead Cost                                 Rs.9,02,00,000/-
             10.       Security Deposit                                         Rs.1,80,31,640/-
             11.       Establishment Cost                                                  −
             12.       Expenditure incurred towards                               Rs.38,00,000/-
                       obtaining dumping yard at 9th Mile
             13.       Financial Loss due to late recovery of                     Rs.82,13,000/-
                       Mobilization/machinery advance

The appellant filed its response to the Counter-Claim denying

the claims raised by the respondent.

5. On the basis of the pleadings of the parties, on 13-07-

2017 eleven Issues were settled for determination. On

consideration of the entire facts and circumstances, the evidence

KMC Brahmaputra Infrastructure Limited vs. The Chief Engineer, Roads & Bridges Department, Government of Sikkim

and the rival arguments of counsel placed before the Tribunal, the

Award was pronounced on 18-12-2018 granting inter alia Loss of

Profit to the appellant. Pursuant thereto, on 22-02-2019 certain

typographical and computational errors that had crept into the

Award were brought to the notice of the Tribunal which considered

and rectified the Award and pronounced finally as follows;

"488. ..................................................................

(i) The Respondent is ordered to pay Rs.2,43,34,347/- to the Claimant against outstanding payments.

(ii) The Respondent is ordered to pay/refund to the Claimant security deposit amounting to Rs.2,05,48,417/-

(iii) The Respondent is ordered to pay/refund an amount of Rs.19,84,000/- to the Claimant so deducted from RA Bill No.8, PA Bill No.4 and RA Bill No.10 respectively.

(iv) The Respondent is ordered to pay an amount of Rs.5,74,79,664/- to the Claimant under the head "Loss and Profits".

(v) The Claimant is ordered to pay a sum of Rs.6,39,44,376/- to the Respondent towards the principal outstanding Mobilization/ Equipment Advance and an amount of Rs.1,19,40,954/- towards interest thereon.

(vi) The Respondent is liable to pay to the Claimant a simple interest @ 12% per annum on the sum of Rs.2,63,18,347/- (Rs.2,43,34,347/- + 19,84,000/-) from the date of the Statement of Claim i.e. 18.02.2017 until 18.12.2018 (the date of award). The interest amount, thus, payable by the Respondent to the Claimant from the date of Statement of Claim till the date award comes to 57,79,942/-.

489. The Respondent in terms of the above award shall adjust Rs.7,58,85,330/- from the amount of Rs.11,01,26,370/- and pay to the claimant the balance amount of Rs.3,42,41,040/- within a period of two months from today failing which the Respondent shall pay simple interest @ 12% per annum on Rs.3,42,41,040/- from the date of the award along with an amount of Rs.3,42,41,040/- until the payment to the Claimant. [emphasis supplied]"

6. Dissatisfied with the grant of Award under Loss of Profit

(supra) to the appellant by the Tribunal, the respondent went

before the Commercial Court by filing an application under section

KMC Brahmaputra Infrastructure Limited vs. The Chief Engineer, Roads & Bridges Department, Government of Sikkim

34 of the Arbitration Act, in Arbitration Case No.04 of 2019 (The

Chief Engineer, Roads & Bridges Department, Government of Sikkim vs.

M/s. KMC Brahmaputra Infrastructure Limited), assailing it.

7. The Commercial Court, by the impugned order dated

17-06-2021, set aside the entire claim for damages awarded under

the head "Loss of Profit" on grounds that it was a windfall as the

Tribunal had awarded the amount in a mechanical manner and as

the respondent itself had not complied with the terms of the

Contract and was somehow responsible for the delay, it was not

entitled to earn a profit. As per the Commercial Court, the

approach of the Tribunal in awarding such damages was erroneous,

patently illegal, perverse and hence, could not be sustained.

8. Aggrieved thereof, the appellant impugns the findings

of the Commercial Court by approaching this Court under section

37 of the Arbitration Act.

9(i). Learned counsel for the appellant contended that the

Commercial Court erroneously held that the appellant having

elected to foreclose the Contract by its letter dated 26-09-2016,

had waived its right to claim any compensation or repatriation

charges and was thereby estopped from claiming "Loss of Profit",

while at the same time noting that foreclosure of the Contract

never fructified. The appellant's letter dated 26-09-2016, does not

amount to a waiver of its right to claim Loss of Profit under the

Contract as erroneously presumed by the Commercial Court, which

also failed to appreciate that foreclosure requires the mutual

consent of both parties to truncate the Contract and cannot be a

unilateral act of a party. Submission of the proposal for foreclosure

which was not accepted, cannot amount to waiver by the proposing

KMC Brahmaputra Infrastructure Limited vs. The Chief Engineer, Roads & Bridges Department, Government of Sikkim

party to make legal claims under the Contract. The words,

"without prejudice" in the communication dated 26-09-2016 means

without prejudice to the position of the proposer if the terms he

proposes are not accepted. There was a misplaced observation by

the Commercial Court on the meaning of the words "without

prejudice".

(ii) Learned counsel for the appellant further contended

that, in fact, the Tribunal had reasoned that the appellant was

entitled to damages for future loss of bargain due to "fundamental

breach" of the terms of the Contract by the respondent, which

ultimately led to its termination. The Commercial Court having

concurred with the Tribunal about the fundamental breach, could

not have called into question the entitlement to claim Loss of Profit,

which was a legal and natural consequence of the fundamental

breach. On this aspect reliance was placed by the appellant on

Maharashtra State Electricity Distribution Company Limited vs. Datar

Switchgear Limited and Others . As the respondent had not assailed

the findings of the Tribunal regarding the "fundamental breach" it

had attained finality.

(iii) In the next leg of his argument, learned counsel urged

that the Tribunal had correctly factored in the contributory delay in

the performance of the Contract by the respondent and considered

its consequences on the execution of the Contract, thereby,

concluding that the delay was also attributable to the respondent

on account of non-performance of their obligations. Accordingly,

Loss of Profit, computed at 50% of the total claim put forth by the

appellant was awarded to them. This contention was fortified by

(2018) 3 SCC 133

KMC Brahmaputra Infrastructure Limited vs. The Chief Engineer, Roads & Bridges Department, Government of Sikkim

Assam State Electricity Board and Others vs. Buildworth Private

Limited . Loss of Profit was neither granted in a mechanical

manner nor was it a windfall to the appellant as erroneously opined

by the Commercial Court which substituted the plausible view of

the Tribunal with its own, which is impermissible. Strength on this

count was garnered from Dyna Technologies Private Limited vs.

Crompton Greaves Limited . Inviting the attention of this Court to

the ratio in Union of India and Others vs. Sugauli Sugar Works (P)

Ltd. it was urged that the Supreme Court observed therein that

the principle is that as far as possible, the injured party should be

provided compensation for pecuniary loss which naturally flows

from the breach. The finding of the Commercial Court that if a

party has not complied with the terms of the Contract and is

somehow responsible for the delay and thereby cannot avail the

benefit of such delay and claim that it is entitled to earn a profit, is

contrary to the settled principles of law. Reliance by the

Commercial Court on MSK Projects India (JV) Limited vs. State of

Rajasthan and Another is completely misplaced as the ratio does

not lay down such a proposition and the decision is distinguishable

on facts.

(iv) The use of the word "perverse" and "patently illegal" by

the Commercial Court is erroneous since the Supreme Court in

Ssangyong Engineering and Construction Company Limited vs. National

Highways Authority of India (NHAI) has explained the import of

"patent illegality" and "perversity". Thus, the Commercial Court

exceeded the scope of section 34 of the Arbitration Act, as nothing

(2017) 8 SCC 146

(2019) 20 SCC 1

(1976) 3 SCC 32

(2011) 10 SCC 573

(2019) 15 SCC 131

KMC Brahmaputra Infrastructure Limited vs. The Chief Engineer, Roads & Bridges Department, Government of Sikkim

illegal or perverse emerges in the claim for Loss of Profit which was

duly awarded by the Tribunal. As the impugned order suffers from

non-application of mind and misconstruction of the findings in the

Award, the present Appeal be allowed and the impugned order of

the Commercial Court, dated 17-06-2021 (supra), be set aside.

10(i). Resisting the arguments put forth by learned counsel

for the appellant, learned counsel for the respondent would

contend that the Commercial Court has rightly set aside the Award

on Loss of Profit. The appellant had executed only 19% of the

work, towards which a sum of more than ₹ 27,00,00,000/- (Rupees

twenty seven crores) only, was already paid, but even after 6 (six)

years of the commencement of the work, the appellant was unable

to build a single kilometer of paved road out of the entire length.

Significant evidence which undermined the claim for Loss of Profit

and the admission of the appellant that it was incurring losses in

the Contract was entirely ignored by the Tribunal. On this aspect,

the respondent relied on Hudson's Building and Engineering

Contracts . It was contended that in fact, the appellant would not

have made any profit in executing the Contract, for the reason that

no profit element was incorporated into the appellant's bid as it had

underbid by 10% less than the estimated value of the Contract.

Reliance was placed on this count in GTM Builders & Promoters Pvt

Ltd vs. Sneh Developers Pvt Ltd and State of State of Madhya Pradesh

and Others vs. M/s. Recondo Limited, Bhopal9 wherein the Courts

were loathe to allow damages towards Loss of Profit in the absence

of proof. The findings of the Tribunal, which have not been

13th Edition at Pages 869-872 (Sweet & Maxwell)

Judgment of the High Court of Delhi in O.M.P.(COMM) 10/2016 & IA Nos.6379/2016 & 4720/2017 dated 03-07-2018

1989 M.P.L.J 822

KMC Brahmaputra Infrastructure Limited vs. The Chief Engineer, Roads & Bridges Department, Government of Sikkim

challenged by the appellant, indicate acceptance of imprudence in

its work, raising serious concerns on its ability to perform the

Contract. The contents of the letter dated 13-09-2014 addressed

to the respondent Department by the appellant would fortify the

submission on whether the appellant would have made any profit

on account of increase in the value of the Contract.

(ii) The Loss of Profit was also granted for the reason that

there was a breach of the contract on account of delay in payment

of two bills, the amounts being de minimis would obviously not

have caused any loss to the appellant. The Tribunal observing that

there was a fundamental breach in the Contract gave reasons for

granting Loss of Profit to the appellant. However, in M/s. Hind

Construction Contractors by its Sole Proprietor Bhikam-Chand Mulchand

Jain (Dead) by Lrs. vs. State of Maharashtra10 and N. Srinivasa vs.

Kuttukaran Machine Tools Limited , the Supreme Court has observed

that intention of a Contract is to be gleaned from its holistic

reading, the conduct of the parties and not merely by

interpretation of one Clause. Clause 43 of the Contract entitled the

Contractor to interest @ 12% per annum on delayed payment,

which indicates that payment of bills within 56 days was not

intended to be the "essence of the contract". MSK Projects India

(JV) Limited (supra) is fairly instructive on whether loss of profits

ought to be payable to a Contractor who failed to abide by the

terms of a Contract. All payments computed by the Tribunal ought

to have been limited to the date of termination and Loss of Profit

not granted as the appellant had itself terminated the Contract.

(1979) 2 SCC 70

(2009) 5 SCC 182

KMC Brahmaputra Infrastructure Limited vs. The Chief Engineer, Roads & Bridges Department, Government of Sikkim

(iii) It was next argued that the fundamental policy

contained in section 73 of the Indian Contract Act, 1872 (for short,

"Contract Act"), is that damages can only be awarded for any loss

or damage which naturally arose in the usual course of things from

such breach, or which the parties knew when they made the

Contract, to be likely to result from the breach of it. Thus, it is trite

that the party claiming compensation as loss of profit or anticipated

profit, must establish that there was a causal connection between

the breach and the loss sustained by the party who suffered the

breach, which is not so in the present case. It was in fact the

appellant's termination of the Contract, vide its letter dated 18-10-

2016, that resulted in its alleged loss of profit. The claim for Loss of

Profit would have been justified if the respondent had illegally

terminated the Contract, thereby, preventing the appellant from

earning any alleged profit from the Contract. Thus, the observation

of the Tribunal that a claim for Loss of Profit would be likely to

result from delay in payment by the respondent, is patently illegal.

Strength was garnered on this count from the ratio in Kanchan

Udyog Limited vs. United Spirits Limited .

(iv) Relying on the ratio in M. Lachia Setty and Sons Ltd. vs.

Coffee Board, Bangalore wherein the Hon'ble Court relied on

Halsbury's Laws of England (4th Edn., Vol. 12, Page 477), for the

law on mitigation of loss, learned counsel advanced the argument

that it is an admitted case that as on the date of termination, the

appellant had executed the Contract works worth approximately

₹ 27,00,00,000/- (Rupees twenty seven crores) only, out of a total

of ₹ 142,00,00,000/- (Rupees one hundred and forty two crores)

(2017) 8 SCC 237

(1980) 4 SCC 636

KMC Brahmaputra Infrastructure Limited vs. The Chief Engineer, Roads & Bridges Department, Government of Sikkim

only, and was yet to execute ₹ 115,00,00,000/- (Rupees one

hundred and fifteen crores) only, worth of work to make its alleged

profit. By terminating the Contract pre-maturely, the appellant

was able to free up and divert its men and machinery to perform

other works, from which the appellant could have derived a profit

which ought to be set off against the appellant's claim for Loss of

Profit, otherwise it would lead to a windfall for the appellant.

(v) Learned counsel for the respondent further contended

that the respondent's case before the Tribunal was that future

damages may only be claimed in the event of a repudiatory breach

under section 39 of the Contract Act, whereas, failure to make a

certified payment within 56 (fifty six) days as envisaged under

clause 59.2(d) is not covered by the ambit of section 39 of the

Contract Act. The Tribunal placed unnecessary emphasis on the

phrase, "Fundamental Breach", in clause 59.2 and treated it as a

repudiatory breach. To fortify his submissions, reliance was placed

on Hind Construction Contractors (supra); N. Srinivasa (supra) and

Transmission Corporation of Andhra Pradesh Limited and Others vs.

GMR Vemagiri Power Generation Limited and Another .

(vi) In the last leg of his arguments, it was contended by

learned counsel that the respondent sought to perform its

obligation under the Contract and acknowledged vide its letter

dated 12-02-2016 that some delays in payment are inevitable due

to MoRTH's involvement, which is routine Government procedure.

Besides, the appellant themselves failed to raise the monthly R.A.

bills in terms of clause 42 of the Contract. The Contract spanned a

period of more than 5 (five) years while bills raised were only 14

(2018) 3 SCC 716

KMC Brahmaputra Infrastructure Limited vs. The Chief Engineer, Roads & Bridges Department, Government of Sikkim

R.A. bills. The Tribunal ignored the appellant's undertaking dated

26-09-2016 wherein it categorically undertook not to claim

compensation/repatriation charges if the foreclosure of the

Contract took place, which led the respondent to believe that the

Contract would be foreclosed, but the appellant proceeded to

terminate the Contract and sought for damages in lieu of future

performance. Thus, the Appeal ought to be dismissed as the

learned Court below has correctly set aside the Tribunal's Award on

loss of profit.

11. In rebuttal, the vehement contention advanced by

counsel for the appellant was that the arguments of the respondent

pertaining to the breach committed by the respondent which led to

termination of the Contract being a "technical breach" and not a

"fundamental breach" ought not to be considered by this Court

while deciding the instant Appeal as these arguments were not

raised before the Court below. The test of the Award is whether

there was a fair conclusion and the Tribunal has articulated all the

essential principles in its order considering all aspects. It is settled

law that an Arbitral Award cannot be interfered with in a cavalier

manner unless the Commercial Court comes to a conclusion that

the perversity of the Award goes to the root of the matter. The

finality of the Arbitral Award is to be respected, hence the Appeal

be allowed.

12. The submissions put forth in extenso have been duly

considered, all documents perused, as also the citations made at

the Bar. This Court is now to consider whether the Learned

Commercial Court by its impugned order was correct in setting

KMC Brahmaputra Infrastructure Limited vs. The Chief Engineer, Roads & Bridges Department, Government of Sikkim

aside the Loss of Profit awarded by the Tribunal to the appellant,

vide its Award dated 18-12-2018?

13. In this context, in the first instance, it is essential to

navigate the parameters for setting aside an Arbitral Award. The

provisions of section 34 of the Arbitration Act are itself explicit on

this aspect. We may refer to section 34(2A) which is relevant for

the present purpose and provides as follows;

"34. Application for setting aside arbitral award.--(1) ...............................................

(2) ................................................. (2A) An arbitral award arising out of arbitrations other than international commercial arbitrations, may also be set aside by the Court, if the Court finds that the award is vitiated by patent illegality appearing on the face of the award.

Provided that an award shall not be set aside merely on the ground of an erroneous application of the law or by reappreciation of evidence.

(3) ...................................................... (4) .................................................... (5) ...................................................... (6) ...................................................."

14(i). While examining the scope of section 34 of the

Arbitration Act, in Renusagar Power Co. Ltd. vs. General Electric Co.15

the Supreme Court laid down that the Arbitral Award can be set

aside if it is contrary to (a) fundamental policy of Indian Law; (b)

the interests of India; (c) or justice or morality. In Oil & Natural

Gas Corporation Ltd. vs. Saw Pipes Ltd.16 apart from the above

mentioned three grounds, the Supreme Court appended another

ground, i.e., if it is patently arbitrary. It was however clarified that

such patent illegality must go to the root of the matter. This was

reiterated in McDermott International INC. vs. Burn Standard Co. Ltd.

and Others wherein the Supreme Court observed that such patent

illegality must go to the root of the matter. The public policy

1994 Supp (1) SCC 644

(2003) 5 SCC 705

(2006) 11 SCC 181

KMC Brahmaputra Infrastructure Limited vs. The Chief Engineer, Roads & Bridges Department, Government of Sikkim

violation, indisputably, should be so unfair and unreasonable as to

shock the conscience of the court. Where the arbitrator, however,

has gone contrary to or beyond the expressed law of the contract or

granted relief in the matter not in dispute would come within the

purview of section 34 of the Act.

(ii) In Datar Switchgear Limited (supra) it was inter alia

observed that the proposition of law is that the Arbitral Tribunal is

the master of evidence and the findings of fact arrived at by the

Arbitrators on the basis of evidence on record are not to be

scrutinised as if the Court was sitting in Appeal. This principle was

upheld in MMTC Limited vs. Vedanta Limited18 and it was explained

therein that the Court may interfere on merits on the limited

ground of the Award being against the public policy of India.

(iii) In Parsa Kente Collieries Limited vs. Rajasthan Rajya

Vidyut Utpadan Nigam Limited it was held that an Arbitral Tribunal

must decide in accordance with the terms of the Contract, but if a

term of the Contract has been construed in a reasonable manner

then the Award ought not to be set aside on this ground alone, while

in National Highway Authority of India vs. Progressive-MVR (JV)20, the

Supreme Court on considering a plethora of decisions on the scope

and ambit of the proceedings under section 34 of the Arbitration

Act, observed that, even when the view taken by the Arbitrator is a

plausible view and/or when two views are possible, the particular

view taken by the Tribunal which is also reasonable should not be

interfered with in proceedings under section 34 of the Arbitration

Act.

(iv) In Dyna Technologies Private Limited (supra), the

Supreme Court while discussing the limitations of the Court in

(2019) 4 SCC 163

(2019) 7 SCC 236

(2018) 14 SCC 688

KMC Brahmaputra Infrastructure Limited vs. The Chief Engineer, Roads & Bridges Department, Government of Sikkim

exercising powers under section 34 of the Arbitration Act,

highlighted as follows;

"24. There is no dispute that section 34 of the Arbitration Act limits a challenge to an award only on the grounds provided therein or as interpreted by various courts. We need to be cognizant of the fact that arbitral awards should not be interfered with in a casual and cavalier manner, unless the court comes to a conclusion that the perversity of the award goes to the root of the matter without there being a possibility of alternative interpretation which may sustain the arbitral award. Section 34 is different in its approach and cannot be equated with a normal appellate jurisdiction. The mandate under section 34 is to respect the finality of the arbitral award and the party autonomy to get their dispute adjudicated by an alternative forum as provided under the law. If the courts were to interfere with the arbitral award in the usual course on factual aspects, then the commercial wisdom behind opting for alternate dispute resolution would stand frustrated.

25. Moreover, umpteen number of judgments of this Court have categorically held that the courts should not interfere with an award merely because an alternative view on facts and interpretation of contract exists. The courts need to be cautious and should defer to the view taken by the Arbitral Tribunal even if the reasoning provided in the award is implied unless such award portrays perversity unpardonable under section 34 of the Arbitration Act.

[emphasis supplied]"

15(i). The aforesaid judgments have detailed the contours of

the powers of the Court in proceedings under section 34 of the

Arbitration Act, on the anvil of which, we now examine the matter

before us.

(ii) On a careful perusal of the Award, it is evident that the

Tribunal while factoring in the Loss of Profit, elucidated its

reasoning from paragraph 362 to paragraph 380 of the Award,

discussed the scheme of section 39 of the Contract Act and inter

alia observed that "(vii) where the parties to the contract have

expressly stipulated a term of the contract as "fundamental" or "of

the essence" and there is breach of such fundamental or essential

term by a party, the aggrieved party may invoke the express term

and terminate the contract. In such a situation, the principle of law

KMC Brahmaputra Infrastructure Limited vs. The Chief Engineer, Roads & Bridges Department, Government of Sikkim

stated in sub-para (iv) above has no application and the aggrieved

party is entitled to claim damages for past losses i.e. losses up to

the date of the contract and also future losses post termination. In

other words, in such event, the innocent/aggrieved party may

make a claim for loss of bargain for the entire period of contract."

The Tribunal also opined that the respondent was under a

misconception that as the appellant had terminated the contract

under an express clause of the Contract and termination was on

account of technical breach of the term of the Contract, although

termed as "fundamental breach", such "fundamental breach" did

not entitle the aggrieved party to loss of profit post-termination.

That, "repudiatory breach" and "fundamental breach" are two

different aspects, but the outcome that follows on termination of

Contract by the aggrieved party in either case, is the same. The

Tribunal further observed that;

"364. By stipulating the breach in clause 59.2(d) as a fundamental breach, the parties agreed the payment of certified bills within the stipulated time to be of essence. Thereby, the parties have ensured the same outcome in the event of breach of fundamental term which would ordinarily follow on termination of contract for repudiatory breach.

......................................................

369. The Tribunal is of the considered view that the Claimant is entitled to the damages for future loss of bargain due to fundamental breach of the term of the contract by the Respondent which ultimately led to the termination of contract.

[emphasis supplied]"

(iii) Insofar as the termination of Contract is concerned, the

Tribunal dealt with it specifically at paragraph 108 of its Award

where it was observed as follows;

"108. Clause 59.2(d) of the contract expressly states that if a payment certified by the Engineer is not paid by the Employer to the Contractor within 56 days of the date of the Engineer's certificate shall be treated as a fundamental breach of the contract. The fundamental breach specified in Clause 59.2(d)

KMC Brahmaputra Infrastructure Limited vs. The Chief Engineer, Roads & Bridges Department, Government of Sikkim

is a standalone breach which entitles the Contractor to terminate the contract. The factum of non-payment of certified bill by the Engineer beyond 56 days of the date of certificate, thus, by itself is sufficient for the Contractor to terminate the contract as such delayed payment is treated as a fundamental breach of the Employer. [emphasis supplied]"

The Court below did not disagree with the conclusion of the learned

Tribunal on this aspect. It may relevantly be pointed out that, it is

a settled position of law that a fundamental breach by its very

nature pervades the entire Contract and once committed the

Contract as a whole stands abrogated. [See, Datar Switchgear

Limited (supra)].

(iv) The Tribunal did not find any merit in the argument of

counsel for the respondent that the claimant underbid and,

therefore the Loss of Profit was misconceived. The Tribunal

reasoned that the Contract is a commercial one, where the

claimant has not bid to make losses, that the ingredient of profit is

always inbuilt in the performance of a particular Contract. It was

also opined that the original price of the Contract was revised from

₹ 99.16 crores where the claimant had bid ₹ 90.86 crores to

₹ 195.22 crores by MoRTH. That, in the said circumstance, the

argument that the claimant's underbidding disentitled it to any

"Loss of Profit" was not accepted. That, the claimant had put forth

Loss of Profit @ 10% of the unexecuted work. That, the measure

of 10% of the unexecuted work toward Loss of Profit is prescribed

by the MoRTH.

(v) The Tribunal relied on the decision of the Hon'ble High

Court of Kerala in State of Kerala vs. K. Bhaskaran21 where it was

observed that the measure of damage no doubt is the amount of

AIR 1985 Ker 49

KMC Brahmaputra Infrastructure Limited vs. The Chief Engineer, Roads & Bridges Department, Government of Sikkim

profit lost to the Contractor by the breach. This is a measure of

compensation for the loss which arose in the usual course of

things. This can be stated as the loss which the parties knew when

they made the contract, as likely to result from the breach of it.

When the plaintiff entered into the contract, he agreed to complete

the work for the stated amount reckoning a sum for his profit also.

(vi) The Tribunal also referred to a decision of the Supreme

Court in Sugauli Sugar Works (supra) relied on by the Kerala High

Court (supra) in the same ratio, wherein it was held as follows;

"22. ............................ One of the principles for award of damages is that as far as possible he who has proved a breach of a bargain to supply what he has contracted to get is to be placed as far as money can do it, in as good a situation as if the contract had been performed. The fundamental basis thus is compensation for the pecuniary loss which naturally flows from the breach. Therefore, the principle is that as far as possible the injured party should be placed in as good a situation as if the contract had been performed. In other words, it is to provide compensation for pecuniary loss which naturally flows from the breach. The High Court correctly applied these principles and adopted the contract price in the facts and circumstances of the case as the correct basis for compensation."

(vii) It is imperative to notice at this juncture that the

Supreme Court held in M/s. A.T. Brij Paul Singh and Others vs. State

of Gujarat that, what must be the measure of profit and what

proof should be tendered to sustain the claim are different matters,

but the claim under the head of Loss of Profit is clearly admissible.

It thus concludes that Loss of Profit is to be granted by the Tribunal

in a breach of Contract.

(viii) That, there was a breach of Contract is evident from

the reasoning put forth by the Tribunal and on reading Clause

59.2(d) of the Contract between the parties, what remains for

(1984) 4 SCC 59

KMC Brahmaputra Infrastructure Limited vs. The Chief Engineer, Roads & Bridges Department, Government of Sikkim

consideration is the method of computation. While addressing the

issue of computation, we may necessarily refer to the

pronouncement of the Supreme Court in M. N. Gangappa (Dead) By

L.Rs vs. Atmakur Nagabhushanam Setty & Co. and Another wherein it

was held that the method used for computation of damages will

depend upon the facts and circumstances of each case.

16. The Tribunal while computing the Loss of Profit inter

alia examined the evidence furnished by the claimant through its

witness and concluded as follows;

"378. The Respondent in its Statement of Defence has not specifically disputed the measure of 10% applied by the Claimant. Moreover, CW-2 has been cross examined by the Respondent at quite some length but his evidence in paragraphs 28 and 29 of the affidavit has not at all been challenged. In the circumstances, there is no justification for the Tribunal to reject the evidence of CW-2 on this count.

379. The Tribunal is of the considered view that measure of 10% of the unexecuted work adopted by the Claimant for claiming loss of profits is a fair and reasonable measure. However, in the facts and circumstances of the case, the Claimant would not be entitled to 10% loss of profit on the entire unexecuted work. In the Tribunal's view, since the Claimant also contributed to delay in performance of the contract by not discharging its some of the important obligations on the time as already noted in the earlier part of the award and the fact that few days before it terminated the contract, the Claimant itself wanted the contract to be foreclosed without imposition of any liability on it, an award of 50% of what has been claimed by the Claimant as the loss of profit of unexecuted work seems to be fair and reasonable.

380. The Tribunal, accordingly, awards 50% of the claim of Rs.11,49,59,328/- under the head "Loss and Profits" made by the Claimant which comes to Rs.5,74,79,664/-" [emphasis supplied]

17. The learned Court below however disagreed with the

findings of the Tribunal while setting aside the Award under loss of

Profit and contrarily observed as follows;

(1973) 3 SCC 406

KMC Brahmaputra Infrastructure Limited vs. The Chief Engineer, Roads & Bridges Department, Government of Sikkim

"39. ........... . Be that as it may, the above facts and circumstances would make it clear that the respondent/claimant had clearly elected to proceed with the foreclosure of the contract-work subject only to the condition that no adverse consequences are attached to it and it had undertaken not to claim any compensation or repatriation charges in the event of such foreclosure which was contemplated by 30.09.

2016. Clearly, apart from having consciously made such election it had also waived its right to claim any compensation/ repatriation charges if the foreclosure took place. It is rather strange that despite the same the respondent/claimant would make a complete volte face and immediately rush to terminate the contract vide its letter dated 18.10.2016. Strictly speaking, the respondent/claimant having unequivocally elected to proceed with the foreclosure of the contract for expediting which it had itself later requested vide its letter dated 28.09.2016 and having waived its right to claim any compensation or repatriation charges could not have still claimed „loss of profit‟ by suddenly terminating the contract nor could it have been awarded by the Ld. Arbitral Tribunal. In other words, the respondent/claimant cannot be allowed to approbate and reprobate at the same time once having elected as above and having undertaken to waive any claim whatsoever in the event of the foreclosure without any adverse consequences on it. ......................... ..............................................................................

42. Viewed from the other angle, the Respondent/claimant having expressly waived its right to claim compensation or repatriation charges in the event of the proposed foreclosure could not have claimed „loss of profit‟. .......... ..............................................................................

46. Suffice it to say, in the light of the above settled position, observation and the peculiar facts and circumstances obtaining in the case on hand the fact that the undertaking dated 26.09.2016 was without prejudice would not enure any benefit to the respondent/claimant when it had consciously and unequivocally elected to proceed with the foreclosure of the contract subject only to the condition that no adverse consequences are meted out to it, and it having clearly waived its right to claim compensation or repatriation charges in the event of such foreclosure by the petitioner-

employer. So much so, vide its subsequent letter dated 28.09.2016 which incidentally was not marked without prejudice the respondent/ claimant would even request the petitioner-

employer to expedite the process of foreclosure. These attenuating circumstances also go against the claims of the respondent/claimant with regard to „loss of profit‟.

KMC Brahmaputra Infrastructure Limited vs. The Chief Engineer, Roads & Bridges Department, Government of Sikkim

47. Needless to say, the approach of the Ld.

Arbitral Tribunal in awarding damages under the head „loss of profit‟ despite the above facts and circumstances is clearly erroneous and patently illegal which goes to the root of the concerned matter. The award to that extent is ex facie perverse and cannot be sustained."

18. It appears from the reasonings extracted supra that the

Commercial Court was aware that the foreclosure of the Contract

never fructified despite which it proceeded to observe that prior to

the termination of the Contract there was a proposal for

foreclosure, vide letter of the appellant, dated 26-09-2016. The

Commercial Court opined that the appellant in the communication

had waived its right to claim any compensation or repatriation,

should the foreclosure materialise. The Commercial Court was

evidently of the opinion that the same conditions of waiver would

have to be read into the communication for termination of the

Contract, sans such specific waiver. The observation of the

Commercial Court that in the Undertaking dated 26-09-2016, the

words "without prejudice" would not enure any benefit to the

appellant who had elected to foreclose the Contract, is an apparent

erroneous observation considering the fact that the words were

employed in the said communication for a proposal for foreclosure.

In any event, the words "without prejudice" as per Black's Law

Dictionary, Tenth Edition, 2014, means "without loss of any rights; in

a way that does not harm or cancel the legal rights or privileges of

a party". In other words, it means without detriment to any

existing right or claim and not as interpreted by the Commercial

Court in paragraph 46 (extracted supra) of its impugned order.

Consequently, the remark of the Commercial Court that the

appellant was approbating and reprobating is also an incorrect

KMC Brahmaputra Infrastructure Limited vs. The Chief Engineer, Roads & Bridges Department, Government of Sikkim

observation. It is indeed absurd to suggest that vide the

communication of 26-09-2016, the appellant had waived all legal

rights even while terminating the Contract.

19. While addressing the observation of the Commercial

Court that the Award of damages under the head "Loss of Profit"

was clearly erroneous, patently illegal and the Award to that extent

was ex facie perverse, in Ssangyong Engineering and Construction

Company Limited (supra) the Supreme Court while expanding on

illegality appearing on the face of the Award observed that such

illegality must go to the root of the matter, and ought not to be a

mere erroneous application of the law. The Award would also be

"patently illegal" if an Arbitrator gives no reasons for an Award and

wanders outside the Contract and deals with matters not allotted to

him. That, "Patent illegality" would also be one in which a decision

is perverse or so irrational that no reasonable person would have

arrived at the same and if a finding of fact is arrived at by ignoring

or excluding relevant material or by taking into consideration

irrelevant material or if the finding so outrageously defies logic so

as to suffer from the vice of irrationality incurring the blame of

being perverse, then, the finding would be rendered infirm in law.

It would be apposite to mention that in Datar Switchgear Limited

(supra) it was laid down that the Tribunal is the master of evidence

and the findings of fact cannot be scrutinized as if the Court is

sitting in Appeal. Interference on merits would be permissible only

if the Award is against public policy [See MMTC Limited (supra)].

20. After having perused the Award and having extracted

hereinabove the relevant paragraphs, we find that elaborate

reasons have been rendered for the conclusion arrived at by the

KMC Brahmaputra Infrastructure Limited vs. The Chief Engineer, Roads & Bridges Department, Government of Sikkim

Tribunal which can neither be termed as "erroneous", "irrational" or

"patently illegal".

21. We also agree with the counsel for the appellant that

reliance on MSK Projects India (JV) Limited (supra) by the

Commercial Court to opine that if a party has not complied with

terms of the Contract and is somehow responsible, even if not

equally for the delay taken cannot avail the benefit of such delay

and claim that it is entitled to earn a profit, is completely

misplaced. This observation of the Supreme Court was made in the

context of a case, the facts of which are distinguishable from the

instant case. The facts therein were that as per the terms of the

agreement between the petitioner (MSK Projects) and the

respondent (State of Rajasthan) the petitioner was required to

complete the project of construction of roads in two phases. In the

first phase, a certain amount of investment was to be made and

after five years, in the second phase, another amount was to be

invested by the petitioner. The petitioner however failed to abide

by the terms of the agreement and did not make any investment

for the second phase and thereby breached the contract. The

State of Rajasthan submitted that the contention of the petitioner

that he is entitled to recover its investment was erroneous and the

petitioner had not approached the Court with clean hands. The

allegations were found not to have been denied by the Petitioner.

That being so, the Supreme Court observed that the State

Authorities had for reasons best known to them not made

reference to the arbitration proceedings for non-execution of the

work of the second phase of the Contract. However, the relief

claimed by the private appellant would prove to be a windfall profit

KMC Brahmaputra Infrastructure Limited vs. The Chief Engineer, Roads & Bridges Department, Government of Sikkim

without carrying out the obligation to execute the work just on

technicalities. In order to do complete justice between the parties,

the Supreme Court ordered that the matter requires adjudication

and reconsideration on two points by the Tribunal. The above

matter is irrelevant for the present purposes as a fundamental

breach of the Contract is the basis of its termination.

22. So far as reliance of the respondent on GTM Builders &

Promoters (supra) and Recondo Limited (supra) are concerned, the

judgments only have persuasive value, over and above which we

notice that the facts in the citations are distinguishable from the

instant case and are of no assistance to the respondent.

23. Coming to the question of interpretation of section 73

of the Contract Act as agitated by learned counsel for the

respondent, it is useful to notice that in MSK Projects India (JV)

Limited (supra) reference was made to A.T. Brij Paul Singh (supra)

where, while interpreting the above provision of law the Court

specifically held that; where in the works contract the party

entrusting the work committed breach of Contract, the Contractor

is entitled to claim the damages for loss of Profit which he expected

to earn by undertaking the works contract. Claim of expected

profit is legally admissible on proof of the breach of Contract by the

erring party. What would be the measure of profit would depend

upon facts and circumstances of each case, but that there shall be

reasonable expectation of profit is implicit in the works contract

and its loss has to be compensated by way of damages if the other

party to the Contract is guilty of breach of contract cannot be

gainsaid. The observation being a settled position of law it also

lends a quietus to the dispute herein.

KMC Brahmaputra Infrastructure Limited vs. The Chief Engineer, Roads & Bridges Department, Government of Sikkim

24. Neither the Court below nor this Court are empowered

under the relevant provisions of law to reappreciate the evidence

on record nor do the provisions of law envisage that Courts while

exercising power under section 34 of the Arbitration Act shall

function as a regular first Court of Appeal. The Court, under

section 34 of the Arbitration Act cannot replace the views of the

Tribunal, if found plausible, by substituting its own views.

25. From a meticulous perusal of the Award, we cannot

bring ourselves to agree with the observations of the Learned

Commercial Court that the findings of the Learned Tribunal suffers

from the vice of being erroneous, patently illegal or ex facie

perverse.

26. In our considered opinion, the Learned Tribunal after

holding that there was a fundamental breach of Contract, factored

in the contributory delay caused by the appellant and fairly

awarded Loss of Profit by slashing it to 50% of the original claim

put forth by the appellant.

27. Order of the learned Commercial Court is set aside and

the Award passed by the learned Tribunal stands restored.

28. Appeal along with all pending applications stand

disposed of accordingly.

29. Parties to bear their own costs.




               ( Meenakshi Madan Rai )                          ( Biswanath Somadder )
                     Judge                                             Chief Justice
                            20-12-2022                                            20-12-2022




     Approved for reporting : Yes
ds
 

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter