Saturday, 09, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Manju Sharma vs Union Of India
2026 Latest Caselaw 1609 Raj

Citation : 2026 Latest Caselaw 1609 Raj
Judgement Date : 4 February, 2026

[Cites 5, Cited by 0]

Rajasthan High Court - Jodhpur

Manju Sharma vs Union Of India on 4 February, 2026

[2026:RJ-JD:5697]

      HIGH COURT OF JUDICATURE FOR RAJASTHAN AT
                       JODHPUR
                    S.B. Civil Writ Petition No. 1857/2026

Manju Sharma W/o Jagdish Sharma, Aged About 55 Years, R/o
6A, 12 Rc Vyas Colony, Bhilwara, Rajasthan.
                                                                       ----Petitioner
                                       Versus
1.       Union Of India, Through Joint Secretary (Transmission),
         Ministry Of Power.
2.       Central Electricity Authority Of India, Having Its Office At
         Sewa Bhawan, Rama Krishna Puram, Sector 1, New Delhi
         110066.
3.       District Magistrate, Bhilwara.
4.       Sub Divisional Magistrate, Bhilwara.
5.       Power Grid Corporation Of India Limited (Powergrid),
         Having Its Registered Office At B9, Qutab Institutional
         Area, Katwaria Sarai, New Delhi 110016.
6.       Power       Grid   Beawar       Mandsaur          Transmission     Limited,
         Having Its Registered Office At B9 Qutab Institutional
         Area, Katwaria Sarai, New Delhi 110016.
                                                                    ----Respondents


For Petitioner(s)            :     Dr. Sachin Acharya, Sr. Advocate
                                   assisted by Mr. Karan Parihar.
                                   Ms. Vaishnav Nikita.
For Respondent(s)            :     Mr. Vineet Dave.
                                   Mr. Harshit.
                                   Mr. Yogantar Ohri.


              HON'BLE MR. JUSTICE SUNIL BENIWAL

Order

Conclusion of Arguments & Reserved on : 29/01/2026 Pronounced on : 04/02/2026

1. This writ petition has been filed by the petitioner with the

following prayer :-

"It is, therefore, most respectfully prayed on behalf of the petitioner that the writ petition may kindly be allowed

(Uploaded on 04/02/2026 at 01:27:54 PM)

[2026:RJ-JD:5697] (2 of 8) [CW-1857/2026]

and by an appropriate writ of mandamus, order or direction:-

a. To quash and set aside the approval under Section 164 of the Indian Electricity Act (Anx.5) dated 04.08.2025 given by Respondent No.1;

b. to pass necessary directions against the Respondents, forbearing the Respondent Company from erecting any high-tension electric tower, transmission lines, foundation for the tower or any such incidental activity on the petitioner's land;

c. in alternate direct the respondents to pay compensation to the petitioner under relevant laws and guidelines including telegraph act, 1885, Guidelines dated 14.06.2024 and Supplementary Guidelines dated 21.03.2025 issued by the Ministry of Power;

d. Any such other and further reliefs be granted as this Hon'ble Court may deem fit and proper."

2. The facts, in nutshell, as narrated in the present writ

petition, are that a high-tension line is in process of installation

between Beawar and Mandsaur with approximate length of 273.37

kms. The high-tension line as indicated above is passing through

the land owned by the petitioner falling in Khasra Nos.1453/957,

961/1 and 962/1 situated in Village Agarpura, Tehsil and District

Bhilwara. The installation of one of the tower, more particularly

Tower No.94/0 so also the high-tension line, which would be

passing through the field of the present petitioner, is questioned in

the present writ petition.

3. While arguing the writ petition, learned Senior counsel

appearing on behalf of the petitioner made the following

submissions :-

(i) the respondents are proposing to install tower as well as

high-tension line in a totally arbitrary and discriminatory manner

while applying arbitrary parameters deciding the distance between

two towers.

(Uploaded on 04/02/2026 at 01:27:54 PM)

[2026:RJ-JD:5697] (3 of 8) [CW-1857/2026]

(ii) the respondent - Corporation has deviated the route of the

transmission line, which has resulted in direct damage to the

petitioner, as the high-tension line would be passing through the

land owned by the petitioner, which would damage maximum

portion of the land owned by the petitioner without there being

any justification to deviate the line. While elaborating this

submission it was submitted that as a routine, transmission lines

are always installed in a straight line and on account of deviation,

the line has been rerouted and is now proposed to pass over the

land belonging to the petitioner.

(iii) there is a Standard Operating Procedure ('SOP') to be

adopted while installing tower as well as high-tension line,

however, in complete violation of the SOP, the Corporation has

proceeded in high handed manner and are bent upon to install the

tower and also lay down the high-tension line.

(iv) the distance between two towers on either side of the

National Highway is not equidistant. On the one side, the tower is

at a distance of 83 mtrs., however, on the other side, it is about

114 mtrs. It was submitted that if the tower which is proposed to

be installed on the land belonging to the petitioner is also installed

at an equidistant of 83 mtrs., it shall cause minimal loss to the

present petitioner.

3.1 After filing of the writ petition, an additional affidavit was

also filed, wherein a google map has been annexed along with the

conversion orders, so as to indicate that the petitioner's land is

converted land. In addition to it, a communication dated

(Uploaded on 04/02/2026 at 01:27:54 PM)

[2026:RJ-JD:5697] (4 of 8) [CW-1857/2026]

21.11.2025 has also been placed on record so as to indicate that

the Corporation is required to abide by certain conditions, which

includes one time processing fee of Rs. 5 lacs and so also the bank

guarantee. It was submitted that the amount as indicated in the

said communication, has been deposited on 22.01.2026 in order

to cover up such lacuna.

Based on the above submission, it is submitted that the

present writ petition deserves to be allowed. The respondents may

either be restrained to install the tower and high-tension line on

the land belonging to the petitioner or appropriate direction be

given to the respondent - Corporation to shift the tower and

install at the boundary of the land belonging to the petitioner so

as to minimize the damage.

4. Per contra, learned counsel appearing for the respondents

vehemently opposed the submissions made by learned counsel for

the petitioner and submitted that the Corporation is installing 765

KV high-tension line between Beawar to Mandsaur in terms of

Notification dated 29.08.2023. It was further submitted that as

many as 734 towers are to be installed for setting up of this 765

KV transmission line and out of 734 towers, 571 towers have

already been installed. It was also submitted that the project is of

National importance and if any tower is proposed on the land

belonging to the petitioner or is creating hindrance in any manner,

then the petitioner is entitled for compensation in accordance with

law.

(Uploaded on 04/02/2026 at 01:27:54 PM)

[2026:RJ-JD:5697] (5 of 8) [CW-1857/2026]

4.1 Learned counsel for the respondents further submitted that

there is no intentional deviation of the transmission line as alleged

by the petitioner. As a matter of fact, the guidelines mandate to

have 90 degree angle to be maintained at the time when the

transmission line is crossing the National highway. Considering

such guidelines, the required deviations have been made,

however, this is neither intentional nor in violation of any Rules or

Guidelines.

4.2 He also submitted that the scope of interference in such

matter is very limited. The issue as raised in the present writ

petition was earlier came up for consideration before the Apex

Court as well as before this Court so also before various High

Courts. While referring to the observation made by the Apex Court

in the case of The Power Grid Corporation of India Limited

vs. Century Textiles & Industries Ltd. & Ors. (Civil Appeal

No.10951/2016), decided on 14.12.2016 so also the judgments

passed by various High Courts in the case of The Power Grid

Corporation of India Ltd. vs. Ajay Kumar Gupta & Ors.

(First Appeal No.3253/2011) - Allahabad High Court; Gram

Panchayat Kudi Bhagtasani, Jodhpur & Ors. vs. State of

Rajasthan & Ors. (DBCWP-PIL No.2704/2016) - Rajasthan

High Court; Madan Dan Arha Abd Anr. vs. Rajasthan Rajya

Vidyut Prasaran Nigam Ltd. & Ors. (DB Civil Appeal (Writ)

No.586/2014) - Rajasthan High Court; M/s Mahalaxmi

Industries & Ors. vs. Union of India & Ors. (DB Civil

Petition No.1258/2016) - Rajasthan High Court; Suresh

Kumar Saini vs. Powergrid Corporation of India & Ors.

(Uploaded on 04/02/2026 at 01:27:54 PM)

[2026:RJ-JD:5697] (6 of 8) [CW-1857/2026]

(Writ Petition No.2494/2014) - Uttarakhand High Court;

Powergrid Corporation of India Ltd. vs. The State of

Maharashtra & Ors. (Writ Petition No.9315/2015) -

Bombay High Court; Parth Krishnakant Patel vs. Managing

Director / General Manager (Legal Cell) & Ors. (Special

Civil Application No.14617/2022) - Gujarat High Court; Om

Prakash vs. Amit Kumar & Ors. (Civil Revision

No.1826/2014) - Punjab and Haryana High Court; Vijay

Ramchandra Agrawal vs. Power Grid Corporation of India

Ltd. - MP High Court, it was contended that the scope of

interference in such matter is very limited. The petitioner is not

able to show that the transmission line is installed in arbitrary

manner or in violation of any guidelines / norms.

4.3 It was further submitted that as a matter of fact, the

petitioner itself has moved an application for seeking

compensation as per law. The petitioner has also made prayer in

the writ petition for seeking compensation and the respondents

have no objection to consider the claim of the petitioner for

seeking compensation in time bound manner.

4.4 It is also submitted that process of installing Tower No.94/0

on the land belonging to the petitioner has already commenced as

the project is to be completed and the transmission line is to be

made operational on the priority basis.

4.5 Learned counsel for the respondents has further submitted

that while considering SBCWP No.20506/2025 (M/s Cse solar

Projects Pvt. Ltd. vs. Power Grid Corporation of India Ltd. & Ors.),

decided on 08.01.2026, this Court while taking into consideration

(Uploaded on 04/02/2026 at 01:27:54 PM)

[2026:RJ-JD:5697] (7 of 8) [CW-1857/2026]

the identical issue, has declined to grant any indulgence while

observing that petitioner's claim for compensation be decided in

time bound manner.

Based on the above submissions, it is submitted that no case

for interference is made out in the present writ petition.

5. Heard learned counsel for the parties and perused the

material available on record.

6. The admitted facts in the present writ petition are that 765

KV line is proposed between Beawar and Mandsaur. As many as

734 towers are to be installed for setting up of 765 KV line, which

would be in between Beawar to Mandsaur at the distance of about

260 Kms. The fact that out of 734 towers, 571 towers have

already been installed, has also not been disputed by the

petitioner.

7. Though the petitioner has questioned the decision of the

respondent - Corporation in deviating the transmission line,

however, the respondents have given a justifiable reason for doing

so. The respondents have adhered to the guidelines, which

mandate that transmission lines should be installed at 90 degree

angle when such lines are passing through National highway.

7.1 Learned counsel for the petitioner was not in a position to

refute the submission made by learned counsel for the

respondents with regard to such requirement and therefore, the

intentional deviation of transmission line is not established.

7.2 Though learned counsel for the petitioner has made

submission that there should be equidistant of 83 mtrs. on both

sides of highway but has not submitted any documents to show

(Uploaded on 04/02/2026 at 01:27:54 PM)

[2026:RJ-JD:5697] (8 of 8) [CW-1857/2026]

the norms / guidelines for mandatory distance between two

towers. In absence of such, this Court has no material to

adjudicate that while installing Towers No. 93/0 & 94/0, the

distance and norms have been followed or not. That being so, just

because the shifting of tower would minimize damage to the

petitioner, this Court cannot direct the respondents to shift the

tower.

8. It is to be noted that the total distance between Beawar and

Mandsaur is about 260 kms. and as many as 734 towers are to be

installed and taking note of such long distance, the towers cannot

be readjusted as desired by the petitioner or individual person.

The installation of tower would, of course cause damage to the

petitioner, but for that purpose there are provisions for claiming

compensation. The petitioner has failed to demonstrate that such

deviation or decision to install towers on the field of petitioner has

been taken for malafide or arbitrary reasons. Considering the

project, which is of National importance and more so, considering

the fact that the petitioner would be appropriately compensated in

accordance with law, this Court finds no reason to interfere in the

present writ petition.

9. As an upshot of the above discussion, the present writ

petition fails and is accordingly dismissed.

10. All pending application (s), if any, shall also stand disposed

of.

(SUNIL BENIWAL),J

-Rmathur/-

(Uploaded on 04/02/2026 at 01:27:54 PM)

Powered by TCPDF (www.tcpdf.org)

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter