Wednesday, 13, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

M/S Mewar Associates vs The State Of Rajasthan ...
2025 Latest Caselaw 4043 Raj

Citation : 2025 Latest Caselaw 4043 Raj
Judgement Date : 9 January, 2025

Rajasthan High Court - Jodhpur

M/S Mewar Associates vs The State Of Rajasthan ... on 9 January, 2025

Author: Madan Gopal Vyas
Bench: Madan Gopal Vyas
[2025:RJ-JD:1545-DB]

HIGH COURT OF JUDICATURE FOR RAJASTHAN AT JODHPUR
                 D.B. Civil Misc. Appeal No. 539/2020
M/s Mewar Associates, through its Proprietor Shri Rajeshwar
Singh son of Shri Ram Singh Chundawat, aged 47 years, resident
of Village and Post Thada Tehsil Salumbar, District Udaipur
(Rajasthan)
                                                                      ----Appellant
                                       Versus
1.       The State of Rajasthan, through the District Collector,
         Dungarpur, Rajasthan
2.       The Water Resources Department, Udaipur through its
         Additional Chief Engineer
3.       The Water Resources, Division Dungarpur, through its
         Executive Engineer.
                                                                   ----Respondents


For Appellant(s)             :    Mr. Manoj Bhandari, Sr. Advocate
                                  assisted by Mr. Aniket Tater
For Respondent(s)            :    Mr. S.S. Rathore, AAG


      HON'BLE MR. JUSTICE SHREE CHANDRASHEKHAR
           HON'BLE MR. JUSTICE MADAN GOPAL VYAS
                           Order

09/01/2025
Per, S.Chandrashekhar,J:

      The challenge laid by M/s. Mewar Associates through its

Proprietor is to the judgment dated 18th September 2019 passed in

Case No.144/2018 (Original Suit).

2.    On the basis of the pleadings of the parties, the following

issues were framed by the Commercial Court: (1) whether the

claimant is entitled for damages to the tune of Rs.16,02,249/- with

interest due to delay and failure on the part of the opposite party,

(2) whether the decision of the Empowered Standing Committee

dated 7th December 2012 is liable to be interfered with on the

ground that the claimant was not provided an opportunity of



                       (Downloaded on 15/01/2025 at 09:28:59 PM)
 [2025:RJ-JD:1545-DB]                  (2 of 15)                    [CMA-539/2020]



hearing, (3) whether the suit is barred by limitation, (4) whether

the Court has jurisdiction and power to entertain the suit and (5)

whether relief can be granted to the claimant. On the issue of loss

caused to the M/s. Mewar Associates (hereinafter referred to as

the appellant-firm) to the tune of Rs.16,02,249/-, the Commercial

Court held that no supporting evidence was produced by it except

some letters relating to acquisition of land. As regards the decision

of the Empowered Standing Committee dated 07 th December

2012, the Commercial Court came to a conclusion that the

appellant-firm was given an opportunity of hearing and that is the

reason it had the knowledge about the said decision. The issues of

limitation and jurisdiction were decided by the Commercial Court

in favor of the appellant-firm.

3.    Mr. Manoj Bhandari, the learned Senior Counsel appearing for

the appellant-firm has raised manifold contentions to criticize the

judgment dated 18th September 2019. One of the submissions

made on behalf of the appellant-firm is that the Administrative

Engineer (in short, "Employer") did not provide full stretch of the

land on which irrigation canal was to be constructed. Another

substantial ground urged on behalf of the appellant-firm is that

there is no discussion about the documentary evidence laid on

behalf of the appellant-firm as to acquisition of a part of the

subject land and that has, therefore, resulted in an erroneous

decision by the Commercial Court at Udaipur. Mr. Manoj Bhandari,

the learned Senior Counsel for the appellant-firm has also referred

to various documents concerning land acquisition, investigation

report dated 14th December 2007 and communication from the

Executive Engineer dated 19 th March 2007 to challenge the

                       (Downloaded on 15/01/2025 at 09:28:59 PM)
 [2025:RJ-JD:1545-DB]                  (3 of 15)                    [CMA-539/2020]



decision of the Commercial Court rendered in Case No.144/2018

(Original Suit).

4.    On the other hand, Mr. Sajjan Singh Rathore, the learned

Additional Advocate General submits that it is not a fact that the

possession of the land was not given to the appellant-firm rather

there was some dispute as to payment of compensation to the

land holders which had nothing to do with the execution of work

by the appellant-firm. The learned Additional Advocate General

would further submit that the appellant-firm had not carried any

construction over Chain 0 to Chain 40 which was unhindered and

the possession thereof was already handed over to the appellant-

firm. The learned Additional Advocate General has referred to

clauses 2 and 3 of the conditions of contract to support the

decision rendered by the Commercial Court.

5.    Briefly stated, the Canal work from 0.0 km to 1.9 km and CD

works at Amarpura projects were awarded to the appellant-firm

the total contract value of which was Rs. 98,67,614/-. Pursuant to

work order dated 16th December 2004 issued in favour of the

appellant-firm, an agreement was executed under which the

scheduled completion period for the work under contract was

24th December 2005. However, the subject Canal work was not

completed by 24th December 2005 and an order extending the

period for completion of the work till 30 th June 2006 was issued on

31st March 2006. A second extension order extending the time for

completing the work till 31st July was issued on 28th June 2006.

Notwithstanding the extensions of time granted by the Employer,

the appellant-firm could not complete the work and the appellant-

firm was saddled with penalty and an order to this effect was

                       (Downloaded on 15/01/2025 at 09:28:59 PM)
 [2025:RJ-JD:1545-DB]                  (4 of 15)                    [CMA-539/2020]



issued on 12th July 2006 directing it to deposit Rs.5,16,038.00/-

under Clause 2. The appellant-firm was further informed that the

remaining work shall be completed through another agency and

the difference of amount shall be recovered from it under Clause 3

(C). But before that, the Superintending Engineer issued an order

vide letter dated 5th July 2006 according approval for termination

of the contract and recovery of damages under Clauses 2 and 3

(C). Later on, the appellant-firm was informed that it was required

to deposit Rs.4,86,746.00/- under Clause 2 and that amount was

adjusted against the security deposit. Additionally, damages to the

tune of Rs.25,76,076.00/- under Clause 3 (C) was required to be

deposited by it and an order to this effect was issued on

21st October 2007.

6.    Before the Commercial Court, the case pleaded by the

appellant-firm was that there were serious defaults and non-

performance of its obligations by the Employer inasmuch as

possession of the bed level cross-section of the land was not given

to it and the Employer remained completely indifferent to the

problems faced by the appellant-firm at the work site. According to

the appellant-firm, possession of a part of the land was given on

20th January 2005 and it had mobilized essential items of the value

of Rs.7,00,000/- and Tractor, JCB machines, Mixture machines,

Vibrators, Tankers and other machinery were employed by it but

the work could not progress at the desired pace on account of

non-cooperation from the Employer and protest by the land

holders who were not paid the compensation for the acquired land.

The appellant-firm claimed loss of profit to it on account of

direction issued by the Assistant Engineer, Siwalwara for stopping

                       (Downloaded on 15/01/2025 at 09:28:59 PM)
 [2025:RJ-JD:1545-DB]                  (5 of 15)                      [CMA-539/2020]



the work through Letter No.419 and failure on the part of the

Employer not to identify the place for disposal of waste materials

during the digging of the canal and stone cutting between RD 29

to 40. For these reasons, the appellant-firm pleaded that it had to

bear additional charge for carriage and disposal of the waste

materials. The appellant-firm further pleaded that the enquiry

report dated 5th March 2008 made favourable recommendations in

its favour but the Employer unilaterally imposed penalty of

Rs.25,62,806/- under Clauses 2 and 3 (C) of the contract. The

appellant-firm also pleaded loss on account of idle man power and

machinery for more than three months. The claims raised by the

appellant-firm were to the following effect:(a) the order of the

Empowered Standing Committee dated 7 th December 2012 should

not be accepted and the appellant-firm be given compensation, (b)

the compensation to the tune of Rs.2,00,000/- on account of idle

men and machinery between the period 19th April 2005 and

26th July 2005 be given to it, and (c) loss of profit to the tune of

Rs.5,00,000/- on account of unfinished work to the tune of

Rs.49,00,000/- be given to it. The appellant-firm also made

further claims such as: (a) Refund of Rs.5,00,000/- with interest

@ 18%, (b) Refund of Rs.1,55,249/- paid as advance, (c) Return

of National Savings Documents worth Rs.4,00,000/-, (d) Payment

of Rs.5,000/- with interest, (e) Payment of Rs.7,000/- with

interest, (f) Return of demand draft of Rs.14,000/- with interest,

and (g) Payment of Rs.20,000/- on account of expenses and legal

fee.

7.     On   the    other       hand,       the      Employer       contested   the

afore-mentioned claims pleading that lay-out was given to the

                       (Downloaded on 15/01/2025 at 09:28:59 PM)
 [2025:RJ-JD:1545-DB]                  (6 of 15)                          [CMA-539/2020]



appellant-firm on 17th December 2004 and it had provided all

cooperation and support to the appellant-firm but the total extent

of work executed was only to the tune of Rs.50,00,154/-. The

appellant-firm was given several notices between 18th January

2005 to 20th May 2005 and the last notice was given to it on

08th May 2006 but it failed to complete the work. Therefore, the

Superintending Engineer vide letter dated 05 th July 2006 granted

permission to proceed against the appellant-firm under Clauses 2

and 3 (C) of the contract. The stand of the Employer is that it is

entitled    to   recover     the     penalty/damages               to   the   tune   of

Rs.36,62,822/-. The allegations of non-cooperation and loss

caused to the appellant-firm were denied and it was specifically

pleaded by the Employer that out of the total stretch of the canal

the land holders had lands stretching to chain 23+1C meter and

the rest of the land belonged to the Government. It was further

pleaded that the appellant-firm had in fact completed the work

between chain 40 to chain 60 which belonged to the land holders

and the appellant-firm had failed to complete the work between

chain 0 to chain 40 and that stretch consisted of the Government

land.

8.      During the trial, the proprietor of the appellant-firm tendered

evidence as PW-1 and several documents were produced which

were marked as Exhibit-1 to Exhibit 58. On behalf of the Employer,

Ashok Regal who was the Assistant Engineer tendered evidence as

DW-1 and proved the documents vide Exhibit-A-1 to Exhibit-A-11.

9.      After having gone through the materials on record, we

observe that the Commercial Court proceeded in the matter on

such assumptions         and presumptions               that       cannot have any

                       (Downloaded on 15/01/2025 at 09:28:59 PM)
 [2025:RJ-JD:1545-DB]                    (7 of 15)                        [CMA-539/2020]



foundation in law. The decision of the Commercial Court on issue

no.2 is clearly erroneous. Even if it is accepted that any

representative of the appellant-firm, which is referred to as

contractor in the decision dated 07 th December 2012, was present

during the hearing before the Committee, a glance at the said

decision would reveal that as regards the stand of the appellant-

firm not even a word has been recorded in the said order. Any

administrative order which ensures civil consequence to a party

must be taken after a proper consideration of stand taken by the

rival parties. The decision of the Empowered Standing Committee

dated 07th December 2012 is a unilateral order which only records

the stand of the Employer and a cryptic conclusion of the

Committee that the claims of the claimants are not tenable and,

therefore, rejected. In "Rajkishore Jha v. State of Bihar" (2003) 11

SCC 519 the Hon'ble Supreme Court held that reason is the

heartbeat of every conclusion and without the same it becomes

lifeless. For a better appreciation of the decision of the Commercial

Court on issue no.2, we would extract the said decision dated

07th December 2012 of the Committee which reads as under:-
             "The meeting of Empowered Standing Committee was held
       on 07.12.12 at 06.00 PM under the Chairmanship of Principal
       Secretary, Water Resources Department, Rajathan, Jaipur to
       decide the claims/ disputes of Shri Rajeshwar Singh Chudawat
       (CLAIMANT) and respondent Department for the construction of
       RMC 0 to 1.90 Km including CD works of Amarpura Irrigation
       Project.
       The following were present in the meeting:
       1.    Shri PL Solanki Chief Engineer cum Addl. Secretary, Water
       Resources, Rajasthan, Jaipur.
       2.    Shri Prakash Tekwani, Joint Secretary (Exp-III) Finance
       Department
       3.    Shri      Ashok    K.    Vyas,     Joint   L.R.,    Law   Department
       4.   Shri AK Bhardwaj as authorised by Addl. Chief Engineer, WR

                         (Downloaded on 15/01/2025 at 09:28:59 PM)
 [2025:RJ-JD:1545-DB]                  (8 of 15)                         [CMA-539/2020]


       Zone,Udaipur
             Executive Engineer, Water Resoruces Division, Dungarpur
       was present as respondent and Contractor was present as
       claimant.
             Committee heard the arguments of claimant in support of
       his claim and arguments of respondent in support of his reply.
       Executive   Engineer,     Water     Resources       Division,   Dungarpur
       informed the Committee that work of RMC from 0-1.9 Km
       awarded to contractor. In this portion partial excavation was
       done under NREGP/Famine Relief works. From chain 0-26 and
       29-38 (total 36 chain of 1080 m) canal alignment was in
       Government land and from chain 27-28 and 38-63 (total 27 chain
       or 810m) in private land. Timely layout was given to contractor
       and there was no hindrance due to land acquisition because most
       part of work site was Government land. Progress of contractor
       could not continue the work and in spite of notices he did not
       complete the work then action under Clause 2 and 3(C) was
       taken. The remaining work got completed from other contractor
       on risk and cost. As per request of the contractor Additional Chief
       Engineer, WR Zone, Udaipur also examined the case and
       submitted report to CE, Water Resources, Rajasthan, Jaipur
       according to which objections are not sustainable.
             Committee perused the facts and record produced before
       Commitee and observed that claims of claimant is not tenable.
       Therefore committee decided to reject the claim."


10.   Under Clause 2 which deals with compensation for delay, the

appellant-firm is bound in all cases to complete 1/8th of whole of

the work if the time allowed for any work was for one month

except special jobs. There are further stipulations for completing

the extension of time and if the appellant-firm fails to complete

the work and the delay in execution of work is attributed to the

appellant-firm it is provided that he shall be liable to pay

compensation to the Government as prescribed thereunder. The

stipulation under Clause 2 proceeds on a premise that the delay in

execution of work is attributable to the appellant-firm. It is also



                       (Downloaded on 15/01/2025 at 09:28:59 PM)
 [2025:RJ-JD:1545-DB]                  (9 of 15)                        [CMA-539/2020]


provided under Clause 2 that the entire amount of compensation

to be levied shall not exceed 10 percent of the value of the

contract. It is further provided thereunder that while granting

extension of time on account of the delay attributable to the

Government the reasons shall be recorded for each delay. It is

therefore necessary that while granting extension of time the

Employer should record reasons but that is completely absent in

the letters dated 31st March 2006 and 26th June 2006. For easy

reference, we would extract the letters dated 31 st March 2006 and

28th June 2006:-

                            Government of Rajasthan
                              Irrigation Department
Serial No. Accts.-3/10826                                 Date:- 31.03.06
       M/s Mewar Associates
       Proprietor Shri Rajeshwar Singh Chundawat
       Village and Post -Thada, Tehsil
       Salumbar District Udaipur (Raj.)


       Subject - Construction of R.M.C. 0 to 1.90 K.M. Including C.D.
                Works of Amarpura Minor Irrigation Project (Contract
                 No. 24 Year 2004-05)
                 District Dungarpur (Contract No. 8 Year 2005-06)

       Context - Your letter no. 106 dated 15.11.2005 and letter no.
                  7527 dated 24.12.2005 of this office.

       Sir,
              In the above context, it is submitted that while
       reserving the right to impose the interest and compensation of
       the State Government contained in clauses 2 and 3 of the
       contract of the said work and to get the work completed at
       your own expense, the time period of the said work is
       temporarily extended till 30.06.2006.
                                                          yours sincerely,

                                                    Executive Engineer.
                                      Water Resources Divison, Dungarpur
       ..........................................................................................................

[2025:RJ-JD:1545-DB] (10 of 15) [CMA-539/2020]

Government of Rajasthan Irrigation Department

No.:- Account - 3 / Date:- 28.06.2006

M/s Mewar Associates, Proprietor Shri Rajeshwar Singh Chundawat, Village and Post-Thada, Tehsil- Salumbar, District- Udaipur (Rajasthan)

Subject- Construction of RMC 0 to 1.90 km. including C.D. Works of Amarpura Minor Irrigation Project (Contract No. - 24, Year 2004-05) District- Dungarpur (Contract No. 8, Year 2005-06)

Reference:- This office's letter no. 10826, Dated 31.03.2006

Sir,

Under the above subject it is submitted that keeping the interest of the State Government contained in clauses 2 and 3 of the contract and the right to impose compensation and get the work completed at your cost, the time period of the said work is temporarily extended till 31.07.2006.

Sd.

Yours sincerely, Executive Engineer, Water Resources Division, Dungarpur"

11. Clause 3 of the contract refers to "risk and cost clause"

which provides under Sub-clause (C) that after giving notice to the

appellant-firm the unexecuted work may be given to another

contractor and in that case any expenses which may be incurred in

excess of the sum which would have been paid to the original

contractor, the said amount shall be recovered from the original

contractor. The employer has undoubted power under Clauses 2

and 3(C) to resort to any punitive measure but existence of such

power would not justify the unilateral action of the Employer.

There should have been some meaningful consideration of the

defence raised rather than to ritually reject them and proceed to

take drastic measures against the appellant-firm. There cannot be

[2025:RJ-JD:1545-DB] (11 of 15) [CMA-539/2020]

a golden scale but the administrative authority is obliged in law to

weigh whether the defence version is a probable one, keeping in

mind the rule of preponderance of probablity. The action taken by

the Employer vide letters dated 5th July 2006, 12th July 2006 and

21st October 2007 are punitive actions which could not have been

resorted to on mere assumption of a hypothetical situation without

any supportive evidence. Even the principles of preponderance of

probability does not give leverage to an authority to create a

hypothesis by its own imagination without any evidence. In "Miller

v. Minister of Pensions" (1947) 2 All ER 372, Lord Denning, J.

defined the preponderance of probability in the following terms :

(All ER p. 373 H)

"(1).... It need not reach certainty, but it must carry a high degree of probability. Proof beyond reasonable doubt does not mean proof beyond the shadow of doubt. The law would fail to protect the community if it admitted fanciful possibilities to deflect the course of justice. If the evidence is so strong against a man as to leave only a remote possibility in his favour which can be dismissed with the sentence, "of course it is possible, but not in the least probable" the case is proved beyond reasonable doubt, but nothing short of that will suffice."

12. On the claim made by the appellant-firm on account of loss

of profit, the Commercial Court completely shut its eyes to the

documents laid in evidence by the appellant-firm. Vide Exhibit-45,

the notification under Section 4 of the Land Acquisition Act, 1894

dated 15th September 2006, notification under Section 6 vide

Exhibit-47 dated 09th March 2007, gazetted publication dated

17th March 2007 vide Exhibit-46 and objections of the agriculturist

[2025:RJ-JD:1545-DB] (12 of 15) [CMA-539/2020]

vide Exhibits-4,5,6 and 7 were produced. The appellant-firm also

brought on the record its objections given to the Employer from

time to time and were marked as Exhibits-8, 10, 11, 36, 39, 40,

55 and 56 but all these documents were overlooked by the

Commercial Court only for the reason that there appears signature

of the appellant-firm on the measurement book. Whereas, the

witness DW-1 examined by the Employer admitted in his cross-

examination that the signature of the appellant-firm was not

matching with his admitted signature. DW-1 was given

suggestions with the reference to the documents laid in evidence

by the appellant-firm to the effect that compensation was not paid

to the land holders, the villagers had taken away machinery

mobilized at the site and that the delay in execution of the work

was caused due to non payment of compensation and disturbances

created by the villagers. However, this witness denied such

suggestions and he went to the extent of denying even the official

documents pertaining to land acquisition.

13. The Employer took unilateral decisions and that can be easily

ascertained on a glance at the contents of the letter dated

5th July 2006, 12th July 2006 and 21st October 2007. The orders

granting extensions of time vide letters dated 31 st March and

28th June 2006 do not indicate any reason for granting such

extensions of time and simply record that the Employer has

reserved its right to recover damages under Clauses 2 and 3 (C) of

the contract. The letter dated 5th July 2006 by which the

Superintending Engineer granted approval for termination of

contract was issued with reference to the letter dated 1 st July 2006

[2025:RJ-JD:1545-DB] (13 of 15) [CMA-539/2020]

of the Administrative Engineer and the said letter was issued

ignoring the fact that extension of time for completing the work

31st July 2006 was already granted to the appellant-firm. Mr.

Sajjan Singh Rathore, the learned Additional Advocate General

submits that noticing the failure of the appellant-firm to complete

the work the contract was terminated as waiting for expiry of the

extended period of time would have been a mere formality. In our

opinion, the termination of contract during subsistence of the

period for completion of the work was illegal. The letter dated

5th July 2006 records that the appellant-firm was able to complete

the work to the tune of Rs.47,07,236.00/- but without referring to

the reasons put forth by the appellant-firm simply records the

appellant-firm did not take any effort to complete the work. The

letter dated 12th July 2006 is also a unilateral decision of the

Employer and it simply refers to the provisions under Clauses 2

and 3 (C) of the contract and determines the quantum of damages

to be recovered from the appellant-firm.

14. The Commercial Court was required to bestow its

consideration to non-performance of its obligation by the Employer

which goes to the root of the matter. Even if it is held that the

appellant-firm was given possession over the stretch of land

belonging to the agriculturist, the Employer had no right

whatsoever as on 20th January 2005 to give possession of such

land because as on that day even the Notification under section 4

of the Land Acquisition Act, 1894 was not published. The normal

rule which governs the civil proceedings is that a fact is said to be

shown if it is proved by preponderance of probability. Under

[2025:RJ-JD:1545-DB] (14 of 15) [CMA-539/2020]

section 3 of the Indian Evidence Act, a fact is said to be proved

when the Court either believes it to exist or considers its existence

show probable that a prudent man under the circumstances would

proceed on the supposition that such fact really exists. The Court

should therefore try to find out whether a prudent man on

weighing the valid probabilities would have found that the

preponderance is in favour of existence of the fact in question.

There may be varied types of probabilities but the Court is

required to ultimately figure out where the preponderance of

probability lies. Furthermore, the preponderance of probability

regarding existence of a fact is examined with reference to the

stand of the parties and the supporting materials thereof, and not

by merely recording stand of the Employer which itself was the

adjudicator. The various documents laid in evidence by the

appellant-firm demonstrating protest by the agriculturist and

difficulties faced by it in execution of subject works could not have

been ignored on a specious plea that the possession of land was

given to the appellant-firm.

15. In an administrative proceeding while strict rules of evidence

are not applicable the general rules of fairness, justice and good

conscience must be followed and a commonsensical approach

should be adopted. This is also well settled that even in the

contractual matters the Employer shall be under an obligation to

act fairly and comply with the basic requirements of Article 14 of

Constitution of India. In a commercial world, it does not satisfy the

[2025:RJ-JD:1545-DB] (15 of 15) [CMA-539/2020]

reason that a contractor would submit bid and take a contract only

to incur penalty and pay compensation to the Employer for so-

called delay on its part to complete the work under contract. This

is really beyond any comprehension that a contractor who was

able to complete more than 50 percent of the work would leave

the work midway and invite imposition of penalty and

compensation etc. to the Employer. In our opinion, there was

fundamental breach of the contract inasmuch as the Employer

could not perform its essential obligations under the contract. In a

situation like the present one, the written terms of contract for

recovery of penalty, damages etc. cannot be enforced against the

appellant-firm.

16. For the aforesaid reasons, the decision of the Commercial

Court in Case No.144/2018 is set aside and the said suit is

decreed. Consequently, the appellant-firm is held entitled for its

claims recorded in paragraph nos.4 and 5 of the judgment dated

18th September 2009.

(MADAN GOPAL VYAS),J (SHREE CHANDRASHEKHAR),J

165-Ravi Khandelwal

Powered by TCPDF (www.tcpdf.org)

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter