Wednesday, 13, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Rajasthan State Road Development And ... vs M/S Praman Construction Pvt. Ltd
2025 Latest Caselaw 17320 Raj

Citation : 2025 Latest Caselaw 17320 Raj
Judgement Date : 19 December, 2025

[Cites 7, Cited by 0]

Rajasthan High Court - Jodhpur

Rajasthan State Road Development And ... vs M/S Praman Construction Pvt. Ltd on 19 December, 2025

Author: Pushpendra Singh Bhati
Bench: Pushpendra Singh Bhati
[2025:RJ-JD:54387-DB]

      HIGH COURT OF JUDICATURE FOR RAJASTHAN AT
                       JODHPUR
                D.B. Civil Misc. Appeal No. 2338/2024

1.       Rajasthan State Road Development And Construction,
         Corportation Ltd. Through Its Managing Director, Setu
         Bhawan, Opp. Jhalana Doongri, Agra Bypass, Jaipur
2.       Rajasthan State Road Development And Construction
         Corporation Ltd., Unit Udaipur, 80 Ashok Nagar, Road No.
         3, Udaipur
                                                                     ----Appellants
                                       Versus
M/s Praman Construction Pvt. Ltd., (A Company Registered
Under The Companies Act, 1956) Regd. Office - 9 Five Star
Compex, Near Kumbhanagar, Hiranmagri Sector 04, Udaipur
                                                                    ----Respondent


For Appellant(s)             :     Mr. Sunil Bhandari
For Respondent(s)            :     Mr. Harshit Bhurani


     HON'BLE DR. JUSTICE PUSHPENDRA SINGH BHATI

HON'BLE MR. JUSTICE ANUROOP SINGHI

Judgment

1. Date of conclusion of arguments 20.11.2025

2. Date on which judgment was reserved 20.11.2025

3. Whether the full judgment or only the operative part is pronounced: Full judgment

4. Date of pronouncement 19.12.2025

Per Dr. Pushpendra Singh Bhati, J:

1. The present D.B. Civil Misc. Appeal has been preferred under

Section 13 of the Commercial Courts Act, 2015 claiming the

following relief:

"It is, therefore, most humbly and respectfully prayed that the record of the case may kindly be called for and by an appropriate writ, order or direction:-

1. The present appeal may kindly be allowed and the judgment / decree dated 05.06.2024 passed by the Commercial Court, Udaipur in Case No. 167/2018 (E.D.) (C.I.S. No. 169/2018), holding the appellant jointly and severally liable for payment of

(Uploaded on 19/12/2025 at 02:24:17 PM)

[2025:RJ-JD:54387-DB] (2 of 11) [CMA-2338/2024]

Rs.27,66,879/- towards the final bill and Rs.13,56,864/- towards the refund of security deposit along with interest @ 9% p.a. and further quashing the order dated 23.09.2010 imposing penalty of Rs.13,00,000/- on the respondent plaintiff and further restraining the appellant from taking any action against the respondent plaintiff pursuant to order dated 23.09.2010, may kindly be quashed and set aside with costs.

2. Any other appropriate order or direction as may be deemed just and proper in the facts and circumstances of the case may kindly be passed in favour of the appellant."

2. Brief facts out of which the instant controversy has

emanated are that the respondent-company was awarded a

contract by the appellant-Corporation for construction of

Sajjangarh Biological Park, Udaipur, and a work order dated

01.09.2009 was issued for a contract value of Rs.

2,74,44,746.85/-.

2.1. As per the work order, the work was to commence on

16.09.2009 and was required to be completed within a stipulated

period of 11 months, i.e., on or before 15.08.2010. A formal

contract governing the execution of the work was entered into

between the parties.

2.2. During execution of the contract, disputes arose between the

parties with regard to execution of work, availability of drawings,

progress of work, and compliance with contractual terms.

2.3. On 23.09.2010, the appellant-Corporation rescinded the

contract and imposed a penalty upon the respondent in terms of

the contract. The respondent was thereafter called upon to remain

present for final measurement of the work done.

(Uploaded on 19/12/2025 at 02:24:17 PM)

[2025:RJ-JD:54387-DB] (3 of 11) [CMA-2338/2024]

2.4. A committee was constituted for taking final measurement of

the work, and final measurement was carried out on 06.10.2010,

in which the respondent participated.

2.5. Thereafter, the respondent submitted claims in respect of the

work executed and raised disputes regarding payment of alleged

outstanding dues.

2.6. On 10.12.2015, the respondent instituted a civil suit before

the competent court seeking recovery of an amount of Rs.

57,19,993/-, along with declaration and permanent injunction,

which came to be transferred to the Commercial Court, Udaipur.

2.7. Upon consideration of the pleadings, evidence and

submissions of the parties, the learned Commercial Court,

Udaipur, vide judgment and decree dated 05.06.2024, partly

decreed the suit, which has given rise to the present appeal.

3. Learned counsel for the appellants, at the outset, submitted

that the impugned judgment and decree dated 05.06.2024 passed

by the learned Commercial Court, Udaipur suffer from serious

errors of law and jurisdiction and are liable to be set aside.

3.1. Learned counsel submitted that the suit instituted by the

respondent on 10.12.2015 was ex facie barred by limitation. It

was contended that the contract was rescinded on 23.09.2010 and

final measurement of the work was carried out on 06.10.2010, in

which the respondent admittedly participated, and therefore, the

cause of action, if any, stood crystallized in the year 2010 itself.

3.2. Learned counsel further submitted that under Articles 18 and

113 of the Limitation Act, 1963, the limitation period of three

years expired, at the latest, in October, 2013, whereas the suit

(Uploaded on 19/12/2025 at 02:24:17 PM)

[2025:RJ-JD:54387-DB] (4 of 11) [CMA-2338/2024]

was filed much thereafter, and the learned Commercial Court

committed a jurisdictional error in entertaining and decreeing a

time-barred suit.

3.3. It was further contended that invocation of Clause 23 of the

contract by the respondent after expiry of limitation could not

revive a stale or time-barred claim, and the learned Commercial

Court erred in treating the same as a fresh cause of action.

3.4. Learned counsel for the appellants submitted that the learned

Commercial Court failed to appreciate that a duly constituted

expert committee conducted final measurement of the work on

06.10.2010 and, based on such measurement, only an amount of

Rs.61,363/- was found payable to the respondent, as reflected in

the Measurement Book and Final Bill.

3.5. It was submitted that despite participating in the final

measurement, the respondent neither signed the measurement

nor challenged the same in any forum, and therefore, the learned

Commercial Court erred in discarding the final measurement and

substituting its own assessment.

3.6. Learned counsel further submitted that the respondent had

abandoned the work on 29.06.2010 and failed to resume the

same even after extension of time was granted up to 15.11.2010,

and therefore, rescission of contract vide order dated 23.09.2010

was strictly in accordance with the contractual terms.

3.7. It was contended that as per Clauses 2 and 3 of the contract,

the appellant-Corporation was fully empowered to levy

compensation for unexecuted work and to forfeit the security

(Uploaded on 19/12/2025 at 02:24:17 PM)

[2025:RJ-JD:54387-DB] (5 of 11) [CMA-2338/2024]

deposit, and the learned Commercial Court exceeded its

jurisdiction in quashing the penalty order and directing refund of

the security deposit.

3.8. Learned counsel submitted that the learned Commercial Court

misread the oral and documentary evidence on record, ignored the

contractual stipulations, and granted a decree which is internally

inconsistent, particularly after rejecting the claims relating to

idling charges and extra work.

3.9. It was lastly submitted that the award of interest at the rate

of 9% per annum is excessive and unsupported either by the

contract or by any statutory provision.

4. Per contra, learned counsel appearing on behalf of the

respondent submitted that the impugned judgment and decree

dated 05.06.2024 passed by the learned Commercial Court,

Udaipur are just, legal and proper, and do not warrant any

interference by this Court in appellate jurisdiction.

4.1. Learned counsel for the respondent submitted that the

objection raised by the appellants regarding limitation is wholly

misconceived. It was contended that the respondent had

submitted its final bill on 01.10.2010, and upon non-release of

payment, made repeated representations, including a written

request dated 14.01.2011.

4.2. It was further submitted that on 21.03.2011, higher officials

of the appellant-Corporation directed the concerned officers to

process the payment of the respondent's bill; however, despite

(Uploaded on 19/12/2025 at 02:24:17 PM)

[2025:RJ-JD:54387-DB] (6 of 11) [CMA-2338/2024]

such directions, the payment was not released, thereby giving rise

to a continuing grievance.

4.3. Learned counsel submitted that the respondent thereafter

invoked Clause 23 of the contract on 07.10.2013 by depositing the

prescribed fee and requested the appellants to refer the dispute to

the Empowered Standing Committee. It was contended that a

detailed claim was also submitted on 25.11.2013 in terms of the

directions issued by the appellants.

4.4. It was contended that despite invocation of the contractual

dispute resolution mechanism, the appellants failed to refer the

dispute to the Empowered Standing Committee within the

stipulated period, and therefore, the cause of action to institute

the suit arose on account of such non-referral.

4.5. Learned counsel for the respondent further submitted that the

suit is also within limitation in view of Article 55 of the Limitation

Act, 1963, which provides a limitation period of three years for a

suit for compensation for breach of contract, to be computed from

the date when the contract is broken, or, in cases of successive or

continuing breaches, when the breach ceases.

4.6. It was contended that in the present case, the breach on the

part of the appellants was a continuing breach, inasmuch as the

respondent's legitimate dues were continuously withheld despite

submission of the final bill, repeated representations, and

invocation of the contractual mechanism, and therefore, limitation

did not commence or conclude in the year 2010, as alleged by the

appellants.

(Uploaded on 19/12/2025 at 02:24:17 PM)

[2025:RJ-JD:54387-DB] (7 of 11) [CMA-2338/2024]

4.7. Learned counsel submitted that the evidence on record

clearly establishes that complete and approved drawings were not

provided to the respondent at the inception of the work, and that

the work was stopped on several occasions due to objections

raised by the Forest Department, which fact stood admitted during

the cross-examination of the appellants' witnesses.

4.8. It was further submitted that the respondent was at all times

ready and willing to perform its contractual obligations, and that

the delay in execution of work was attributable to non-availability

of approved designs and lack of coordination between the

departments of the appellants.

4.9. Learned counsel for the respondent submitted that the

learned Commercial Court, after detailed appreciation of oral and

documentary evidence, recorded a categorical finding that the

appellants had taken contradictory stands with regard to supply of

drawings and stoppage of work, and such findings are findings of

fact which do not call for interference in appeal.

4.10. It was contended that the learned Commercial Court rightly

held that the respondent had executed work beyond the original

scope of the contract, and that the appellants could not unjustly

enrich themselves by withholding payment for the work executed

by the respondent.

4.11. Learned counsel submitted that the rescission of the

contract and imposition of penalty vide order dated 23.09.2010

were arbitrary and unjustified, and the learned Commercial Court

was correct in quashing the said order.

(Uploaded on 19/12/2025 at 02:24:17 PM)

[2025:RJ-JD:54387-DB] (8 of 11) [CMA-2338/2024]

4.12. Learned counsel for the respondent placed reliance on the

following judgments in support of the submissions advanced on

behalf of the respondent:

1. J.C. Budhraja vs. Chairman, Orissa Mining Corporation Ltd. And Another (Civil Appeal No's. 1971-1973 of 2000 decided on 18.01.2008)

2. Khan Bahadur Shapoor Freedom Mazda vs. Durga Prasad Chamaria and ors. (Civil Appeal No. 77 of 1957 decided on 01.03.1961)

5. Heard learned counsel for the parties and perused the

material available on record as well as the judgments cited at the

Bar.

6. This Court observes that since the present appeal is being

pressed and argued primarily on the issue of limitation, it is

appropriate to first examine whether the suit instituted by the

respondent on 10.12.2015 was within the prescribed period of

limitation.

6.1. This Court notes that it is an admitted position on record that

the contract between the parties was rescinded by the appellant-

Corporation vide order dated 23.09.2010, and the respondent was

called upon to participate in the final measurement of the work.

6.2. This Court further notes that the final measurement was

carried out on 06.10.2010 by a duly constituted committee. Thus,

by the said date, the contractual relationship between the parties

stood conclusively terminated and the final quantification of work

executed had taken place.

(Uploaded on 19/12/2025 at 02:24:17 PM)

[2025:RJ-JD:54387-DB] (9 of 11) [CMA-2338/2024]

6.3. This Court finds that once the contract was rescinded and

final measurement was conducted, the cause of action, if any, in

favour of the respondent stood crystallized, at the latest, on

06.10.2010.

6.4. This Court observes that the respondent's reliance on

invocation of Clause 23 of the contract on 07.10.2013 for

reference of the dispute to the Empowered Standing Committee

cannot extend or revive the period of limitation, as a contractual

dispute resolution mechanism cannot override the statutory

mandate of the Limitation Act, 1963.

6.5. This Court further observes that even the invocation of Clause

23 by the respondent was itself beyond the period of limitation.

The cause of action having accrued on 06.10.2010, the statutory

period of limitation expired in 05.10.2013 , and the request for

reference to the Standing Committee was made after expiry of the

prescribed limitation period.

6.6. This Court finds that a reference sought to the Standing

Committee beyond the period of limitation cannot create a fresh

or independent cause of action, nor can it revive or validate a

claim which had already become time-barred under the Limitation

Act, 1963.

6.7. This Court further finds that mere representations,

correspondence, or internal departmental directions for processing

of payment do not give rise to a fresh cause of action, nor do they

arrest the running of limitation once the right to sue has accrued.

(Uploaded on 19/12/2025 at 02:24:17 PM)

[2025:RJ-JD:54387-DB] (10 of 11) [CMA-2338/2024]

6.8. This Court observes that the plea of the respondent based on

Article 55 of the Limitation Act, 1963 on the ground of an alleged

"continuing breach" is misconceived in the facts of the present

case. Once the contract was rescinded and final measurement

undertaken, no continuing contractual obligation subsisted

between the parties.

6.9. This Court further observes that withholding of payment after

termination of the contract and final determination of dues does

not constitute a continuing breach within the meaning of Article

55, but at best gives rise to a single and complete cause of action,

which accrued in the year 2010.

6.10. This Court finds that under Articles 18 and 113 of the

Limitation Act, 1963, the limitation period for instituting a suit for

recovery of money is three years from the date when the right to

sue accrues, which, in the present case, expired in October, 2013.

6.11. This Court holds that the suit having been instituted only on

10.12.2015, was clearly barred by limitation, and the learned

Commercial Court committed a jurisdictional error in entertaining

and decreeing a time-barred suit.

6.12. This Court further observes that since limitation goes to the

very root of the matter, once the suit is held to be barred by

limitation, no adjudication on the merits of the rival claims is

warranted.

7. In view of the aforesaid discussion, this Court holds that the

suit instituted by the respondent was barred by limitation, and

(Uploaded on 19/12/2025 at 02:24:17 PM)

[2025:RJ-JD:54387-DB] (11 of 11) [CMA-2338/2024]

consequently, the impugned judgment and decree dated

05.06.2024 cannot be sustained in law.

8. Accordingly, the present D.B. Civil Misc. Appeal No.

2338/2024 is allowed. The judgment and decree dated

05.06.2024 passed by the learned Commercial Court, Udaipur in

Commercial Case No. 167/2018 (E.D.) is hereby quashed and set

aside.

9. All pending applications, if any, stand disposed of.

(ANUROOP SINGHI),J (DR. PUSHPENDRA SINGH BHATI),J

SKant/-

(Uploaded on 19/12/2025 at 02:24:17 PM)

Powered by TCPDF (www.tcpdf.org)

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter