Citation : 2025 Latest Caselaw 12576 Raj
Judgement Date : 29 August, 2025
[2025:RJ-JD:38393] (1 of 13) [CW-12222/2025]
HIGH COURT OF JUDICATURE FOR RAJASTHAN AT
JODHPUR
S.B. Civil Writ Petition No. 12222/2025
M/s Dara Engineering And Infrastructure Pvt. Ltd., Having Its
Registered Office Situated At 42-A, Ajeet Colony, Opp. Balniketan
School, Ratanada, Jodhpur - 342001, Represented Through Its
Authorised Signatory Shri Daulat Singh S/o Shri Jagdish Singh,
Aged 37, Resident Of 29, Shekhawat House, Sangariya, Jodhpur
- 342013.
----Petitioner
Versus
1. State Of Rajasthan, Through Its Principal Secretary, Indra
Gandhi Nahar Department, Jaipur.
2. State Of Rajasthan, Through Its Chief Secretary (Budget),
Department Of Finance.
3. State Of Rajasthan, Through Its Secretary, Water
Resources Department, Jaipur.
4. Chief Engineer, Indra Gandhi Nahar Project, Bikaner, Sri
Ganganagar Road, Ignp Colony, Bikaner - 334001.
5. Additional Chief Secretary, Indra Gandhi Nahar
Department, Jaipur.
6. M/s Babu Lal And Company, Situated At C-202, M D Vyas
Nagar, Bikaner, Rajasthan.
----Respondents
For Petitioner(s) : Mr. Sharad Kothari.
Mr. Pranjul Mehta.
For Respondent(s) : Mr. N.S. Rathore, AAG with
Mr. Ram Avtar Sikhwal, AGC and
Mr. Arpit Samariya, AAAG
Mr. Anand Purohit, Sr. Advocate
assisted by Mr. Mayank Roy.
HON'BLE MR. JUSTICE SUNIL BENIWAL
Order
Reserved on : 26/08/2025 Pronounced on : 29/08/2025
1. The petitioner has preferred the present writ petition with
the following prayers :-
"i- By an appropriate writ, order or direction the impugned order dated 18.06.2025 (Annex.14) passed by the Respondent No.2 be quashed and set-aside.
[2025:RJ-JD:38393] (2 of 13) [CW-12222/2025]
ii- By an appropriate writ, order or direction the Petitioner's technical bid may be approved in light of the conditions enshrined in the NIT No.01/2024-25 (Bid No.5) and the Petitioner company may be declared as a responsive bidder.
iii- By an appropriate writ, order or direction it may also be declared that according to the conditions of bidding documents, pressurized water pumping for house hold is similar in nature work experience to the pressure irrigation system.
iv- By an appropriate writ, order or direction, during the pendency of this Writ Petition, if any work order is issued in favour of any participant bidder, the same may kindly be stayed.
v- Any other appropriate writ, order or direction which this Hon'ble Court may deem just and proper in the facts and circumstance of the case may kindly be passed in favour of the petitioner.
vi- Costs of the writ petition may kindly be awarded to the petitioner."
2. The facts as stated in the writ petition in nut-shell are that
the respondent No.4 floated a notice inviting bid dated 29.11.2024
(Annexure-2). The bid was invited for development of pressure
irrigation system in the remaining area of 18250 Htr. of Guru
Jambheshwar Lift Canal System of Indira Gandhi Nahar Project
Stage-II ('instant tender').
2.1 The petitioner along with two other persons being qualified
and interested in the instant tender participated in pre-bidding
meeting dated 06.12.2024, whereby clarification was sought with
regard to certain tender conditions. The clarification was issued on
06.12.2024 (Annexure-3). Later, vide communication dated
15.01.2025 (Annexure-4), the petitioner's bid was declared to be
non-responsive.
2.2 The petitioner being aggrieved by rejection of his technical
bid, preferred first appeal under the Rajasthan Transparency in
Public Procurement Act, 2012 on 16.01.2025 (Annexure-6) before
[2025:RJ-JD:38393] (3 of 13) [CW-12222/2025]
the Principal Secretary, IGNP Department, Jaipur, which was
rejected vide order dated 16.04.2025 (Annexure-9).
2.3 The petitioner thereafter preferred second appeal on
28.04.2025 (Annexure-10) while challenging the order dated
16.04.2025, however, the second appeal too came to be rejected
by the Second Appellate Authority vide order dated 18.06.2025
(Annexure-14).
2.4 Being aggrieved by the rejection of the second appeal vide
order dated 18.06.2025, the petitioner preferred the present writ
petition.
3. Learned counsel appearing on behalf of the petitioner has
made the following submissions:-
(i)- The technical bid of the petitioner has been declared as non-
responsive on 15.01.2025 due to lack of experience for operation
& maintenance of pressure irrigation system despite the petitioner
having provided relevant experience certificate of operation &
maintenance of water supply system.
(ii)- The first appellate authority has dismissed the appeal vide
order dated 16.04.2025 while giving incorrect interpretation to
tender conditions and has relied on the clarification given pursuant
to the pre-bid meeting dated 06.12.2024.
(iii)- While pointing out Sr. No.2 & 5 of the clarification given on
06.12.2024 (Annexure-3), it is submitted that the query was
sought on some other aspect, whereas a clarification stating that
"operation & maintenance of pressure irrigation system is must
and operation & maintenance of water supply system will not be
considered, change in criteria is not admitted." has been added as
[2025:RJ-JD:38393] (4 of 13) [CW-12222/2025]
an afterthought to accommodate private respondent, who has
apparently bid much higher than the petitioner.
(iv)- The requirement of operation & maintenance of pressure
irrigation system cannot be considered as key component as any
specified item will be considered as key component only if its cost
is at least 10% value of the whole work and as per the BOQ (Bills
of Quantity), the operation & maintenance of pressure irrigation
system is less than 10%.
In view of the above fact situation, the operation &
maintenance of pressure irrigation system cannot come in way of
the petitioner and the respondents have wrongly declared the
petitioner as non-responsive.
(v)- Note No.7 appended to Condition no.3 of Section 3 of the
NIB document, which clarifies as to what is work of similar nature
states that for pressure distribution pipe network, experience of
pressure distribution network in both irrigation and water supply
work shall be considered. In view of such explanation, it is stated
that the petitioner's bid was required to be considered as he is
having requisite experience in pressure water supply system.
(vi)- The clarification dated 06.12.2024 does not opine operation
& maintenance of pressurized house water supply system as being
not similar to operation & maintenance of pressure irrigation
system.
(vii)- The Second Appellate Authority has passed the impugned
order without application of mind and without considering the
submissions made by the petitioner in his memo of appeal so also
in his written submissions. The said Authority has assigned two
reasons and out of these two reasons, the reason No.1 is rather
[2025:RJ-JD:38393] (5 of 13) [CW-12222/2025]
supporting the submission made by the petitioner and the reason
No.2 has no relevance with the present controversy. While
elaborating the submission, it is stated that the first reason is
simply referring to the NIT conditions and the foot-note, which
even petitioner is not disputing and the second reason, which
relates to BOQ is having no relevance to the present controversy
as BOQ simply provides detail about the costing of different
segments of work. It is stated that as a matter of fact, the order
passed by the Second Appellate Authority is totally non-speaking
and unreasoned order.
(viii)- The Second Appellate Authority has neither considered the
submissions made by the petitioner nor has assigned any reason
as to on what basis the decision of the appellate authority is
justified.
3.1. In support of the submissions, the learned counsel for the
petitioner relied on the judgment passed by the Division Bench of
this Court in D.B. Spl. Appl. Writ No. 127/2022; LRs of Manphool
Ram Vs. The State of Rajasthan & Ors. (decided on 24.04.2024)
and submits that the Division Bench of this Court has disposed of
the appeal while observing that if the order of the appellate
authority is passed without considering the grounds and without
examining the memo of appeal, the order is nothing but only
amounts to performing of rituals. The Second Appellate Authority
has given no reason as to why Note No.7 appended to Condition
no.3 of Section 3 of the NIB document was not applicable in the
present case. As a matter of fact, Note No.7 clarifies the fact that
the operation & maintenance experience in pressure water supply
system would also be considered as a requisite experience for the
[2025:RJ-JD:38393] (6 of 13) [CW-12222/2025]
purpose of the present tender. That being so, the order passed by
the Second Appellate authority is non-speaking and deserves to be
quashed and set-aside.
3.2. In view of the submissions made above, learned counsel for
the petitioner submits that the experience as possessed by the
petitioner in operation & maintenance of the pressure water
supply system, as per the NIT conditions was required to be
considered in assessing the eligibility of the petitioner.
4. Per contra, learned counsel appearing for the respondent-
State makes the following submissions:-
(i)- Learned counsel submits that there are concurrent findings
of the First Appellate Authority so also the Second Appellate
Authority and therefore, no indulgence is required to be granted in
the present writ petition.
(ii)- The contract is, in fact, in two parts i.e. first with regard to
development pressure irrigation system and second with regard to
operation & maintenance. Learned counsel refers to point
No.6.1.1, which provides that if the tender conditions are not
fulfilled, the same is required to be rejected.
(iii)- It is the wisdom of the authority who has to decide the terms
and conditions of the contract. Therefore, petitioner cannot
question terms and conditions of the tender.
(iv)- The First Appellate Authority as well as Second Appellate
Authority has considered all the submissions made by the
appellant and thereafter passed a reasoned order which requires
no interference.
Learned counsel for the respondent-State relied on the
judgment passed by the Apex Court in the case of TATA Cellular
[2025:RJ-JD:38393] (7 of 13) [CW-12222/2025]
Vs. UOI, reported in AIR 1996 SC 11, which says that unless
there is perversity or illegality, the Court should not interfere in
contractual matters. He further relied on judgment passed by the
Apex Court in the case of Galaxy Transport Agencies,
Contractors, Traders, Transports & Suppliers Vs. New J.K.
Roadways, Fleet Owners and Transport Contractors & Ors.,
reported in (2021) 16 SCC 808 so also in Jagdish Mandal Vs.
State of Orrisa & Ors., reported in (2007) 14 SCC 517 while
highlighting that the scope of judicial review in such cases is very
limited and in view of the concurrent findings given by the two
authorities below, the discretionary remedy could not be exercised
in the present case and the petition, therefore, deserves to be
dismissed.
4.1 Learned Senior counsel Mr. Anand Purohit appearing on
behalf of the private respondent makes the following
submissions :-
(i)- Petitioner submitted two bids and both were rejected on the
same ground, however, the appeal was preferred only in relation
to one tender.
(ii)- The private respondent has fulfilled all the conditions and
therefore, respondents rightly proceeded to award the contract in
favour of the respondent. The petitioner sought clarification in the
pre-bid meeting and the issue as raised in the present writ petition
was also discussed there and it was made clear that the
experience required in pressure irrigation system is must.
(iii)- Petitioner is not having experience in pressure irrigation
system and therefore, his bid was rightly declared as non-
responsive.
[2025:RJ-JD:38393] (8 of 13) [CW-12222/2025]
(iv)- If the petitioner was eligible as per NIT conditions then there
was no occasion to seek clarification in the pre-bid meeting.
(v)- Petitioner has not alleged malafides and therefore, the
decision taken by the authorities in accepting the bid of private
respondent cannot be allowed to be questioned by the petitioner.
5. In rejoinder to the reply submitted by respective
respondents, learned counsel for the petitioner makes following
submissions:-
(i)- There is no question of alleging malafide as petitioner has
challenged the order of the Second Appellate Authority on the
ground that the impugned order is short of reasons and as a
matter of fact, the order impugned shows no application of mind.
(ii)- The second reason in dismissing the appeal as quoted in the
impugned order relates to BOQ, which defines the budgetary
provisions of the tender in question and as a matter of fact, BOQ
relates to allocation of budget under various heads and therefore,
second reason in the impugned order has no relevancy with the
issue as raised before the said Authority so also in the present writ
petition.
(iii)- The petitioner has given full details while submitting his first
appeal, second appeal and so also in the written submission
explaining as to how the pressure distribution system in water
supply is identical to that of operation & maintenance of pressure
irrigation system, however, no reason has been assigned as to
how the said explanation submitted by the petitioner is not
acceptable.
(iv)- Though the petitioner was eligible as per NIT conditions,
however, since there was anomaly in interpreting the tender
[2025:RJ-JD:38393] (9 of 13) [CW-12222/2025]
condition, for enhancement of the scope of the experience, the
clarification was sought in the pre-bid meeting. Whatever
clarification is given in the pre-bid meeting is not material rather
the present case is required to be considered in light of the tender
condition and if based on the tender condition, the petitioner is
found eligible then in that event the petitioner is required to be
treated as eligible.
6. Heard learned counsel for the parties and perused the
material available on record.
7. Before considering the submissions made by the respective
counsels on merits, it would be appropriate to first examine the
correctness of the order passed by the Second Appellate Authority.
7.1 A perusal of the second appeal indicates that the petitioner
has made his submission so as to justify his claim that experience
possessed by him for operation & maintenance of pressure water
supply system is similar to operation & maintenance of pressure
irrigation system. The petitioner has also submitted written
submissions and stated that in view of conditions No.7 & 8, the
experience possessed by him for operation & maintenance of
pressure water supply work is required to be treated similar and
sufficient enough to make him eligible for the bid in question.
7.2 The Second Appellate Authority in its order dated 18.06.2025
has recorded the submission made by the representative of
petitioner as point No.1, 2 & 3. It was specifically stated in point
No.2 that in view of Conditions No.7 & 8, the experience in
operation & maintenance of water supply is required to be treated
as similar and sufficient experience to make him eligible.
[2025:RJ-JD:38393] (10 of 13) [CW-12222/2025]
Another submission was made to the effect that the
petitioner submitted three experience certificates of pressure
distribution in water supply and elaborately explained as how
experience irrigation and water supply are similar. The
representative of the Department also made submissions
countering the submissions made by the representative of the
petitioner. The representative of the Department relied on the
foot-note of Condition 3(ii)(c). The representative of the
Department tried to justify that the experience in pressure
irrigation system is different from the experience in water
distribution system.
7.3 In view of the submissions made by the petitioner and the
representative of the Department, the Second Appellate Authority
was required to deal with the submissions made by the parties
before it.
7.4 Before proceeding further it would be appropriate to
reproduce the operative part of the order passed by the second
appellate authority :-
"mHk; i{kksa dks lquk x;k rFkk fcM nLrkostksa ,oa izLrqr
vfHkys[kksa dk esjs }kjk /;kuiwoZd voyksdu ds mijkar fuEu fu'd'kZ ij igqaprk gwWaw a%& 1- mikiu laLFkk }kjk fufonk dh "krksZa esa Operation &
Maintenance dh "krZ flapkbZ O;oLFkk ls lacaf/kr leku
izd`fr ds dk;Z ds fy, fu/kkZfjr dh xbZ gSA fufonk izi= ds
DykWt&lh ds QqVuksV esa mDr dk Li'V mYys[k fd;k x;k
gSA
[2025:RJ-JD:38393] (11 of 13) [CW-12222/2025]
2- BOQ ds fcUnq la[;k 3 esa Hkh mYys[k fd;k x;k gS fd
"maintaining equipment and records according to
RFPIM 2000 and imparting three season of training
in one year to members of WUA for operation and
maintenance of sprinklers systems and various
records."
mijksDr rF;ksa ds vk/kkj ij vihykFkhZ;ksa }kjk izLrqr
f}rh; vihy dks eSa [kkfjt djrk gwWa D;ksafd mikiu
laLFkk }kjk jktLFkku yksd mikiu esa ikjnf"kZrk fu;e 2013
ds fu;e 36 (2) (d) ,oa 38 (a) (ii) ds vuqlkj ,oa fufonk
izi= esa Li'V :i ls mYysf[kr "krksZa dh ikyuk djrs gq,
vihykFkhZ dks v;ksX; ?kksf'kr fd;k x;k gSA vr% izFke
vihyh; vf/kdkjh }kjk fn, x, fu.kZ; fnukad 16-04-2025 ls
eSa lger gwWaA
mHk; i{k lwfpr gksosa A"
A perusal of the finding given by the Second Appellate
Authority leaves no iota of doubt that it has not at all considered
the submissions made by the petitioner or by the Department. The
two reasons assigned while deciding the second appeal do not
indicate as to how the submissions made by the petitioner are not
acceptable and how submissions made by Department are
justified. In fact, the first reason appears to support the
contention made on behalf of the petitioner, as it states that the
tender conditions concerning operation and maintenance in
irrigation works relate to similar types of work. It further refers to
[2025:RJ-JD:38393] (12 of 13) [CW-12222/2025]
the footnote attached to clause (c), which clearly reinforces this
interpretation.
The second reason, wherein it refers to condition No.3 of
BOQ is a reason which is beyond comprehension as to how the
same is applicable while adjudicating the present dispute. The
BOQ is an estimated price schedule of different items of work
contract and also provides different works to be performed by the
successful bidder and therefore, the same has no relevancy to the
issue in hand.
8. Based on the above reasons, the Second Appellate Authority
proceed to observe that the authorities have complied with Rule
36(2)(d) & 38(a)(ii) of the Rules of 2013 and therefore, the
petitioner has rightly been declared as ineligible.
9. In opinion of this Court, the impugned order dated
18.06.2025 passed by the Second Appellate Authority is totally
non-speaking and shows total non-application of mind on the
submissions advanced by the respective parties. This Court does
not deem it appropriate to examine the submissions made by
respective parties on merits as any adjudication made on the
merits would certainly have impact on the adjudication to be made
by the Second Appellate Authority.
10. In view of the above given circumstances, the present writ
petition is allowed. The impugned order dated 18.06.2025
(Annexure-14) is quashed and set-aside. The matter is remanded
back to the Second Appellate Authority to decide the matter
afresh after considering the submissions made by the parties in
the memo of appeal so also in the written submissions made by
the petitioner and the submissions made by the department.
[2025:RJ-JD:38393] (13 of 13) [CW-12222/2025]
11. Since the interim order was granted by this Court on
01.08.2025 and the matter pertains to larger public interest,
therefore, this Court deems it appropriate to direct the Second
Appellate Authority to decide the second appeal within a period of
seven days. Till then, the interim order dated 01.08.2025 shall
remain in currency.
12. Pending application(s), if any, stand(s) disposed of.
(SUNIL BENIWAL),J Rmathur/-
Powered by TCPDF (www.tcpdf.org)
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!